Quantity Estimation of Building Basic Health Unit
Quantity Estimation of Building Basic Health Unit
7 Paved 169,514
1 Rehabilition of B H U 408,349
3 04--13 Dismantling brick work in lime or cement mortar Cft 321.75 11.86 3815.15
7 11-09-b Cement plaster 1:4 upto 20' height 1/2" thick sft 8128.08 11.49 93391.64
10 11-23-a-03 Distempering New surface : Three coats sft 7408.08 3.91 28944.11
12 12-17-a P/F brass spring hinges to wire gauzed door. Each 3 61.65 184.95
Sub-Total: 408348.52
Cost Estimate of Internal Eletrification of main Building
S CSR Item
Descreption Unit Qty Rate Amount
No. Coad
8 23-11 Soakage Pit (6'dia x 15' deep) complete Each 1 9,917.15 9917.15
Total : 61524.76
TASK-7
HEALTH FACILTY IMPROVEMENT & RFEHABILITATION OF BASIC HEALTH UNIT MUGHAL KOT FR D.I
KHAN
1 Plain Cement Concrete including placing, compacting, finishing & curing (Ratio 1:4:8)
2 Plain Cement Concrete including placing, compacting, finishing & curing (Ratio 1:2:4)
143.00
Perapet Wall Copping 1 0.75 0.16 17.16
Total:
321.75 cft
Total:
726.75 cft
5 Cement plaster 1:4 upto 20' height 1/2" thick
Deduction
11 First class deodar wood wrought joinery work GI wire guaze fixed to chowkat with 1/2" strip
D2 2 3.50 6.50 45.50
Total: 45.50 sft
12 Prepare & paint new surface door & windows prime coat & 2nd Coat
Description Side No. Width (ft) Height (ft) Quantity (sft)
D1 1 2 4.00 8.50 68.00
D2 1 4 3.50 6.50 91.00
D3 1 4 2.50 6.50 65.00
W1 1 4 5.83 6.00 139.92
W2 1 2 3.00 6.00 36.00
V1 1 4 3.00 2.00 24.00
Total: 423.92 sft
13 Provide grey cement skirting 3/8" thick complete Extra if skirting or dado is finished with pigment
Male Exam: Room Long Wall 2 2 15.25 4 244.00
Exam: Room Short Wall 2 2 12.00 4 192.00
Female Room Long Wall 2 2 15.25 4 244.00
Female Room Short Wall 2 2 12.00 4 192.00
Waiting Room Long Wall 1 3 10.00 4 120.00
Waiting Room Short Wall 2 2 21.50 4 344.00
Bath Long Wall 2 4 5.75 4 184.00
Bath Short Wall 2 2 12.00 4 192.00
Front Wall 2 1 47.75 4 382.00
Total : 2094.00 sft
14 Rehandling of earthwork upto a lead of 25 m.
Description Coverd Area Hight Qty
As per Coverd Area 1095.8125 0.33 361.62
49.25 22.25 1095.8125
Total: 361.62 Cft
15 Plain Cement Concrete including placing, compacting, finishing & curing (Ratio 1:2:4) on Roof
22 11-23-a-03 Distempering New surface : Three coats sft 2834.54 3.91 11074.83
Prepare & paint new surface door &
23 13-06-c-01 sft 276.00 7.14 1971.39
windows prime coat.
Prepare & paint new surface door &
24 13-06-c-02 sft 276.00 10.03 2767.12
windows.Each Subsequent coat.
