0 ratings0% found this document useful (0 votes) 325 views27 pagesAsphalt Overlays For Highway and Street Rehabilitation
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content,
claim it here.
Available Formats
Download as PDF or read online on Scribd
CE IY |
ASPHALT OVERLAYS
FOR HIGHWAY i
AND STREET i
REHABILITATION .
ne
be eee eee fe
pe
pe
THE ASPHALT INSTITUTE
Manual Senior No. IF
103 Edition
(aliases
NX pin
Say cies
‘Scanned with CemScamert
£.
¥
Chapter UI .
TRAFFIC ANALYSIS
3.01 INTRODUCTION—This chapter gives procedures for determin-
ing traffic effects, expressed as equivalent 80 kN(18,000 Ib) single-axle
load applications (EAL), for input into the overlay design methods
presented in Chapters IV, V and VIII. A standard procedure taken from
The Asphalt Institute manual, Thickness Design—Asphalt Pavements
for Highways and Streets, Manual Series No. 1, (MS-1) is presented
‘along with a simplified procedure taken from The Asphalt Institute
publication, Asphalt Pavement Thickness Design, Information Series
No. 181 (IS-181). The standard procedure should be used unless detailed
information. regarding traffic:characteristics is not available, in which
case the simplified procedure is applicable.
3.02 TRAFFIC VOLUME ESTIMATES—Of primary concern are the
number of axle loads expected to be applied to the pavement during a
given period of time. Knowledge is required of the number and type of
vehicles expected on the highway facility.
‘Most states in the United States, in cooperation with the U.S. Federal
Highway Administration (FHWA), collect truck count and weight data
every one or two years. Truck weight and vehicle count data are usually
available from the local department of highways. Many other countries
also collect this type of information. .
‘When traffic count and classification data are not available, estimates
can be obtained from the data given in Table III-1, Distribution of
Trucks on Different Classes of Highways. This table was compiled from
truck count data collected by the states in cooperation with the FHWA.
The range of percentages in Table III-1 indicates the probable range for
the United States. Individual cases may be either smaller or larger than
the range.
USS, statistical data indicate that the volume of heavy trucks on all
classes of American highways averages about 11 percent of total traffic
volume. Regionally, a range of 2 to more than 25 percent heavy trucks
can be expected, Ten percent heavy trucks is not incommon on urban
highways and the number varies from fewer thin . :0 more than 15 per-
cent. During peak-hour traffic periods the pe: :entage of trucks usually
will-be less than the daily average. Heavy truck traffic during veak-hour
is about one-half the daily average percentage of trucks on urban
arterials, and from-one-half to (wo-thirds on rural highways.
The use of local traffic data is recommended; however, local traffic is
subject to variations and care should be taken in collecting and using
these data.
Scanned by CamScanner
‘Scanned with CemScamerFor two-lane streets and highway the Design Lane i
DEFINITIONS) may be either lane of the pavement fastity, Fer nl
lane streets and highways it is usually the outside lane. Under some con-
ditions more trucks may travel in one direction than in the other. In many
locations heavily-loaded trucks will travel in one direction and empty
trucks in the other direction. In the absence of specific data, Table III-2
may be used for determining the relative proportion of trucks to be ex-
pected for the Design Lane.
‘An overlay may be designed to support the cumulative effects of traffic
for any period of time. The selected period, in years, for which the
overlay is to be designed is called the Design Period (See Article 1.02
DEFINITIONS).
: ‘Traffic growth—and in some cases, no growth or decline—must be an-
ticipated when determining the structural requirements of the overlay.
Normal growth in the United States is about 3 to 5 percent per year com-
pounded. However, new facilities or new developments can generate in-
creases of greater magnitude. Growth rates ranging from 4 to 9 percent
WAVE DEE SuRgested Tor rural highways-and from:
cent for some Interstate highways.
Growth may be accounted for in design using the Growth Factors
given in Table I1I-3. These factors multiplied by the first-year traffic
estimate will give the total volume of traffic expected during the Design
Period.
3.03 ESTIMATING EAL—The recommended traffic analysis pro-
cedure determines the equivalent 80 KN (18,000 Ib) single-axle load ap-
plications (EAL) to be used in the overlay thickness determination. The
following terms apply:
Truck Factor—the number of
axle load applicators contributed by one
© Number of vehicles—total number of vehicles involved. p
EAL is calculated by ‘multiplying the number of vehicles in cach weight
‘tor and obtaining the sum of the pro-
Jass by the appropriate Truck Fact ‘ !
ducts: "EAL = 2 (number of vehicles in each weight class x Truck
Factor). -
‘Truck Factors can be determined for individual trucks of any type or
for combinations of truck types. It is recommended that Truck Factors
be determined for individual truck types (e-8- 2-axle single-units, 3-axle
single-units, 5-ax!" tractor-trailer units,. « .). Typical Truck Leute
given in Table (1-4 for a variety of U.S. truck and high ce an
tions. In certain areas, highway truck-weights may be Lan hi ish a Gis
typical because of traf fic generated by local industries, sucl i au ee
such cases the Truck Factor may be several times the typical ¥2
and local evaluation can be very important.
equivalent 80 KN (18,000 Ib) single-
passage of a vehicle.
