2.1 Circular and RecNodes PERT CPM Lecture 2 Example and Assignment
2.1 Circular and RecNodes PERT CPM Lecture 2 Example and Assignment
3
CPM/PERT
Example 1.
A project to manufacture a product is composed of the following activities:
A critical activity is an activity that cannot be delayed without delaying the completion of the project.
A delay of n days on a critical activity will increase the length of the project by n days.
Critical activity should be monitored carefully to avoid delays.
A critical activity has a total float of zero.
A path from the start node to the finish node that consists entirely of critical nodes is a critical path.
A critical path is the longest path from start node to finish node.
The length of the critical path is the minimum time required for project completion. It is equal to LT(n) =
ET(n), where n is the finish node
C=8 F = 12
3 5 6
B=9
D=7
1 E = 10
A’ = 0 4
A=6
2
For clearer example fill free to visit this you tube site and pdf
https://www.youtube.com/watch?v=WrAf6zdteXI
http://www.improhealth.org/fileadmin/Documents/Improvement_Tools/PERT.pdf
https://www.youtube.com/watch?v=-TDh-5n90vk
Example 2. The MMF Academy is considering building a new athletic complex on campus. The complex
would provide a new gymnasium for inter-school sports activities, expanded office space, classrooms,
and intramural facilities. The following activities would have to be undertaken before construction starts.
Step 1: Determine the list of activities, its immediate predecessors, and approximate time, which is already
provided in the problem.
Step 4: Determine the earliest start time and earliest finish time of the initial activities.
Let ES = earliest start time for an activity
EF = earliest finish time for an activity
t = activity time
The earliest finish time for any activity, then EF = ES + t
Step 5: Compute for the earliest start time and earliest finish time using the forward pass.
Step 6: Develop the latest start time and latest finish time using the backward pass.
Let LS = latest start time for an activity
LF = latest finish time for an activity
t = activity time
Step 7: Compute for the latest finish time and latest start time.
Step 8: Compute for the slack of all activities using the formula provided below and identify the zero slack to
determine the critical path. The slack value can be obtained using the formula below:
Slack = LS – ES = LF - EF
2 6
A F
D
6 5 14 H
1 A’ 4 7 8
E’ 7
B E
C 6 G
8 10 13
3 5
Slack = LS – ES = LF – EF / EF = ES + t / LS = LF – t
A 0 2 6 8 2 No
B 0 0 8 8 0 Yes
C 8 8 18 18 0 Yes
D 18 19 23 24 1 No A ES EF
E 18 18 24 24 0 Yes t LS LF
F 24 24 38 38 0 Yes
G 24 25 37 38 1 No
H 38 38 45 45 0 Yes
A 0 6 D 18 23 F 24 38
6 2 8 5 19 24 14 24 38
START H 38 45
FINISH
7 38 45
B 0 8 C 8 18 E 18 24 G 24 37
8 0 8 10 8 18 6 18 24 13 25 38
Asynchronous Activity:
A promoter of championship boxing match must perform the task shown in the table before the boxing match
can held (all durations are in days).
a. Construct the project network.
b. Determine the critical path/s.
c. Find the completion time of the project.
𝑎+4𝑚+𝑏 𝑏−𝑎 2
𝑡= 𝜎2 = ( )
6 6