#405 Maintenance of Emergency Generator

This risk assessment document evaluates the risks associated with maintaining an emergency generator on board a ship. It identifies hazards such as lack of knowledge, improper cable connections, lack of spare parts, power failures, slips and trips, and adverse weather. For each hazard, it analyzes the severity, likelihood, and risk rating both with and without additional controls. The existing controls include lock-out/tag-out procedures, following maintenance instructions, competent crew, spare part availability, and avoiding hazardous areas during maintenance. No additional controls were found necessary to further reduce the risks.

Uploaded by

Tolias Egw
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
2K views2 pages

#405 Maintenance of Emergency Generator

This risk assessment document evaluates the risks associated with maintaining an emergency generator on board a ship. It identifies hazards such as lack of knowledge, improper cable connections, lack of spare parts, power failures, slips and trips, and adverse weather. For each hazard, it analyzes the severity, likelihood, and risk rating both with and without additional controls. The existing controls include lock-out/tag-out procedures, following maintenance instructions, competent crew, spare part availability, and avoiding hazardous areas during maintenance. No additional controls were found necessary to further reduce the risks.

Uploaded by

Tolias Egw
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

AKRON RISK ASSESSMENT R/A NO : 405

TYPE OF ACTIVITY: ROUTINE / NON- DESCRIPTION OF ACTIVITY : MAINTENANCE OF EMERGENCY GENERATOR


ROUTINE

RISK ASSESSMENT GUIDE : RISK MUST BE REDUCED TO AS LOW AS REASONABLY PRACTICABLE (ALARP)
STEP 1 : CONSIDER SEVERITY OF HARM (S) STEP 2 : CONSIDER LIKELIHOOD (L) STEP 3:CALCULATE RISK
1: NEGLIGIBLE: Near Miss or Simple First Aid/ Simple Repairs by ship staff/ Spill within spill trays 1: IMPROBABLE-Event not expected to occur RISK RATING RR = S x L
2: MINOR : Injury require Medical Treatment; MTC/ Repair need external assistance / Spill on deck < 1 m3 2 : RARE: Expected to occur in exceptional situations RR RISK CATEGORY
MODERATE: Serious injury or multiple minor injuries; LTI / Repairs affecting seaworthiness of ship leading to CoC / Spill on
3: 3: POSSIBLE: May occur at some time / occurred in the past
deck > 1 m3 1- 5 L - LOW
CRITICAL : Single fatality, Serious injuries, permanent disability / Requires lay up repairs or extensive drydockings, 3rd
4: 4: LIKELY : Possibility of occurrence of isolated incidents
party claims/ Spill overboard < 100L 6 - 10 M - MEDIUM
CATASTROPHIC : Mutiple Fatalaities or Long Term disabilities/ Total Loss of ship or immediate layup/dry-docking for major
5: 5: CERTAIN: Is expected to occur in most situations
repairs / Major overboard spill > 100 L 11 - 25 H - HIGH

NO HAZARD DESCRIPTION RISK EXISTING CONTROLS RISK RATING RISK ADDITIONAL CONTROLS RESIDUAL RISK RESI-
(WITH CONTROLS IN CATEG (IF NOT REQUIRED, WRITE "N". RATING DUAL
PLACE)
L/M/H IF REQUIRED, LIST OUT THE ADDITIONAL (WITH ADDIT'L RISK
CONTROLS ) CONTROLS)
CAT.
( S x L= RR) (S x L = RR) L/M/H
S L RR S L RR
1. Lack Of Knowledge 1. Improper 1. Competent crew on board. 2 2 4 L N
Maintenance.
2. Follow Makers instructions for over haul..
2. Damage to
machinery 3. Pre work meeting to be carried out.
4. Senior Engineer in attendance through out the
maintenance.
5. Sufficient manpower available.
2. Electric Cables wrongly connected. 1. Damage to the 1. Lock out / Tag out in place. 2 2 4 L N
machinery 2. Follow makers instructions for overhaul. Cable
connection to be made as per installation diagram.
3. Pre work meeting to be carried out.
3. Lack of Spares 1. Improper / 1. Minimum spares for critical machinery available 2 2 4 L N
Incomplete on board at all times.
Maintenance 2. Maintenance carried out only when spares
available on board.

FORM NO: S-20 / REV. 0 / 01 MAR 2010 Page 1 / 2 R/A NO :405


NO HAZARD DESCRIPTION RISK EXISTING CONTROLS RISK RATING RISK ADDITIONAL CONTROLS RESIDUAL RISK RESI-
(WITH CONTROLS IN CATEG (IF NOT REQUIRED, WRITE "N". RATING DUAL
PLACE)
L/M/H IF REQUIRED, LIST OUT THE ADDITIONAL (WITH ADDIT'L RISK
CONTROLS ) CONTROLS)
CAT.
( S x L= RR) (S x L = RR) L/M/H
S L RR S L RR
4. Power failure during emergency 1. Collision , 1. Avoid maintenance in high traffic density areas. 5 2 10 M If break down maintenance the 5 1 5 L
generator overhaul when done in Grounding, Injury 2. Avoid maintenance when navigating in restricted ensure 2 generators are running so
dense traffic area or navigating near in areas or near shallow patches. that there is no power failure
restricted area or near shallow 3. Senior Engineer in attendance through out the
patches. maintenance.
4. Engine room to be kept manned during the
maintenance so that any contingency can be
immediately handled.
5. Slips & Trip Hazards 1. Injury to 1. Proper PPE to be used by all personnel. 2 2 4 L N
personnel 2. Sufficient lighting available in the area.
3. Area free of any tripping hazards. / oil.
6 Adverse weather conditions 1. Injury to 1. Maintenance on Emergency generator will not 2 2 4 L N
personnel / Power be carried out in bad weather.
Outage 2. Master & Officer on watch informed about the
maintenance.

Final Asesssment : Provided no deviations from the recommended control measures, the residual risk assessed is As Low As Resonably Practicable (ALARP).
Supplementary measures include correct use of PPE & Tool Box talks that ensure all workers are fully aware of the control measures.

Residual risk - HIGH : If RR is "High" category, written instructions for conducting the job and approval shall be obtained from the shore office to commence the operation.
Residual risk - MEDIUM: If RR is "Medium" , a constant monitoring of events shall be maintained and ensure all identified preventative and mitigating measures are always in place.

PREPARED BY: TECH. DEPT , S & Q DEPT. APPROVED BY: S & Q MANAGER
01 03 2010

FORM NO: S-20 / REV. 0 / 01 MAR 2010 Page 2 / 2 R/A NO :405