Scanned by CamScanner
‘Scanned with CemScameri
DISTRIBUTION OF TRUCKS ON DIFFERENT CLASS OF HIGHWAYS™ .
cant Ta
or Other i 7 mi
ion fal fal uiben sytem
range Range hago “Range Resend FangeReoage flange _Aetage andes
ec em 8 om | om ol eT
Paste ete Be 8 Oe | he OS
Sate or more Bote Oo ee es
A angleunts oot 8 atts sh | attr hke kaha,
White ti es
sae 1s 1 ag) tt] ad eee ae
tote A ee og cial eis co
fon moe eas tm | west bar ab
Airline 8 ohn # oe H| Be fh tu ber
ad 10 % 100 | 168 100
{Srna dl suppl by ta Highway Sttstis Dison, US. Heder Highway Amita :
Asincluding full-railer combinations in some states. ian! os
Scanned by CamScanner
inten es
‘Scanned with CemScamerTABLE II2 PERCENTAGE oF TOTAL TRUCK TRAFFIC IN
“ DESIGN LANE ae
Number of Percentage of
Traffic Lanes Trucks In
(Two Directions) Design Lane
2 50
4 45 (35-48)
6 of more . 40 (25-48)"
Tprobable range.
ROWTH FACTOR”
TABLE Ill-3 G
ranvat Growin Fate, Percent ao :
= a7 om ic
spectore LEA wnare =
sowin Is zero, Growth Factor = Design Period.
30
M Annus! Gi
Scanned by CamScanner
‘Scanned with CemScamerTABLE III DISTRIBUTION OF TRUCK FACTORS FOR DIFFERENT CLASSES OF
{ HIGHWAYS AND VEHICLE!
‘Urban Syatems | All Systems
Vehicle Type Tnterstate Rural Other Rural “Ai Raed “Ail urban
Tange [Average] Range [Average] Fpnge [Average] Range | Average| Range
‘Single-unit rocks
Basle, Ars 002 |o01008| 092 |ooroc| oo
019 Jorso30| 021 Jorsoas| 020
oss |ooo185| 073 oarss7| O87
eozoxe| oo7 |00z017| 007
fos0088| o47 |o29082| 048
foao-to7| 083 loses] 070
fos7-1.15| 098 |0564.70) 095
leo0a| 093 |oo1005) oo2 joovaor
(io31| 026 }o1so42| 021 Jorsasz
is153| 103 os2199) 73 Jozeisa
3016 | 009 Joosozs| oor |onear
11080) 047 [024102] 048 Jossa7e
134| 099 |ogorsa) o73 [asta
be 102 |oes1s9] 095 Joss133
Sale or moro**
‘Al multiple units
All trucks
SEpee S222
fosr1ae| os7 "|oer-150| 0.94 |ager4a| 1100 Jo72158) 09s Jorrs3e
024077] 031 |0.20052| 042 87 | 020 Jo.soss| o40 fozrass
“Compied For data supplied by the Highway Salaies Dvslon, US, Fedeal Highway Admiatnstation
ncluding full traller combinations In some states.
Scanned by CamScanner
ooo
‘Scanned with CemScamerTABLETIIIS TRAFFIC CLASSIFICATIONS
‘Approximate Range—
Tralfic EAL Type of Number of Heavy
Class Street or Highway Trucks Expected During
Design Period
1 5x10? + Parking Lots, driveways $-7,000
i * Light tratlic residential streets
Light tratfic farm roads
W 10" + Residential Streets 7,000-15,000
* Rural farm and residential roads
M108» ‘Urban minor collector streets 70,000-150,000
* Rural minor collector roads
vo. f__+ Urban minor arterial and Nght ____.700,000:1,500,009__
industrial streets
‘Rural major collector and minor
arterial highways
Wor 3x10® = Urban freeways, expressways 2,000,000-4,500,000
and other principal arterial
highways,
* Rural interstate and other
principal arterial highways
Urban interstate highways 7,000,000-15,000,000
+ Some industrial roads :
vi) t07
‘whenever possible the traffic analysis and design procedures given in The
Asphalt Institute manual, Thickness Design—Asphalt Pavements for Highways
and Streets (MS-1) should be used for roads and streets in traffic category IV or
igher.
3.04 DETERMINING DESIGN EAL—The following steps outliné
the procedure for determining Design EAL:
(1) Determine the average number of each type of vehicle expected
on the Design Lane during the first year of traffic.
(2) Sclect from Table II-4, a Truck Factor for each vehicle type
found in step (1).
* (3) Select, from Table III-3, a single Growth Factor for all vehicles
or separate Factors for each vehicle type, as appropriate. :
(4) Multiply the numberof vehicles of each type times the Truck
Factor and the Growth Factor (or Factors) determined in steps (2) and
(3). Sum the values determined to obtain Design EAL.
32
oo
Scanned by CamScanner
‘Scanned with CemScamerKSHEET FOR TRAFFIC ANALYSIS i
EXAMPLE WOR!
