Section (12) - Civil Works PDF
Section (12) - Civil Works PDF
CIVIL WORKS
Section 1:2: Civil Works
Table of Contents
1 SCOPE OF WORKS .... ..... ..................................................................................... ............ ... .,...... .. ................ 3
2 General Conditions .... ................. .. ............... .......................... ............ ............ ... ........... .. ...... ........... .. ... ... 24
3 Specification Of Building Works ................................ ...................... .... ............. ........ ..... ............ ... .......... 27
12.1.1 General
• The Civil works required under this contract shall be designed and executing the building
works. The main offer for the civil works shall be conventional type for the structural system,
the contractor shall provide all material and labor necessary for executing the building works.
• The preliminary general layout submitted by the contractor in his offer should include all
rooms with their net dimension according to the specifications and the zone is authorized for
the final distribution of the substation components according to the requirements of operating
and maintenance without any extra payment to the contractor.
• Owner engineer representative. (EETC)
• For future extension: Foundation works only for 66 kV GIS outdoor switchyard (Outdoor
equipment beside Transfonner area, Suppmts of GIB connection, neutral points, and sealing
ends).
• 66 kV GIS switchgear building sufficient for 66 kV GIS system and the future extension
including cable trenches and ducts.
• Foundations Jor [4x40MVA] Transfonners and separation fire walls or on the same raft of
catch basin and One separated underground oil pit for all transfonners.
• Control building sufficient for 66 kV GIS System including future extension and 22kV
switchgear room including basement under 22kV switch gear room.
• One Firefighting rooms and RC foundation for galvanized steel F.F water tank.
• Wire mesh Fences around all area of 66 kV GIS switchyard and power transfonners and
capacitors banks including future works .
• Main and secondary roads and access roads.
• Boundary fence and gates.
• Guard rooms.
• Guard towers.
• Shed roof for vehicles.
• Water supply system for S/S.
• Sewerage system for S/S.
• Sanitmy installation.
• Fire hydrants system
• Station earthing system for the S/S as well as the future extension in buildings.
• Site preparation, grading, leveling, cutting or back filling to reach zero level, replacement soil,
yard lighting .... etc.
• Cable trenches and ducts for medium voltage cables 22 kV up to the boundary fence and for
control cables including future works.
• Any other civil works required completing the works ·
The contractor shall clean the site from all vegetation bushes trees and any other obstacles
above and underground without extra changes .
The Contractor shall level the areas of Sites by excavating the high areas, filling and
compacting the low areas. Any soft soil or other material, which the EETC engineer
consider unsatisfactmy for the leveling works, shall be excavated and removed from the
site and replaced by clean sand. All banks and slopes shall be formed to a gradient not
exceeding 1 (ve1iical) in 2 (horizontal). Surfaces can be made level or with a suitable cross
gradient to prevent corrosion resulting from water and wind . "The surface finish and sub-
grade material shall be durable enough so that any operations performed during the
transportation and installation of equipment shall not damage the surface finish" . The
erosion protection will be provided for switchyard area and transformers area with a layer
not Jess 10 em of gravel higher than final zero level .
Needful side pitching should be canying out around all buildings roads and boundary
fence to supp01i the soil and according to site condition and under the owner approval if
needed .
The lo~~t i o.n of c.iv ~ l ·works ~h fftdd ~ J f~ act.:C)If.:iing tn the sugge:· t:: t:~ !ayout.
• The building should be provided with an approved type of overhead crane with capacity
1.5 times the weight of the heaviest equipment but not less than 3 tons.
• The building shall also be provided with a galvanized steel caged ladder with platform
fixed at the end wall of building for purpose of maintenance of the overhead crane.
• The crane rails and its suppmts on the columns inside switchgear building shall be
constructed.
• R.C. Cable trenches and ducts.
• The contractor shall constmct two sectional doors for equipment and enough personal
doors, enough windows.
• The sectional doors shall be electrically operated, ve1tically rolled, in dimension (width
and height) suits the equipment dimensions.
• All walls shall be 25 em thick made of solid cement bricks size 25x12x6 em rendered
internally and painted 4 coats of washable oil paint of an approved quality and color.
• The inside faces of walls shall have cement rendered applied in two layers as specified.
Four coats of oil paint of approved qualities and colors as specified.
• .The cei]i!lg .shall ~e p~in_tecl L,."- (O!'!e pri!"ner coat ?- 3 C8E-ts of pl~~tic pai:'!t) of an-epprovcd . :_---
quality and color.
• The floor should be as following:
v' 10 em P.C.
v' Insulation of two perpendicular layers of water proofing membrane with thickness not
less than 4 mm each layer with overlap 15 em welding system including ski1ting with
15 em height.
v' 15 em R.C according to approved design.
• The finishing floor should be as following:
• The walking areas and under equipment the floor shall be concrete screed not less than 10
em thick with smooth surface helicopter finish to be treated with hardener material before
painting to avoid any damage due to the erection, painted with 2 layers of epoxy paint of
an approved quality including ski1ting of cement plaster 10 em height painted the same as
floor . The GIS roof shall be provided with following:
v' · Light weight concrete having average thickness 7.0 em with slope towards roof drains
(including rain pipes ofP.V.C).
v' Covering the lightweight concrete with not less than 3 em thick cement screed. 2-
Perpendicular layers of damp proof courses membrane bitumen type or similar
thickness not less than 4 mm with over lab 15 em welding system, including skirting
25 em
v' Covering the area with geotextile for protection
v' Laying the thennal insulation 5- em thickness from approved extruded polystyrene
insulation board with density not less than 36 kg/m3.
v' Covering the area with second layer of geotextiles for top protection.
v' Sand and cement mortar with average thickness 6 em
v' Covering with cement tiles 20x20x2 em with cement mortar included slop skilting of
same tiles.
v' Expansion joint about 20 mm are to be filled with bituminous elastic material
• The minimum clearance between ·walls and the equipment shall be as per the
manufacturer' s recommendation considering it shouldn' t be less than the following:
v' 4 m the width of the main lobby (maintenance lobby).
v' 2.5 m the width of the secondary lobby.
v" 2m the width of the longitudinal corridors behind equipment, measured from the face
of local control panels to the face of the equipment..
• The walking area width shouldn't be less than 2.0 min addition to the width of the cable
trenches.
• The building shall be provided with ventilation, lighting and fire detection system as
specified in their relevant section.
• The windows are fixed type for 66 kV GIS switchgear building and movable type for
other rooms opened by an approved mechanism and they should be aluminum type of
suitable size to give sufficient lighting and ventilation.
• All windows should be provided with fixed wire mesh screen and the glass should be
wired single glass 6 mm for 66 kV switchgear building and where broking glass may fall.
• Concrete surface:
../ The surface of concrete finished against fonns must smooth, fl"ee from projections
and thoroughly filled with mortar, immediately after the removal of the fonns all
voids shall be neatly filled in with cement mottar of the same consistency as the
mmtar in the concrete .
,,- The appe~~ed placement joinfbetween beams and columns should be soften and the
surface of concrete should be painted with an approved cementous base materials to
be homogenous color, the using of the materials must be according to the production
company instructions .
../ The smface of fair face concrete which will be rendered must be painted with an
approved epoxy material to connect the rendering, the using of the materials must be
according to the production company instructions.
• The external and internal doors for equipment transpmiation should be double leaves of
steel sheets (Marie Scott or similar) reinforced with sufficient steel stiffeners and bracing
angles fixed on R.C frame and painted with (2) coats of primer and (3) coats of washable
oil paint of an approved quality and color considering to the following dimensions:
../ For 66 kV switchgear building entrance the doors should not be less than 2.8 m height
and 2.5 m width .
../ Passage should be provided with two entrance aluminum doors with the same width
and height of passage .
../ The outer surfaces of the external walls shall be cement plastered and finished with
an approved type of high quality of cement based weather resistant and color stable
decorative fac;:ade material (Dry mix type or equivalent) and plinth of Pharaoh Stone
with height 1 m above sidewalk should be carrying out of an approved quality
and color.
../ The outer sutfaces of the superstructure concrete elements (columns, beams,
parapets .. .. etc.) shall be finished with the same materials of the walls facades but with
the different texture .
../ The windows are (fixed type and movable type) for 66 kV switchgear building and
movable type only opened by an approved mechanism and they should be aluminum
type (P.S jumbo type Alu Misr Company) or similar of suitable size to give sufficient
lighting (design sections under the owner's engineer approval) .
../ For 66 kV switchgear buildingthe windows of fixed type should be canying out on
both sides and at an high level, the movable type should be canying out on the inner
side only and at a level higher than the roof of the medium voltage room and the
number of windows should be not less than (4) and at a suitable position (under
owner's engineer approval) taking into consideration the architecture view.
A~#lfJ..
Data Centre 66/22 kV GIS S/S Page 7/53 Rev.02
For Mohamed Nagib Military Base
Section J2: Civil Works
./ All doors fittings and accessories shall be of high quality and subject to owner's
engineer approval.
./ The panic lock devices shall be provided to the doors for 66 kV building in exist way
and their steel doors .
