Project
Project
Greetings of Peace!
This is to signify our intention to avail the Local Government Support Fund-Other Financial
Assistance to Local Government Units as provided in Local Budget Circular No. 131 dated January 8,
2021 to finance the Construction, Concreting, Rehabilitation, Repair or Improvement such as but not
limited to the following to wit:
With this, we would like to request for the release of our financial assistance from your end to
sustain and improve our local infrastructure.
Approved by:
Present:
HON. JOMAR M. GUINANDAM - Punong Barangay/Presiding Officer
HON. REY-ARR M. CORONADO - Sangguniang Barangay Member
HON. JOSEPHINE P. COLANGGO - Sangguniang Barangay Member
HON. JUANITA P. VIDAD - Sangguniang Barangay Member
HON. ELENA F. ABRENICA - Sangguniang Barangay Member
HON. ALBERTO M. ESTIMO - Sangguniang Barangay Member
HON. CHARLITO P. TAN - Sangguniang Barangay Member
HON. MELDRED S. NANTES - Sangguniang Barangay Member
HON. CRISPINA M. GUINANDAM - IPMR
HON. MARK JHUN R. CORPUZ - Sangguniang Kabataan Chairperson
RESOLUTION NO. 07
Series of 2023
The Presiding Officer presented to the august body the need to adopt a Barangay Resolution
address to Secretary Amenah F. Pangandaman to allocate some fund amounting Five Million Pesos
(P5,000,000.00) for Solar Power Street Lights in Barangay Legarda Uno, Dinas, Zamboanga del Sur;
WHEREAS, a Solar Power Street Lights project has been seen that has a greater impact not only
providing luminance during night time on the streets but also provides security to the commuters for a
safe travel and accidents and provides no electric bill and minimal maintenance cost;
WHEREAS, there are reports of robbery, snatching and carnapping happening during night time
in our barangay and the neighboring barangays with no street lights installed;
NOW, THEREFORE, after due deliberation and consideration on the matter, on motion of
Sangguniang Barangay Member Hon. Charlito P. Tan, Committee on Infrastructure, and duly seconded
by all members present, it was;
RESOLVED FURTHER, to furnish copy of this Approved Barangay Resolution No. 05, series
of 2023 to the Office of Department of Budget and Management for appropriate and immediate action.
SECRETARY’S CERTIFICATION
ROSELLE I. CORDOVA
Barangay Secretary
Attested by:
PROJECT PROFILE/PROPOSAL
FY 2023 LOCAL GOVERNMENT SUPPORT FUNDS-
FINANCIAL ASSISTANCE TO LOCAL GOVERNMENT UNITS
Approved by:
JOMAR M. GUINANDAM
Punong Barangay
Republic of the Philippines
Province of Zamboanga del Sur
Municipality of Dinas
Barangay Legarda Uno
-o0o-
PROGRAM OF WORKS
NUMBER
DESCRIPTION OF WORK % WEIGHT EQUIPMENT DESCRIPTION
NEEDED AVAILABLE
Mobilization/Demobilization Stake Truck 1
General Requirement One Bagger Mixer 1
Earth Works Welding Machine 1
Reinforced Concrete Works Boom Truck 1
Carpentry Works
Solar Power Street Lights
TOTAL
Name of Project : INSTALLATION OF SOLAR POWER STREET LIGHTS WITH REINFORCED CONCRETE PEDESTAL
Location : Legarda Uno, Dinas, Zamboanga del Sur
Contract Duration : 180 Calendar Days
MARK-UPS IN
ITE TOTAL MARK-UPS TOTAL
ESTIMATED PERCENT
M DESCRIPTION QUANTITY VAT INDIRECT TOTAL COST UNIT COST
DIRECT COST
NO. OCM PROFIT % VALUE COST
I. Mobilization/Demobilization 1 Lot 40,000.00 10% 15% 25% 10,000.00 2,500.00 12,500.00 52,500.00 52,500.00
II. General Requirements 1 Lot 74,000.00 10% 15% 25% 18,500.00 4,625.00 23,125.00 97,125.00 97,125.00
III. Earth Works 1 Lot 74,000.00 10% 15% 25% 18,500.00 4,625.00 23,125.00 97,125.00 97,125.00
