SAP QM SD Intigration Points
SAP QM SD Intigration Points
By : Krishan
1) Before despatching the final goods to customer, there will be a final inspection
randomly.
2) Once goods despatched to end customer and in that if there is any quality
issues and customer returns the material, at this juncture also, quality inspection
will be carried out on the issue raised by customer. For this SD will raise a
necessary quality notification thru which, the message will be passed on to
quality.
For both the above stages, in material master under Quality view, we would
assign inspection type (one for pre despatch and another one for post despatch).
In material master --> go to quality management view --> select inspection set up
--> select inspection type --> In inspection give 06 and 10 and click on active -->
save it.
So when you do PGR for return material, it will create a inspection lot. So than
QM people will do the required setting and when we do PGR it will go to quality
stock.
Sales Order:-
Integration Points Module
- Availability Check - MM
- Credit Check - FI
- Costing - CO/ MM
- Tax Determination - FI
- Transfer of Requirements - PP/ MM