Method of Statement For Concrete Works
Method of Statement For Concrete Works
plant
Mutlaq Al-Ghowairi Contracting Company
METHOD STATEMENT FOR CONCRETE WORK,
HANDLING AND PLACING, STEEL REINFORCEMENT
AND FIXING, FORM AND FORMWORK.
Document No:
Date: 20-Nov-22 Rev.0 Contract: SA10C2
Page 1 of 15
Tabuk2 independent sewage treatment
plant
Mutlaq Al-Ghowairi Contracting Company
METHOD STATEMENT FOR CONCRETE WORK,
HANDLING AND PLACING, STEEL REINFORCEMENT
AND FIXING, FORM AND FORMWORK.
Document No:
Date: 20-Nov-22 Rev.0 Contract: SA10C2
INDEX
Page
1. PURPOSE. 3
2. SCOPE. 3
3. REFERENCE DOCUMENTS. 3
4. DEFINITIONS / ABBREVIATIONS. 3
5. RESPONSIBILITY. 3-4
6. TOOLS AND REQUIPMENTS. 4-5
7. WORK PROCEDURE. 5
7.1 Rebar work. 5-6
7.2 Form work. 6-7
7.3 Concrete Cement. 7-8
7.4 Concrete Pouring. 8-10
7.5 Curing 11
7.6 Surface Preparation of Concrete Structure. 11
7.7 Coating Application on Concrete Surface. 11
8. INSECTION AND TESTING. 11
9. DOCUMENTATION. 12
10. HSE REQUIRMENTS. 12
Page 2 of 15
Tabuk2 independent sewage treatment
plant
Mutlaq Al-Ghowairi Contracting Company
METHOD STATEMENT FOR CONCRETE WORK,
HANDLING AND PLACING, STEEL REINFORCEMENT
AND FIXING, FORM AND FORMWORK.
Document No:
Date: 20-Nov-22 Rev.0 Contract: SA10C2
1. PURPOSE.
The purpose of this document is to present the systems of methods and principles to be adopted
in execution rebar cutting, bending & installation, formwork installation, concrete pouring and
Concrete surface preparation of structures for independent sewage treatment plant Tabuk 2 –
Tabuk City.
2. SCOPE
This Method Statement covers all activities rebar cutting, bending & installation, formworks
installation, concrete pouring of different structure and concrete surface preparation of
structures for independent sewage treatment plant Tabuk 2.
3. REFERENCE DOCUMENTS
a. Design Drawing / IFC Drawings.
b. STA – Appendix 1 – Tabuk 2 ISTP Project Specification.
Section 3.7.28: Concrete work.
Section 3.7.29: Concrete handling, placing and curing.
Section 3.7.30: steel reinforcement & fixing.
Section 3.7.31: Forms, Formwork & Falsework.
c. Project Quality Plan.
d. International standard:
ASTM C-150: standard Specification for Portland cement.
BS EN 932-1 1997: Test of General properties of Aggregate part 1 – Method of sampling
BS EN 932-2 1999: test of General properties of Aggregate part 2 – Method for reducing
laboratory sampling.
ASTM D 75-30: standard method of test for sampling of aggregates
ASTM C 136: particle size distribution.
ASTM C 117: Fines Content
ASTM D 2419: Sand Equivalent.
ASTM C 136: Fineness Modulus.
ASTM C 1524: Water Soluble Chloride Content.
BS EN 1744-1: Acid soluble sulphate content (SO3).
BS EN 1744-1: Total Sulphur Content
BS EN 933-3: Flakiness Index (for coarse aggregate only).
BS EN 933-7: Shell Content (for coarse aggregate)
ASTM C 127: Water absorption.
ASTM C 127/128: Specific Gravity or particle Density
ASTM C88: Magnesium Sulfate Soundness
BS EN 1367-4: Volume stability (drying shrinkage test)
ASTM C131/535: Resistance to Fragmentation (Los Angeles Test).
ASTM C40 / AASHTO T21: Organic Impurities.
Page 3 of 15
Tabuk2 independent sewage treatment
plant
Mutlaq Al-Ghowairi Contracting Company
METHOD STATEMENT FOR CONCRETE WORK,
HANDLING AND PLACING, STEEL REINFORCEMENT
AND FIXING, FORM AND FORMWORK.
Document No:
Date: 20-Nov-22 Rev.0 Contract: SA10C2
4. DEFINITIONS/ ABBREVIATIONS
5. CLIENT Saudi Water partnership company (SWPC)
6. CONTRACTOR Mutlaq Al-Ghowairi Contracting Company L.L.C
7. PQP Project Quality Plan
8. HSE Health, Safety and Environment
9. PPE Personal Protective Equipment
10. RESPONSIBILITY :
A. Project Manager (PM): shall ensure that all documents are verified before and after
approval.
