Unit 5, 6 & 7 Capital Budgeting 1
Unit 5, 6 & 7 Capital Budgeting 1
Capital Budgeting
1. A project requires initial investment of Rs. 40,000 and it will generate annual cash inflows of
Rs. 10,000 for 6 years. You are required to find out pay-back period.
PBP = 4 years
2. From the following information you are required to calculate pay-back period: A project
requires initial investment of Rs. 40,000 and generate cash inflows of Rs. 16,000, Rs. 14,000,
Rs. 8,000 and Rs. 6,000 in the first, second, third, and fourth year respectively.
Sol:
Initial Investment = 40,000
3. A machinery is costing Rs. 75,000; life of the machine is 5 years, depreciation is charged
using SLM and tax rate applicable to the company is 50%. Cash flows before depreciation
and taxes are given to you. Calculate Payback period.
Year 1 2 3 4 5
CIF 30,000 28,000 20,000 15,000 15,000
Sol: Initial Investment = 75,000, Life of Machine 5 years, Dep using SLM, Taxes @ 50%
4. A project costs Rs.20,00,000 and yields annual profits of 300,000 after depreciation but
before taxes. Calculate Payback period if tax rate is 50% and depreciation is charged at
12.5%.
Sol:
Initial Investment = 20,00,000
Depreciation = 12.5%
Dep = 2,50,000
Taxes @ 50%
EBT = 3,00,000
(-) Taxes@50% = 1,50,000
EAT = 1,50,000
(+)Dep = 2,50,000
CFAT = 4,00,000
5. X ltd is considering the purchase of a new machine, which will carry out some operations at
present performed by laborers. Two alternative models, A and B are available for the
purpose. From the following information, prepare a profitability statement for submission to
the management and calculate Payback period.
Depreciation is calculated under straight line method. Taxation may be taken at 50% of net
profit.
Sol:
Calculation of Depreciation:
Life of Machine in
years 5 6
PBP = Initial
Investment/Annual CFAT 2.11 years 2.61 years
Machine A is recommended because it has lesser PBP as compared to Machine B
6. A project costs Rs.10,00,000 and has a scrap value of Rs.1,00,000. Its streams of income
before depreciation and taxes during first year through five years is 2,00,000; 2,40,000;
2,80,000; 3,20,000 and 4,00,000. Assume a 50% tax rate and depreciation on straight line
basis. Calculate the accounting rate of return for the project.
Sol:
Year 1 2 3 4 5 6
X 8,00,000 8,00,000 8,00,000 8,00,000 - -
Y 15,00,000 9,00,000 15,00,000 8,00,000 6,00,000 3,00,000
Calculate ARR for the project and suggest which one is better?
8. The company is considering investment of Rs. 1,00,000 in a project. The following are the
forecast for cash flows after tax, 1st year Rs. 10,000, 2nd year Rs. 40,000, 3rd year Rs.
60,000, 4th year Rs. 20,000 and 5th year Rs.5000. From the above information you are
required to calculate: (1) Pay-back Period (2) Discounted Pay-back Period if rate of
discounting is 10%.
Sol: Initial Investment = 1,00,000; CFATs are given for 5 years
9. The GE Company is considering an investment that will result in a $2,000 cash flow in one
year, a $3,000 cash flow in two years, and a $7,000 cash flow in three years What is the
Financial Management - Alaknanda Lonare
present value of this investment if all cash flows are to be discounted at an 8% rate? Should
GE Company management be willing to pay $10,000 for this investment?
PVCOF = $10,000
Calculation of PVCIF:
As the NPV is negative therefore, GE Company management should not pay $10,000 for this
investment
10. A project cost Rs. 25,000 and it generates cash inflows through a period of five years Rs.
9,000, Rs. 8,000, Rs. 7,000, Rs. 6,000 and Rs. 5,000. If the required rate of return is assumed
to be 10%. Find out the Net Present Value and Profitability Index of the project.
Sol:
11. A project costing Rs. 5,00,000 has a life of 10 years at the end of which its scrap value is
likely to be Rs. 50,000. The firm cut-off rate is 12%. The project is expected to yield an
annual profit after tax of Rs. 1,00,000; Depreciation being charged on straight line basis. At
12% P.A. the present value of the rupee received annually for 10 years is Rs. 5.65 and the
value of one rupee received at the end of 10th year is Re. 0.322. Ascertain the Net Present
Value of the project.
Sol: Cost of Project = 5,00,000; Life of project = 10 years; Scrap value = 50,000; r = 12%;
EAT = 1,00,000; PV of annuity factor for 1 rupee at 12% = 5.65; PV of 1 rupee at the end of
10th year (1/(1+0.12)10)= 0.322
NPV = ?
PVCOF = 5,00,000
Calculation of PVCIF:
EAT = 1,00,000
(+) Depreciation = 45,000
CFAT = 1,45,000
PV of annuity @ 12% = 5.65
PVCIF = 8,19,282
(+) PV of Scrap (50,000*0.322) = 16,099
Total PV of CFAT (PVCIF) = 8,35,381
OR
PVCIF can be calculated as below as well.