./ Expansion joint should be carrying out every (30-35 m) for hot region and (40-50 m)
for moderate region .
./ Sidewalk round the building and platfonns should be covered with steel-Crete tiles of
an approved quality and color and with width lot less than 1.00 111 and should be
provided with curbstone .
./ The side wall nearest transformers should be from R.C as fire protection.
12.1.1.3 Transfonners foundations
• The contractor shall design and construct reinforced concrete fair face foundations of the
outdoor main transfonners also to cany the loading from the oil filled transfonners with
any additional loads due to transfonners operation, due to seismic and other natural
phenomena and according to soil investigation report.
• The foundation box for eve1y transfonner should be designed in the fonn of an open
to
·r:;G\.anguhu· concrt:te box and large enougii capacitate the. i :) rilne the' ml voluine and
the oil level shall not be higher than 400 mm below the upper edges of the foundation box.
• The transfonner shall be placed on rails/beam supported on two intermediate R.C buttress
walls, the rails for transfonner foundation and in front of all transfonners should be
suitable for operation and maintenance and included fixing system according to the
owner's engineer approval.
• The transfotmer foundation box should be filled with 20 em of gravel size 32-64 mm
above galvanized expanded steel grating (design according to the owner's engineer
approval) gravel should be well sieved and washed before placing, the floor slab should
be drained to a sump that makes emptying by pumping possible.
• The transfmmer foundation box outside surfaces below the ground surface shall be
insulated by using two perpendicular layers of water proofing membrane with thickness
not less than 4 mm each layer with overlap 15 em and the vertical insulation of R.C walls
protected with brick walls not less than 12 em thickness.
• The foundation box intemal surfaces shall be insulated by using oil resistance epoxy
insulation painting according to owner's engineer approval.
• The horizontal insulation shall be two perpendicular layers of water proofing membrane
with thickness not less than 4 mm each with overlap 15 em between the plain and
reinforced concrete and should be protected by 2 em thick cement screed.
• A protection fair face R.C walls between each transfonner and at two ends should be
constructed with height not less than 6.0 m above final zero level, with considering thf}t
the height ofthis R.C wall shall be higher than the highest point of the transfonner with
2.0 m at least, length suitable for transformer dimensions and thickness not less than 25
em ..
• Each wall should have R.C footing resting on P.C. with area, thickness and level
depending on the type of soil and recommendation of soil investigations report the
minimum dimension ofR.C footing should be not less than 1.00 m.
• All reinforced concrete surfaces of the foundations of fire protection walls below the final
zero level should be properly insulated using at least three layers of an approved
bituminous emulsion with provided that verifying the recommendations of the worst soil
investigation repmts.
• Oil Pit.
./ The contractor shall design and construct 01i.e separated underground R.C oil pit for
all transformers. The oil should be with capacity not Jess than 1.2 times the volume
of the oil of one transfonner.
./ The oil pit includes the connected pipe to the sump of each of transfonners
foundations with min slop 1:100 and with diameter not less than 150 mm .
./ The concrete should be composed of sulphate resisting cement mixed with additional
material Addicted (DM2) or similar kind .
./ Outside concrete walls should be insulated by using two perpendicular layers of water
proofing membrane with thickness not less than 4 mm each layer with overlap 15m
and protected by brick walls not less than 12 em thickness .
./ The internal faces ofR.C walls and ceiling should be smoothly cement rendering and
insulated by using oil resistance epoxy insulation painting according to owner's
engineer approval.
./ Kickers should be provided with water stop to prevent water penetration.
• Foundations of Buildings
-./ The fouilcl&tiutiS slivu.i.J uc; ui adc;quate· Jimensici;iS w achieve the -worst soil
investigation report recommendation and contour map and to prevent settlement,
overturning or other displacement and shall with stand the loadings calculated .
./ Foundations shall normally be placed on virgin soil or well compacted fill according
to the requirements of the site or as specified in the worst soil investigation report
./ All reinforced concrete of the foundation below the final zero level should be properly
insulated by at least here layers of bituminous emulsions and with provided that
verifying the recommendation of worst soil investigation repmis.
12.1.1.4 Firefighting building:
• The contractor shall design and construct building for firefighting equipment of fair face
reinforced concrete (R.C skeleton type) of columns, beams, slabs and suitable foundation
according to the worst soil repmi and provided with all necessary accessories and at least
one exhaust fan.
• The contractor shall construct fair face R.C foundation for galvanized steel F.F. water
tank
• All walls shall be 25 em thick made of solid cement bricks size 25x 12x6 em below zero
level and solid cement bricks size 25x12x6 em above zero level rendered internally and
painted 4 coats of washable oil paint of an approved quality and color.
• The floor should be 15 em RC covered with of mosaico tiles 3Ox3 0 cn1 v-:ith skirting 15
em height. The roof of the building shall be as specified.
• The outer surfaces of external walls shall be cement plastered and finished with an
approved type of high quality of cement based weather resistant and color stable
decorative fas:ade material (dry mix or equivalent) and plinth of Pharaoh Stone with
height 1 m above sidewalk should be carrying out of an approved quality and color.
• Ceiling shall be fair face concrete and painted with one primer+ three coats of plastic
paint.
• The outer surface of the concrete elements shall be as specified in control building.
• The windows should be tilting aluminum type opened by an approved mechanism , and
the door should be steel type with enough dimension for entrance of equipment and
painted with (2) coats of primer and (3) coats washable oil paint of an approved quality
and color.
• The firefighting building should be with suitable area for the supplied equipment by
contractor.
• The superstructure concrete elements (columns, beams, parapets .... etc) shall be external
finished with the same materials of the walls facades but with the different texture.
• Lighting work (supply and erection) should include all tubes, lamps ... etc according to
relative section in specifications.
• The roof should be as following:
./ R.C slab
./ Two perpendicular layers of water proofing membrane with thickness not less than 4
mm each layer with overlap 15 em welding system including skirting 25 em height
./ Covering the water proofing membrane with one layer of geotextile .
./ Cement screed with thickness not less than 3.0 em .
./ Thennal insulation of extruded Polystyrene boards of an approved quality with
thickness not less than 5.0 em and density not less than 36 kg/m3 .
./ One layer Geotextile membrane (ultraviolet resist) for protection .
./ Light weight concrete of average thickness 7.0 em having th~ slope toward roof drains
(inciudiHg raii1 pipes of P. ;./c)
./ Sand and cement mortar with average thickness 6.0 em .
./ Cement tiles 20x20x2 em with cement mortar included skirting of same tiles .
./ Expansion joint about 20 mm are to be filled with bituminous elastic material.
• The floor should be as following:
./ lOcmP.C .
./ Insulation of two perpendicular layers of water proofing membrane with thickness not
less than 4 mm each layer with overlap 15 em welding system including skirting with
15 em height.
./ Cement screed with thickness not less than 3.0 em
./ 15 em R.C (according to approved design) .
./ Sand and cement mmiar with average thickness 8.0 em .
./ The floor should be covered with mosaic tiles 30x30 em with skitting 10 em height
as flooring type.
• Two lavatory rooms, fitted with water closet, one in connection with the offices with
area not less than 12 m 2 and should be provided with two western type water closets,
two urinals and two hand washing basins, with natural ventilation. Sanitary work shall
include all intemal and external, piping installations and drainage system and the
second in connection with the workshop with area not less than 6.0 m 2 •
• Kitchen room of an area not less than 9 m 2 with its facilities and one stainless steel
sink and sanitary work. It shall include all internal and external piping, installation
and drainage systeni.. Walls for the whole height and floor shall be finished by ceramic
tiles. It should have natural ventilation.
• The contractor should construct the civil works of the capacitor banks and future
construction.
• Necessary pressurized ventilation and air condition according to relative section in
specification and the contractor should connect the sewage water of air condition to
the network of building.
• Polyethylene water tank with capacity 2 m 3 should be erected on the roof on steel
structure base with pump not less than (2hp) Calpeda or simil:u type with all
acct:ssories coimected with the water supply system and drainage for the controi
building.
• For present and future works the contractor should consider RC floor of medium
voltage switchgear
• Expansion joint should be carrying out every (30-35 m) for hot region & (40-45 m)
for moderate region
The width of control building entrance and conidor shouldn't be less than 3 m.
The minimum clearance of the equipment from the building walls shall be as per the
manufacturer's recommendation considering it shouldn't be less than the following:
1.50 m between the walls and the backside of the equipment which has a rear access.
0.50 m between the walls and the backside of the equipment which doesn't have a
rear access
1.50 m between the walls and the end of the equipment row.
5.00 m the width of the operator loopy in control room.
3.00 m the width of the passage between every two rows of AC/DC equipment,
medium voltage switchgear and battery racks.
2.50 m the width of the operator's lobby in other equipment rooms.
• Medium voltage switchgear room including future extensi0n.
• Clear height of the control building from the finishing floor level to the false-ceiling
shouldn't be less than 4 m.
• Water supply and sanitmy works (supply and erection) should be including all intemal
and external installation and drainage system according to items (12 . 1.1.1~ and
12.1.1.13)
• Lighting (supply and erection) for the substation building will be according to relative
section in specification.
