0% found this document useful (0 votes)
565 views

ITP For Structural Cabling System Testing and Commissioning

This document is an inspection and test plan for structural cabling system testing and commissioning of an unnamed project. It outlines two key activities: documentation and testing/commissioning. Documentation includes pre-qualification of subcontractors, shop drawing approval, material approval, and method statement approval. Testing and commissioning includes pre-commissioning of the system and final testing of fiber optic and UTP cables using a Fluke test in each applicable area. The document provides inspection levels and specifies that the contractor and consultant must approve the plan and sign off after works completion.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
565 views

ITP For Structural Cabling System Testing and Commissioning

This document is an inspection and test plan for structural cabling system testing and commissioning of an unnamed project. It outlines two key activities: documentation and testing/commissioning. Documentation includes pre-qualification of subcontractors, shop drawing approval, material approval, and method statement approval. Testing and commissioning includes pre-commissioning of the system and final testing of fiber optic and UTP cables using a Fluke test in each applicable area. The document provides inspection levels and specifies that the contractor and consultant must approve the plan and sign off after works completion.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 1

INSPECTION & TEST PLAN

Projet Name & Details


REF. NO.

REV. NO.
DATE :
PAGE : 1 OF 1

ACTIVITY: Structural Cabling System Testing and Commissioning

AREA/LOCATION:

ITP approved by CONTRACTOR's QA/QC: ITP approved by Consultant:


Signature: Signature:
Date: Date:
INSPECTION LEVEL
SERIAL NO. DESCRIPTION FREQUENCY SPECIFICATION / CRITERIA VERIFICATION RECORD
ITL CONTRACTOR Consultant

1 DOCUMENTATION
Once (Approval prior to
1.1 Pre-Qualification subcontractor Project specifications and drawings. -- R R
submit the submittal)

1.2 Shop Drawing Approval Each Shop Drawing Project specifications and drawings. -- H R

Each submittal ( prior to


1.3 Material Approval Project specifications and drawings. -- H R
order the material).

Once (Approval prior to


1.4 Method Statement Approval Project specifications and drawings. -- H H
start of activity)

2 Testing and Commissioning

Each Area where applicable


2.1 Pre-commissioning of the system (As per Consultant Project specifications and drawings. -- W W
requirements)

Final Testing and Commissioning: Each Area where applicable


2.2 Fluke Test for the Fiber optic and UTP (As per Consultant Project specifications and drawings. -- W H
cables. requirements)

LEGEND: H: HOLD W: WITNESS S: SURVEILLANCE R: REVIEW


ITP Sign-Off post completion of Works
CONTRACTOR APPROVAL Consultant APPROVAL

NAME : NAME :

SIGN : SIGN :
DATE: DATE:

PAGE 1 of 1