B. Construction manager (CM): will ensure that the resources are available to carry out
the work as per schedule.
C. Site Engineers: Shall report to the CM and are responsible for the day to day planning and
supervision as well as implementing the technical requirements, dimensions, and
measurements related to the execution of work and equipment preparation.
Page 4 of 15
Tabuk2 independent sewage treatment
plant
Mutlaq Al-Ghowairi Contracting Company
METHOD STATEMENT FOR CONCRETE WORK,
HANDLING AND PLACING, STEEL REINFORCEMENT
AND FIXING, FORM AND FORMWORK.
Document No:
Date: 20-Nov-22 Rev.0 Contract: SA10C2
D. QA/QC Engineer: Shall report to the project manager and he is responsible for the
implementation of project quality plan and insuring the maintenance and effectiveness of
the project quality systems.
G. Work foreman: Responsible to day to day supervision of the work and ensure works carry
out the work tasks correctly and in a safe manner. He acts as a direct link to between
Construction Manager and the works and he reports the works progress and material
planning through daily report.
H. Surveyor: Shall report to the CM and Site Engineers, also responsible in determining
the precise location, distances, directions and elevation of points, lines and contours
of important features in the survey area. Records the results of surveys and verify the
accuracy of data, prepares plots for documentation Safety Supervisor/Officers: Shall
coordinate to the CM and provides safety guidance and advice from commencement
of activities until completion. He will also raise all safety related issues observed at the
work site to CM for compliance.
Page 5 of 15
Tabuk2 independent sewage treatment
plant
Mutlaq Al-Ghowairi Contracting Company
METHOD STATEMENT FOR CONCRETE WORK,
HANDLING AND PLACING, STEEL REINFORCEMENT
AND FIXING, FORM AND FORMWORK.
Document No:
Date: 20-Nov-22 Rev.0 Contract: SA10C2
Concrete mixer
Fire Extinguishers
Grinder
Survey Instruments
K. WORK PROCEDURE
Page 6 of 15
Tabuk2 independent sewage treatment
plant
Mutlaq Al-Ghowairi Contracting Company
METHOD STATEMENT FOR CONCRETE WORK,
HANDLING AND PLACING, STEEL REINFORCEMENT
AND FIXING, FORM AND FORMWORK.
Document No:
Date: 20-Nov-22 Rev.0 Contract: SA10C2
c. During site delivery rebar shall be stored according to sizes with tags and should be legibly
mark.
d. Bar sizes, spacing, locations and quantities of reinforcement steel will be clearly indicated and
wire reinforcement, bending schedules, and supporting and spacing devices will be shown and
also joints, with applicable joint reinforcement.
f. Bar splicing and placement with projects concrete placing schedule and joint locations will be
indicated in the detail drawings. Standard hooks and minimum bend shall comply with ACI 318,
Section 7. MGC.CO will indicate locations of reinforcement bar cut-offs, splices and development
lengths.
All reinforcement shall be bent at the temperature range of 5°C and 100°C
The straight bar length for a hook of 180° shall be not less than 4 times the bar diameter
or 65mm whichever is the larger
The straight bar length of a hook of 90° shall be not less than 12 times the bar diameter
The straight bar length after hook in stirrups shall be 6 times the bar diameter or 60mm
whichever is the larger
7.2 Formwork
Design formwork in conformance with methodology of ACI 347R for anticipated loads,
lateral pressures, depth of concrete placement and rate of concrete placement.
7.2.1. Products shall comply with:
Page 7 of 15
Tabuk2 independent sewage treatment
plant
Mutlaq Al-Ghowairi Contracting Company
METHOD STATEMENT FOR CONCRETE WORK,
HANDLING AND PLACING, STEEL REINFORCEMENT
AND FIXING, FORM AND FORMWORK.
Document No:
Date: 20-Nov-22 Rev.0 Contract: SA10C2
7.2.2. Tolerance:
Form tolerances comply with the requirements of ACI 117 for tolerances for formed
surfaces except as specified in IFC Drawings.
a. Forms shall be constructed according to required dimensions, plumb, straight and mortar
light, and all joints and seams shall be made mortar-light. Forms shall be substantial,
properly braced, and tied together to maintain position and shape and to resist all pressures
to which they may be subject
b. Provide means for holding adjacent edges and ends of form panels tight and in accurate
alignment to prevent the formation of ridges, fins, offsets, or similar surface defects in the
finished concrete. Forms shall be tight and shall prevent the loss of mortar and fines during
placing and vibration of concrete.
c. Provide exterior corners in concrete members with chamfers as specified.
d. Provide means for removing forms without injury to surface of finished concrete.