• Fire detection system as specified in the relative section in the specification.
• The contractor should take into consideration that the provision for future extension
and according to the suggested layout.
• The contractor should provide the Telecommunication, AC/DC, control and
protection, medium voltage switchgear rooms, offices with air conditioning.
• The floor of medium voltage shall be concrete screed not less than 10 cm thick with
smooth surface helicopter finish to be treated with hardener material before painting to
avoid any damage due to the erection, painted with 2 layers of epoxy ~aint of an approved
quality including skirting of cement plaster 10 cm height painted the lsame as floor.
• The floor of the control room, telecommunication room and AC/DC r~om should be raised
floor of an approved quality. Fixed at RC slab finished with smoot~ surface finished by
1
Helicopter treated with hardener material.
• The floor of Auxiliary transformer rooms should be concrete screed not less than 10 cm
thickness included skirting of cement plaster 10 cm height with smooth surface treated
with hardener material before painting to avoid any damage due to erection and painted
with two layers of an oil resistant epoxy paint of an approved quality and color.
• The floor of the main entrance should be covered with granite tiles with minimum
dimension 40x40x2 cm of an approved quality and color, the main entrance stairs should
be RC with steps covered with granite 4 cm thickness horizontally and 2 cm vertically of
an approved color and quality
• The floor of the office room and corridor should be covered with non-slip porcelain 30x30
tiles not less than 10 cm thick of an approved quality and color including porcelain skirting
10 cm height.
• The floor of medi:im voltage room should be provided with steel cHannels with suitable
section Infront of each panel to permit easy movement of circuit breaker
• The floor of workshop and stores rooms shall be cover with unverified ceramic tiles
(heavy duty) of an approved quality and color and skirting of 10 cm height as floor type.
• The floor of battery room shall be covered with (heavy duty anti alkaline or anti-acid)
ceramic tiles of 1.6 cm thickness (Somga) or similar kind of first grade of an approved
quality and color. It should be on a bed of mortar and using anti-acid or anti-alkaline joint
filler with 6-8 mm width. all materials used in the battery room must not be affected by
the battery gases and fumes.
of suitable size to give sufficient lighting an ventilation of (design sections under the
owner's engineer approval) concerning the type of the glass as per the following:
./ For 66 kV building and where broken glass may fall, wired glass 6 mm shall be used .
./ For control building where air conditioning room will be 80% reflected double glass
6 mm for each type for EETC approval. For other rooms will be single glass 6-mm
type for EETC approval. All windows should be provided with fixed wire mesh
screen.
• The external and internal doors for equipment transpo1tation should be double leaves of
steel sheets (Marie Scott or similar) reinforced with sufficient steel stiffeners and bracing
angles fixed on R.C frame and painted with (2) coats of primer and (3) coats of washable
oil paint of an approved quality and color .
./ For medium voltage room, the doors should not less than 2.8 m height and 2.5 m
width
./ For control room, auxiliaiy transf01mers rooms, workshop and store room the doors
should not less than 2.5 m height and 2.0 m width .
./ For battery room the door should be not less than 2.2 m height and 1.50 m width.
v'· .-i'J1e dOOIS uf auxiiia1} i.raIJ::>lOllllt;1S ruom::; Shouid be-prnvided With Steel louvers as
ventilation grills .
./ For offices, service room and lavatories the doors should be of wooden type with
height not less than 2.2 m and painted with (2) coats of primer and (3) coats of oil
paint of an approved quality and color two doors at least should be in control room .
./ Control room, AC/DC and PLC doors should be hinged aluminum type (double
leaves) with dimension not less than 2.5 m height and 1.5 m width, the upper part
should be glass 6 mm thickness and the lower patt should be fiber glass with height
0.80 m of an approved quality and color .
./ Main entrance door of control building should be with height not less than 2.5 and
width 2.75 hinged aluminum type (four leaves) fixed in R.C frame and provided with
wire mesh glass 6 mm thickness of an approved quality and color.
./ Personal internal doors should be hinged aluminum type with height not less than 2.20
m and 1.0 m width, the upper part should be glass 6mm thickness and the lower part
should be fiber glass with height 0.80 m of an approved quality and color .
./ The panic lock devices shall be provided to the doors for basement, medium voltage
switchgear and battery room in exist way and their steel doors .
./ The doors of the air-conditioned room shall be provided with door closer devices .
./ All doors filling and accessories shall be of high quality and subject to the owner's
engineer approval.
• The main stairs shall be of reinforced concrete with steps covered with granite 4 cm
thickness horizontally and 2 cm vertically of an approved quality an color.
• The hand railing for platfonns, pits, stairs, etc. shall be of steel pipe 2" diameter white
metal hand rails of an approved quality section fixed to steel balusters of square or round
steel bars of approved sections electro-statically painted two coats of red lead and two
coats oil paint.
./ Expansion joint about 20 mm are to be filled with bituminous elastic material.
./ All wooden doors should be from Swedish musky timber type .
./ All the aluminum doors should be P.S. jumbo type (Alu Misr Company) or similar of
an approved types.
/ Sidewalk round the building and platforms should be covered with steel-Crete tiles of
an approved quality and color and with width lot less than 1.00 m and should be
provided with curbstone.
• Metal Works:
/ The handrail for stairs and platfonns should be steel pipe of 2" .diameter and Epoxy
pained with an approved quality and color and fixed to steel balusters of square or
round steel bars of approved section, the steel balusters should be fixed in R.C stairs
with suitable method .
' \.
{ Permanent ladder of steel stair should be provided for accessing to the roof of
buildings
/ Safety wire mesh should be provided under wall pushing for transfonners bays.
/ All the above mention steel work should be painted with Epoxy painting system .
• All walls shall be 25 cm thick made of solid cement bricks size 25xl2x6 cm
• The inside face of external walls and ceiling should be cement rendered in two layers and
painted with (one primer coat + 3 coats) of washable plastic paint of an approved quality
and color.
• The walls shall be externally finished with an approved type of high quality of cement
base weather resistant and color stabled decorative fac;:ade material (dry mix type or
equivalent)
• The external faces of beams, columns and parapet should be finished with same materials
of walls facades but with different texture and plinth of Pharaoh Stone with height lm
above sidewalk should be canying out of an approved quality and color.
• The internal walls should be solid bricks with a cement rendered in two layers as specified
and painted with (one primer coat+ 3 coats) of washable plastic paint of an approved
quality and color.
• Sidewalk around al 1buildings according to suggested layout of steel-Crete tiles with width
not less than 1.0 m, covered with steel-Crete tiles of an approved quality and color and
«bnn!r! h.~ Ht level (~25 cm) <1bove final zP-ro kvrl _Hn~ pr0vided V.'ith i::t~ rbstone.
• The lavatory walls should be solid bricks covered with ceramic tiles 20x30 cm for all
height of an approved quality and color.
• The roof should be as following:
o R.C slab.
o Light weight concrete of average thickness 7 .0 cm having the slope toward roof
drains (including rain pipes of P.V.C).
o Cement screed with thickness not less than 3.0 cm.
o Two perpendicular layers of water proofing membrane with thickness not less
than 4mm each layer with overlap l 5 cm welding system including ski1ting 25
cm height.
o One layer geotextile for protection
o Thennal insulation of extruded Polystyrene boards of an approved quality with
thickness not less than 5.0 cm and density not less than 36kg/m3.
o One-layer Geotextile membrane (ultraviolet resist) for protection.
o Sand and cement mortar with average thickness 6.0 cm.
o Cement tiles 20x20x2 cm with cement mortar included ski1ting of same tiles.
o Expansion joint about 20 mm are to be filled with bituminous elastic material
• The floor should be as following: -
o Sandwich type concrete consist of: -
O 15 cm R.C .
o Insulation of two perpendicular layers of water proofing membrane with
thickness not less than 4mm each layer with overlap 1S cm welding system
welding system including skirting with 15 cm height.
O 10 cm P.C.
o Sand and cement m01tar with average thickness 8.0 cm .
o The floor should be covered with ceramic tiles 3 Ox3 0 cm with skirting 10 cm
height.
o The Floor oflavatory should be covered with non-slip ceramic tiles (20x20 cm)
of an approved quality and color.
• The windows should be sliding aluminum type with glass 6 mm thickness provided with
sliding wire mesh screen and the toilets window should be tilting aluminum type provided
with fixed wire mesh screen of an approved quality and color.
• The doors should be wooden type and painted with (2) coats of primer and (3) coats of oil
paint of an approved quality and color.
• Water supply and sanitmy work (supply and erection) should include all extemal
installations and drainage system according to item ( 12.1.1.14 and 12.1.1.13 ).
• Lighting work (supply and erection) should include all bulbs, tubs, lamp, electrical ceiling
fans ... etc according to relative section in specification.
• Galvanize steel ladder with safety cage provided for access to the roof.
pipe 3" diameter fixed in R.C columns with anchor bolts, the lower part should be 4 meters
consists of concrete and brick works as following :-
o R.C. footings resting on plain concrete with area, thickness and level depending
on the type of the soil and recommendation of the worst soil investigation report
and the minimum dimension ofR.C footing should not be less thanl.OOm.
o Continuous R.C. rigid beam connecting the R.C. footings .
o R.C columns each 3.60 m (paneled width) and column's width dimension not less
than 30 em.
o R.C. top and middle continuous beams with minimum depth 25 em.