*— Four-Lane iod: 20 Years.
sign Period:
Location: Interstate Rural Highway Desig}
Kk 4% Growth EAL
Vehicle ‘Number of Trucl eacler (14223)
Type Vohicies(t) Factor @ 3 4
1 ee
‘Single Unit Trucks = 52,200
Axle, Tire 87,600 x 0.02 x ar = 433/600
2-Axlo, 6-Tire 23600 x 0.19 x a = 400
Axle of More 4400 x + 0.56 x 9. = 449/200
All Singles 115,600 Subtotal 7
Tractor Semi-Trallers and Combinations
axle 2400 «x)= (OST x 29.8 31,900
eaxle 7300 x 0.62 x 29.8 134,900
S-Axle or More. $0200 x 0.94 x 29.8 = 1,406,200
All Tractors, Ete, "59,600 subtotal 1/873,000
All Trucks 175,200 Design EAL = Total 1,832,200
—_—-—Thtasod-on ADT. = 5000,durina Jisst year of trattic, 40 percent In the Design Lane,
E-=-5000, :
12 percent heavy trucks (2-axle, 6-tire and larger) and 12 percent panet antptckup—-———
trucks (axle, 4tire).
‘Average values for Interstate Rural highways from Table IIl-4.
Figure I1-1—Example worksheet for traffic analysis
Figure IlI-1 is an example of a worksheet showing the calculation of
Design EAL for a four-lane highway following the procedure outlined
here.
3,05 SIMPLIFIED PROCEDURE FOR DETERMINING DESIGN
EAL—The simplified traffic analysis procedur: separates traffic into six
classes, as shown in Table III-5. Each class is associated with a particular
equivalent number of 80 KN (18,000 Ib) single-axle load applications
(EAL), the type of highway or street, and the average daily number of
heavy trucks expected on the facility during the design period. Heavy
trucks are described as two axle, six-tire trucks or larger. Pickup, panel
and light four-tire trucks are not included. Trucks with heavy-duty, wide-
base tires are included. The appropriate value of EAL is used with this
procedure.
Scanned by CamScanner
‘Scanned with CemScamer.° Chapter IV
——_-_ evaluation is as follo
’ DEFLECTION PROCEDURE
4.01 EVALUATION FOR OVERLAY DESIGN OF ASPHALT
PAVEMENT STRUCTURE—In many cases evaluation for overlay
design will be undertaken because the pavement in question is rough or is
exhibiting surface distress. In other cases increased traffic volume or
changes in axle loadings may be anticipated, and an evaluation made to
determine whether or not a structural overlay is needed. The pavement
deflection procedure presented in this chapter can be useful for both
cases,
The general procedure for using pavement deflections for structural
ee
“1. Establish the length of pavement
evaluation,
7 2. Perform a deflection survey.
7 3. Calculate the representative rebound deflection (RRD).
v 4, Estimate the design EAL (EAL,).
v 5. Determine the overlay thickness.
4.02 LENGTH OF PAVEMENT FOR STRUCTURAL EVALUA-
TION—Pavement condition, subgrade strength, and drainage conditions
usually will vary over the length of a pavement being considered for
overlay. As a consequence it may be possible to reduce costs within the
same contract limits by designing different thicknesses of overlay for dif-
ferent sections of pavement. Where visual inspection or test data clearly
indicate differences, it is recommended that the pavement be divided into
Separate design sections, and that overlay thicknesses be designed
separately for each section.
In some cases deflection data may be available sufficient for
establishing separate design sections by locating areas having similar
deflection characteristics. Basically the procedure involves plotting
deflection data by stations, selecting adjacent areas that appear to have
the same average deflection, and testing for statistical significance, ,
_ 4.03 DEFLECTION SURVEY—The magnitude of pavement deflec-
lion is an indicator of the ability of the Pavement to withstand traffic
loading. Research in several different areas in North America has
Sstablished correlations between wheel load, pavement rebound deflec-
w
ided in the structural
Scanned by CamScanner
‘Scanned with CemScamerFigure 1V-1—Benkelman Beam
tion and repetitions of load. These correlations, measured under a stand-
ardized loading, may be used to evaluate the structural adequacy of
Pavements. They also may be used to determine the extent of corrective
action, if any is.needed. To make such evaluations, representative deflec-
tions must be measured and traffic must be analyzed. apy
For measuring pavement deflections there are available a number of
nondestructive devices which attempt to simulate the loading response
Scanned by CamScanner
‘Scanned with CemScamer_esuting from a moving whee! load. Severat approaches are availab
cluding measuring static deflection using full-scale loads, and measul
dynamic deflections using dynamic steady-state loads or single dynamic--™
impact loads. |
CSince the Benkelman Beam has probably the most widely-developed
data base from its use in measuring deflection on highway pavements, the
basic procedure described in this manual is based on a rebound test pro-
cedure using this device. Details on the use of the Benkelman Beam,
Dynaflect and Road Rater, are included in Chapter XV.)
