04 - Part A - Track
04 - Part A - Track
1.1 SCOPE:
1.1.1 This specification deals with the requirements for the manufacture,
supply, assembly, installation, testing and commissioning of
Permanent Way Works.
1.1.3 Permanent Way works involved for the proposed New Line /
double line / 3rd line / 4th line / RE Works can briefly be described
as under:
(a) Setting out the line and level of track for the proposed line and
establishing working, bench marks and alignment references,
taking the details from bench marks and alignment references
established by the Employer / by the same or other Contractor
earlier in main lines, and in station yards including for loops,
turnouts, cross over roads, derailing switches, sand humps etc.
(b) Supply of ballast along the track in mid-section and in yards and
running out this ballast to the top of formation and compacting of
ballast with mechanical means.
_________________________________________________________________________________
Volume I – Part A - Track 1 of 112
Specifications RVNL
(d) Supply of rails for item (c) above, and all rail & sleeper fastenings
required for the above works and for installation of track in main
lines and yards.
(h) Insertion of new turnouts on main line and running lines where
necessary under block.
(k) Welding of rail joints by Flash Butt/ SKV process for Conversion of
free rails to LWR/CWR/SWR /10 or 20Rail panels.
_________________________________________________________________________________
Volume I – Part A - Track Page 2 of 112
Specifications RVNL
(s) Making and supply of ‘As Built’ drawings for the new assets
created.
Note:
(1) The above are not an exhaustive list comprising of all works to
be done under this contract. Major works only have been listed
for guidance.
2.0 Standards:
2.1.1 ABBREVIATIONS
UIC Code 864 – 5 Technical Specification for the Supply of Rail Seat
Pads
_________________________________________________________________________________
Volume I – Part A - Track Page 4 of 112
Specifications RVNL
_________________________________________________________________________________
Volume I – Part A - Track Page 5 of 112
Specifications RVNL
2.2.1 The works shall be carried out as per the Standard Specifications
laid down for each item read with provisions made in the above
manuals and Codes.
2.2.3 The relevant RDSO’s Specifications and Drawings for each of the
Permanent Way Component and Assembly shall be followed for
_________________________________________________________________________________
Volume I – Part A - Track Page 6 of 112
Specifications RVNL
2.2.4 For the supply of goods or material or performing any work or test,
when reference is made in the contract to a specific standard(s),
specification(s) or code(s), the provisions of the latest current
edition or revision of the relevant standard(s), specification(s) and
code(s) in effect shall apply, unless otherwise expressly stated in
the Contract. Where such standard(s), specification(s) or the
code(s) are notional, or relate to a particular country or region,
other authoritative standards which ensure an equal or higher
quality than the standards and codes specified will be accepted
subject to the Engineer’s prior review and written approval.
Differences between the standards specified and the proposed
alternative standards must be fully described in writing by the
contractor and submitted to the Engineer at least 28 days prior to
the date when the contractor desires the Engineer’s approval. In
the event the Engineer determines that such proposed deviation
does not ensure equal or higher quality or does not serve the
requirements, the contractor shall comply with the standards
specified in the documents.
_________________________________________________________________________________
Volume I – Part A - Track Page 7 of 112
Specifications RVNL
SN Particulars Details
1 Gauge 1676 mm (B.G)
2 Standard of loading 25-T 2008.
3 A Rail profile- Main Line 60 or 52 Kg 1st quality of 880
MPa / 1080 MPa CR / 1080
MPa HH, rails rails depending
upon the route.
B Loop Lines and sidings. 52 Kg 1st or 2nd quality, 880 or
C Guard Rail on Bridges. 710 UTS rails.
D Check Rail on Level Crossings
Note:
1. Released 52 kg rails, if
available, will be issued for
being used as Guard rails
on Bridges and Check Rails
at Level Crossings.
2. Rails required for track in
main line, loops in station
yards and sidings will be
given by the Employer free
of cost.
3. Rails required for
manufacture of turnouts
including lead rails, SEJs,
derailing switches, glued
insulated rail joints shall be
arranged by the Employer
free of cost for fabrication by
the Contractor at his cost.
4. Type of sleeper Mono block 60 kg. PSC sleepers
for track.
_________________________________________________________________________________
Volume I – Part A - Track Page 8 of 112
Specifications RVNL
SN Particulars Details
5. Sleeper density As per Para 209 (2) of IRPWM
Main line – 1660 nos./KM
Loop line – 1540 nos./KM
Siding – 1660 nos/KM
Higher sleeper density can be
provided with approval of the
Principal Chief Engineer.
6. Ballast cushion Main line – 350 mm (Clean)
Loop line – 250 mm
7. Rail lengths and rail end fittings. Free 13 m / 26 m long rails for
Fish plated track.
SWR of 3 x 13 m rail panels with
fish plates at ends.
LWR 1 km. long panel with
switch expansion joints at ends.
CWR station to station long
panel with switch expansion
joints at ends.
8. Maximum cant 165 mm
9. Maximum cant deficiency Generally 75 mm
For nominated stock 100 mm
10 Maximum cant excess Generally 75 mm but 100mm
may have to be provided if
directed by the Engineer
11 Maximum cant gradient Generally 1 in 720 or flatter.
1 in 360 in very exceptional
circumstances only.
12 Rate of change of cant/cant 35 mm / sec
deficiency
13 Turnouts in yards: Where passenger trains ply both
on main lines and loops: 1 in 12
Turnout with thick web curved
switches and CMS crossings
(preferably weldable) laid on
PSC sleepers on fan shaped
layout.
Loops and sidings where
passenger trains do not ply: 1 in
8.5 turnout with curved switches
and CMS crossings laid on PSC
sleepers on fan shaped layout.
Note: 1 in 8½ symmetrical split
type turnout may also be used
on loops where passenger trains
_________________________________________________________________________________
Volume I – Part A - Track Page 9 of 112
Specifications RVNL
SN Particulars Details
ply.
Derailing switch 60 / 52 kg on 60
kg. PSC sleepers.
2.4 INTERFACES:
_________________________________________________________________________________
Volume I – Part A - Track Page 10 of 112
Specifications RVNL
2.4.2 The contractor shall strictly adhere to the work plan made for
works requiring interfacing. Any delay either on his part or on the
part of other agencies and other bottlenecks that could affect the
pace of works shall be informed to the Engineer in time so as to
enable him to take corrective steps.
3.1 REQUIREMENTS:
_________________________________________________________________________________
Volume I – Part A - Track Page 11 of 112
Specifications RVNL
3.1.5.1 The contractor shall set up a site supervision system, which shall
be part of the overall safety assurance system and quality
management system.
_________________________________________________________________________________
Volume I – Part A - Track Page 14 of 112
Specifications RVNL
3.1.6.4 The supervisors shall work on a full time basis during the entire
installation process.
3.1.7 Workmanship:
3.1.7.2 Unless otherwise specified, the Engineer shall decide the final
colours for all paintwork and other finishes to be applied to any part
of the works, which shall confirm to the practice of Indian Railways.
3.2.1 Establish work site and get shared access to work jointly for the
relevant works. All the civil works may not be complete at the same
time and may be completed in stages to facilitate the track laying
operation.
3.2.2. Partial completion of track work to provide shared access for the
works of other agencies. Completion of track work, which can be,
completed without non-interlocking of the station yards.
3.2.3 Completion of track works jointly with Signalling work and Facility
works for additions and alterations to station Yards with or without
non-interlocked working after CRS sanction in Phases.
_________________________________________________________________________________
Volume I – Part A - Track Page 15 of 112
Specifications RVNL
4.1 INTRODUCTION
4.1.2 No permanent Works shall be carried out until all methods and
materials have been approved by the Engineer in charge.
4.1.4 The test results of each test to be carried out as per Employer’s
requirement shall be recorded and submitted in a format approved
_________________________________________________________________________________
Volume I – Part A - Track Page 16 of 112
Specifications RVNL
4.2.2.2 Subsequently, before use for installation, all the materials and
components shall be inspected by the Engineer.
_________________________________________________________________________________
Volume I – Part A - Track Page 17 of 112
Specifications RVNL
5.1 RAILS
5.1.2.2 Rails will be supplied by the Employer only for laying in track in mid
sections and yards for main lines and loops, including for laying in
between turnouts in crossovers (between heels of crossings),
check rails for Level crossings and guard rails for bridges. In case
the Contractor proposes to use PQRS method or linking the track
first with second hand rails and then doing TRR with long welded
rails for installation of track, required free rails will be issued free of
cost.
Rails will also be supplied for fabrication of turn outs including lead
rails, SEJs and glued insulated joints. The contractor should obtain
rails of appropriate specifications.
_________________________________________________________________________________
Volume I – Part A - Track Page 18 of 112
Specifications RVNL
5.1.2.3 For accountal of rails, recovery for shortages etc., refer to Part II
(Employer’s Requirements) of Bidding Document.
ERC MK III, GFN liner, GR sole plate & SGCI inserts shall be
manufactured in accordance with the relevant technical
specification of Indian Railway mentioned clause 2.1.2 (7).
Standard fishplates and fish bolts shall be of four bolt type, suitable
for use with UIC60 / 52 Kg rail section, and shall be manufactured
in accordance with the relevant technical specifications of Indian
Railways as mentioned in clause 2.1.2 (7).