• Expansion joints every 15-20 m and constructive joints every 30-40m.
• The space between columns is filled with solid cement bricks below zero level and solid
cement bricks above zero level and the thickness of walls is 25 em above rigid connecting
ground beams and walls with thickness 12 em above the middle beams up to the top
beams.
• The walls should be provided with horizontal asphalt damp proof coarse 1.50 em thick
laid on the complete width of the wall underground surface.
• The inside and outside walls together witli concrete elements shall be cement rendered
finished as specified for the facades of S/S buildings.
• At least 3 layers of modified bitumen and with provided verifying that worst soil repoti
should insulate all reinforced concrete of foundations and walls in contact with earih and
up to 25 em above finished ground surface.
• Two main entrance gates of steel type will be provided as double leaves 6.0 m wide and
3.25 m height moved on a steel roller in addition to a steel personal gatel.O m wide and
3.0 m height.
• The lower pmi for all gates should be covered with steel sheet plates of 0.8m height and
with thickness not less than 4mm and with total weight not less than the following: -
o 750 kg for main gate.
o 150 kg for each personal gate.
• All the steel sections and details of all gates will be according to owner's engineer
approval.
• All gates should be painted with (2) coats of primer and (3) coats of washable oil paint of
an approved quality and color.
• Light work (supply and erection) of the boundary brick wall fence should be provided
with street light fittings to illuminate the areas on both sides of it and to be include all
bulbs, tubs, lamps ... etc. according to relative section in specification.
• The light fitting for the boundary brick fence will be directly mounted to its top with
maximum of spacing 21.0 m (6 panels) using brackets suitable for two luminaries
including a lamp 250w to illuminate the boundary fence from both sides.
• The contractor's offer shall include total price for boundary wall and unit price for one
longitudinal meter of the fence.
• In case of difference between Inside and outside levels for S/S area is more than 50 cm.The
contractor should constmct reinforced retaining wall or side pitching for fences instead of
reinforced foundation according to soil investigation report and approved design.
and maintenance.
r4/,~J..
Data Centre 66/22 kV GIS 5/S Page 20/53 Rev.02
For Mohamed Nagib Military Base
Seciio;: J2: Civil Works
• The reinforced concrete should be composed of sulphate resisting cement mixed with
additional material addicrete (DM2) by rate 2KG per cubic meter concrete or similar
kind of an approved quality
• Inside faces shall be smoothly cement rendering and insulated by epoxy insulation
painting, outside concrete surfaces should be surrounded with two perpendicular
layers of water proofing membrane with thickness not less than 4 mm each layer with
overlap 15 em welding system and protected with brick walls not less than 12 em
thick
• Kickers should be provided with water stop to prevent water penetration
• All tanks have upper RC slab included enough manholes opening (0.6 x 0.6 m)
provided with cast iron cover and inside steel ladder.
12.1.1.16 Lighting
• Contractor shall supply and install the interior and exterior lighting for firefighting building,
main road, secondary road, guard room, boundary wall fence gates, this lighting should be
designed to achieve the specified levels of illumination and lighting colors.
• The main lighting circuits, the routing of lighting cable, the number of lighting switches and
the routing of telephone cable as indicated in relative sections.
• All necessa1y drawings for lighting poles (locations, structural sections and foundations
should be according to owner's engineer approval.
• The lighting fittings should be decorative shape.
• The lighting fittings for the boundary brick fence shall be directly mounted with maximum
of spacing 21 m (6 panels) using brackets suitable for two luminaries including a lamp 250
W to illuminate the boundary fence from both sides
• All lighting units should be saved energy type.
• The contractor should supply and install telephone cable and their required plugs for office,
PLC room and control room.
The contractor may employ a civil Sub-Contractor or use a competent specialized section of his own
organization to caiTY out the civil works. If the Contractor intends to sub-contract the civil
engineering and civil works design and/or construction, his tender must include full details of
comparable works carried out elsewhere by the Sub-Contractor, together with details of the financial
stability and general efficiency of the proposed Sub-Contractor.
12.2.5 Responsibility
The contractor should be responsible of stability of any existing construction near from the new
works. The Contractor shall be solely responsible in all respects for the suitability and stability of
the buildings and foundations as regards the purposes for which they are required, and EETC will
keep a supervising Engineer on site to see that the building works are canied out according to the
final design submitted by him and approved by EETC, and that the quality of work and the used
materials are of the approved standard for the work in question. The Contractor shall be solely
responsible for verifying the suitability of his designed foundations to the nature of the ground.
When the soil has been excavated to the designed levels according to the approved Contractor's
design and the nature of the ground is found to require any modification in the design. this
modification has to be approved , and it shall be canied out by the Contractor without extra charge.
Tenders should in designing buildings Endeavour to realize easiness of running accessibility and
facility for dismantling of machinery.
The bidders have upon their own responsibility and their own expanse, carefully study before
tendering for the nature of soil in which he foundations are to be constructed.
The contractor shall be solely responsible for dealing without extra charge, with all difficulties
whatsoever which may be encountered in the execution of work whether foreseen or not, including
but not by way limitation, unsound ground excavation, dewatering ... elc.
the supply, construction and completion of the construction, site facilities and services, to meet the
commission date.
12.2.10 Samples
The Contractor shall submit samples of all materials for approval before using them in the works.
12.2 .11 The contractor must submit the quality surveillance program and concrete repair system for EETC
approval.
• all the inside wall fillings partitions shall be make for a thickness not less than 12 em of bricks
and shall be designed and executed in such a manner as to constitute, in conjunction with the frame
work a perfect sound and suitable structure in every respect.
• The extemal walls shall be provided with an isolating Damp proof coarse hereinafter specified
specification.
• the framework shall consist of columns, horizontal bracings etc. and shall be designed and
executed to take all stresses due to weight, wind pressure, crane loads, live loads, dynamic moving
loads and seismic effect.
• Prevailing Standards. The design of buildings shall be carried out in accordance with the standards
and regulations given in the Egyptian code and the Building Code Requirements for reinforced
concrete.
• All brick walls which in building should have a density not less than 1.8t/m3 .
12.3.1 Loadings
12.3 .1.1 General: All buildings and other constructions shall be designed for maximum influence of the
following lo~ds combined in different load cases:
• Dead weigh ·
• Pay load, pennanent and movable
• Wind load
• Seismic load
• Load from conductors
• Short-circuit impacts
• Operation loads
• Mounting loads
12.3.1.2Pay Load
All buildings shall be designed for the following loads.
12.3 .1.3Roofs:
Dust of sand and drifting sand from sand storms uniformly distributed 0.8 kN/m 2 .
12.3 .1.4Fioors
12.3.1.4.1 Loads from installations and equipment including transportation, min 5.0 kN/m 2
12.3.1.4.2 Floor area around equipment unifonnly distributed 3.0 kN/m 2 .
12.3 .1.5 Wind load
• The design wind load for a building, other construction equipment or part thereof shall be
derived from the dynamic wind pressure.
• The buildings shall be designed to withstand the horizontal wind pressure and th~ suction
force from the wind upon the roof.
• Ridged roofs and shed roofs are supposed to be subjected to an uplifting force.
• The wind pressure for building and methods of calculations shall be according to Egyptian
standard and shall be submitted to the Owner for approval during the design stage.
12.3 .1.6 Seismic Load
12.3 .1.6.1 Seismic load design shall be done according to the Egyptian Code.
12.3 .1.6.2 Minimum total lateral seismic force V assumed to act non-concurrently in the direction
of the main axes of the structure is taken as: V = ZIKCSW Where:
• V: The total lateral force or shear at the base
12.3 .2 Grouting
An approved type of non-shrink grouting material shall be used to fill the gap between
the lop of the concrete base and the base plates of the transfonners rails, steel structure
wherever it needed.
No grouting of the machinery bed plates, sole plates pedestals, etc. shall be canied out,
except in the presence of the Owner Engineer, and only after the alignment and leveling-
up ofthe machinery to be grouted has been checked and passed by him.
12.3.3 Drainage
A satisfactory drainage system is to be constructed for structures yards and roads, so
that the anticipated Precipitation will be suitably led off into the sunoundings.
12.4.1.2Tenders must satisfy themselves before tendering with regard to the nature of the materials to be
excavated and its effect upon the operations in connection with the excavation which they may have
to carry out, the levels and slopes thereof, requirements as to piling, timbering and pumping, methods
of carrying out the excavation and all other particulars what sever, and shall make allowance in the
schedule rates as they deem fit to provide for flatter slopes if necessary, or for any contingencies with
regard to excavations that may arise in canying out the and works and the contractor will be held
responsible to have acted as aforesaid.
12.4.1.3The contractor shall dispose the soil from the excavation on site in accordance with the provisions of
sub clause, and in a manner to be approved by the Owner Enp ineering in writing.
