0% found this document useful (0 votes)
39 views1 page

Weekly Delay Letter

This letter from Sinohydro Corporation (Mtius) Ltd to Evaco Construction Ltd concerns delays and disruptions to infrastructure works on the Le Clos du Littoral Phase 2A project for the period ending. The letter encloses a schedule detailing events that caused delays and is serving as notice to support Sinohydro's request for an extension of time and additional costs for the project.

Uploaded by

SamuelVilbrun
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
39 views1 page

Weekly Delay Letter

This letter from Sinohydro Corporation (Mtius) Ltd to Evaco Construction Ltd concerns delays and disruptions to infrastructure works on the Le Clos du Littoral Phase 2A project for the period ending. The letter encloses a schedule detailing events that caused delays and is serving as notice to support Sinohydro's request for an extension of time and additional costs for the project.

Uploaded by

SamuelVilbrun
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Our Ref:

Date: 11 July 2017

Evaco Construction Ltd


Riviere Citron
Arsenal

For the attention of the Head of Operations, Mr Werner

Dear Sir

LE CLOS DU LITTORAL PHASE 2A INFRASTRUCTURE WORKS


WEEKLY DELAY LETTER

We herewith enclose a schedule which put into perspective events that have cause delays
and disruption to our general progress of work for the period ending …………...

We deem this to be a notice in support of our request for an extension of time and
additional costs.

Yours faithfully
For and on behalf of Sinohydro Corporation (Mtius) Ltd

Fan Jinhui
Site Manager