v Using the Benkelman Beam, (Figure [V-1) pavement deflections are
obtained for the project under study by testing the outer, wheel-path at a
minimum of ten locations selected within each section of equal, or nearly
equal, performance (based on the results of a condition survey), or a
minimum of 12 per kilometre (20 per mile). The random sampling tech-
nique (See Chapter XIV) is used to select the test locations. A represen-
tative rebound deflection (RRD) value is the mean of measured rebound
deflections, which have been adjusted for temperature and most critical
period of the year, plus two standard deviations. This value encompasses
approximately 97 percent of all deflections measured.--
est locations having adjusted deflections greater than the mean of ad-
justed rebound deflections plus two standard deviations should be con-
sidered for local treatment. Additional deflection measurements should
be made to determine the extent of such weak areas. These locations may
require patching or local increases in thickness to provide uniform sup-
port for the entire length of the section. Deflection measurements
representing these special treatment locations are omitted from calcula-
tions to obtain the representative deflection~
The Benkelman Beam has a narrow 3.66m (12 ft) beam that is placed
between the dual tires of a rear wheel of a loaded truck. The foot, or
probe, located at the end of the beam, rests on the pavement under the
rear axle and between the tires. The beam is pivoted at a point 2.44m (8
ft) from the probe end. The truck moves ahead at creep speed and the
total pavement rebound deflection is read on a dial gauge. (Rebound
deflection is the amount of vertical rebound of a surface that occurs
when a:load is removed trom the surface.)
:/4,04 REPRESENTATIVE REBOUND DEFLECTION—When the
deflection tests on the pavement section are completed, the Gare
pavement rebound deflections are used to determine a Representative ie
bound Deflection for the design section. This value is the mean Te Te:
bound deflections which have been multiplied by a temperature atest
ment factor for reference to 21°C (70°F) and, if necessary, @ cr
‘Scanned by CamScanner
‘Scanned with CemScamer
|
|period adjustment factor, plus two standard deviations. The Represen-
tative Rebound Deflection, then, equals ao
: & + 2s)fe
Where: = the arithmetic mean of the individual valu
been adjusted for temperature
s = standard deviation
temperature adjustment factor
critical period adjustment factor
Standard Deviation: The standard deviation, s, may be computed us
ing the following formula. (This formula is set up for maximum ¢ase
when using a hand calculator or a digital computer.)
[sx2_- Xx
n-
's = standard deviation
x = individual test value, corrected for temperature
¥
ies that have
Where:
= average test value = Z x/n
‘n= number of individual test values
‘Adjustment Factors: Because of changes in temperature and moisture
content, the deflection of a given pavement will usually vary from hour
to hour, from day to day and from one season of the year to the next,
and also may vary from one year to the next for a given reason. For flexi-
ble pavements subjected to frost action, there may be a significant
strength loss in the pavement aggregate base or subgrade during the
spring thaw period as the underlying layers become saturated. This
strength loss will occur regardless of the total strength or overall thickness
of the pavement. However, the amount of strength loss is a function of
the pavement thickness. For instance, it will be less with pavements hav-
ing thicker granular base courses. Also, pavements located in areas with
milder climates having significant rainfall will be subject to more gradual
strength changes than those undergoing the effects of lower temperatures
and frost penetration. Furthermore, the peak deflections for these loca-
tions might occur in the summer or fall instead of the spring.
Because of these effects, corrections to the measured deflections must
take into consideration variations in both temperature and moisture con-
tent, as well as the design and geographical location of the pavement.
The procedure for determining the mean temperature of the asphalt-
bound layers is detailed in Chapter XVI)Figure 1V-2 gives temperatuce
adjustment factor curves for various ihicknesses of dense-graded ag-
38
Scanned by CamScanner
‘Scanned with CemScamerMEAN PAVEMENT. TEMPERATURE, *C
Figure 1V.
THICKNESS OF Un}
eel TREATED aa an
Tete ORea, .
pct mum ATE DASE
so Tk INCHES
BEEN AOA ENT racTons ron
MEAN PAVEMENT TEMPERATURE, °F
ee Oe OR ay Bearer)
TEMPERATURE ADJUSTMENT FACTOR (F)
-2—Average pavement temperature versus
Benkelman Beam deflection adjustment factors for Full-
Depth and three-layered asphalt concrete Pavements
gregate bases. (A thickness of Omm (0 in.) corresponds to a Full-Depth
asphalt concrete pavement.)
If all deflection measurements are made at the same temperature then.
the adjustment can be applied to the mean deflection value. However,
deflection values may be obtained over a period of several hours, during
which time substantial changes can occur in pavement temperature. In
these cases the temperature adjustment should be made before
calculating the mean deflection and standard deviations.
The critical period is the interval during which the pavement is most
likely to be damaged by heavy loads. It is extremely important that the
i i si iod.
Representative Rebound Dellection reflect the most critical perioe
Here are recommended methods for determining the critical period ad-
justment factor:
»”
Scanned by CamScanner
‘Scanned with CamScamer‘A method of estimating pavement life is detailed below. Too man}
trancous forces affect the condition of the pavement for any meth
~tima:ing its life to be considered as anything but an indication.
estimate, however, is a valuable tool to use in planning future
especially if the pavement section is re-evaluated every two or three
to check the estimate and establish the trend of performance.
To estimate how long before an overlay is needed:
1. Determine the Representative Rebound Deflection (RRD) |
described in Article 4.04.
2. Using the Design Rebound Deflection Chart, Figure IV-5, and let
ting the RRD equal the Design Rebound Deflection, obtain ihe
maining EAL, EAL,.
3. Determine the average number of each type of vehicle on th
design section for the current year.
4, Multiply the number of vehicles of each type by the appropriate
Truck Factor selected from Table 111-4. 4
5. Sum the values and divide this number into the EAL, to determine
a Growth Factor.
6. Estimate the traffic growth rate in percent.
7, With the Growth Factor enter Table III-3 in the column represent-
ing the growth rate and find the Design Period for that Factor.