. Ah~Htel
Data Centre 66/22 kV GIS S/ S Page 30 /53 Rev. 02
For Mohamed Nagib Military Base
Section 12: Civil Works
12.4.1.4AII emth filling shall be carefully deposited in successive layers of a qumter of a meter thickness and
compacted at the optimum moisture content to achieve the required density. The layers shall be raised
in the same measure as the masomy or concrete. The Owner Engineer shall make no earth filling
around the masomy or concrete works before inspection and approval. The emth fitting used must be
completely clean free from debris and organic matters (clean sand).
12.4.1.5The Contractor shall be responsible for the design, construction and stability of all slopes, piling,
trenches and timbering, and shall make due provisions when setting out the lines of any proposal
excavation fcir the required slopes for any pilling and timbering in connection with the excavation,
including sufficient provisions for canying the foundations for any reasonable depth below the
estimated levels shown in the contract drawings, or given in the specifications (except in the cases
mentioned in this clause or elsewhere).
12.4.1.6During the carrying out of the excavation, if by reason of delay or the effect of floods, bad weather
slips or from any cause whatsoever, any sand, mud, weeds or other materials be deposited or
accumuiated lin the excavaieJ arc1is. Such mai.erials shaH be reiuoved by ~he Cuilt·&ctc;- r.t his c.·,v;~ ·
cost and as directed by the Owner Engineer, so that the finished surface of the excavation for the
foundations shall be rendered perfectly bars to c-he depth required prior to depositing any concrete,
masonry or rubble thereon. The Contractor shall, likewise at his own cost, keep the top of the work in
progress free from deposits of any kind.
12.4.1. 7 All the excavation works shall be completely dry, unless otherwise specified or authorized by the
Owner's Engineer. The contractor shaJl provide ample pumping appliances to keep the whole of the
works, including the deepest foundations, free from water and provide for all necessa1y temporary
drainage's by digging and maintaining a channel all-round the areas of the permanent works
sufficiently deep to ensure that the water level will be kept lower than the lowest bed level of the
foundations or otherwise to the satisfaction of the Owner Engineer. The Owner Engineer shall approve
the positions of all temporary sumps. No sumps shall be pennitted within the area of the foundations
of the permanent work without the written authorization of the Owner's Engineer and on such
conditions as they may agree to.
12.4.1.8Al\ foundations beds shall be surveyed and inspected from time to time during their excavation by the
Owner Engineer, and shall be passed by him previously to any masonry or other work being deposited
thereon. Due notice shaH be given by the contractor when he considers that any foundation bed has
been properly and finally prepared, so that the Owner Engineer may anange to make the necessary
survey and inspection at the first favorable opportunity. If, after a bed has been inspected and passed
by the Owner Engineer, the trough for any cause whatsoever becomes obstructed with debris, mud or
other materials, the contractor shall remove the same in a satisfact01y manner at his own cost then the
bed '" 1ii again be inspected by the Owner Engineer before pouring of concrete. If the levels or
dimensions of the foundation pits are greater than those stipulated, the excess shall be with concrete
by the contractor at his own expense.
12.4.1 .9If in the opinion ofthe Owner's Engineer it is necessaJy for the safety of the pennanent work that any
special timber or other piling should not be withdrawn, the same may be cut off and such length be
left in the work as he may direct. In the absence of any special provision in the contract Documents,
no payment will be made for any special piling so left in.
12.4.1.10 The Contractor shall be entirely responsible for any effect or damage which the carrying out
of any of the excavation work, including the disposal or excavated material, may have upon any
portion of the works either permanent or tempormy or any of the surrounding prope1ty whether
belonging to the Owner or other. The Contractor shall be entirely responsible for all slips and any
damage caused thereby to the works or to the adjoining property, and small make good at his own cost
any such damage to the satisfaction of the Owner's Engineer, he shall without extra cost take such
precautions as shall in the opinion of the Owner's Engineer be adequate to avoid slips by making the
excavation in steps (by shoring or other kind) . No additional payment will be made to the Contractor,
if, by reason of slips, the quantity of excavation is increased.
12.4.1.11 The measurement of excavation, unless otherwise specified shall be the net area of the
foundations of any pmtion of the permanent work as applied to the vetiical height between the finished
level of the foundations and surface of the grounds as detem1ined from agreed cross- sections . The
agreed cross-sections shall be taken by the Owner Engineer and the Contractor's Engineer immediately
prior to the commencement of any portion of the works and shall not include any material deposited
on the original surface ofthe ground by the contractor or otherwise.
12.4.1.12 All costs and charges what's over, in connection with carrying out the excavation in
accordance with the provisions of this clause and the contract Documents, including the provisions of
all main and subsidia1y suds dams piling, timbering, strutting and all temporary works also all
Dumping denaturing and draining, fonnation of steps between slopes in excavation fot foundations
and whatever else that may be necessary for the proper and satisfactory carrying out of work, are to
be taken as being included in and covered by the schedule prices and rates for excavations. In the
absence of any express conditions in the contract Documents, no soil shall be transported more than
one hundred and fifty (150) meters without the previous order or approval in writing of the owner
Engineer specifYing the approximate quantities to be so transpmied and the place or places from and
to which soil is to be taken. The quantities of soil actually and duly transported according to such order
or authorization shall be checked and accorded by the Owner Engineer and the Contractor's Engineer
at the time of the execution of such work. Soil shall be trans potted to a place, which will be chosen by
EETC Engineer, and no extra price would be paid. The execution of the building works for the reactor
station shall also include the following:
• All necessary excavation, earth filling and raising the ground to the final approved level
without extra charge
• The excavation in any kind of soil and subsoil water shall be taken into consideration.
• All cable trenches suitable to carry necessary cables in the whole s/s area and up to the
boundaty fence.
• switchyard ,substation buildings and transfonners foundations.
• Any other works in S\S site.
• All embedded parts for evety pmt of the installation.
• Proper execution of intemal and extemallighting.
12.4.1.13 The ground, before any concrete is laid thereon, must be well rammed, and any soft part of
sand must be removed and replaced with concrete or strengthened by any other approved means until
capable of retaining with great safety the maximum loads on site.
Contractor shall be solely responsible for dealing without extra charge, with all difficulties
whatsoever which may be encountered in the execution of the work whether foreseen or not,
including, but not by way limitation, unsound ground excavation, dewatering etc. Permissible
stresses on the soil under foundations shall be fixed according to the nature of the soil at site.
12.4.2.1 The attached soil investigation report is considered part of contract documents. Further geo
technical investigations shall be canied out by the Contractor, on his responsibility and account
without extra charge, to verifY the prope1ties ofthe soil.
12.4.2.2 The dimensions designed and quantities of foundation which will be constructed should not be
less than those calculated on the basis of the attached soil repmt. Also all the requirements stated
in the attached soil repmt (i.e. foundation level, soil replacement, etc.) shall be executed by the
contractor without extra charge.
12.4.2.3 Cvi1sliitant of me suii investigation whid1 vviH u;;; ;;iJGS;:;it uy the contractor ;1n;st be a:p!mwcd by ·
EETC.
12.4.2.4 In case that the contractor after canying out his soil investigation or after beginning the execution
of works find that the type of 1hefoundation must be different from that stated in the attached soil
report, or if the dimension and quantities of the foundations niust be bigger than those calculated
on the basis of the attached soil investigation report, or if the nature in the attached soil report
and these differences result in additional requirements such as an increase in the depth of the
foundation level, u~e of soil replacement., etc., all of these modifications shall be carried out by
the contractor, without extra Payment.
12.4.2.5 It means that the contractor should stick with the worst soil repmt either it is attached with tender
document report or contractor soil report without extra payment and time.
12.4.5.4 When these finished levels have been approved by Engineers, the contractor will be responsible
for leveling, the sites to suite.
12.4.5.5 The contractor shall also clean the site from all vegetation, bushes tress, and any other obstacles
without extra charge.
12.4.5.6 The contractor has to compare he contour map with he actual levels of site and prepare another
one on his responsibility and account without extra charge.
12.4.5.7 All banks and slopes should be fanned tot a gradient not exceeding one (vertical) in two
(horizontal).
12.4.5.8 Surfaces can be level with a suitable cross-gradient to prevent corrosion resulting from water
and wind.
12.4.5.9 Backfilling
12.4.5.9.1 Offer price should be included backfilling (for SIS area) to reach to zero level (using
clean sand on layers, each layer not exceed than 25 em, sprayed with water, well
compacting, proctor test not less than 95 %)
12.4.5.9.2 The contractor shall submit also separate price for 1 m 3 of backfilling.
12.4.6.2Mixing
12.4.6.2.1 The cement, sand, gravel and epoxy material against water ground will be so mixed and the
quantities of water added shall be such as to produce a homogeneous mass of proper uniform
consistency. Dirt and other undesirable substances shall be carefully excluded.
12.4.6.2.2 Machine mixing by automatic hatching plant or computerized mixer by weight will be required
for ordinary and reinforced concrete, unless it is pennitted by the Owner's Engineer to use hand
mixing which shall be done on a clean tight floor, Not more than one cubic meter of concrete
material shall be mixed on a platfonn at a time. Weak concrete can be hand mixed.
