ITP For Access Control System Installation

This inspection and test plan outlines the quality control process for installing an access control system during Phase 2 of upgrades to facilities and infrastructure at Al Udeid Air Base in Qatar. It specifies that the contractor must submit documentation like shop drawings and material approvals for review prior to related work. It also requires inspection of delivered materials and oversight of the installation process to ensure compliance with project specifications and drawings. The plan designates roles and sign-off procedures for the contractor and consultant to verify that quality standards are achieved.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
232 views

ITP For Access Control System Installation

This inspection and test plan outlines the quality control process for installing an access control system during Phase 2 of upgrades to facilities and infrastructure at Al Udeid Air Base in Qatar. It specifies that the contractor must submit documentation like shop drawings and material approvals for review prior to related work. It also requires inspection of delivered materials and oversight of the installation process to ensure compliance with project specifications and drawings. The plan designates roles and sign-off procedures for the contractor and consultant to verify that quality standards are achieved.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 1

INSPECTION & TEST PLAN

FALCON-3 FACILITIES AND INFRASTRUCTURE - PHASE 2 REF. NO.


STATE OF QATAR MINISTRY OF DEFENCE
P2-470556 REV. NO. 0
AL UDEID AIR BASE, QATAR
DATE :
PAGE : 1 OF 1

ACTIVITY: Access Control System Installation

AREA/LOCATION: Falcon-3 Phase 2 (Pilot Readiness Bldg., Shelter 1-4, Generator Sunshade and Fire Pump Bldg.)
ITP approved by CONTRACTOR's QA/QC: ITP approved by Consultant:
Signature: Signature:
Date: Date:
INSPECTION LEVEL
SERIAL NO. DESCRIPTION FREQUENCY SPECIFICATION / CRITERIA VERIFICATION RECORD
S/C CONTRACTOR Consultant

1 DOCUMENTATION
Once (Approval prior to
1.1 Pre-Qualification subcontractor Project Specifications and drawings. H H R
submit the submittal)

1.2 Shop Drawing Approval Each Shop Drawing Project Specifications and drawings. H H R

Each MAR ( prior to order


1.3 Material Approval Project Specifications and drawings. H H R
the material).

Once (Approval prior to


1.4 Method Statement Approval Project Specifications and drawings. H H R
start of activity)
2 MATERIAL INSPECTION

Check the Material as per approved


2.1 Each Delivery Project Specifications and drawings. H H H
submittal.

3 Installation

Each Area where applicable


3.1 Installation of the system (As per Consultant Project Specifications and drawings. H H H
requirements)

LEGEND: H: HOLD W: WITNESS S: SURVEILLANCE R: REVIEW


ITP Sign-Off post completion of Works
CONTRACTOR APPROVAL Consultant APPROVAL

NAME : NAME :

SIGN : SIGN :
DATE: DATE:

PAGE 1 of 1