‘The Design Period is the estimated number of years before an
overlay is needed.
Example
‘Tworlane rural highway carrying an average of 5,000 vehicles per day,
10 percent of them being heavy trucks (2-axle, 6-tre, and larger) and |4
percent of them being panel and pick-up trucks (2-axle, 4-tire) Fifty per-
cent of the trucks are in the design lane. Using the results of the
Benkelman Beam deflection tests, estimate the length of time before an
overlay is needed.
1. RRD = 1.08mm (0.042 in.) (See Example, Article 4.04.)
2, Remaining EAL, (EAL,) = 500,000 (from Figure 1V-5).
3 Traffic Analysis:
Scanned by CamScanner
‘Scanned with CemScamerpaneer
015
o0
n
10,000,000 100,900,000
Scanned by CamScanner
‘Scanned with CemScamer
DESIGN REBOUND DEFLECTION, MM~y
7) No. of Truck EAL
ee ‘ Vehicles - Factor* (1x2)
So 2 3
Single Unit Trucks
axle, dre (58) 127, 00 x 0.02 2.300
2axle, 6-tire (12) x 0.21 5,500
\ 3-axle or more GQ) 6 x 0.73 a
Alll singles (73) 159,900 Subtotal z
t Tractor, Semi-Trailer & Combinations
| axle 1) 2,200 x 047 = 7 1000
| 4axle (4) 8,700 x 0.83 = 7
1 S-axle @2) 48,200 x 0.98 = 47,200
All tractors, etc. (27) 59,100 Subtotal = 55,400
All Trucks (100) 219,000 BAL, = Total = 68,200
‘Truck factors for other rural highways from Table M4.
4, Total trucks, per year, design lane = 219,000 EALg = 68,200
5, Growth Factor = EAbr = 500.000 . 7.33
EALy — 68,200
Traffic Growth Rate = 4 percent.
Estimated years before overlay = 6.5 (from Table III-3).
vv B. OVERLAY DESIGN BY DEFLECTION ANALYSIS
To find the thickness of overlay needed:
Determine the Representative Rebound Deflection as described in
Article 4.04.
Estimate the design EAL, (EAL,) that the pavement will be re-
uired to support in the future, after overlay, using the procedure
described in Chapter III.
Enter the overlay thickness chart, Figure IV-6, at the Represen-
tative Rebound Deflection determined in Step 1 and move up ver-
tically to the curve representing the design EAL, (EAL,) deter-
mined in Step 2 (interpo...ce if necessary) Move horizontally to the
Overlay Thickness scale and read the thickness of overlay
required,
1
46
Scanned by CamScanner
c = = s
‘Scanned with CamScamerMETERS
)VERLAY THICKNESS, MILLI!
Oyen oT ASPHALT CONCRETE
eae a
0.000 0.020 oo80 one omeo G10 orm ace aTeD ana
PRD, INCHES
Figure IV-6—Asphalt concrete overlay thickness required to
reduce pavement deflections from a measured to 2 desigx
deflection value (rebound test)
Example
Design an overlay for 2 four-lane Intersuate
average of 16,000 vehicles per day.
c
For the proposed section to be overizid, the ectimeca
10,200,000 and the RRD = 1.l1mm (0.06 in) the &
the R 1 thickoes of
the overlay required is found in Figure 1V-6 19 be 125mm (5 =).
Example
Design an overlay for a fourlane Intersizte raral highway wich 22
average of 8,000 vehicles per day.
1, Representative Rebound Deflection: RRD = Lime @9em)
2. Traffic Analysis: The Volume is $0 percent of the previous exax-
ple or EALy = 5,000,000.
3. Overlay Thickness: From Figure 1V-5 = 100mm .- 0m) 3
This example can be compared to the previous exampic to show icw ©
traffic affects overlay requirements, even though the deflecions are che
same,
a7
‘Scanned with CemScamerChapter V
EFFECTIVE THICKNESS PROCEDURES
FOR STRUC:
DESIGN OF OVERLAYS ON
-The effective thickness pro
jays is based on (he
§ PROCEDUR
5.01 EFFECTIVE THICKNES!
TURAL EVALUATION AND
ASPHALT PAVEMENT STRUCTURES
cedure for the structural evaluation and design of over
concept that pavements deteriorate, ic., have reduced life, after ¢
posure to traffic for extended periods of time. In effect, a pavement
ruses" a part of its total life as a result of load repetitions imposed by
traffic, By the time distress conditions appear on the surface of the paver
ment a certain amount of the useful life of the pavernent has been used
and must be accounted for in the design process. Ac the same time the
“remaining life’ of the existing pavement can be utilized in designing the
pavement for future conditions.