12.4.6.2.3 Placing
• No concrete shall be laid before an order has been obtained from the owner Engineer.
• Concrete shall be used on the work immediately after mixing, and any concrete not laid
in place within half an hour after mixing shall not be used in the work and shall
immediately be removed fi·om the vicinity.
• Unless otherwise specified in writing by the Owner, ordinary concrete shall be placed in
layers twenty-five centimeters thick, and each layer shall be rammed carefully and its
surface kept damp and clean.
• In case of reinforced concrete construction, concrete shall be placed in horizontal layers,
stirred and damped with suitable tools and mechanical vibrator until it completely fills the
forms, closes enough against all surfaces and is in perfect and complete contact with all
the reinforcement.
• Concrete shall not be placed in water, unless it is absolutely necessary, and then only after
the necessity and method of throwing the concrete in water have been as approved by the
owner's Engineer in writing.
• All vertical edges of concrete below ground level must have strongly and n~atly made
coffi·age and must not be poured against the sides 'of the excavatim1.
• The surface of the ground and coffi·age must be well&. Watered before any concrete is
placed.
• When placing of concrete is to be intenupted long enough for the concrete to take its final
set, the working face shall be given a shape by the use of key ways or other means that
will secure a proper union with subsequent work. All concrete surfaces on or against
which concrete is to be placed shall be roughened before placing any new mortar or
concrete upon them. Where smooth surfaces are required, and on all surfaces that will be
pennanently exposed to the weather, a flat square shoal or other suitable tools shall be
worked up and down next to the fonn until the coarse material is placed back and a mortar
layer is brought next to the fonn.
• Temperature requirements at the site should be taken into consideration.
homogenous color, the usmg of the materials must be according to the productive
company instructions
• The surface of fair face concrete which will be rendered must be painted with an approved
epoxy materials to connect the rendering, the using of the materials must be according to
the productive company instructions
12.4.6.2.6 Forms
• Fonns to shape the concrete to the required lines shall be used whenever necessmy.
• The forms shall be of sufficient strength and rigidity to hold the concrete and to
withstand the necessary pressure of ramming without deflection fi·om the prescribed
lines.
• For concrete surface that will be exposed to view and for all other surfaces that are to
be finished smooth, the lagging for fonns must be surfaced and level edged, or
notched.
• The inside of the fonns shall always be cleaned from impurities and rubbish all shall
be well watered and soaped or._oiled before any concrete is piaced.
• In no circumstances, shall forms of centering be removed before the lapse of 15 days
after placing the concrete, unless a written order is given by the owner Engineer.
12.4.6.2. 7 Reinforcement
• Reinforcing steel shall be placed in the concrete, as shown on the working drawings
submitted by the contractor and approved by the Owner's Engineer.
• Bars shall be single, and joints snail be avoided as much as possible.
• No welding shall be used and, if joints are necessary, the layers shall overlap for a
length equal to fifty times the diameter of the bar, measured along the straight pati,
and the ends shall be backed and finally bound together with steel wire.
• It must be possible to bend a cold bar through an angle of 180° around a bar of the
same diameter without fracture.
• The steel shall comply in other respects with the standard specifications in force for
structural steel for bridges and general buildings.
• The steel must be cleaned of all scales, dust and Losses rust immediately before
depositing any concrete.
• The reinforcing bars shall be carefully secured in position by means of steel wires and
stirrups .
• Samples of bricks shall be submitted for approval before the commencement of the works, and all
bricks used in the works shall be of as good a quality as the approved samples.
• Bricks shall be carefully handled in transit between stacks and soaking tanks, and between tanks
and work site.
• Bricks with broken edges or otherwise damaged may be rejected by the Owner Engineer.
• The selection of the bricks suitable for building the structure shall be entirely left to the discretion
of the Owner Engineer whose decision shall be final
• All bricks shall be thoroughly soaked in clean water before use and the contractor shall provide
and maintain at his own expense a suitable plant to enable this to be done.
• The practice, frequently adopted, of soaking bricks for a few minutes only just before using them
is in hot climate particularly objectionable and shall on no account be employed.
• Bricks shall be used in a thoroughly saturated condition and therefore cannot be removed from the
soaking pit until actually required for use.
• Brickwork shall be built in cement mortar in the proportion oftlu·ee hundred kilograms of cement
to one cubic meter of sand.
12.5.6 Rendedng
All the inside faces of walls and ceilings shall be cleaned wet enough before rendering and shall be
sprinkled with cement mmiar cor. composed of 450 kg cement for one cubic meter sana for all
project excluding the false ceiling area which mentioned before. The rendering must be made of two
layers as follows:
• Ceilings
Cement rendered of average total thickness of 2 em of cement mmiar composed ofJOO kg
cement for one cubic meter of sand, for all project excluding the false ceiling area, which
mentioned before.
12.5. 7 Paintings
• Oil Paint: All intemal walls shall be painted with 4 coats of paint of an approved quality and
color.
• Plastic Paint: All ceiling shall be painted with 4 coats of plastic paint of a good and approved
quality and color.
• Anti-Alkaline Oil Paint: The ceiling of the battery room shall be painted with anti-alkaline oil
paint. The Contractor shall submit a sample of this paint to be tested and approved before
commencing the painting.
• Ali ircm and steei work indudmg necessary fittings and iunber for use in the pemianent work
(gates, ladder, pipes ... etc) shall be painted with two coats of red lead (primer) and (3) coats of
oil paint of an approved quality and color. They shall be painted and fixed to the walls by means
of iron collars in 1: 4 cement and sand mortar.
• Distempering
All the other plastered internal faces of walls shall be given two coats of a light colored washable
distemper after primary coat of an approved make prepared by an app-roved factmy. Open
gargoyles shall not be
• Employed
All piping shall be complete with watetiight joints fittings, and painted in an approved manner.
• All wooden works (doors, windows, timbers, fixed frames ....) should be painted with (3) coats
of oil paint of an approved quality and color.
12.5.8 Windows
• The windows shall be 80% reflected double glass aluminum type for offices, control room and
any room provided with air condition. Windows shall be fixed on Alomital frame, which fixed
on wooden Frames 2" X 6" They shall be fixed in the masonry with 1: 4 cement and sand mortar
in a workmanlike manner, in accordance with the approved drawings and to the satisfaction of
the Owner's Engineer.
• The windows shall be aluminum type (color and design for EETC approval) concerning the type
for the glass as per following
For 66 kV building and where broken glass may fall using wired glass 6 mm.
For control building where air conditioning room will be 80% reflected double glass type
for EETC approval6mm for each.
For other rooms will be single glass 6mm type for EETC approval.
• The details of the Alometal frames shall be submitted for approval.
• The sashes shall be made to open by means of metal levers operated from floor level.
• The windows shall be opened by an approved mechanism under easy reach from floor level.
• The windows shall be sample size to give sufficient lighting and ventilation.
• The windows are (fixed type and movable type) for 66 kV switchgear building movable type
only for other rooms opened by an approved mechanism and they should be aluminum type
(Teclmal or similar) of suitable size to give sufficient lighting and ventilation of (design sections
according to owner's engineer approval)
• For 66 kV switchgear building the windows of fixed type should be cany out on both side and
at a high level, the movable type should be caiTy out on the inner side only and at a level higher
than he roof of medium voltage room and the number o windows should be not less than (4) and
at a suitable position according to owner's engineer approval tacking into consideration the
architecture view.
12.5.9 Doors
• The external and intemal doors for equipment transpmiation should be double leaves of steel
sheets reinforced with sufficient steel stiffeners and bracing angles fixed on R.C. frame and
painted with (2) coats of primer and (3) coats of washable oil paint.
• The doors of aluminum type should be fixed on wooden frames 6"xl.5" which fixed in the
masonry with 1:4 cement and sand mortar.
• The doors of wooden type with shutter and glass should be fixed on frame 6"x2" of an approved
quality and dimension and should be painted with 2 coats of primer and 3 coats of washable oil
painL.
• All doors should be fitted with a standard lock of the best quality according to the instructions
of the owner's engineer.
• The doors for basement, battery room and maintenance conoder shall be provided with paint
lock devices, and the doors of the air conditioned rooms shall be provided with an approved
type of door closer.
• Regarding the quality and proportions of paint mixes, also handling of all painted work in best
condition, the Egyptian standard specifications should be applied.
• Sufficient detailed drawings and calculations for doors and windows (aluminum, wooden and
iron works) should be submitted by the contractor for approval by owner's engineer.
12.5.10 Paving
• All kinds of paving are placed by using a mortar composed of 300 kg cement to one cubic meter
sand.
• All the tiling shall be provided with a colored border round the walls and machine beds.
• Steel-Crete Tiles: The steel-Crete tile shall be 20 x 20 x 3 em of an approval quality and color The
tile shall be made as follows:
../ Face tile not less than 8 nun thick of mortar in the propmtion of 2 parts colored cement+ one part
sand+ 80 kilograms of steel powder of silverseet to everyone cubic meter of mix .
../ 2nd layer made of 2 pmts sand + 1 part cement.
• Ceramic tiles (heavy duty and anti-alkaline or anti-acid) not less than 10 mm thickness of first grade
of an approved quality and color.