5.2.4 Ballast
The ballast shall be supplied by the Contractor in accordance with
the specifications as laid down by the Indian Railways.
Specifications are given as Annexure A to Section J – Specification
to Permanent Way Works.
_________________________________________________________________________________
Volume I – Part A - Track Page 19 of 112
Specifications RVNL
_________________________________________________________________________________
Volume I – Part A - Track Page 20 of 112
Specifications RVNL
6.1 INTRODUCTION
6.1.1 General
This para details the requirements for manufactured items for the
Works.
6.2.1 General
_________________________________________________________________________________
Volume I – Part A - Track Page 21 of 112
Specifications RVNL
_________________________________________________________________________________
Volume I – Part A - Track Page 22 of 112
Specifications RVNL
6.2.3 Switches
6.2.3.1 General
1) All switches on main lines as well as on loop lines and sidings,
shall be manufactured from ultrasonically tested 60 / 52 kg rails to
IRS Specification T 12. The switch rail shall be in one piece with
no joint within the switch rail length.
2) All switches with slide chairs and other components shall confirm
to relevant RDSO drawing and IRS Specification as mentioned in
clause 2.1.2 (7).
3) Switches shall provide adequate flange way clearance between
the stock rail and the switch rail with the switch rail in the open
position at JOH.
6.2.4 Crossings
6.2.4.1 General
1) The crossings for use in main lines shall be cast manganese steel
crossing.
2) The cast manganese steel - crossings shall be manufactured from
Austenitic Manganese steel as defined in UIC Code 866 and as
per relevant technical specification of Indian Railways for CMS
crossings as mentioned in clause 2.1.2 (7) and as per RDSO
Drawings.
3) The wheel load transfer surfaces of all CMS crossings shall be
artificially hardened by explosive hardening to achieve hardness of
about 350 BHN before installation.
4) All crossings shall conform to RDSO Drawings and IRS
Specifications.
1) Check rails in all turnouts & diamond crossings shall have facility
for adjustment of check rail clearances up to 10 mm over and
above the initial designed clearance. Each check rail end shall be
flared by machining.
2) Height of check rail above running rail & the lengths and positions
of the check rail shall provide safety and be compatible with the
overall track layout and Schedule of Standard Dimensions (BG)
2004.
The design of the dead end shall be submitted by the contractor for
Engineer’s approval. The contractor shall interface with the
Engineer for the details required for the design of stops.
2) The switch rail shall be in one piece with no joints within the
switch rail length and shall house well when closed.
7.1 The setting out of longitudinal and vertical alignment for track
construction and for laying curves, turnouts etc. shall be the
responsibility of the contractor; the following principles shall be
adopted for setting out and execution.
7.2.2 Survey and setting out of works shall be carried out by surveyors
of appropriate experience and qualification.
7.2.3 The Engineer may carry out checks to verify the accuracy of the
setting out and Contractor’s compliance of the completed works
with given alignment and the specifications. Provisions and
arrangement shall be made by the Contractor to facilitate the
checks. However, full responsibility lies with the Contractor for the
accuracy of line and level of the tracks
7.3.3 The successful tenderer shall take action for verification of the
details of the established bench marks and alignment references,
establishment of working bench marks, working alignment
_________________________________________________________________________________
Volume I – Part A - Track Page 25 of 112
Specifications RVNL
7.3.5 Based on these reference markers, the entire work shall be carried
out by the Contractor.
7.3.6 The contractor should fix reference markers on both the cesses at
intervals of not more than 200 m on straight and 20 m on curves to
indicate the centre line of track. On these reference markers,
marks should also be made to indicate the levels of bottom of the
sleeper and the rail levels. The rail level so fixed should be the
inner rail level in the case of curves.
7.3.7 These reference markers which also indicate the bottom level of
the sleepers and the rail levels should be got checked and
approved by the Engineer.
7.3.8 The track setting marks for the centre of the track shall be shown
by plates or nails fixed to the bridge spans, on the upper surface of
the slab or as approved by the Engineer. The track setting marks
for the vertical setting of the track running surface shall be shown
by angle plates sealed onto the bridge side walls. They shall be
referenced with respect to the theoretical track level as approved
by the Engineer.
7.3.9 The part of the works detailed from Para 7.3.1 to 7.3.7 above
should be done before the start of any work related to installation
of track.
_________________________________________________________________________________
Volume I – Part A - Track Page 26 of 112
Specifications RVNL
7.5.1 The Contractor shall ensure that critical dimensions laid down for
the project are met. Regular checking should be carried out during
the construction stages to ensure that the specified permissible
deviations are not exceeded.
7.5.2 The Contractor shall ensure that all survey and setting out points
shall be established on Site to required accuracy. He shall also be
responsible for each stage of the setting out work and for verifying
compliance before construction starts.
8.1 INTRODUCTION
8.1.1 General
8.1.4 All temporary/service tracks required for track work on main lines
and yard lines shall be arranged & laid by the contractor with prior
approval of the Engineer. The contractor shall remove these
temporary/service tracks after completing the track work as
approved by Engineer. The rails released from temporary/service
track may be used on yard lines, if the condition of rails is within
specified tolerances and approved by Engineer.
_________________________________________________________________________________
Volume I – Part A - Track Page 28 of 112
Specifications RVNL
8.2.1.2 Method statements for track laying shall, as a minimum, cover the
following items, where ever applicable:
(a) shipping
(b) handling & transport
(c) stacking
(d) pre-assembly/assembly
(e) delivery
(f) surveying
(g) setting out
(h) assembly
(i) ballasting
(j) track installation
(k) welding
(l) tamping
(m) lining & levelling
(n) stabilisation
(o) as-constructed records
(p) cleaning
(q) final fastening down
_________________________________________________________________________________
Volume I – Part A - Track Page 30 of 112
Specifications RVNL
8.3.1 General
8.3.1.1 The track gauge throughout except in sharp curves shall be 1673
mm measured between gauge faces, 14 mm below rail top
surfaces perpendicular to the centre line of the track.
8.3.1.2 In all main line & yard line track, (excluding turnouts, crossovers,
diamond crossings and derailing switches) rails shall be laid with -
1:20 inward rail slope.
8.3.1.3 The Contractor shall take due cognisance of his proposed rail
jointing system and the rail fastening assembly spacing in the
selection of the appropriate length of welded rail panels. Rails
shorter than the minimum length shall only be permitted in the
following locations:
8.3.1.4 The contractor shall lay the bridge approach sleepers with
appropriate sleeper of the correct RDSO number and at specified
spacings. If this is not done, the flaring end of the guard rails
cannot be fitted with specified fittings. In such an eventuality, the
Contractor should make his own arrangements for either locating
_________________________________________________________________________________
Volume I – Part A - Track Page 31 of 112
Specifications RVNL
8.3.2.1 All rail joints throughout in the main lines including turnouts except
at Glued Insulated Rail Joints, shall be welded, except where fish
plated joints are necessitated.
8.3.2.2 The welding of free rails of standard lengths into short welded rail
panels and long welded / continuously welded rail panels for main
lines and yard shall be by adoption of Flash Butt Welding process.
Alumino Thermic Welding of rail joints shall only be used in
exceptional circumstances, where Flash Butt Welding process
cannot be adopted, that too with prior approval of the Engineer.
Temporary joints between rails shall be by fish plates & clamps
without drilling of holes in rails.
8.3.2.3 All the welded joints for welding less than 13 m rail length shall
have prior approval of the Engineer.
8.3.5.3 All fish-plated joints shall be fitted with the nuts on the inside of the
track.
_________________________________________________________________________________
Volume I – Part A - Track Page 32 of 112
Specifications RVNL
8.3.6.1 All glued insulated rail joints shall be shop manufactured using
minimum 6 m long rails. Site fabricated glued insulated joints shall
be provided only with the prior approval of the Engineer.
8.3.6.2 Except in the case of glued insulated joints in the turnout zone, the
positioning of the glued insulated joint with respect to the approach
shall be such as to keep a minimum distance of 6.00 m from an
existing weld in the rail.
_________________________________________________________________________________
Volume I – Part A - Track Page 33 of 112
Specifications RVNL
8.3.11.1 Rails shall only be cut by using rail cutting machines. The
proposed method and equipment for the cutting of rails shall have
the prior approval of the Engineer. Gas cutting of rails is strictly
prohibited.
8.3.11.2 Rails required to be cut shall be cold sawn square and vertical
across the rail. A deviation from square or vertical of more than
0.50 mm, measured about the rail head, shall not be permitted. All
burrs shall be removed from the rail ends.
8.3.12.1 All fish bolt holes in rails, where ever required shall be drilled by
using proper jigs and drilling machines. The proposed method and
equipment for the drilling and cutting of rails shall have the prior
approval of Engineer.
8.3.12.2 Any holes required for signal and traction bonds shall be formed
with prior approval of the Engineer.
8.3.12.3 All holes in the rails shall be chamfered using chamfering kit &
procedure approved by the Engineer.
8.4.1 General
_________________________________________________________________________________
Volume I – Part A - Track Page 34 of 112
Specifications RVNL
8.4.1.2 The completed track shall have the following minimum ballast
cushion under the sleeper or bearer:
(a) Ballast cushion: (Measured from underside of sleeper to the
formation)
Main lines (under lower rail) As per Para 212 (2) (a) & (b) of
IRPWM.