e. Do not embed any form-tying device or part thereof other than metal in the concrete
f. Use only form or form-tying methods that do not cause spalling of the concrete upon form
stripping or tie removal.
g. Survey report to be attached with request for inspection in acceptable format with all
required information.
a. Forms, shores, or re-shore shall be removed only after the concrete has reached sufficient
strength to carry the dead weight of concrete plus all applicable construction and external loads
without causing damage, overstress, or excessive or permanent deflection. Comply with
recommendations of ACI 347R.
b. Removal strength is based on field cured specimens tested in accordance with ASTM C39.
c. Do not remove supports and without construction instruction.
d. Minimum allowable time after the last cast concrete is placed before forms, shoring, or wall
bracing may be removed as per below table.
Page 8 of 15
Tabuk2 independent sewage treatment
plant
Mutlaq Al-Ghowairi Contracting Company
METHOD STATEMENT FOR CONCRETE WORK,
HANDLING AND PLACING, STEEL REINFORCEMENT
AND FIXING, FORM AND FORMWORK.
Document No:
Date: 20-Nov-22 Rev.0 Contract: SA10C2
7.3 CONCRETE:
a. Concrete materials.
Grey Cement: ASTM C150, type V, for lean concrete or blinding concrete.and all other structural
concrete Use only one brand of cement throughout the project.
b. Concrete Mixes.
The Concrete Mixes shall be in accordance with:
Nonstructural concrete (28 days design strength equal to 20 N/mm 2):
Lean concrete
Conduits duct banks
All Pre cast concrete elements (28 days design strength equal to 35 N/mm 2):
All cast in place Structural concrete (28 days design strength equal to 30 N/mm 2):
Foundations
Column
Beam
Roof slab
Walls
Paving
Walkways
Above structures
7.4 Concrete Pouring:
a. Before concrete work Civil QC Inspector and Site engineer will make sure the
availability of the resources and clearance from other discipline as follow,
Form work and rebar inspection shall be done and approved by consultant.
Release form available from other discipline for proceed the work.
Enough manpower is available for concrete work.
Standby vibrator is available at site.
For night pouring lighting shall be available for smooth work.
Availability of Safety officer.
Availability of polyethene sheet and burlap for immediate curing.
Availability of bonding agent.
b. Concrete mixing and delivery will be from approved batching plant. Mix design will be
submitted to consultant for Approval. The Design mix will provide the details of materials
certificates, mixing ratio and test results and independent lab for conducting all the tests
including slump, sampling, for workability. Technician will be deployed for this activity.
c. Construction joint must be plan and shall be indicated in the drawing for client review
Page 9 of 15
Tabuk2 independent sewage treatment
plant
Mutlaq Al-Ghowairi Contracting Company
METHOD STATEMENT FOR CONCRETE WORK,
HANDLING AND PLACING, STEEL REINFORCEMENT
AND FIXING, FORM AND FORMWORK.
Document No:
Date: 20-Nov-22 Rev.0 Contract: SA10C2
and approval.
d. At time of placing concrete we ensure that surface on which concrete is to be placed
has been cleaned with no debris, tying wires and that temporary cleaning openings have
been closed/sealed.
e. Prior to having the concrete on site, it is ensured that suitable tools, walkways and
safe secure approach for foot traffic over reinforcement or freshly placed concrete is
deployed.
f. Delivery of concrete will be properly scheduled by a manner that ensure the time
elapsing between mixing and placing is as short as possible, unless retarders have been
incorporated in the mix that have satisfactory demonstrated that workability and other
properties can be retained (concrete supplier document).
g. One set of six cylinders will made from each sample. The Identification numbers of the
cylinder will include the pour number. If any filed result not confirm to the specified
criterion then the Lab Tech will immediately notify the QA/QC who will instruct the
appropriate method of disposition.
h. During the course of the pour the QA/QC and the Laboratory Technician will check
each delivery ticket with attached Concrete batch report to ensure that the concrete
grade of used concrete is that batch is conformant as regards composition. He will record
all data relevant construction operations on each delivery ticket.
Serial number of ticket and data Truck no.
Name of Contractor and location of site Grade concrete.
RMC- mix design number.
Time of loading at suppliers work Quality of concrete.
Arrival and departure time of truck Time of completion of discharge.
Type of the brand and amount of the client, Aggregates and Admixtures.
Total Mixing of water
W/C ratio
i.The Lab Tech will take samples of the concrete at the specified frequency each 100 m3 of
the same mix design and carry out the required test. All field test results will be
recorded. Each sample will be tested in the field for Concrete Temperature: Below
33˚C hot weather
Slump: As per the approved mix design
j. Concrete dropped into place will be dropped vertically. Height of any drop of concrete
will not exceed 1.5m. Temporary openings, using of chute prolonging of the pumping
hose or other means that could reduce the height of concrete dropping will be
deployed.
k.Care will be taken to ensure that the time between placing of different lift of layers of
concrete is short enough to prevent the formation of cold joint that adequate
provision has been made for the number of delivery trucks.
l.The following checks and precautionary measures to be implemented while placing
concrete.
