#405 Maintenance of Emergency Generator
#405 Maintenance of Emergency Generator
RISK ASSESSMENT GUIDE : RISK MUST BE REDUCED TO AS LOW AS REASONABLY PRACTICABLE (ALARP)
STEP 1 : CONSIDER SEVERITY OF HARM (S) STEP 2 : CONSIDER LIKELIHOOD (L) STEP 3:CALCULATE RISK
1: NEGLIGIBLE: Near Miss or Simple First Aid/ Simple Repairs by ship staff/ Spill within spill trays 1: IMPROBABLE-Event not expected to occur RISK RATING RR = S x L
2: MINOR : Injury require Medical Treatment; MTC/ Repair need external assistance / Spill on deck < 1 m3 2 : RARE: Expected to occur in exceptional situations RR RISK CATEGORY
MODERATE: Serious injury or multiple minor injuries; LTI / Repairs affecting seaworthiness of ship leading to CoC / Spill on
3: 3: POSSIBLE: May occur at some time / occurred in the past
deck > 1 m3 1- 5 L - LOW
CRITICAL : Single fatality, Serious injuries, permanent disability / Requires lay up repairs or extensive drydockings, 3rd
4: 4: LIKELY : Possibility of occurrence of isolated incidents
party claims/ Spill overboard < 100L 6 - 10 M - MEDIUM
CATASTROPHIC : Mutiple Fatalaities or Long Term disabilities/ Total Loss of ship or immediate layup/dry-docking for major
5: 5: CERTAIN: Is expected to occur in most situations
repairs / Major overboard spill > 100 L 11 - 25 H - HIGH
NO HAZARD DESCRIPTION RISK EXISTING CONTROLS RISK RATING RISK ADDITIONAL CONTROLS RESIDUAL RISK RESI-
(WITH CONTROLS IN CATEG (IF NOT REQUIRED, WRITE "N". RATING DUAL
PLACE)
L/M/H IF REQUIRED, LIST OUT THE ADDITIONAL (WITH ADDIT'L RISK
CONTROLS ) CONTROLS)
CAT.
( S x L= RR) (S x L = RR) L/M/H
S L RR S L RR
1. Lack Of Knowledge 1. Improper 1. Competent crew on board. 2 2 4 L N
Maintenance.
2. Follow Makers instructions for over haul..
2. Damage to
machinery 3. Pre work meeting to be carried out.
4. Senior Engineer in attendance through out the
maintenance.
5. Sufficient manpower available.
2. Electric Cables wrongly connected. 1. Damage to the 1. Lock out / Tag out in place. 2 2 4 L N
machinery 2. Follow makers instructions for overhaul. Cable
connection to be made as per installation diagram.
3. Pre work meeting to be carried out.
3. Lack of Spares 1. Improper / 1. Minimum spares for critical machinery available 2 2 4 L N
Incomplete on board at all times.
Maintenance 2. Maintenance carried out only when spares
available on board.
Final Asesssment : Provided no deviations from the recommended control measures, the residual risk assessed is As Low As Resonably Practicable (ALARP).
Supplementary measures include correct use of PPE & Tool Box talks that ensure all workers are fully aware of the control measures.
Residual risk - HIGH : If RR is "High" category, written instructions for conducting the job and approval shall be obtained from the shore office to commence the operation.
Residual risk - MEDIUM: If RR is "Medium" , a constant monitoring of events shall be maintained and ensure all identified preventative and mitigating measures are always in place.
PREPARED BY: TECH. DEPT , S & Q DEPT. APPROVED BY: S & Q MANAGER
01 03 2010