Case Studies On Dispute Resolution in Construction Projects For Framing An Expert Solution
Case Studies On Dispute Resolution in Construction Projects For Framing An Expert Solution
net/publication/340918270
CITATIONS READS
2 5,712
1 author:
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by B. Hemanth Sai Kalyan on 15 March 2021.
Published By:
Blue Eyes Intelligence Engineering
Retrieval Number A3688058119/19©BEIESP 476 & Sciences Publication
Case Studies on Dispute Resolutions in Construction Projects for Framing an Expert Solution
Time
Causes
S.No Case Details Judgment Taken
Categorized
to Solve
Exemption from
Performance, No evidence to prove against insurance claim. So, 12
1 compensating insured
Insurance amount has to be compensated. years
amount.
The said contract norms are required to be satisfied
Challenging the 6
2 Contractual for awarding of contract which is not done. So no fault
contract norms months
in the contract.
Performance, The arbitrator was found to accuse the contractor for
Challenging the award Payment, other’s mistake. The bills were not cleared also 3
3
of the arbitrator. Arbitrational, evidence for faulty construction is there. Hence years
Contractual arbitral award is wrong.
Denial of payment Performance,
The reasons stated are sham and no evidence to 5
4 stating poor quality of Arbitrational,
produce. Payment has to be done within one month. years
material. Payment
When arbitration had to be done it hasn’t, resulting
Challenging lower Performance,
in delay and losses. The quality of materials is also 2
5 court’s decision for the Arbitrational,
poor. Therefore work should be continued with quality years
benefit of the project. Contractual
material
There was involvement of middle men in the
Compensation for the Compensation, compensation process resulting in deficient payment. 15
6
land taken is very less Land Acquisition The order is to fulfill the payments and only then years
carryon with the construction in the acquired land
Poor quality Evidence shows involvement of corruption in this
Performance,
construction either to be case. The option is given to the sufferer weather to 10
7 compensation,
compensated or pay back make repairs or get back the full amount which in both years
Payment
the full amount. cases the contractor has to pay.
Performance, No need for arbitration because there is no breach in
Petition about need for
8 Arbitrational, the contract documents in the first place. The quality is 1 year
arbitration.
Contractual also up to the mark.
Performance, Arbitration has taken place. The findings are not
Challenging poor 2
9 Arbitrational, there to justify poor performance. Hence the payments
performance claim years
Payment have to be rightfully done.
The contract documents are not clear which allows
Challenging the Performance,
the contractor to not plead guilty. The quality of work 10
10 payments done citing poor Payment,
performed is not up to the mark but the contractor years
performance. Contractual
cannot be blamed for this
Contending the Various parameters are required to be satisfied for
4
11 unreasonable restrictions Contractual awarding a contract which are of utmost importance.
months
for awarding a contract. Hence no fault.
Though the quality of construction is poor in this
case, the court feels that it is the mistake of the
Petition about poor
Performance, petitioner to identify the said poor quality during the
construction quality and 3
12 compensation, initial stages of the construction itself and also the
the compensation to be years
Payment contract period has been passed which means that the
paid for the same.
defendant is in no way responsible for the payment of
compensation.
There is no evidence placed before the Court to
Petition about poor
Performance, show that the overhead tank had been built with low 11
13 construction quality and
compensation quality materials. As such, the writ petition is liable to months
reconstruction
be dismissed. Hence, it is dismissed.
Published By:
Blue Eyes Intelligence Engineering
Retrieval Number A3688058119/19©BEIESP 477 & Sciences Publication
International Journal of Recent Technology and Engineering (IJRTE)
ISSN: 2277-3878, Volume-8, Issue-1 May 2019
Petition about The allegations made by the petitioner had not been
Performance,
objections on the award substantiated with sufficient records. Further, there is
Payment, 8
14 given by the arbitrator. no evidence placed before this Court to show that the
Arbitrational, years
arbitrator was at fault. Hence, it is dismissed.
Contractual
Respondent and the arbitrator produced enough
Performance, evidence which make sure that the respondent receives
Petition against arbitral
Payment, the money as put by the arbitrator and the petitioner is 6
15 award to be paid to the
Arbitrational, liable to pay even the interest on the money which years
contractor.