Loop lines 250 mm
_________________________________________________________________________________
Volume I – Part A - Track Page 35 of 112
Specifications RVNL
8.4.2.6 The use of vehicles on the completed bottom ballast will result in
the rejection of the bottom ballast in that particular length where
the vehicle has been used. In such a length all contaminated
ballast should be removed and replaced with new ballast. Re-
grading and rolling of such line should be done to the satisfaction
of the Engineer. No further track laying operation shall be done
until the bottom ballast has been re-inspected and approved by the
Engineer.
8.4.3.1 General
_________________________________________________________________________________
Volume I – Part A - Track Page 36 of 112
Specifications RVNL
The system of track laying over the laid and compacted ballast
shall be as proposed by Contractor and approved by Engineer.
The following stipulations shall also be followed by the Contractor.
Flash butt welding shall not be undertaken until the track has
sufficient ballast to hold it to alignment both before and after
welding.
The track laying system shall be such that no wheeled vehicles
shall travel directly over the bottom ballast during the track laying
operation.
In case the top surface of the ballast gets disturbed, the same
shall be repaired/re-compacted to prescribed levels, to the
satisfaction of the Engineer.
The sleepers shall then be laid out on the bottom ballast at the
specified spacings. The sleepers shall be correctly aligned and
squared.
Alternatively, pre-assembled panels may be laid directly onto the
prepared bottom ballast for installation of track by utilisation of
PQRS or by any other method, which should have prior approval
of the Engineer.
Sleeper shoulder then shall be adequately ballasted and
compacted to obtain enough lateral resistance of track.
The rail panels shall then be laid on the sleepers and fastened to
the sleepers.
After a suitable length of track has been laid, but before any
movement of rail mounted Construction Plant or equipment on that
track, the laid sleepers shall be levelled and tamped by
mechanical means, approved by the Engineer, to ensure the final
lines and levels of the resulting track are within acceptable
tolerances as approved by Engineer. However the contractor shall
be responsible for safety of track after Engineer’s inspection &
approval and track components damaged due to running of rail
mounted construction plant and equipment or any other reason
shall be replaced by the contractor to the Engineer’s satisfaction
Track markers, bonding, etc. shall not be installed until the track is
aligned to final line and level, and the final fastening down
operation has been completed.
_________________________________________________________________________________
Volume I – Part A - Track Page 37 of 112
Specifications RVNL
8.4.4 Drainage
_________________________________________________________________________________
Volume I – Part A - Track Page 38 of 112
Specifications RVNL
8.5.1 General
The moveable length of a switch rail shall be securely strapped to
the stock rail during all handling and transportation. In any case,
before installation of switch the prevailing camber due to pre-
curving should be checked. If the switch or stock rail has lost
camber, pre-curving should be redone by cold bending with jim-
crow to the satisfaction of the Engineer.
Check rails shall be set and checked to the correct clearance by
using the running edge of the crossing as the datum.
The assembly sequence of turnouts, diamond crossings, derailing
switches and rail expansion joints shall be submitted for
Engineer’s Approval as part of the overall method statement for
pre-assembly, handling, storage, transportation, unloading and
installation.
On completion of a turnout, the Contractor shall immediately
scotch the switches with a purpose made hardwood timber scotch
and securely clamp the switches as directed by the Engineer with
an appropriate clamp as approved by the Engineer. The clamp
shall be capable of being padlocked with the switch in the closed
position.
No on-track Constructional Plant, equipment and machinery shall
be allowed to operate over a turnout until it has been inspected
and approved by the Engineer.
The contractor at this time shall interface and ensure the designed
switch opening while fixing the first stretcher bar.
All stretcher bars for switches shall be supplied and installed by
the Contractor and approved by the Engineer.
_________________________________________________________________________________
Volume I – Part A - Track Page 39 of 112
Specifications RVNL
8.5.1.2 Installation
8.6.2.1 The destressing of rails shall not be undertaken until it has been
demonstrated to the Engineer’s satisfaction that the track has been
completed to the specified standards and specifications and the
method of working for destressing of the relevant track form has
been approved by the Engineer.
8.6.2.3 The long welded rails shall be laid on rollers placed on the metal
base plates or sleeper or rail table, with the rollers placed at a
maximum spacing of 6 m. Rollers shall have suitable diameter to
avoid contact between rail and intermediate sleepers.
8.6.2.4 After placing the long welded rail on rollers, it shall be stress
relieved by causing it to vibrate simultaneously over its whole
length, either by use of vibrators distributed along the whole rail
length, and in sufficient number, or by tapping the rail on each side
of the head with wooden mallets as approved by Engineer.
_________________________________________________________________________________
Volume I – Part A - Track Page 40 of 112
Specifications RVNL
8.6.2.5 The switch expansion joint shall be carefully greased prior to fitting.
Destressing operations of LWR / CWR, should be done, following
the provisions of the latest LWR manual of Indian Railway
8.6.2.7 The stress free temperature for destressing of the long welded rail
shall be achieved either naturally or artificially by the use of
hydraulic rail tensors as approved by Engineer.
The installation details for buffers stops and dead ends shall be
submitted by contractor for Engineer’s approval.
8.7.3 Joints should be avoided in check rails and on the running rails
within the level crossings and a further 3 meters on either side. In
the case of SWR, the short welded panel may be continued
through the level crossing, avoiding fish plated joint on the level
_________________________________________________________________________________
Volume I – Part A - Track Page 41 of 112
Specifications RVNL
crossings and within 6 meters from the end of level crossing. The
level crossing should not fall within the breathing length of LWR as
per the provisions contained in LWR Manual.
8.7.4 Level crossings beyond the outermost stop signals of the station /
block hut shall be under the control of the Engineering Department
of Railways and shall be termed as Engineering Gates.
At all Gates which are unmanned, the contractor shall provide rail
posts in the new locations. At all manned gates, the contractor
shall shift the lifting barriers / gate leaves complete with associated
equipment like winches and locking arrangements to the new
locations and re-fix on new foundations.
8.7.6 All road signs and level crossing indicators shall be shifted by the
Contractor to appropriate locations as permanent markers as per
para 916 of IRPWM.
8.7.7 Rails and fastenings in contact with the road shall be thoroughly
cleaned with wire brush and a coat of anti-corrosive paint applied.
8.7.9 Flange way clearances, cross level, gauge and alignment should
be checked and corrected as necessary, fittings and fastenings
properly fixed and tightened and the track packed thoroughly
before laying the road surfacing or pavement between the gates.
_________________________________________________________________________________
Volume I – Part A - Track Page 42 of 112
Specifications RVNL
8.8.3 Guard rail should be provided on all girder bridges (including Pre-
stressed concrete girder bridges without deck slab) whether major
or minor. Guard rails should also be provided on all major and
important ballasted deck bridges and also on such other minor
bridges where derailment may cause serious damages.
On all flat top, arch and PRC girder bridges with deck slab, where
guard rails are not provided, the whole width of the bridge between
the parapet walls shall be filled with ballast up to the top of sleeper
level.
8.8.5
i. The typical arrangement showing important dimensions for fixing
guard rails is shown in the sketch and table below para 228(2) of
IRPWM. The same should be followed.
ii. The guard rails should be splayed; ends of guard rails should be
bent vertically and buried; and a block of timber fixed at the end.
Fixing of guard rails to the sleepers shall be as shown in RDSO
plans for steel channel sleepers (for steel girder bridges) and PSC
sleepers (for ballasted deck bridges and all bridge approaches).
iii. The top table of the guard rail should not be lower than that of the
running rail by more than 25 mm. In the case of bridges on curves
with super-elevated track, the difference should be measured with
reference to a straight line connecting the running tables of inner
and outer rails.
8.8.6 General
_________________________________________________________________________________
Volume I – Part A - Track Page 43 of 112
Specifications RVNL
8.9.1 General
8.9.1.2 The welding process shall be suitable for 60 Kg. rail sections to
880 Grade of IRST-12-2009 Specification. Welding process should
also be suitable for 52 kg section of 710 grade of IRS T 12-2009
Specification.
8.9.1.4 Arrangements shall be made to have test welds and their testing
for proving the flash butt welding technique use and the alumino-
thermic weld process used and also the competence of the
welders deployed for welding work.
8.9.1.6 All welds shall be indelibly marked with an individual number that
clearly identifies the welder and the weld. This weld number shall
be painted on the rail web. The number, once painted on the rail,
shall be maintained until taking over the works. The weld
identification shall contain a maximum of five characters.
8.9.2.1 General
The Flash Butt Welding of rail joints shall be undertaken in
accordance with the relevant Indian Railway Manual for Flash Butt
Welding of rail mentioned in Clause 2.1.2 (7) and further
supplemented below.
Rails with ends which are outside the required end straightness
tolerance shall not be welded; the rail end can be cut to bring it to
within the specified tolerances or the rail shall be removed from
the site. Rail ends that are out of tolerance for straightness after
welding may be straightened by the use of a purpose made rail
end straightener approved by Engineer which does not cause
damage /indentation to the rails, alternatively the executed weld
may be cut and re-welded.