‘The procedure assumes that as a pavement uses part ofits total life it
behaves as if it were an increasingly thinner pavement, i.c., its effective
thickness becomes less and less to account for the expended portion of
the total life of the pavement
“To calculate the effective thickness of an existing pavement it is 1
necessary to know the composition of each pavement layer, the thickness 1
of each pavement layer, and the properties of the subgrade, To complete :
the design process it is also necessary that some estimate be made of the
Future traffic to which the pavement will be exposed after overlay. Tral- e
ficis determined in terms of equivalent 80 KN (18,000 Ib) single axle load
applications (EAL). t
Fhe overlay thickness is the difference between the thickness required
for a new pavement to withstand the future traffic EAL to which the '
pavement will be exposed after overlay and (he effective thickness of the :
existing pavement. .~ d
5,02 SUBGRADE ANALYSIS—o design the thickness of an overlny
using the effective thickness method jt is necessary 10 know the strength
properties of the subgrade. When original desinn records are available,
port limited testing sil i desirable to assure the design engineer that no
Shange in soil conditions has taken place during the life of the existing
caadeay. When original design data are not available, subgrade soll
Strength should be established. Thus, one ofthe first steps inthe effective
thickness procedure is to collect soil specimens to check or determine
Strength values on which to base the required total thickness design, To ‘
wold biased results, random sample locations should be selected in each
Soil type encountered, The subgrade soil samples are tested in the
laboratory to determine their strength values, using the resilient modulus, :
49
Scanned by CamSeanner
RA
‘Scanned with CamScamer(Metric)
= 8.0 + 3.8 (R-value)
(US. Customary) M, (psi) = 1500 CBR or :
= 1155 + 555.(R-value) »~
Alternatively, subgrades can be designated by class using the following |
uideli ?
iidelines. In this procedure subgrade soils are classified into three
Poor soils become quite soft and plastic when wet. Included are those
soils having appreciable amounts‘of clay and fine silt. The coarser silts
and sandy loams also may exhibit poor bearing properties in areas
where frost penetration into the subgrade is a factor. Typical proper-
ties: Resilient modulus = 30 MPa (4,500 psi), CBR = 3, R-value = 6.
Medium soils retain a moderate degree of firmness under adverse
moisture conditions. Included are such soils as loams, silty sands, and
sand-gravels containing moderate amounts of clay and fine silt.
Typical properties: Resilient modulus = 80 MPa (12,000 psi), CBR =
8, R-value = 21
Good subgrade soils retain a substantial amount of their load-support
capacizy when wet. Included are the clean sands and sand-gravels and
soils free of detrimental amounts of plastic materials. Excellent
subgrade soils are unaffected by moisture or frost. They include clean
and sharp sands and gravels, particularly those that are well graded.
Typical properties: Resilient modulus = 170 MPa (25,000 psi), CBR
= 17, Revalue = 43.
The appropriate value of subgrade resilient modulus, M,, is used with
this procedure.
5.03 TRAFFIC ANALYSIS—Design EAL, (EAL,)is estimated using
the procedures outlined in Chapter 111.
~/4.04 EFFECTIVE THICKNESS OF EXISTING PAVEMENT
STRUCTURE—Two methods are presented for determining the effec-
tive thickness, T,, of existing pavement layers. Method 1 involves the use
of a conversion factor tv. the entire Laren ee _ ones
dition rating, plus the use of equivalency fact ors,
various pavement materials to equivalent thicknesses of asphalt concrete.
Scanned by CamScanner
a
‘Scanned with CamScamerMethod 2 involves the use of conversion factors for each pavement I
(based on the ‘condition of each layer prior to overlay) to directly convert
(as yer to an. equivaent thickness of asphalt concrete, THe details of
the two methods follow.
Method 1
The conversion factors (C) given in Figure V-I are based on a remain-
ing life analysis of typical pavement structures using the Present Ser
iceability Index (PSI) as a measure of pavement distress.{PSI is determi
‘ed as described in Chapter Il, Article 2,03, or Chapter XIII,
‘The two curves in Figure V-1 reflect differences in how pavements per-
form after overlay. It has been observed that after overlay some
pavements exhibit a reduced rate of change in PSI, compared to their rate
Pf change before overlay. The upper curve (line A) represents this condi-
tion, The lower curve (line B) represents a projected rate ‘of change in PSI
about the same as before overlay, and is somewhat more conservative.
The choice between the two curves is largely a matter of judgment and
experience.
CONVERSION FACTOR
25
PRESENT SERVICEABILITY INDEX (PS!)
ae
Figure V-1—Conversion factors
The equivalency factors of the emulsion bases in Table V-1_ vary
depending on the characteristics ofthe base. These are identified by Type
I. Il or lll, and have the characteristics described below.
Type |—Emulsified asphalt mixes plant-mixed with processed,
dense-graded aggregates, and having propertics similar to
asphalt concrete.
. 51
'
Bee mee
B¥r ASH
ic
ks
an
w
iy
ur
an
ris
Scanned by CamScanner
‘Scanned with CemScamerType N—Emutsified Asphalt mixes made with semi
i processed, crusher-
Tun, pit-run, or bank-run ‘aggregates, eal
Type M—Emulsitied Asphalt mixes with sands of sity’ sands,
TABLE v1 EQUIVALENCY FACTORS FOR CONVERTING
LAYERS oF OTHER MATERIAL TYPES TO EQUIVALENT
THICKNESSES OF ASPHALT CONCRETE
Material Equivalency
Type Factor (E)
Asphalt Concrete 1.00
Type | Emulsitied asphalt base 0.95 -
Type Il Emulsitied asphalt base 0.83
‘Type Ill Emulsitied asphalt base Os?
