Assignment 4 Operations Management
Assignment 4 Operations Management
2022-24
SUBMITTED TO:
Dr. Saurabh Tiwari
SUBMITTED BY:
SUBHESH NARAYAN PADHI
1.Ans
FCFS Sequence A, B, C, D, E, F
Job Sequence Job Work Flow Time Job Due Date Job Lateness
A 6 6 22 0
B 12 18 14 4
C 14 32 30 2
D 2 34 18 16
E 10 44 25 19
F 4 48 34 14
ΣJW=48 ΣFT=152 ΣJL=55
Avg. Completion Time = Sum of flow time / No. of jobs = 152/6 = 25.34 Days
Utilization Metric = (Total Job work / sum of flow time) x100 = (48/152) x100= 31.58%
Avg. no. of jobs in system = sum of flow time/Total job work = 152/48 = 3.17 jobs
Avg. job lateness = Total late jobs/ no. of jobs = 55/6 =9.17 days
2.Ans
SPT Sequence D, F, A, E, B, C
Job Sequence Job Work Flow Time Job Due Date Job Lateness
D 2 2 18 0
F 4 6 34 0
A 6 12 22 0
E 10 22 25 0
B 12 34 14 20
C 14 48 30 18
ΣJW=48 ΣFT=124 ΣJL=38
Avg. Completion Time = Sum of flow time / No. of jobs = 124/6 = 20.67 Days
Utilization Metric = (Total Job work / sum of flow time) x100 = (48/124) x100= 38.71%
Avg. no. of jobs in system = sum of flow time/Total job work = 124/48 = 2.58 jobs
Avg. job lateness = Total late jobs/ no. of jobs = 38/6 =6.3 days
3.Ans
3 9 19 33 42
50
B3 A6 F 10 D 14 C9 E8
B7 A 12 F 15 D 15 C 18 E 16
3 10 22 37 52 70 86