Contractual pertains to escalation of costs.
Published By:
Blue Eyes Intelligence Engineering
Retrieval Number A3688058119/19©BEIESP 478 & Sciences Publication
Case Studies on Dispute Resolutions in Construction Projects for Framing an Expert Solution
Compensation 10
From the case studies a clear understanding of what are the Arbitration 9
main causes which are the responsible for the arrival of a
dispute are the case studies a clear understanding of what are Illegal 5
the main causes which are the responsible for the arrival of a Land Acquisition 4
dispute are of disputes from the cases studies, shown below in Insurance 1
the table are the rankings of most frequent causes.
From the 35 case studies done, 23 of them are performance
Table 2: Ranking of Causes
related issues which include poor quality of work, poor
material quality, etc. Followed by contractual related and
Occurrence
Causes payment issues, occurred for 19 times and 16times
(No/of times)
respectively. Some of the cases are inter related which each
Performance 23 other which is a combination
Contractual 19 of two or more causes.
Payment 16
Published By:
Blue Eyes Intelligence Engineering
Retrieval Number A3688058119/19©BEIESP 479 & Sciences Publication
International Journal of Recent Technology and Engineering (IJRTE)
ISSN: 2277-3878, Volume-8, Issue-1 May 2019
It can be understood that it is in most often times an influencing the disputes resolutions as observed from the
amalgamation of different causes which are both legal case studies are also considered while framing of the
inter-related and intra-related amongst each other and thus is expert system.
suggests that no particular cause is individually responsible This is advantages because it gives an alternative solution to
for a dispute. the issue depending on its nature and the factors considered
are also inclusive of whose side the mistake is. These will not
B. Statistical Analysis of Data Using SPSS Software. only let helps in identifying the mistakes happening in the
first place but also gives a better understanding of the case as
Statistical Package for Social-Sciences-SPSS22.0 is used it proceeds, so that the decision to be taken will have a correct
in this study. Table 3 shows the means (frequency) and of and precise solution.
each cause. C. Prototype of The Expert System
Table 3: Means of causes The proposed prototype shows the categorization of disputes
and the possible solution. However it only projects the best
Causes Mean possible way to solve a particular dispute but it doesn’t
Performance 0.6571 actually solve the dispute by itself.
Compensation 0.2857 Figures 2, 3 and 4 show the expert system for the
Arbitration 0.2571 performance cause. The characteristics of a particular
Land Acquisition 0.1143 problem are identified through the flow chart which narrows
Insurance 0.0286 down to the solution.
Figure 5 depicts the expert system for the rest of the causes
Payment 0.4571
and their possible solutions of alternative dispute resolution
Contractual 0.5429
techniques.
Illegal 0.2286
B. Expert System
From the obtained results and the observations from the
judicial point of view, the expert system has been framed
with respect to its convenience, ease of understanding and
Fig 2: Categorization of performance (Work)
the problem solving capacity. This system has importance to
its name in the form of an expert system because of its ability
to solve the disputes with minimal human interference.
The process of framing of expert system involved the inputs
of legal advisors from esteemed construction firms along
with the opinions of the people in industry with vast
experience. The problem solving capacity of each of the
advised solution is also taken into account. Factors
Published By:
Blue Eyes Intelligence Engineering
Retrieval Number A3688058119/19©BEIESP 480 & Sciences Publication
Case Studies on Dispute Resolutions in Construction Projects for Framing an Expert Solution
Published By:
Blue Eyes Intelligence Engineering
Retrieval Number A3688058119/19©BEIESP 481 & Sciences Publication
International Journal of Recent Technology and Engineering (IJRTE)
ISSN: 2277-3878, Volume-8, Issue-1 May 2019
Published By:
Blue Eyes Intelligence Engineering
Retrieval Number A3688058119/19©BEIESP 482 & Sciences Publication
Case Studies on Dispute Resolutions in Construction Projects for Framing an Expert Solution
Published By:
Blue Eyes Intelligence Engineering
Retrieval Number A3688058119/19©BEIESP 483 & Sciences Publication
View publication stats