The Contractor shall make arrangement for the measurement of
residual stresses on the test welds on both side of rail and weld.
_________________________________________________________________________________
Volume I – Part A - Track Page 45 of 112
Specifications RVNL
8.9.3.1 General
8.10.1 General
_________________________________________________________________________________
Volume I – Part A - Track Page 46 of 112
Specifications RVNL
_________________________________________________________________________________
Volume I – Part A - Track Page 47 of 112
Specifications RVNL
8.13 Dismantling
8.13.1 Scope:
_________________________________________________________________________________
Volume I – Part A - Track Page 48 of 112
Specifications RVNL
8.13.3
a. A foot by foot inspection of the proposed portion to be dismantled
shall be carried out jointly by the representatives of the contractor,
Railway and Engineer and a record of inventory of existing
materials should be made.
8.13.4
a. The released rail panels (if any) shall be cut into lengths of 11m to
13m by using gas cut/flame. The rails shall be cut in plumb without
any structural damage. The length of each rail shall be measured
and written at the end of rail in white paint.
_________________________________________________________________________________
Volume I – Part A - Track Page 49 of 112
Specifications RVNL
d. Each rail end should be marked with the length in metres to two
decimal places, in white on black painted back ground on the web.
e. For each lot of stacked rails, there shall be a board of steel plate of
20 cm x 20 cm with welded angle of 50 x 5 mm and height of 90
cm above ground level and encased in concrete foundation. This
display board shall indicate lot no., type of rail, total number of rails
and total length.
8.14.1 General
The track parameters of completed track work, shall be measured
by the Contractor in the presence of Engineer and the
measurement recorded shall be in a format approved by the
Engineer and submitted both in hard and electronic copy.
The variations in horizontal alignment, vertical alignment versines,
cross level/cant, twist and gauge shall not exhibit cyclic patterns.
All the track parameter measurements shall be taken in the
unloaded condition of the track.
For no individual component / manufactured item / assembly
tolerances shall be allowed to exceed the specified completed
track tolerances limit.
_________________________________________________________________________________
Volume I – Part A - Track Page 50 of 112
Specifications RVNL
Track tolerances shall comply with the limits as laid down in para
2.3.2 and as below:-
Tolerances
Curves Twist on transition portion of 0.5 mm / m
curve(over designed value)
Turn-outs Stock rail joint (longitudinal location) + 15 mm
Nose to Nose of crossing in + 10 mm
crossovers
Flange-way clearance at the of the + 5mm/ -0
switch planning mm
Switch toe opening + 1mm / -0
mm
Switch toe squareness 5 mm
Deviation of measured versine over + 1mm
its designed value for switches, lead
track and curved crossing (measured
on 6 meter half overlapping chord)
Switch (i) Gauge + 1mm
Expansion
Joint
(ii) Gap at opening + 2mm
(iii) Out of squareness of switch rails + 2mm
Packing of Sleepers should not be loose (when Max. 10 %
sleepers checked by a canne-a-boule) Sleepers
8.14.3.1 The completed track geometry shall be measured for the following
track parameters as a minimum.
(a) Gauge
(b) Horizontal Alignment (Versine) of minimum one rail
(c) Cross Level/Cant
(d) Twist
(e) Vertical unevenness (Right hand rail)
(f) Vertical unevenness (Left hand rail)
8.14.3.2 The proforma for the measurement of track parameter submitted by
contractor for Engineer’s approval shall consist of the following as
a minimum:
a) A common base point for recording of location
b) Cross level/cant
c) Gauge
_________________________________________________________________________________
Volume I – Part A - Track Page 51 of 112
Specifications RVNL
The proforma shall show the design figure, actual figure and the
difference between design and actual and shall allow columns for
marking of twist.
8.14.3.4 The as-built recordings of rail level and horizontal alignment along
longitudinal direction with respect to the designed level and
alignment shall be obtained by the use of appropriate electronic
survey instruments as directed by the Engineer. Horizontal location
readings shall be presented as co-ordinates. Deviation from
designed co-ordinates shall also be shown.
8.14.3.5 The vertical and horizontal rail location readings shall be taken at
coincidental kilometrages.
8.15.1 It shall be ensured that all track laying confirms to the prescribed
standards.
8.15.2 A track laying register shall be maintained at site by the contractor.
In this register he shall arrange concurrent recording of relevant
data including the approved longitudinal section, programme of
work, requirement and availability of materials, position and
performance of tools, equipment, track machines, daily labour
position and output, position and the condition of the finished track
both structural as well as geometrical.
_________________________________________________________________________________
Volume I – Part A - Track Page 52 of 112
Specifications RVNL
9.1 GENERAL
9.2.1 The tests and inspections have been divided into categories as
defined in the following clauses. The tests listed below are not
comprehensive and shall be revised to include all identified
Specification tests by the Contractor.
_________________________________________________________________________________
Volume I – Part A - Track Page 54 of 112
Specifications RVNL
10 MATERIAL TESTS
1. In addition to the requirements of the present Specification, all
materials shall be tested in accordance with all specifically listed
Codes and Standards and any Code, Standard or procedure
submitted by the Contractor and Approved by Engineer.
2. The Contractor shall submit the test and inspection proforma for
approval of the Engineer for any test or inspection.
10.1.1 Rail
10.1.2 ERC MK III, GFN Liner, SGCI insert and Grooved Rubber sole
plate
_________________________________________________________________________________
Volume I – Part A - Track Page 55 of 112
Specifications RVNL
ERC MK III, GFN Liner and grooved rubber sole plate rail pad for
ballasted track on PSC sleeper shall be inspected and tested in
accordance with the relevant technical specification of Indian
Railways as mentioned in clause 2.1.2 (7)
10.1.5 Welding
10.1.5.1 General
1) All Welds done by adoption of Flash Butt or Alumino Thermic
process shall be tested ultrasonically as per relevant Manual for
Ultrasonic testing of rails and welds as mentioned in clause 2.1.2
(7).
2) All the defective welds whether identified as a result of USFD
testing or otherwise shall be removed from the track and re-welded
by the contractor. The cost of re-welding of the defective / rejected
welds and that of associated rail length including cutting of rails,
adjustments and all related works shall be borne by the contractor.
_________________________________________________________________________________
Volume I – Part A - Track Page 56 of 112
Specifications RVNL
The buffer stops Dead ends and sand humps shall be inspected
for their completeness as per approved drawings.
10.2.1 General
a. As soon as the work in one or more block sections is completed
and inspected as aforesaid, the same shall be connected to the
existing system at one or both ends as a siding with prior sanction
of the C.R.S either through a connection to be retained
permanently or a temporary connection as a phase to be removed
subsequently. On the specific requirement of the Contractor, the
Engineer shall arrange to obtain approvals to the proposed plan
and sanction of the C.R.S through the Railways. The Contractor on
receipt of the advice of receipt sanctions should arrange to provide
the connection as per approved plan to the satisfaction of the
Engineer observing the railway rules in this regard. The completed
track as aforesaid shall then be rolled, repacked and tested by
_________________________________________________________________________________
Volume I – Part A - Track Page 58 of 112
Specifications RVNL
10.2.2 Submissions
_________________________________________________________________________________
Volume I – Part A - Track Page 61 of 112
Specifications RVNL
1 SCOPE
These specifications will be applicable for stone ballast to be used
for all types of sleepers on normal track, turnouts, tunnels and
deck slabs etc. on all routes.
2 DETAILED SPECIFICATIONS
2.1 GENERAL
2.2.2 The “Water Absorption” tested as per IS: 2386 Pt-III 1963 following
the procedure given in Annexure 3 should not be more than 1%.
i) The Screen for sieving the ballast shall be of square mesh and
shall not be less than 100 cm in length 70 cm in breadth and 10
cm in height on sides. The following tolerances in the size of holes
for 65 mm and 20 mm sieve shall be permitted.
_________________________________________________________________________________
Volume I – Part A - Track Page 63 of 112
Specifications RVNL
ii) While carrying out sieve analysis, the screen shall not be kept
inclined, but held horizontally and shaken vigorously. The pieces
of ballast retained on the screen can be turned with hand to see if
they pass through but should not be pushed through the sieve.
3 Deleted
4 METHOD OF MEASUREMENT
Stacking shall be done on a neat, plain and firm ground with good
drainage. The height of stack shall not be less than 1 m except in
hilly areas where it may be 0.5m. Top width of stack shall not be
less than 1.0 m. Top of stack shall be kept parallel to the ground
plane. The side slopes of stack should not be flatter than 1.5:1
(Horizontal: Vertical). Cubical content of each stack shall normally
be not less than 30 cum in plain areas and 15 cum in hilly areas.
_________________________________________________________________________________
Volume I – Part A - Track Page 64 of 112
Specifications RVNL
5.2 The tests viz., determination of Abrasion Value, Impact Value and
Water Absorption should be got done through approved
laboratories or contractor’s own laboratory in the presence of the
Engineer.
5.3.1 On supply of the first 100 cum, the tests for size, gradation,
Abrasion value, Impact value and water absorption (if prescribed)
shall be carried out by the Contractor in the presence of the
Engineer. Further supply shall be accepted only after this ballast
satisfies the specifications for these tests.
Supply in stacks
For stack of For stack of Supply in
volume less volume more wagons
than 100 cum than 100 cum
a) Size and Gradation
Tests.