Year EAT Dep CFAT PV @12% PVCIF
145,00 12946
1 100000 45,000 0 0.893 4
145,00 11559
2 100000 45,000 0 0.797 3
145,00 10320
3 100000 45,000 0 0.712 8
4 100000 45,000 145,00 0.636 92150
Financial Management - Alaknanda Lonare
0
145,00
5 100000 45,000 0 0.567 82277
145,00
6 100000 45,000 0 0.507 73462
145,00
7 100000 45,000 0 0.452 65591
145,00
8 100000 45,000 0 0.404 58563
145,00
9 100000 45,000 0 0.361 52288
145,00
10 100000 45,000 0 0.322 46686
10* Scrap
* Value** 50,000 0.322 16099
83538
Total PVCIF 1
12. A project is under consideration of a firm. The initial outlay of the project is Rs. 10,000 and
it is expected to generate cash inflows of Rs. 4,000, Rs. 3,000, Rs. 5,000 and Rs. 2,000 in
four years to follow. Assuming 10% rate of discount, calculate the Net Present Value and
Benefit Cost Ratio of the project.
PVOCF = 10,000
Calculation of PVCIF
PVIF @
Year CFAT 10% PVCIF
1 4,000 0.909 3636
2 3,000 0.826 2479
3 5,000 0.751 3757
4 2,000 0.683 1366
PVCIF 11238
PVCOF 10,000
NPV 1238
PI 1.12
Financial Management - Alaknanda Lonare
13. The cost of a project is Rs. 32,400. It is expected to generate cash inflows of Rs. 16,000, Rs.
14,000 and Rs. 12,000 through its three years’ life period. Calculate the Internal Rate of
Return of the Project.
Sol: PVCOF = 32,400; IRR =?
Calculation of PVCIF
Lower Interest Rate + NPV of Lower Rate x (Higher Rate- Lower Rate)
NPV Lower Rate (-) NPV Higher Rate
IRR = 14.94%
14. There are two mutually exclusive projects under active consideration of a company. Both the
projects have a life of 5 years and have initial cash outlays of Rs. 1,00,000 each. The
company pays tax at 50% rate and the maximum required rate of the company has been given
as 10%. The straight line method of depreciation will be charged on the projects. The project
X is expected to generate a net cash inflow before depreciation and taxes of Rs. 40,000
throughout its life and project Y is expected to generate a net cash inflow before depreciation
and taxes of Rs. 60,000, 30,000, 20,000, 50,000 and 50,000 from one to five years
respectively. Compute: PBP, ARR, NPV, PI, and IRR. (HW)
15. The Alpha co. ltd. is considering the purchase of a new machine. Two alternative machine A
and B have been suggested, each having an initial cost of Rs. 4,00,000 and requiring Rs. 20,000
as additional working capital at the end of 1st year. Cash flows after taxes are expected to be as
follows:
4 2,40,000 1,20,000
5 1,60,000 80,000
The company has target of return on capital of 10% and on this basis, you are required to
compare the profitability of the machines and state which alternative you consider financially
preferable.
Sol:
PVCOF = 4,18,181
Calculation of PVCIF
16. M/s Pandey Ltd. is contemplating to purchase a machine A and B each costing Rs. 5,00,000.
Profits before depreciation are as follows:
Calculation of Depreciation:
Financial Management - Alaknanda Lonare
Beginning Dep
Year Bal at the end of the year
amount @12%
1 500,000 60000 440,000
2 440,000 52800 387,200
3 387,200 46464 340,736
4 340,736 40888 299,848
5 299,848 35982 263,866
17. Calculate the NPV of the following project requiring an initial cash outlay of Rs. 20,000 and
has no scrap value after 6 years. The net cash flows after taxes for each year of Rs. 6,000 for six
years. Assume the present value of an annuity of Re. 1 for 6 years at 8% p. a. interest is 4.623.
(HW)
18. After conducting a survey that cost Rs. 2,00,000, X ltd, decided to undertake a project for
placing a new product in the market. The company’s cut off rate is 12%. It was estimated that the
project would cost Rs.40,00,000 in plant and machinery in addition to working capital of
Rs.10,00,000. The scrap value of plant and machinery at the end of 5 years estimated at
5,00,000. After providing for depreciation on straight line basis, profit after tax was estimated as
follows:
Year 1 2 3 4 5
PAT 3,00,000 8,00,000 13,00,00 5,00,000 4,00,000
0
Ascertain, Net Present Value of the project if cost of capital is 12%.
Sol:
Ye
PAT Dep CFAT PVIF PVCIF
ar
300,00 1,000,0 892,85
1 700000 0.893
0 00 7
800,00 1,500,0 1,195,7
2 700000 0.797
0 00 91
1,300,0 2,000,0 1,423,5
3 700000 0.712
00 00 60
500,00 1,200,0 762,62
4 700000 0.636
0 00 2
400,00 1,100,0 624,17
5 700000 0.567
0 00 0
1,000,0 567,42
5 Working Capital 0.567
00 7
500,00 283,71
5 Salvage Value 0.567
0 3
PVCI 5,750,1
F= 40
PVC 5,200,0
OF = 00
Financial Management - Alaknanda Lonare
550,14
NPV = PVCIF - PVCOF
0