The effective thickness, T,, of each existing pavement layer is
calculated by multiplying the actual thickness, T, of each layer by the
conversion factor, C, and the appropriate equivalency factor, E:T, = T
x Cx E. The total equivalent thickness of the pavement is obtained by
summing the individual values for all pavement layers.
(NOTE: The use of Method 1 is'restricted to pavements consisting of
the materials listed in Table V-1 for which equivalency factors have been
established. For pavements containing material types not included in
Table V-1, Method 2 should be used for determining effective thickness.)
Example
otimine the effeive thickness of a twosayer Full-Depth asphal
Pavement, PSI © 2.3. Even though cracked, the cracks ane Not open and
the pavement appears to be stable, It consists of 50mm
surace course and a 1sOmm (Gin) Type ll emuliied a pas base
course. A conversion factor C = 0.70 is selected fe :
Geuvalency factor E = 0.83 forthe Type Il emulsined cone) he
determined from Table V.1. ae
T, (AC) = 50x0.70x1.00 = 35mm (1.4 in.)
T, (Type I) “= 1505 0.70 x0.83 = 87mm ¢
T, (All layers) = 122mm (4.8 in.)
u
Scanned by CamScanner
‘Scanned with CemScameriti termine
Method 2 er conditions are det 3
© nm this method individual pavement yelected from Table V-2. The
and appropriate conversion Ae ier is the product of the actual 1
effective thickness, Te, of hi ia propriate conversion factor: Te = i
thickness, T, of each layer and the ap} ure is the sum of the effective
x C. The Ty of the total pavement struct 1
thicknesses of all the layers. e data on materials to o
There are not sufficient equivalency Ce tabulated conversion t
set specific conversion factors for them. Thus, terials, are in some x
factors in Table V-2, encompassing most paving a ‘are based on a t
+ degree subjective, Although the ranges in values shown are MATT e
subjective analysis, experience has shown that they are reaso! e “
useful for overlay design. bs
Example
Determine the effective thickness of a two-layer asphalt pavement con- che
sisting of a 75mm (3-in.) asphalt concrete surface over a 200mm (8-in.) ya
emulsified asphalt base. The surface shows considerable cracking and of
well-defined ruts in the wheelpaths. The base shows some cracking but
little deformation in the wheelpaths. Conversion factors C = 0.5 for the ral
surface and C = 0.7 for the base are determined from Table V-2. ata
T, (AC surface) = 75x0.5 = 38mm (1.5 in.) ally
T, (base) = 200x0.7 = 140mm (5.5 i sad
T, (All layers) = 178mm (7.0 in.) ates
of
Example ‘om
Determine the effective thickness of a three-layer pavement consisting “(Az
of a 100mm (4-in.) asphalt concrete surface, a 150mm (6-in.) cement han
stabilized base and a-100mm (4-in.) untreated crushed gravel base. The
surface shows numerous transverse cracks and considerable alligator aij
cracking in the wheel paths. The cement-stabilized base shows signs of aff
pumping and loss of stability along the pavement edges. The conversion .
factors, C = 0.5 for the surface, C = 0.3 for the cement-stabilized base CRS
and C = 0.2 for the crushed gravel base, are determined from Table V-2. oe
T, (AC surface) = 100x0.5 = 50mm (2.0 in.) bd
T, (cement-stabilized base) = 150.x0.3 = 45mm (1.7 in.) rban
T, (gravel base) = 100x0.2 = 20mm (0.8 in.) fic is
Te (all layers) 115mm (4.5 in.) asing
3, t
Scanned by CamScanner
‘Scanned with CemScamer@ are they Spply ONLY to
Palicable ts ongharement evaluation for overlay
inal thickness design,
.)
Classification
of Material Description
— of Matera Paco
a) Native
Subgrade in all cases
>) Improved s; -
jubgrade**—predominantly granular
materials—may contain some sil
silt and clay but
have P.l, of 10 or less
©) Lime modified sub:
grade constructed from high
Plasticity soils—P.l, greater than 10.
Granular Subbase or Base—Reasonably well- 0.1-0.2
graded, hard aggregates with some plastic fines
and CBR not less than 20, Use upper part of range
if P.L is 6 or less; lower part of range if P.l. is more
than 6,
mM Cement or lime-fly ash stabilized subbases and 0.20.3
bases** constructed from low plasticity soils—P.1.
of 10 or less,
Vv a) Emutsitied or cutback asphalt surfaces and 0305
bases that show extensive cracking, con-
siderable raveling or aggregate degradation, ap-
preciable deformation in the wheel paths, and
lack of stability,
b) Portland cement conciete pavements, (including
those under asphalt surfaces) that have been
broken into small pieces 0.6 metre (2 ft) or less
in maximum dimension, prior to overlay con-
struction. Use upper part of range when subbase
is present; lower part of range when slab is on
subgrade,
¢)-Cement or lirhe-tly ash stabilized bases** that
have developed pattern cracking, as shown by
reflected surface cracks. Use upper part of
rangq when cracks are narrow and tight; lower
part of range with wide cracks, pumping or
evidence of instability.
factors for con-
7 vanges of Conversion Factors are multiplying
Meee cl inennest of existing structural layers to equivalent thickness or
asphalt concrete.