• Marble tiles
/ The marble tiles should be 2 em thickness of the first grade quality of an approved color.
• Border
/ Border (concrete curbstone) should be (50x30x15 em).
12.5.14 Roofing
The roof shall be provided with following:
e R.C slab. ·
• 2 perpendicular layers of water proofing membrane with thickness not less than 4 mm
each layer with overlap 15 em welding system including skirting 25 em height.
• Covering the water proofing membrane with one layer of geotextile.
• Cement screed with thickness not less than 3.0 em.
• thennal insulation of extruded Polystyrene boards of an approved quality with thickness
not less than 5.0 em and density not less than 36 kg/m3.
• One layer Geottextile membrane (ultraviolet resist) for protection.
• Light weight concrete of average thickness 7.0 em having the slope toward roof drains
(including rain pipes ofP.V.C)
• Sand and cement mortar with average thickness 6.0 em.
• Cement tiles 20x20x2 em with cement mortar included skirting of same tiles.
• Expansion joint about 20 mm are to he filled with bituminous elastic material.
• Floors
o The floor of SIS building should be as followings.
v· 10 em P.C.
v' Insulation of two perpendicular layers of water proofing membrane with thickness not
less than 4mm each layer with overlap 15 em welding system including skirting with
15 em height.
/ R.C slab (according to approved design).
/ Sand and cement mmtar with average thickness 8.0 em for tiles floor.
/ Finishing of floor as specified.
o The floor of fire fighting building, guard room . .. etc should be as followings:.
/ 10 em P.C.
./ Insulation of two perpendicular layers of water proofing membrane with thickness not
less than 4mm each layer with overlap 15 em welding system including skitting with
15 em height.
./ 15 em R.C slab (according to approved design) .
./ Sand and cement mortar with average thickness 8.0 em .
./ Finishing of floor as specified.
12.5.14.1 RainPipes
Rain pipes shall be supplied and fitted. They shall be cast iron pipes of about four inches internal
diameter 3/16 inch thickness, together with all head receptacles, bends and junctions, and other
samples to be submitted for approval.
12.5.15
• Main staircases from ground level shall be of reinforced concrete including their beams, slabs etc.
not less than 2 em for the vettical slab. The plinths shall also be of square slabs of granite of suitable
size and of thickness not less than 2 em .
./ The hand railing for platfonns, pits, stairs, etc. shall be of white metal handrails of an approved
quality and section fixed to steel balusters of square or round steel bars of approved sections
painted with two coats of red lead and two coats of oil paint.
./ The railing shall be of anti-corrosive, and its design according to the approved drawings.
• Secondary staircases leading from basement to ground floor shall be fair face reinforced concrete,
including their beams, landings, slabs, etc ...They shall be treated with hardener additive and steps
should be protected with steel angles 50x5 Ox5. The railings shall be of steel according to the approved
drawings and shall be given the necessary paint.
• Miscellaneous Ironwork
./ All metal work of girders, trusses, framework, ladders, chequer plate coverings, etc., shall be of
approved quality, and the names of the finns supplying such materials, are to be submitted for
approval.
./ All materials for steel work shall be well and clearly rolled to the dimensions, sections and weights
specified or required, and shall be sound and free from cracks, surface flaws, laminations, scales,
blisters, and from rough, jagged and imperfect edges and etfect of every king .
./ The edges of all plates and ends of all angles, channels, bars or other rolled sections shall be truly
square and neatly out and all bars satisfactorily removed before the work is riveted together.
Columns must be erected in true position and strictly ve1tical and roof beams effectually stayed
during the progress of the work.
./ All steel under this item shall have a tensile strength of not less than 40 kilograms per square
millimeters and an elongation according to Egypt ian specification. It must be possible to bend a
cold bar through an angle of 180° around a bar of the same diameter without fracture. It shall
comply with Egyptian Standard Specification for Structural Steel.
./ No welds shall be without the previous permission of the Owner's Engineer. Welding shall comply
with the Egyptian Standard specifications .
./ Any welds carried out without pennission shall be subject to rejection .
./ Should any patts that are required to be bent, joggled, cranked or heated for any purpose, be
overheated, strained or distorted, they will be rejected and must be replaced by sound work.
./ All chequer plates required for coverings shall be of mild steel approved pattern complying with
the E.S.S .and of a minimum thickness of 1/4" The plating shall be suitably stiffened on all sides
with angles, according to approved drawings, electrically welded to the plates .
./ The chequer plate covers shall be of reasonable pmtions so as to be convenient for manhandling.
Two or four standard holes for lifting bars shall be cut in each separate portion of chequer plate
covers. The chequer plates shall be provided with edge protection angles of suitable cross section
fixed in concrete by means of iron-hocked bars electrically welded to the angles .
./ Sufficient detailed drawings and calculations for the ironwork shall be submitted by the Contractor
for approval by Owner's Engineer.
./ The cast iron work shall be made from a metal of high quality. All casting is to be clean and sound
in all respects, free from air or sand holes, lumps, flaws or faults. The specifications of Egyptian
Building Depmtment regarding this item shall be applied .
./ All grout used for bedding steel work in concrete or masonry shall be in neat cement and covered
by the schedule of prices of the ironwork.
• Sanitary Installations
v' All sanitary installation shall be of approved type complying with the British Standard
- Specific~tion~ or eq~i--vaient. ·:r'!:..v ~ontractor shaH arrange fGr tbc ii1:;tc: !1ativn vt t~vV0 vlater c.loscts
in every substation building .
./ The price given shall include the supply and installation of all the combination type WCS, urinals,
lavatories glazed tiles on all the walls, traps, cittems and with all accessories, stop .
./ Equipment for washing the eyes and safety shower shall be provided adjacent to the battery, either
in the same room or immediately adjacent, outside the door to the adjoining room. The eye-
washing facilities shall be ananged as permanently mounted eye-washing shower connected to a
pres-surmised water system .
./ For the toilets, the following equipment shall be supplied and installed:
2 Western type water closet of the low flush type.
Hand washbasin with mixing faucet for hot and cold water.
Urinal with suitable partitions of marble.
Floor drain.
The total number of toasts shall be according to the drawings.
v' For Service room (kitchen)
Stainless steel sinks with (one eye+ one strainer).
Stainless steel floor drain (gully) .
./ 2 Hot Water Heaters electric type, capacity about 50 liters, for every one Hot water heater. The
heater shall be installed connection with the toilets, showers, and panhy .
./ Two Drinking Fountains with Chilled water shall be installed in the Control Building.
./ Piping for hot and cold water shall be made of poly-propylene (HDBE) pipes
./ Solid and wastewater piping shall be made of cast iron .
./ Waste water piping for acid contaminated water shall be made of (HDBE) pipes .
./ Cocks taps, plugs, sockets, showers, unions, etc. The work shall include all necessary excavation,
driving of wells, manholes with their covers, drainage system, glazed stone ware pipes and their
accessories, C.l. Pipes and their accessories, ventilators, Universal C.I. Pipes, water gutters and
their accessories, water pipes, lead pipes, and all complete drainage system including
sedimentation tanks, wells and trenches for drainage, etc.
12.5.15 .1 Material
12.5.15.1.1 General
• All materials used in the works shall be of the best of their kind, and shall conform in quality
and treatment to the conditions specified in the following clauses.
• The Contractor shall be responsible to arrange and obtain all the materials as (gravel, sand,
cement, steel reinforcement, etc.) without any suppoti from EETC and without extra charge.
• The Contractor shall submit samples of all materials, fit- tings and parts which he proposes
to incorporate in the works, for approval and shall not use any of the same un- less and until
so approved.
• Before entering into any sub-contract for materials, or iron works and steel works, the names
of the merchants or finns shall be submitted for approval. Should the owner's Engineer at
any time during the execution of the work not be satisfied with the materials supplied from
such a finn, he shall have the power to cancel his previously given consent as regards supply
of any material from the same firm.
• In case the Contractor does not submit, for the approval of Owner's Engineer the names of
weli-knowll. rirst ciass fmndor the suppiy of tlie mi:neriais, the Owiler's Engineei· sFi'aJi have · .
the power to specifY any particular merchant or finn for supply of such materials, and the
Contractor shall, obtain such materials from the same finn or manufacturer without extra
charge.
12.5.15.1.2 Gravel
• All gravel is to be deseti gravel well washed, free from all soluble salts or ether impurities.
It is to be well graded and is nonnally to pass a mesh of 30 millimeters and be retained on
mesh of 6 millimeters.
• When ordered by the Owner's Engineer, gravel shall be sieved and thoroughly wetted at least
one day before being used in the concrete mixture.
• The contractor should use gravel in concrete mixture that used in construction and also in the
soil replacement and it's forbidden to use crushed lime stone of dolomites.
• Each consignment is to be kept in a separate compattment that can be looked. The key of
the store and its compattments shall be kept with the Owner Engineer.
• The Contractor has to supply full patticulars as to the number of tons of each consignment,
date of grinding, result of test the Owner's Engineer may require its barns and further
infonnation as.
• No cement shall be used in the works without the permission of the Owner's Engineer.