IV. Reinforced Concrete Works 1 Lot 647,625.00 10% 15% 25% 161,906.25 40,476.56 202,382.81 850,007.81 850,007.81
V. Carpentry Works 1 Lot 58,625.00 10% 15% 25% 14,656.25 3,664.06 18,320.31 76,945.31 76,945.31
VI. Solar Street Lights 1 Lot 2,915,273.81 10% 15% 25% 728,818.45 182,204.61 911,023.07 3,826,296.88 3,826,296.88
TOTAL 3,809,273.81 952,380.95 238,095.24 1,190,476.19 5,000,000.00
DETAILED ESTIMATE
Mobilization/Demobilization:
Item: 1
Quantity: 1 Lot
Quantity Unit Unit Cost Total
Mobilization/Demobilization 1 Lot 40,000.00 40,000.00
General Requirements:
Item: II
Quantity: 1 Lot
Quantity Unit Unit Cost Total
Temporary Facilities 1 Lot 20,000.00 20,000.00
Project Billboard 1 Lot 6,000.00 6,000.00
Safety & Health 1 Lot 48,000.00 48,000.00
Earth Works:
Item: III
Quantity: 1 Lot
Quantity Unit Unit Cost Total
Materials
Site Clearing 1 Lot 20,000.00 20,000.00
Excavation & Backfilling 120 cu. m. 350.00 42,000.00
Gravel Bedding 6 Lot 1,600.00 9,600.00
Carpentry Works:
Item: V
Quantity: 1 Lot
Materials Quantity Unit Unit Cost Total
Form Lumber 600 bd, ft 33.00 19,800.00
½ Marine Plywood 16 cu. m 1,100.00 17,600.00
CWN 100 kgs 95.00 9,500.00
Pole Thickness:
3.5mm
Solar Lamp Technical Spec
Lamp Body Material : Aluminum Alloy
Power : 200W
Technics : Painted Matte
Illumination Time : 36h
Cell Type : Lithium
Charging Time : 8h
Usage : Garden, Street
IP Rating : IP65
Certification : CE, RoHS
Voltage : 3-6V
With Light Source
Solar Panel : 5V 50W, Poly
Battery : 3.2V / 48000mAh, LiFePO4, 32650
LED Light : White, 300PCS SMD2835
Pole Height
6 meter
RED DOTS are Proposed Installation of Solar Lights:
I. There is a Sangguniang Resolution endorsing the propose project and that the same is part of
the duly approved Barangay Development Investment Program and the Annual Investment
Program of the Barangay Local Government Unit of Barangay Legarda Uno, Dinas,
Zamboanga del Sur;
II. The Barangay Local Government Unit of Legarda Uno, Dinas, Zamboanga del Sur has the
capacity to implement the proposed project either by administration or contract;
III. The Proposed Project of Barangay Local Government Unit of Legarda Uno, Dinas,
Zamboanga del Sur is readily implementable within the prescribed timelines and that there
are no issues related to the site and title, including informal settlers thereon and right-of-way
acquisition;
IV. The Barangay Local Government Unit of Legarda Uno, Dinas, Zamboanga del Sur has
complied with the standards prescribed by the appropriate government agencies and has
secured necessary clearances of Certification from the same agencies before the
implementation of the eligible project(s) e.g., Environmental Clearance;
V. The Barangay Local Government Unit of Legarda Uno, Dinas, Zamboanga del Sur commits
to fund the cost of maintenance and repair;
Doc. No.______________
Page No.______________
Book No.______________
Series of ______________
Republic of the Philippines
City of Pagadian
Zamboanga del Sur
x_______________x
I. There is a Sangguniang Resolution endorsing the propose project and that the same is part of
the duly approved Barangay Development Investment Program and the Annual Investment
Program of the Barangay Local Government Unit of Barangay Legarda Uno, Dinas,
Zamboanga del Sur;
II. The program and/or project shall be implemented in accordance with the plan and existing
policies of the National Government.
Doc. No.______________
Page No.______________
Book No.______________
Series of ______________