Sub-Total: 54312.41
Internal Eletrification
CSR Item
S No. Descreption Unit Qty Rate Amount
Coad
Wiring of light point in 3/0.029 PVC
1 15-50 insulated sheathed cable on sahl wood Each 15 867.02 13005.3
strip batten
6 15-81 Supply and Fixing 20 Amp power plug Nos 2 182.7 365.4
CSR Item
S No. Descreption Unit Qty Rate Amount
Coad
8 23-11 Soakage Pit (6'dia x 15' deep) complete Each 1 9,917.15 9917.15
Total : 55215.04
TASK-7
HEALTH FACILTY IMPROVEMENT & RFEHABILITATION OF BASIC HEALTH UNIT MUGHAL KOT FR
D.I KHAN
Estimate for Type 4 House
1 Excavation in foundation of building, bridges etc complete : in hard soil or soft murum
4 Damp proof of cem. conc. 1:2:4 i/c bitumen coat, 1 layer polythene & 2 coats bitumen (2" thick)
Description No Length (ft) Width (ft) Quantity (sft)
Long Wall 2 23.5 0.75 35.25
Cross Wall Of Room 3 17.125 0.75 38.53
Verandia Front Wall 1 11.75 0.75 8.81
Carridor Long Wall 1 13.00 0.75 9.75
Carridor Short Wall 2 6.25 0.75 9.38
Long Wall Kitchen+Bath+WC 2 15.5 0.75 23.25
Cross Wall Kitchen+Bath+WC 3 6.25 0.75 14.06
Cort Yard 1 22.88 0.75 17.16
Cross Wall 1 15.25 0.75 11.44
Total: 167.63 sft
5 Pacca brick work in ground floor Cement, sand mortar 1:4
Description No Length (ft) Width (ft) Depth (ft) Quantity (cft)
Long Wall 2 23.5 0.75 11 387.75
Cross Wall Of Room 3 17.125 0.75 11 423.84
Verandia Front Wall 1 11.75 0.75 11 8.81
Carridor Long Wall 1 13 0.75 11 107.25
Carridor Short Wall 2 6.25 0.75 11 103.13
Long Wall Kitchen+Bath+WC 2 15.5 0.75 11 255.75
Cross Wall Kitchen+Bath+WC 3 6.25 0.75 11 154.69
Cort Yard 1 22.88 4.5 8 823.68
Cross Wall 1 15.25 0.75 8 91.50
Parpet Wall (Total Length) 1 114.16 0.75 1 85.62
Fency Wall 1 16.25 0.75 2 24.38
S-Total: 2466.39 cft
Deduction
D1 1 4.00 0.75 7.00 21.00
D2 3 3.50 0.75 8.50 66.94
D3 2 3.00 0.75 7.00 31.50
D4 1 2.50 0.75 7.00 13.13
W1 2 6.00 0.75 6.00 54.00
W2 1 6.00 0.75 6.00 27.00
W3 1 3.00 0.75 4.00 9.00
S.Total: 213.56
Total: 2252.83
RCC in roof slab, beam, column & other structural members, insitu or precast. Type C (1:2:4)
6
Description No Length Width (ft) Depth (ft) Quantity (cft)
Slabe
Rooms 1 24.25 17 8/9 0.50 217.16
Carridar 1 6.25 13.75 0.50 42.97
Kitchen,Bath, WC 1 15.5 7.5 0.50 58.13
Lintle
D1 1 5.5 0.75 0.5 2.06
D2 3 5 0.75 0.5 5.63
D3 2 4.5 0.75 0.5 3.38
D4 1 4 0.75 0.5 1.50
W1 2 7.5 0.75 0.5 5.63
W2 1 7.5 0.75 0.5 2.81
W3 1 4.5 0.75 0.5 1.69
Projection (Kit,Bath, Ver &
1 27.75 2.00 0.33 18.32
Window)
Total: 359.26 cft
7 Plain Cement Concrete including placing, compacting, finishing & curing (Ratio 1:2:4) On Roof
2 coats of bitumen laid hot using 34 lbs. for %sft over roof & blinded with sand at 1 cft per % sft
8
Description No Length Width (ft) Quantity (cft)
Rooms 1 24.25 17 8/9 434.32
Carridar 1 6.25 13.75 85.94
Kitchen,Bath, WC 1 15.5 7.5 116.25
Total: 636.51 sft
9 S/F of Polythene sheet on roof in two layers as spfd:
Rooms 1 24.25 17.91 434.32
Carridar 1 6.25 13.75 85.94
Kitchen,Bath, WC 1 15.5 7.5 116.25
Total: 636.51 sft
10 Single layer of tiles 10"x5"x1.25" laid over 4" earth and 1" mud plaster on top of RC roof slab
Rooms 1 24.25 17 8/9 434.32
Carridar 1 6.25 13.75 85.94
Kitchen,Bath, WC 1 15.5 7.5 116.25
Total: 636.51 sft
Supply & fabricate M.S. reinforcement for cement concrete (Hot Rold Bars) Grade 40
11
Steel Reinforcement 359.26 6.00 2240 0.96
Total: 0.96 tonne
S/F: of Steel doors 18 SWG MS sheet with angle iron frame 1½"x1½"x1/8", bolt, hinges & paint etc.