- No. of Tests One for each One for each One for each
stack stack. wagon
- Size of one sample * 0.027 cum 0.027 cum for 0.027 cum
every 100
cum or part
thereof
b) Abrasion Value
Impact Value and
One test every 2000 cum
Water Absorption test
@ Testing Frequency
_________________________________________________________________________________
Volume I – Part A - Track Page 65 of 112
Specifications RVNL
5.5.3 All tests for Abrasion value, Impact value and water absorption
shall be done at the cost of the contractor.
_________________________________________________________________________________
Volume I – Part A - Track Page 66 of 112
Specifications RVNL
1. Apparatus
1.1 The abrasion test for track ballast shall be carried out using Los-Angeles
machine.
1.2 The abrasive charge shall consist of 12 nos. cast iron or steel spheres
approx. 48 mm dia and each weighing between 390 and 445
ensuring total weight of charge as 5,000 25 gm.
1.3 IS sieves of sizes 50 mm, 40mm, 25 mm and 1.70 mm.
1.4 Drying Oven
2. Test Sample
2.1 The test sample of 10,000 gm shall consist of clean ballast conforming to
the following grading.
2.2 The sample shall be dried in oven at 100-110 0C to a constant weight and
weighted (Weight ‘A’).
3. Test Procedure
The test sample and the abrasive charge shall be placed in the Los-
Angeles abrasion testing machine and the machine rotated at a
speed of 20–33 revolutions/minute for 1000 revolutions. At the
completion of test the material shall be discharged and sieved
through 1.70 mm IS sieve.
4.2 The proportion of loss between Weight ‘A” and Weight ‘B” of the test
sample shall be expressed as a percentage of the original weight of
the test sample. This value shall be reported as
( A−B)
Aggregate AbraisonValue = x 100 %
A
_________________________________________________________________________________
Volume I – Part A - Track Page 67 of 112
Specifications RVNL
1. Apparatus
2. Test Sample
2.1 The test sample shall be prepared out of track ballast so as to conform to
following grading.
2.2 The sample shall be oven dried for 4 Hours at a temperature of 100-
1100C and cooled.
2.3 The measure shall be filled about one-third full with the prepared
aggregate and tamped with 25 strokes of the tamping rod. A further
similar quantity of aggregate shall be added and a further tamping of 25
strokes given. The measure shall finally be filled to overflowing, tamped
25 times and the surplus aggregate struck off, using a tamping rod as a
straight edge. The net weight of the aggregate in the measure shall be
determined to the nearest gm. (weight ‘A’).
3. Test Procedure
3.1 The cup of impact testing machine shall be fixed firmly in the position on
the base of the machine and the whole of the test sample placed in it and
compacted by 25 strokes of the tamping rod.
3.2 The hammer shall be raised 380 mm above the upper surface of the
aggregate in the cup and allowed to fall freely on to the aggregate. The
test sample shall be subjected to a total of 15 such blows each being
delivered at an interval of not less than one second.
_________________________________________________________________________________
Volume I – Part A - Track Page 68 of 112
Specifications RVNL
4.1 The sample shall be removed and sieved through 2.36 mm IS sieve. The
fraction passing through shall be weighed (Weight “B”). The fraction
retained on the sieve shall also be weighed (Weight ‘ C ’) and if the total
weight ( B + C ) is less than the initial weight ( weight “A” ) by more than
one gm, the result shall be discarded and a fresh test made.
4.2 The ratio of the weight of the fines formed to the total sample weight shall
be expressed as a percentage.
B
Aggregate Impact Value= x 100
A
4.1 Two such tests shall be carried out and the mean of the results shall be
reported to the nearest whole number as the Aggregate Impact Value of
the tested material.
_________________________________________________________________________________
Volume I – Part A - Track Page 69 of 112
Specifications RVNL
WATER ABSORPTION
(Based on IS 2386 Part III –1963)
1. Apparatus
2. Test Sample
3. Test procedure
3.1 The sample shall be thoroughly washed to remove finer particle and dust,
drained and then placed in the wire basket and immersed in distilled
water at a temperature between 22-32 0C.
3.2 After immersion the entrapped air shall be removed by lifting the basket
and allowing it to drop 25 times in 25 seconds. The basket and sample
shall remain immersed for a period of 24 ½ hours afterwards.
3.3 The basket and aggregate shall then be removed from the water, allowed
to drain for few minutes, after which the aggregate shall be gently
emptied from the basket on to one of dry clothes and gently surface dried
with the cloth transferring it to second dry cloth when the first will remove
no further moisture. The stone aggregate shall be spread on the second
cloth and exposed to atmosphere (away from direct sunlight) until it
appears to be completely surface dry. The aggregate then shall be
weighed (weight ‘A”).
( A−B)
Water Absorption= x 100
A
_________________________________________________________________________________
Volume I – Part A - Track Page 70 of 112
Specifications RVNL
Two such tests shall be made and individual and mean results shall be reported.
_________________________________________________________________________________
Volume I – Part A - Track Page 71 of 112
Specifications RVNL
This specification is issued under the fixed serial No.T-19. This was originally
adopted in 1961 and was revised in 1965, 1984 and 1994. Since then, number
of amendments have been made in this specification on account of
technological improvements in the AT welding process. Besides this, R&D work
was undertaken on upgraded AT welding technology. This fourth revision
includes current technological improvements in the AT Welding process and
additional provisions for implementation of upgraded AT welding technology with
superior weld performance on Indian Railways.
1. INTRODUCTION
1.2 The quantity of the ‘MIXTURE’ required for welding one rail joint shall be
called a ‘portion‘.
1.5 Except for welds executed for laboratory evaluation and acceptance test,
all welds shall be executed under the supervision of personal possessing
valid competency certificate From RDSO or from Termit Portion Plant,
Northern Railway, Lucknow or Thermit Welding Centre, (TWC), South-
Central Railway, Vijayawada.
2. SCOPE
3.1 The portion shall be submitted for acceptance batch wise. A batch shall
consist of 300 portions or part thereof manufactured from similarly and
simultaneously treated raw materials.
_________________________________________________________________________________
Volume I – Part A - Track Page 73 of 112
Specifications RVNL
Batch numbering shall be given year wise in a six digit code, whose first
two digits will indicate two digits of the year of manufacture and the
balance 4 digits, the serial number of the batch. The batch number at the
beginning of each year shall therefore, commence from 0001.
3.2 Every portion shall be packed in a moisture proof bag of polythene to IS:
9738, “Indian Standard Specification for Polyethylene bags for general
purposes“ Grade HM HDPE of 150 micron thickness which should be
sealed so as to make it air tight. The Polyethylene bag should then be
packed in a heavy duty bag made of New cloth to IS: 187.The open end
of the cloth bag shall be stitched and sealed in such a manner that there
is no access to the ‘portion’ without damaging the bag or breaking its
seal.
3.4 The insignia of the firm and rail type should be printed on the exterior of
the cloth bag as per the under mentioned, colour scheme:
3.5 Till the portions with manual tapping system are being supplied, such
portions shall be marked with Bold Letter “M” on the bag in same colour as
used for marking the Rail Section. The letter size indicating Rail section &
Tapping System shall be of minimum 150 mm high. The marking on Bags
will be done on both the faces as per following example :
_________________________________________________________________________________
Volume I – Part A - Track Page 74 of 112
Specifications RVNL
4. ACCEPTANCE TEST:
Two portion shall be randomly selected per batch and weight of each portion
shall be within + 0.25% of the approved weight of the portion which shall be
recorded by the inspector.
One portion shall be utilized for execution of test weld as per approved
parameters for AT Welding technique. While executing the test joint,
characteristics of the alumino-thermic reaction, i.e. whether it is quiet, normal
or boiling shall be observed and if the reaction is found to be boiling, the
batch shall be rejected. The reaction and tapping shall be within 20+ 3
seconds for manual tapping. In case of A.T. welding technique with Auto
tapping thimble/ One shot crucible, the reaction and tapping time shall
conform to the tapping time range approved for the particular AT welding
technique, as indicated in approval certificate and QAP of Firm. Following
tests shall be conducted for assessing the quality of portion:
i. Ultrasonic test on test weld as per Annexure-1.
ii. Checking of weld metal dimensions of test weld with approved weld metal
dimensions of that particular AT Welding technique.
iii. Mechanical and metallurgical test as per Para 4.2.
iv. Weld metal chemistry test as per Para 4.1.
_________________________________________________________________________________
Volume I – Part A - Track Page 75 of 112
Specifications RVNL
4.2.1 Two new rail pieces of same section and grade, each approximately 750mm
long, shall be used to make test weld joint. The welded joint shall be made
as per the technique offered by the manufacturer. The rail table and sides of
rail head shall be finished to the geometrical tolerances specified in Clause
18.1.
Table – 1 A
Note:
i) For 25 mm gap SKV welding & for any preheating device used ( Air-
petrol / Compressed Air Petrol / Oxy – LPG )
X = 40 mm
Y = 100 mm
ii) For 50 mm gap combination joint welding & for any preheating device
used.
_________________________________________________________________________________
Volume I – Part A - Track Page 76 of 112
Specifications RVNL
X = 60 mm
Y = 120 mm
iii) For 75 mm wide gap welding & for any preheating device used.