• Cement shall be delivered to site at least 21 days before it is required for use.
• All cement shall fulfill the conditions of the latest standard Specifications for P01tland
cement, cement certified by the chemical Department as not conforming with the above
specifications cannot be used on the works and shall have to be removed as soon as possible
from the cement store.
• The Contractor shall supply all labor and materials for packing samples and shall bear the
cost of their dispatch to the destination prescribed above.
• The contractor shall use P01tland cement for all finishing works (masonry, rendering,
paving, etc.).
• For fo1mdation the contractor should use cement according to the ii~yestigation soil report.
12.5.15.1.5 Asphalt
Only natural asphalt shall be used. The natural asphalt block shall consist of pure, soft
homogeneous calcium car bonate saturated in bitumen and contain no more than two percent (2%)
of clay and not less than twelve percent ( 12%) of bitumen.
12.5.15.1.7 Wood
All wood shall be sound straight, free from flaws , cracks, knots and other defects cut from inner
fibers of trees, only well-seasoned wood shall be used in the permanent work.
• Bars shall be single, and joints shall be avoided as much as possible. No welding shall be
used and, ifjoints are necessary, the layers shall overlap for a suitable length according to
the specification.
• The steel shall comply in other respects with the standards and specifications in force for
structural steel for bridges and general buildings.
• The steel must be cleaned of all scales, dust and Joss rust immediately before depositing
concrete. Reinforcing bars shall be carefully secured in position by means of steel wires and
stirrups.
• The sudden removal of the fonnwork shall cause a thennal shock to the partly hardened
concrete, so the formwork must be removed slowly and with care to avoid the damage of
concrete.
• Form work, either sown or wrought required for the works shall not be measured separately.
Specification of proposed aluminum alloy shall be submitted to the company for approval.
• Prior to laying of the reinforcement bars, all wrought formworks should be coated with one
layer of approved mould oil.
• All joints should be finished properly in a manner accepted by the engineer.
• Fonnwork should be so constructed that no ties, wires, etc. pass through it. Special pmvose
made wall-ties, etc, may be permitted with the approval of the engineer and hey should be
of type such that they are positioned within he concrete member with the cotTect cover.
• Holes left by cones or the like should be made good immediately after the fonnwork is
removed.
• Fillets 2 cmx2 em shall be fanned on all exposed extemal comers by means of an approved
type and quality.
• Cast iron shall have a tensile strength of at least 140 N/nun 2• it shall be made
from the best gray pig and scrap Iron, and shall be close-grained, tough and
uniform in character.
• Malleable iron shall be of the black hemi type with a tensile strength of not
less than 330 N/mm 2 .
Copper, Aluminum and Aluminum Alloys:
• Copper and aluminum stranded conductor material shall meet the
requirements of IEC standards.
• Conductor tubing shall be in accordance with IEC Publication 114.
• Specification of proposed aluminum alloy shall be submitted to the company for approval.
12.6.3 Corrosion Protection
• General : All pmts ofthe work shall be protected against con·osion under service conditions. The
protection shall also prevent corrosion during transport, storage and erection.
• Painting: All ungalvanized extemal surfaces which may be removed for maintenance purposes,
shall be painted at the manufacture's work.
• Gal ~anizing: £ xcepfwhere otherwise specitied, atl fenous pmts shall be galvaniieu. Gaivaliliing
shall be applied by the hot-dip process and shall consist of a continuous coating to minimum thick-
ness. as follows :
Average of Any Individual
Description
Specimens tested Specimen !JIB
The zinc coating shall meet the requirements according to ASTM A123, A153, A239 And A385. All
steel shall be fully fabricated before galvanizing, no machine or shop work, boring, punching etc., will
be allowed after galvanizing. Minor damage to the galvanizing resulting from transpmtation and the
like, shall be repaired at site in an approved manner, e.g. by painting with approved zinc-paint,
containing at least 92 weight percent zinc powder.
The contractor shall submit stress diagrams and calculations, structural details and shop drawings
to the company for approval.
12.6.5 Working Loads
• For the calculation of sag and tension the following temperatures of conductors and eatih
wires shall apply:
./ Minimum temperature of air conductors and earth wires:
./ Maximum temperature of air: + 4 7 °C
./ Maximum temperature of conductors: + 80 °C
./ Maximum temperature of earth wires: +55 °C
• The incoming and outgoing lines will be dead-ended on towers outside the switchyard and
connected line bays at low mechanical conductor tension.
• Loads from phase conductors to earth wires shall be calculated with respect to their cross
sections and span lengths.
• All columns and beams shall be designed to withstand full one-sided unbalanced conductor
, ah.d e~uih wire puil, i.e. no reiief puil Jrom t;Onelucwrs ami eartii wires iri adjacetifbays shall
be considered.
• The horizontal angle of approach of these conductors and emth wires will not exceed + 150
from the Perpendicular.
• Maximum simultaneous working loads on the structures shall be as follows:
./ Seismic load
Seismic load design shall be done according to the EGYPTION CODE, from which the
lowest value is applied.
Minimum total lateral seismic force V assumed to act no concunently in the
V = Z I K C S W where
V: The total lateral force or shear at the base.
Z: Numerical coefficient dependent upon seismic zone.
I: Occupancy importance factor.
K: Numerical coefficient depending on energy reception.
C: Numerical coefficient depending on the period of vibration of the building.
S: Numerical coefficient for site structure resonance.
W: The total dead load
./ Wind Loads:
Item Lit
Compression numbers. 120
-
Main
·
legs . 120
Other members. 180
Redundant members 250
Tension members. 300
12.6.8 Welding
Welding shall be executed by certified welders only and comply with the, requirements of AWS
Dl.l.lap joints shall be avoided whenever possible. Welds intended for pickling before galvanizing
must be continue and free from cavities and pits, which might fonn acid receptacles.
• All structures in the switchyard shall be provided with ladders, steps, screens and guards in
approved positions to facilitate access for inspection and maintenance. Step bolts shall not be
used in the switchyard structures.
• Steel frames, limiting the height and width of loaded vehicles to maximum permissible high of
3.5 m and a width of 3.0 m shall be installed in the switchyard at both ends of the roads.
Size No Unit 1 2 3 4 5
Label height mm 50 74 10 5 21 0 29 7
Text height mm 30 40 60 12 0 16 0
Stem width mm 4.5 6 8 15 20
Frame width mm 5 6 8 15 15
./ One line-destination label, size 4, on both sides of the cross-ann, in the middle phase.
Capacitive voltage transfonners: One label, size 3, in the middle phase.
Earthing switches: One label, size 1, on each operating mechanism.
Line traps: One label, size 3,in one phase or, if required, in both phases.
Lightning arresters: One label, size 3, in the middle phase.
Transfonners: One label, size 5, on the service side.
• Phase markings:
Line exits: One label, size 5, in each phase, on both sides cross-ann.
Earthing switches: One label size 1, on each operating mechanism.
Other apparatuses: One label, size 3, in each phase.
13.7.1.5.3 Fixing: Labels shall be fixed with stainless steel screws:
./ Labels sizes 1, 2 and 3 shall have 2 fixing holes 6mm .
./ Labels sizes 4 and 5 shall have 4 fixing holes 6mm .
./ Enameled labels shall have stainless steel hole reinforcements to avoid damage to the
enamel when fixing.
o Control cable tenninals and, for small load circuits also power tenninals shall be clearly
marked for identification.
• The marking system shall be logically built-up from letters and/or figures in one system
consistently used within the switchgear or control gear.
• Internal wiring within switchboard, control board or apparatus units shall have all wire
ends marked, the marking to include as a minimum the same marking as has the terminal
to which the wire end is connected. The marking shall be carried out with sleeves or
similar. Tape is not pem1itted.
• Current and voltage circuits shall also have phase marking and, where necessary, polarity
marking. Protective earth wires snail be marked with green/yellow.
. • Cables connected to switchboard, control board, external apparatus etc., shall be marked
with cable numbers according to the cable list and core number according to the extemal
connection diagram. In addition, all cable cores shall bear the same marking as the
tenninals to which cores are connected. Marking with glued tape is not permitted.
• The marking shall be indicated with ferrules. The fenules shall be of white insulated
material and be provided with glossy finish to prevent adhesion and dirt.
e - They shaH be cleariy ~nd durabiy marked in biack and shail nm: be affjcted by damp or
oil.
• Trenches with buried cables shall be marked with labels.on walls where applicable or with
labels on posts with one set up at each end of a road crossing, one set up for every point
of change of direction of cable trench, and one set up for each twentieth meter of a cable
trench.
• The trenches shall be provided with waming tapes along all the trenches.
• All labels shall be of plastic or metal outdoors and of enameled metal outdoors, and shall
have the text or symbol engraved. Text and symbols shall be of dark color and the surface
shall be in light.
• All labels shall be in English and shall be subject to the company's approval.
• All labels shall be pennanently fixed to the switchboard and apparatus. Glued labels and
marking tape are not acceptable.
• Some of above required markings and labeling May, according to the company's
approval, be combined or omitted, especially as regards uncomplicated paris of the
equipment.
Warnings: waming markings or notices shall be in English and Arabic will be provided