12
Description No. Width (ft) Height (ft) Quantity (sft)
D1 1 4 7 28.00
Total: 28.00 sft
13 First class deodar wood wrought joinery in doors and windows etc. complete : 1.5" thick
D2 3 3.50 8.50 89.250
D3 2 3.00 7.00 42.000
15 Provide & fix 20 gauge steel chowkat for doors, windows & CS windows,including holdfast etc :
D2 3 3.5 8.5 89.25
D3 2 3 7 42.00
D4 1 2.5 7 17.50
Total : 148.75 sft
16 Make & fix cleats for doors & windows including hinges and screws.
Cleats 6
6.00
Total: 6.00 Nos
Providing and Fixing steel windows with openable glazed panels With 22 SWG wire gauze : Glass pane
17 3mm
Description No. Width (ft) Height (ft) Quantity (sft)
W1 2 6 6 72.00
W2 1 6 6 36.00
W3 1 3 4 12.00
Total: 120.00 sft
18 MS flat 1/2"x1/8" grill in windows of approved design.
W1 2 6 6 72.00
W2 1 6 6 36.00
W3 1 3 4 12.00
Total: 120.00 sft
19 Prepare & paint new surface door & windows prime coat & 2nd Coat
Description Side No. Width (ft) Height (ft) Quantity (sft)
D2 2 3 6 6 108.00
D3 2 1 6 6 36.00
D4 2 1 3 4 12.00
W1 2 2 6 6 72.00
W2 2 1 6 6 36.00
W3 2 1 3 4 12.00
Total: 276.00 sft
20 Filling, watering and ramming earth under floor with surplus earth from foundation, etc
Rooms 1 22.75 16.41 0.5 186.66
Carridar 1 5.50 12.25 0.5 33.69
Kit, Bath, WC 1 6 14.75 0.5 44.25
Court Yard 1 23.50 14.5 0.5 170.38
Total: 434.98 cft
20 Supplying and filling sand under floor or plugging in wells
Rooms 1 22.75 16.41 0.33 123.20
Carridar 1 5.50 12.25 0.33 22.23
Kit, Bath, WC 1 6 14.75 0.33 29.21
Total: 174.64 cft
21 Plain Cement Concrete including placing, compacting,finishing & curing (Ratio 1:4:8)
Description No Length (ft) Width (ft) Depth (ft) Quantity (cft)
Rooms 1 22.75 16.41 0.33 123.20
Carridar 1 5.50 12.25 0.33 22.23
Kit, Bath, WC 1 6 14.75 0.33 29.21
Court Yard 1 23.50 14.5 0.33 112.45
Total: 287.08 cft
22 Provide & lay topping of concrete 1:2:4, incl. surface finishing & dividing in panels : 2" thick
Description No Length (ft) Width (ft) Quantity (cft)
Rooms 1 22.75 16.41 373.33
Carridar 1 5.50 12.25 67.38
Kit, Bath, WC 1 6 14.75 88.50
Total: 529.20 sft
23 Burnt brick (1st class) pavement on edge grouted with sand including preparation of bed
Description No Length (ft) Width (ft) Quantity (cft)
Court Yard 1 23.5 14.5 340.75
Total : 340.75 sft
24 Cement plaster 1:4 upto 20' height 1/2" thick
Description Side No. Length (ft) Height (ft) Quantity (sft)
Rooms Long Wall 2 2 22.75 11 1001.00
Rooms Short Wall 2 3 16.41 11 1083.06