**Originally meeting m
fied by most state highway
trengths and compaction requirements specl-
anway departments (See Article 1,02 DEFINITIONS),
Scanned by CamScanner
‘Scanned with CemScamerTABLE V-2
“THICKNESS
TO
ION FACTORS FOR CO!
cower PAVEMENT COMPONENTS ~
OF EXISTING
EFFECTIVE THICKNESS (T,) (continued) —-
iin rin
Fa ors”
Classification
of Material
v
vil
of Material
2) Asphalt concrate surtace and base that oxnibit 0.50.7
appreciable cracking and crack patterns.
»
that exhibit some fing cracking, some raveling or
aggtngate degradation, and slight deformation in
the wheel paths but remain: stable.
¢) Appreciably cracked and faulted portland ce-
ment concrete pavement (including such under
asphall surfaces) that cannot be alfectively
undersealed. Slab fragments, ranging in size from
approximately one to four square metres (yards),
and have been well-seated on the subgrade by
heavy pneumatic tited rolling.
a) Asphalt concrete surfaces and bases that 07.09
exhibit some fine cracking, have small intermit-
tent cracking patterns ang slight deformation in
the wheel paths but temain stable.
by) Emutsitied or cutback asphalt surlace and bases
that are stable, generally uncracked. show no
bleeding, and exhibit little deformation in the
wheel paths.
©) Portland cement concrete pavements (including
such under asphalt surlaces) that are stable and
undersealed, have some cracking but contain no
pieces smaller than about one square metre
(yard),
a) Asphalt concrete, including asphalt concrete 0.9.1.0
base, generally uncracked, and with little defor-
mation in the wheel paths.
b) Portland cement concrete pavement that is
stable, undersealed and generally uncracked.
¢) Portland cement concrete base, under asphalt
surface, that is stable, non-puinping and ex-
hibits little reflected surface cracking.
Scanned by CamScanner
‘Scanned with CemScamer
‘
d
'
t—_ EPTH ASPHALT CONCRETE
FULL-DI
Figure V-2—Design chart for FullDepth asphalt concrete
(Sal. Metric)
FULL-DEPTH ASPHALT CONCRETE
Scanned by CamScanner
‘Scanned with CemScamer5.05 CALCULATING OVERLAY THI ee
thickness overlay design procedure g ICKNESS—The effective
ven inthis q
relationship ‘ ni this manual makes use of the
T= 1,-T.
Ty = thickness of overlay
' Ty = thickness of a new pavement required for expected traffic (EAL4)
E and subgrade conditions (M,) after overlay (obtained from Design
Chart V-l or V-2), and
T,. = effective thickness of the existing pavement structure (See Article
5.08)
Example
: Design an overlay for the pavement described below.
| Given: subgrade M, = 82.7 MPa (12,000 psi)
EALg = 2x 106 repetitions
Te (all layers) = 115mm (4.5 in.)
From Design Chart V-1, (V-2),T, = 240mm (9.5 in.)
1, = 1, 1
Ty = 240 - 115 = 125mm (4.9 in.)
Use 130mm (5.0 in.)
Example
Design an overlay for the pavement described below.
Given: subgrade M, = 103.4 PMa (15,000 psi)
: EALy = 3x 108 repetitions
: Te (all tayers) = 178mm (7.0 in)
From Design Chart Vel, (V-2),Ty = 240mm (9.5 in)
To = Ta- Te
Ty = 20 = 178 = 62mm (23 ind
‘Scanned by CamScanner
‘Scanned with CemScamer: -
CORRECTING SURFACE DEFICiENCI
CURFACE PREPARATION AND
ONSTRUCTION OF OVERLAYS
ne
Y —The major reasons for
ise adequate pavements are excessive permeability, sur-
Surface roughness, and surfaces with low skid-resistance. TE
6.01 NEED FOR RENEW
overlaying otherwi Sante
face raveling,
Permeability and Raveling 7
The causes of excessive permeability and raveling usually are thesame:
construction during wet or cold weather, mixtures that lack sufficient
asphalt, or pavements that have not been compacted to proper density.
Any of those causes may affect pavement strength, but not necessarily to
3 ° a
the point where structural distress will develop. The requirements for ef- i
fective corrective treatment of excessive permeability and raveling arethe =
same: a surface treatment or overlay that also seals the surface.
3
Roughness 7
1
Surface roughness may be caused by settlement, raveling, nonuniform
wear, corrugations and similar irregularities. Local structural distress
should be corrected, followed by local or general leveling of minimum
thickness to ensure a smooth riding surface. Leveling should be followed =;
by a surface treatment or overlay. |
‘A distorted cross-section may result in a poor riding surface on an
otherwise satisfactory pavegient. Correction of this deficiency involves
construction of leveling wedges followed by an overlay,
In many cases riding quality can be restored by planing or cold-milling
the rough or distorted surface of the pavement. If it is determined that a
structural overlay is not required, a thin overlay should be applied to
teplace the material removed.
Slippery Surface
Corrective design for a slippery surface requires a skid-resistant surfac-
ing material, Properly designed sand-asphalt or fine-graded asphalt con-
crete made with hard, polish-resistant aggregate is required. In some
cases, surface treatments and slurry seals can also be used effectively. If
hydroplaning is a problem an open-graded wearing or friction course can
be applied. Open-graded courses also can be used to reduce traffic noise.
Scanned by CamScanner _
Se
‘Scanned with CemScamer