X = 80 mm
Y = 150 mm
Table 1 B
Hardness BHN
Weld
Sr.No. Rail Section / Chemistry
Metal Heat affected zone (H)
(W)
1 72 UTS rail of all sections 229 ± 20 of actual parent
with normal & wide gap + 20 metal hardness (location
-0 ‘P’)
2 90 UTS rail of all sections 265 ± 20 of actual parent
with normal & wide gap. + 30 metal hardness (location
-0 ‘P’)
3 52 kg (90 UTS) Vs 90 R (72 265 ± 20 of actual parent
UTS) combination joint with + 30 metal hardness (location
50 mm gap. -0 ‘P’)
4 60 kg (90 UTS) Vs 52 kg (90 265 ± 20 of actual parent
UTS) combination joints with + 30 metal hardness (location
50 mm gap. -0 ‘P’)
5 60 Kg H.H. rail Not less than [actual
321 (min) parent metal hardness
(Location ‘P’) – 100] BHN
6 UIC Cr-Mn or Cr-V alloy 311 ± 20 of actual parent
steel rail + 20 metal hardness (Location
-0 ‘P’)
7 60Kg/ 110 UTS 320 ± 20 of actual parent
+20 metal hardness (Location
-0 ‘P’)
8 60Kg/ 90UTS/ NCC rail 265 ± 20 of actual parent
+30 metal hardness (Location
-0 ‘P’)
9 60Kg/ 90UTS/ Cu-Mo rail 265 ± 20 of actual parent
+30 metal hardness (Location
-0 ‘P’)
_________________________________________________________________________________
Volume I – Part A - Track Page 77 of 112
Specifications RVNL
The test weld shall withstand a minimum load and show corresponding
minimum deflection as stipulated in column 4 of Table – 2 for different
sections and types of rails. The deflection at centre at the actual transverse
breaking load shall not be less than that specified in column 5 of Table-2.
Table - 2
Min deflection
in mm at the
Min
center at the
S. transverse
Rail Type Rail Section actual
No. breaking load
transverse
in tones
breaking load
in col.4
1 2 3 4 5
A 75 UTS to IRS T- 60 R 50 15
12 for normal gap 75 R 55 15
welding & wide 90 R 65 15
gap (75 mm) 52 Kg 85 18
welding. 60 Kg 95 18
B 90 UTS to IRS T – 75 R 60 15
12/UIC 860-0 or 90 R 80 15
equivalent for 52 Kg 90 15
normal & wide gap 60 Kg 115 15
(75 mm) welding.
Min deflection
in mm at the
Min
center at the
S. transverse
Rail Type Rail Section actual
No. breaking load
transverse
in tones
breaking load
in col.4
1 2 3 4 5
Head Hardened
E Rails to IRS T 12 60 Kg 115 12
for normal gap
welding.
F 90UTS/ NCC rail to
IRST-12 for normal
60 Kg 115 15
& wide gap (75mm)
welding
G 90UTS/ Cu-Mo rail
to IRST-12 for
60 Kg 115 15
normal & wide gap
(75mm) welding
4.2.3.2. If the fracture does not occur through weld, a slice shall be cut
transversely at the weld and etched in boiling 1:1 Hydrochloric acid
for about 20 minutes to determine casting defects, if any.
_________________________________________________________________________________
Volume I – Part A - Track Page 79 of 112
Specifications RVNL
It the results of any of the tests referred to in clause 4.1 and 4.2 are found
to be unsatisfactory, the batch will stand rejected.
Any other process proposed to be adopted by the firm for disposal of the
rejected batch, shall have prior approval of RDSO.
6 ACCEPTANCE:
6.1. Acceptance shall be done batch wise. Every individual batch that satisfies
the conditions prescribed in this specification shall be accepted. Each
bag containing the portion shall be sealed by the manufacturers and the
container shall be suitably stamped / sealed by the Inspecting Officer.
The stamp / seal shall be such that it shall not be possible to open the
container without breaking stamp / seal.
6.2. The manufacturer shall dispatch the accepted portions immediately to the
consignee so as to reach consignee within 30 days from the date of issue
of inspection certificate.
8 TESTING FACILITIES:
The manufacturer shall, at his own expenses, supply all labour, materials,
consumables, rail pieces and appliances for testing both for initial tests
and retests as may be carried out in presence of the Inspecting Officer, in
his own premises or at any other acceptable place in accordance with
this specification.
The purchaser or the Inspecting Officer shall have free access to the
premises of the manufacturer at all reasonable times. They shall be at
_________________________________________________________________________________
Volume I – Part A - Track Page 80 of 112
Specifications RVNL
liberty to inspect all the records and the manufacture of ‘portions‘ at any
stage.
11. For the purpose of approval, the following definitions shall apply:
13.2 The weld samples shall be tested in a recognized laboratory / test center
for which prior approval of RDSO shall be necessary.
_________________________________________________________________________________
Volume I – Part A - Track Page 81 of 112
Specifications RVNL
13.3 Following scheme shall be followed for fatigue testing of thermit welded
rail joints :
ii) The weld sample shall be made with one meter long new rail
pieces to have an overall length of 2.0 m. The rail and joint shall
be ultrasonically tested.
13.4 Retest :
If the results of Fatigue test referred to in clause 13.3 fail to meet the
requirements of the fatigue test, the technique shall be rejected. The
technique can be reoffered by the firm as per provisions of ‘General
guidelines for vendor approval’ (latest version) issued by Track Design
Directorate.
14.1 Subject to the results of the tests in clause 12 and 13 being satisfactory,
service trials for a period of one year or till passage of 10 GMT traffic over
the joint, whichever is earlier, shall be undertaken on 50 to 100 trial joints
welded using the above batch of portion. For the purpose of field trials, an
order shall be placed by the nominated zonal Railway on the
manufacturer for supply of portions as well as welding of trial joints. The
trial joints shall be distinctly marked by painting letter “T” on the web of
the rail beyond 300 mm from the joints. During execution of trial welding
at site spoilt joints, if any, shall be cut and re-welded by the contractor at
his own expense.
14.2 All the trial joints shall be ultrasonically tested soon after welding as per
procedure at Annexure – 1. Up to a maximum of 2% defective welds,
shall be cut and re-welded by the manufacturer at his own expenses. If
more than 2% joints are found defective, the trial shall be discontinued
_________________________________________________________________________________
Volume I – Part A - Track Page 82 of 112
Specifications RVNL
14.3 Failure of more than 2% joints during service trial will render the
technique unacceptable.
15. The approving authority shall have free access to the premises of the
portion manufacturer at all reasonable times. The Portions Manufacturer
shall furnish all the technical data to the approving authority as and when
called for.
16.1 For the purpose of approval, the following definitions shall apply :
“Welder” shall mean an individual with adequate skill and competence for
executing Alumino Thermic welding of rail joints at site.
16.2. Competency certificates for welding supervisors and welders of the zonal
railways shall be issued by the Thermit portion Plant of Northern Railway
at Lucknow or Thermit Welding Centre, (TWC), South-Central Railway at
Vijayawada. Competency Certificates for welding supervisors and welders
of firms shall be issued by D.G. (M & C) R.D.S.O, Lucknow.
16.3. Test weld joints will be made using any rail section at the discretion of the
approving authority. Welding supervisors / welders found competent shall
be deemed to be fit for A. T. welding of all rail sections for the particular
category as per clause 16.1. For execution of test weld joints, the welding
supervisors / welder desires of obtaining approval shall have to utilize his
_________________________________________________________________________________
Volume I – Part A - Track Page 83 of 112
Specifications RVNL
16.4. The firm shall pay, in advance, charge for certification of supervisors /
welders as per the rates decided by RDSO for this purpose. Payment
should be made through demand draft drawn in favour of Director
(Finance), RDSO, Manak Nagar, Lucknow 226011.
16.5. Six test welds shall be made by the welding supervisors / welders and his
team for the particular category of welding technique (as per Clause 16.1)
for which approval is sought. Following tests shall be carried out at the
sponsoring firm’s works premises or at RDSO, LUCKNOW.
16.6.1 For the purpose of reassessment, the welding supervisor / welder shall
submit, to the approving authority, the following details duly
countersigned by the concerned Assistant Engineer of zonal Railway.
a. A record of joints welded / supervised by him.
b. No. of joints failed in service.
_________________________________________________________________________________
Volume I – Part A - Track Page 84 of 112
Specifications RVNL
16.6.2 Based on the above details and personal interview, the approving
authority will issue competency certificate. Fresh competency certificate
will have to be issued whenever there is a change in the process of
welding or when a person who has been earlier trained and issued with a
final competency certificate has not been executing welding for a period
of more than 2 years or the work done by him has been rated as
unsatisfactory.
16.6.4 Following methodology shall be used for issuing the Identification Code
Number for welders /supervisors of Railway or firm:
a. Certificate number for welder/supervisors of Zonal Railway
The format for the certificate number of the welder/supervisor of the Zonal
Railway shall be as follows:
A A B B B C C C
A A B B B C
where,
A A
It is Code number for the agency to which the welder/supervisor belongs i.e.