Carridar Long Wall 1 2 5.5 11 121.00
27 Plain Cement Concrete including placing, compacting,finishing & curing (Ratio 1:3:6)
Description No. Length (ft) Weidth (ft) Height (ft) Quantity (Cft)
Plinth Protiction (around the
Building 1 91.16 3 0.25 273.48
Total: 273.48 sft
28 Plain Cement Concrete including placing, compacting, finishing & curing (Ratio 1:2:4) as a copping
Description No. Length (ft) Weidth (ft) Height (ft) Quantity (Cft)
Copping of Perapet Wall 1 114.16 0.75 0.16 13.70
Total: 13.70 Cft
29 Provide grey cement skirting 3/8" thick complete Extra if skirting or dado is finished with pigment
Description No. Length (ft) Hight (ft) Quantity (sft)
Room 1 Long Wall 2 15 0.5 15.00
Room 1 Short Wall 2 11 0.5 11.00
Room 2 Long Wall 2 12 0.5 12.00
Room 2 Short Wall 2 12 0.5 12.00
Carridar Long Wall 2 12.25 0.5 12.25
Carridar Long Wall 2 5.5 0.5 5.50
Perapet Wall Rooms+carridar 1 117.83 0.5 58.92
Total: 126.67 sft
30 Cast iron rain water down pipe fixed in position : 3" dia
4 12 48.00 Rft
31 Khuras on roof 2'x2'x6"
4 4 Nos
32 Bottom khuras of brick masonry in c/s mortar 1:6,4'x2'x4.5" over 3" cem. concrete 1:4:8
4 4 Nos
TASK-7
HEALTH FACILTY IMPROVEMENT & RFEHABILITATION OF BASIC HEALTH UNIT MUGHAL KOT FR D.I
KHAN
Cost Estimate of Compound Wall
CSR Item
S No. Descreption Unit Qty Rate Amount
Coad
Excavation in foundation of building, bridges
etc complete : in ordinary soil & Filling,
1 3-23-b+3-16-a Cft 5663.25 3.07 17386.18
watering and ramming earth under floor with
surplus earth from foundation, etc
5 11-09-b Cement plaster 1:4 upto 20' height 1/2" thick Sft 6825 11.49 78419.25
7 11-25-a-03 White washing: New surface : Three coats Sft 5375 1.78 9561.59
HEALTH FACILTY IMPROVEMENT & RFEHABILITATION OF BASIC HEALTH UNIT MUGHAL KOT FR
D.I KHAN
ESTIMATE OF COMPOUND WALL
Excavation in foundation of building, bridges etc complete : in ordinary soil & Filling, watering and
1
ramming earth under floor with surplus earth from foundation, etc
Cement Concrete (brick/stone ballast, 1.5" to 2"/nullah shingle well graded and cleaned) in foundation
2
& plinth (Ratio 1:4:8)
3 Pacca brick work in foundation and plinth in Cement, sand mortar 1:6
TASK-7
HEALTH FACILTY IMPROVEMENT & RFEHABILITATION OF BASIC HEALTH UNIT MUGHAL KOT FR
D.I KHAN
Cost Estimate of Brick on Edg Paved
CSR Item
S No. Descreption Unit Qty Rate Amount
Coad
2 Plain Cement Concrete including placing, compacting, finishing & curing (Ratio 1:4:8)