00 for AT portion manufacturing firms
01 for departmental welders
02-99 for welders of welding contractors. The codes shall be allotted for
different contractual agencies undertaking AT welding of rails (other than
portion manufacturers)
B B B
Specific person number (from 001 to 999) The specific person number will
be continuous for a Zonal Railway/Firm.
c. For para 16.6.4 (a) i.e. for welders/supervisors of Zonal Railways: First
two/three initials of the Railway to which the supervisor or welder belongs.
_________________________________________________________________________________
Volume I – Part A - Track Page 85 of 112
Specifications RVNL
Or
For para 16.6.4 (b) i.e. for welders/supervisors of portion manufacturing firms
and welding contractors: Code allotted for the portion manufacturing firms,
for whom welders/ supervisors of portion manufacturing firms and welding
contractors are approved.
Alphabetic codes allotted to the portion manufacturing firms are given below:
In case of welders belonging to the welding contractors, this code will signify
the portion manufacturing firm for which the competency certificate of welder
is valid.
17.1 Alumino-thermic welding of rails shall be executed at site only under the
direct supervision of welding supervisor and by welder, both having valid
competency certificate issued by RDSO / TPP, Lucknow / TWC
Vijayawada (see Part ‘C’)
17.2 All Alumino-thermic welding work shall be executed with the use of weld
Trimmer and Profile Grinder. Additionally, rail tensors shall be used
wherever work is done on welded rails.
Note: In case of welding of old rails dispensations for not using weld
trimmers and profile grinder shall be obtained from Chief Engineer.
All the welded joints shall be cleaned and examined carefully to detect any
visible defect like cracks, blow holes, shrinkage, mismatch, surface finish
(smooth surface finish required) etc. Any joint which shows visible defect
shall be declared defective.
_________________________________________________________________________________
Volume I – Part A - Track Page 86 of 112
Specifications RVNL
The bottom of the joint shall be checked by feeling with fingers as well as
inspected with the help of a mirror for presence of `fins` at the parting line of
the mould. If fin is observed in any joint, the joint shall be declared defective.”
All the finished welded joints shall be checked and ensure that the joint
geometry is within the following tolerances:-
Note: Dispensation for joint geometry, in case of old rails may be permitted by
Chief Engineer. The details of geometry of each joint shall be jointly signed by
the firm’s and railway’s representative and kept as a record. Any joint found not
conforming to the above stipulations shall be cut and re-welded, free of cost, by
the firm.
All the joints shall be ultrasonically tested by the Railways as per the
procedure given at Annexure –1.
Where one bad joint is required to be replaced by the new joints, the
entire cost of both the joints shall be borne by the firm. Such re-welded
joints shall also be tested ultrasonically and if found defective, shall again
be cut and re-welded free of cost. However, cumulative number of AT
welds defective in ultrasonic testing and in other criteria shall be limited to as
per clause 19.1.
iv. All defective joints shall be broken with the help of Jim crow in presence of
firm’s representative and a joint report be prepared. Defects observed on
fractured faces shall be recorded in form of photograph/ sketch.
v. Sectional DEN/Sr. DEN shall carry out investigation/analysis for all in track
fractured joints and joints broken as per iv) above. Information shall be
compiled in the format indicated below:
_________________________________________________________________________________
Volume I – Part A - Track Page 88 of 112
Specifications RVNL
18.4.1 In the event of the failure of sample test joint in any of the
requirements of this specification, the Railway will be at liberty to suspend
further welding. However, two more randomly selected joints from the
same lot of 100 joints shall be subjected to retests as per clause 4.2.
Both the joints should clear all the tests. IF the report is also not
satisfactory, further welding of joints shall be suspended until the firm has
examined the welding technique and satisfies the requirements of Clause
4 by welding one test joint. The clearance for recommend of welding shall
be given by RDSO.
19. GUARANTEE
19.1 Rail joints welded by a firm shall be guaranteed against failure which
includes failures in execution, acceptance, acceptance & regular ultrasonic
testing and during service up to 2 years from the date of welding the joints in
track or from the date such welded joints made ‘in cess’ and inserted in the
track are open to traffic. Any such welded joints which fail in the criteria given
above within the guarantee period shall be re-welded free of cost by firm as
per stipulations of clause 18.3.
19.2 In case of failure of sample test joints (refer Clause 18.4), the period of
guarantee for 100 joints represented by the sample joint shall be
extended for a further period of one year. In case of failure of joints or
joints exhibiting signs of failure by cracking within extended period of
guarantee, the joints shall be re-welded free of cost by the supplier as per
stipulations of Clause 18.3.
19.3 The welded joints with the extended period of guarantee shall be marked
‘X’ with yellow paint on the outer side of the web of the rail near the joint
in addition to the markings prescribed in Clause 20. Such marked joints
shall be kept under careful observation by the purchaser.
20. MARKING:
Each joint shall have a distinctive mark indicating month, year of welding,
agency and welder/supervisor identification code number (as appearing
on the competency certificate) at non-gauge face side of AT weld on
head as give below:
M M Y Y
Month Last two digits of the year
A A B B B C C C
Identification Code
where,
A A
Code number for the agency to which the welder/supervisor belongs i.e.
00 for AT portion manufacturing firms
01 for departmental welders
02-99 for welders of welding contractors. The codes shall be allotted for
different contractual agencies undertaking AT welding of rails (other than
portion manufacturers)
B B B
– Specific person number (from 001 to 999) The specific person number will
be continuous for a Zonal Railway/Firm.
or
_________________________________________________________________________________
Volume I – Part A - Track Page 90 of 112
Specifications RVNL
Alphabetic codes allotted to the portion manufacturing firms are given below:
In case of welders belonging to the welding contractors, this code will signify
the portion manufacturing firm for which the competency certificate of welder
is valid.
The approving authority can delete the name of any portion Manufacturer /
Welding Supervisor / Welder from the approved list based on complaints
regarding the performance.
2.1 EQUIPMENT:
_________________________________________________________________________________
Volume I – Part A - Track Page 91 of 112
Specifications RVNL
2.2 PROBES:
The following probes having Lead zincronate- titanate crystal shall be used
for Ultrasonic testing of Alumino-thermic joints.
a. Normal ( 0° ) 2 MHz, 18 mm. φ Double crystal.
b. 70°/2 MHz, 20mm.dia. or 20mm.x20 mm. ( square )crystal size, Single
crystal - 1 no.
c. 45°/ 2 MHz, 20mm.dia. or 20mm.x20 mm.( square ) crystal size, Single
crystal – 2 no.
2.3 CABLES:
Co-axial cable for each probe shall be used .The length shall not be more
than 2.0 meter.
2.4 COUPLANT:
Soft grease to RDSO Specification No.WD-17-MISC.-92 or WD-24 Misc.-
2004/ any thick oil of high viscosity grade (having viscosity grade of 150 cst
or more) is to be used as couplant while undertaking hand probing of AT
welds. The list of approved vendors for soft grease to above mentioned
specification is issued by Quality Assurance (Mechanical) Directorate of
RDSO bi-annually. The same is available on website of RDSO
www.rdso.indianrailways.gov.in.
_________________________________________________________________________________
Volume I – Part A - Track Page 92 of 112
Specifications RVNL
The sensitivity of the ultrasonic equipment shall be set with the help of a
standard AT welded rail piece of 600 mm (300 mm rail each side of joint)
length having a simulated flaw at standard locations as shown in Fig. 1.
5.1 CALIBRATION:
Following procedure shall be adopted for calibration of 00 2 MHz double
crystal probe:
i. Select range 300 mm with range control key.
ii. Select Mode T-R i.e. Double Crystal mode.
iii. Set Delay 0.
iv. Set Probe Zero 0.
v. Feed longitudinal wave velocity (5920 m/s) / Press measure 0 key.
vi. Feed angle 00.
vii. Connect 0˚ Double Crystal probe and put it on IIW (V1) Block after
applying couplant at 100 mm width side.
viii. Set first reflected peak at 3.3 div. using probe zero. Place Gate over it and
read the beam path, depth shall be 100 mm.
ix. Second reflected peak will appear at 6.7 & third peak at 10.0.
x. If last peak is not at 10.0, velocity may be adjusted to set the last peak at
10.0 (if velocity control available).
xi. The equipment is calibrated for 300 /200 mm Longitudinal wave for 0˚
Double Crystal probe.
xii. To verify the calibration, put probe on top of rail head, the back peak
position will be at 5.2 for 52 Kg. rail & at 5.7 for 60 Kg. rail.
_________________________________________________________________________________
Volume I – Part A - Track Page 93 of 112
Specifications RVNL
a) For any flaw signal obtained by normal probe from the head region,
i. Flaw signal 40% and above and up to 60% to be declared as
DFWO.
ii. Flaw signal above 60% to be classified as DFWR.
b) For any flaw signal obtained by normal probe from web or foot location,
i. Flaw signal of height more than 20% from the web or foot and up to
40% to be classified as DFWO.
ii. Flaw signal of height more than 40% from the web or foot or more to
be classified as DFWR.
6.1 CALIBRATION:
Following procedure shall be adopted for calibration of 700 2 MHz single
crystal probe:
i. Select range 165 mm with range control key.
ii. Select Mode T+R i.e. Single Crystal mode.
iii. Set Delay 0.
iv. Set Probe Zero 0.
v. Feed Shear wave velocity (3230 m/s) / Press measure 70 key.
vi. Feed angle 700.
vii. Connect 70˚/2MHz Single Crystal probe and put it on IIW (V1) Block
after applying couplant and direct the beam towards 100 mm
curvature.
viii. Move the probe slightly to and fro to get maximize signal.
ix. Using probe zero set this peak at 6.0 or by using gate read beam
path 100 mm.
x. To verify the calibration, Direct the probe towards 25 mm curvature
and maximize the peak.
xi. Put the gate on this peak, the beam path shall be 25 mm.
xii. The equipment is calibrated for 165 mm shear wave.
the hole is obtained. Now set the height of the reflected signal to 60% of
full screen height by suitable manipulation of the gain control. This gain
shall be used for testing.
_________________________________________________________________________________
Volume I – Part A - Track Page 95 of 112
Specifications RVNL
_________________________________________________________________________________
Volume I – Part A - Track Page 96 of 112
Specifications RVNL
_________________________________________________________________________________
Volume I – Part A - Track Page 97 of 112
Specifications RVNL
Place 450 /2MHz probe on the rail head surface at a distance equal to
height of rail from the centre of the AT weld (Fig. 5). Select T+R single
crystal mode. Move the probe 20mm either side of this position (probe
index marking) to pick up half-moon crack in the central region of weld
reinforcement as shown in Fig 6. This exercise shall be carried out two-
three times from each side of the weld and signal from simulated flaw
should appear at a distance of approximately 400mm for 52-kg rail. This
distance will vary with respect to rail section height. The signal so obtained
shall be adjusted to 60% of full screen height by manipulating the gain
control.
_________________________________________________________________________________
Volume I – Part A - Track Page 99 of 112
Specifications RVNL
The tandem probe rig scan on the rail table by 450 probe is used to detect
any vertically oriented defect like lack of fusion in the rail head, web and
foot region below web.
_________________________________________________________________________________
Volume I – Part A - Track Page 100 of 112
Specifications RVNL
_________________________________________________________________________________
Volume I – Part A - Track Page 101 of 112
Specifications RVNL
10.1 A thermit welding done in situ shall be joggled fish plated with two clamps
till tested as good by USFD.
10.2 The defective joints (DFWO or DFWR) based on the criteria mentioned in
preceding paras shall not be allowed to remain in service for initial USFD
testing of AT welds and subsequent testing within the guarantee period of
contract and these joints shall be cropped, re-welded and tested again.
The re-welded joints shall be scanned ultrasonically again with the same
set of acceptance criteria to ensure freedom from any harmful defects.
joint defective in flange testing, operator shall ensure that signals are flaw
signals and not the signals coming due to geometrical configuration of the
weld. Following method shall be adopted for taking decision in this regard:
i. Horizontal distance of flaw shown on screen of the equipment shall be
observed.
ii. Measure the actual distance from probe index to confirm if the flaw
signal is coming from the weld collar/reinforcement or from the
weldment. (Fig.4)
c. Oil or grease shall be used for proper acoustic coupling instead of water for
AT weld testing. Operator shall use the same couplant during testing and
setting the sensitivity.
d. More than one DFWO defect in one weld shall be classified as DFWR.
_________________________________________________________________________________
Volume I – Part A - Track Page 103 of 112
Specifications RVNL
ANNEXURE -3
SPECIFICATION OF 3-PIECES PRE-FABRICATED MOULD
MANUFACTURED BY A.T. PORTION MANUFACTURERS FOR USE DURING
A.T. WELDING OF RAILS
AS PER IRST-19- 2012
0.0 FOREWARD:
0.1 Indian Railways have introduced Alumino-thermic welding of rail joints
since five decades. The mould required for accommodating molten
thermit steel around the joint to make a bond between the rails, was
earlier made of green sand. Due to introduction of short preheating
process in eighties, the moulding practice was switched over to
prefabricated sodium silicate dry sand mould or Pre-Fabricated Mould
(PFM) with an intention to minimize the welding time and bring
improvement in quality of joint.
Earlier 2 pieces PFM were used in Indian Railways. The main drawback
of 2 pieces PFM was the appearance of Fins at the bottom of AT joints.
To overcome this AT welding defect a new 3 pieces PFM has been
developed as per the figure given in Fig.1. Third bottom piece of one set-
3 pieces PFM during AT welding shall not result the bottom fin. However
care must be taken during fitment of 3 pieces PFM so that the two parting
line at the rail flange edges are avoided.
1.0 SCOPE: This standard includes basic requirements & quality control of
raw materials required for moulding, manufacture of moulds, quality
control during manufacture and of finished product and packing
conditions for use during A.T. welding of rails of different sections as per
IRS-T-19- 2012. This standard shall be applicable for A.T. Portion
manufacturers.
2.0 REFERENCES:
While preparing this standard following specifications have been referred
to:
IRS Specification for fusion Welding of rails
IRS-T-19-2012
by Alumino-thermic process
IS:1918-66 (Reaffirmed
Method of physical tests for foundry sands.
2003)
Specification for High Silica sand for use in
IS:1987-2002
foundries.
IS:6773-78 (Reaffirmed Specification for Sodium Silicate for use in
2003) foundries.
IS:10091-81 Specification for Iron Oxide Powder for use in
(Reaffirmed 2003) foundries.
IS:2-1960 (Reaffirmed
Rules for rounding off numerical values.
2006)
IS:12446-2007 Specification for Bentonite for use in
_________________________________________________________________________________
Volume I – Part A - Track Page 104 of 112
Specifications RVNL
foundries.
IS:10033-1992 Zircon and Graphite based core and mould
(Reaffirmed 2003) washes
IS:307-1966
Carbon-di-oxide gas of commercial grade
(Reaffirmed 2006)
IS:9738-2003 Polyethylene Bags for General Purposes
IS: 11099-1984
Universal Sand testing machines.
(Reaffirmed 2005)
4.1. 2 The manufacturer shall keep record/ inspection certificate of high silica
sand, being used in the production as per IS-1987-2002 with proper
_________________________________________________________________________________
Volume I – Part A - Track Page 105 of 112
Specifications RVNL
traceability. The manufacturer should also carry out its own inspection
check on the Silica sand and proper record shall be maintained with
traceability.
4.2.1 Sodium silicate used as a binding agent for pre-fabricated mould shall be
of appropriate grade as per IS:6773-1978 (Reaffirmed 2003). The grade
used as per requirement of firm shall be indicated in QAP of firm.
4.3.1 Iron oxide is added to the sand mixture to increase the hot strength of the
mould. The iron oxide shall be free from clay and in powder form. Iron
oxide to IS:10091-81 (Reaffirmed-2003) shall be used as Iron Oxide
ingredient.
4.5.1 To achieve good finish of the weld surface, mould wash shall be used. It
shall be alcohol base Zircon wash Gr. ZA to IS: 10033-92 (Reaffirmed
2003). (See Appendix- II).
_________________________________________________________________________________
Volume I – Part A - Track Page 106 of 112
Specifications RVNL
5.2 The dimension of the mould shall be such as to give required weld metal
geometry of the joint approved by RDSO. The mould shall fit properly
with the rail and in the mould shoe.
5.3 The mould may be suitably reinforced for adequate stiffness and stiffener
design & location shall be a part of the drawing.
7.2.1 Firm should have a Quality Assurance Plan duly approved by the
competent authority.
7.2.2 Firm shall keep all the records of quality checks of all incoming raw
materials as mentioned in Cl. 4.0 of this specification. The process
control activities shall also have necessary inspection record as per the
approved QAP.
7.2.3 The proportion of the ingredients, pressure and time of passing of CO2
gas should also be checked.
7.2.4 The dimensions of the pattern for its conformity to the drawings of
approved weld design should also be checked. All the measuring
instruments shall be maintained in functional order.
_________________________________________________________________________________
Volume I – Part A - Track Page 107 of 112
Specifications RVNL
7.3.1 For Inspection of finished mould, the Batch size shall be production of
each day subject to maximum of batch size of AT welding portion of
firm+5%, which shall be included in QAP of firm.
7.3.2 The mould should be sound and it should not break during transit under
normal condition. The name of the test and their frequency, to be carried
out on finished mould by the manufacturer at their own and by purchaser
or nominated agency shall be as under:
7.3.5 Ringing Test: Ringing Test shall be carried out by using a small and light
hammer made of 10 mm steel rod for checking soundness and degree of
ramming during manufacture. The mould shall have characteristic ringing
sound and shall not break.
7.3.10 The manufacturer shall provide test results of raw materials and the
batches offered for inspection to the Inspecting officials.
9.0 PACKING:
9.2 A pair of such packed moulds shall again be packed in carton paper
boxes confirming to IS:2771 (Second Revision). Proper sealing shall be
done on each carton.
_________________________________________________________________________________
Volume I – Part A - Track Page 109 of 112
Specifications RVNL
9.3 Each carton shall be clearly marked giving manufacturer's name, date of
manufacture and rail section, batch number for easy identification.
_________________________________________________________________________________
Volume I – Part A - Track Page 110 of 112
Specifications RVNL
_________________________________________________________________________________
Volume I – Part A - Track Page 111 of 112
Specifications RVNL
_________________________________________________________________________________
Volume I – Part A - Track Page 112 of 112