Concrete will be checked for conformity to mix design, grade and type.
Re tempering of concrete after placement is prohibited,
The ambient temperature will be measured and concreting will not be carried
Page 10 of 15
Tabuk2 independent sewage treatment
plant
Mutlaq Al-Ghowairi Contracting Company
METHOD STATEMENT FOR CONCRETE WORK,
HANDLING AND PLACING, STEEL REINFORCEMENT
AND FIXING, FORM AND FORMWORK.
Document No:
Date: 20-Nov-22 Rev.0 Contract: SA10C2
m. Pre-pour inspection of the rebar, from panels, embedded items and construction
joints will be carried out before concrete pouring. Two (2) Concrete pumps will be
engaged for concrete pouring and one pump (42m) will be at the work place for
standby (For main pours exceeding 500m3). The concrete pumps is to be carried.
Internal- type concrete vibrators will be used for concrete compacting during concrete
placing to ensure adequate vibration during the entire pouring stage. In case of time
delayed due to two consecutive layers concrete forming a cold joint formation will be
rectified by applying approved bounding agent in between the joints.
n.The cylinders will be marked uniquely for traceability / identification at a future date,
which will be witness by the client during the time of testing.
Total 6 cylinders 7 Days - 3-cylinder test
28 Days- 3- cylinders test
o. The Laboratory shall test 6 cylinders and reports the results contractor QA/QC will be
reviewed and keep the record.
p. Contingency Measures: Large pours cannot readily be stopped due to failure in
concrete supply or plant breakdown. For this reason. Adequate back up and standby
facilities in all aspects will be provided.
q.The concrete temperature will be measured. Temperature of concrete when deposited
will not be less than 10°c and does not exceed 33°C. Slump test will be carried out to
confirm the workability of concrete and to ensure that the slump is as per mix design
requirements.
r.The concrete will be poured in layers not exceeding 600mm in depth and compacted
with vibrator throughout the entire depth of the layer to achieve uniform compaction.
The vibrator will be withdrawn slowly to prevent formation of voids.
s. Place concrete within 120 minutes after mixing of water to cement and aggregates or
before the drum has revolved 300 revolutions which ever come first.
t.Interval between concrete deliveries shall be such that no more than 20 minutes
interruption elapses during placement of a single foundation or slab, unless approved
by the contractor’s Engineer.
u. Concrete shall not be placed during rain, nor shall rain, be permitted to fall upon
uncured surfaces.
7.4.1. HOT WEATHER CONCRETE
a. General: When hot weather conditions exist that would seriously impair the quality and
strength of concrete, place concrete in compliance with ACI 305R and as specified herein.
b. Curing: Early provide curing for hot weather concreting in accordance with ACI 305R.
c. Mixing: Delivery and Placement: Cool ingredients before mixing to maintain concrete
temperature at time of placement below 32°c. Mixing water may be chilled.
d. Cover reinforcing steel with water-soaked burlap if it becomes too hot, so that steel
temperature will not exceed the ambient air temperature immediately before embedment
in concrete.
7.4.2. Equipment failure during the concrete placement.
Page 11 of 15
Tabuk2 independent sewage treatment
plant
Mutlaq Al-Ghowairi Contracting Company
METHOD STATEMENT FOR CONCRETE WORK,
HANDLING AND PLACING, STEEL REINFORCEMENT
AND FIXING, FORM AND FORMWORK.
Document No:
Date: 20-Nov-22 Rev.0 Contract: SA10C2
During the placement of concrete MGC.Co shall arrange the standby equipment and
concrete batch plant as listed below,
a. Vibrator.
b. Concrete delivery pump.
c. Concrete truck mixer.
d. Concrete batch plant.
e. Power trowel.
7.4.3. Cold Joint.
If, however, a cold joint is formed due to unavoidable reasons, the following procedure is
adopted for treating it as mention below,
a. If concrete is so green that it can be removed manually and if vibrators can penetrate
the surface without much effort, fresh concrete can be placed directly against the old
surface. The old concrete should be covered by fresh concrete as quickly as possible
and the joint thoroughly and systematically vibrated.
b. In case concrete has hardened a bit more but can still be easily removed by a light
hand pick, the surface will be raked thoroughly and the loose concrete removed
completely without disturbing the rest of the concrete in depth and used a approved
concrete bonding agent is placed on the cold joint, fresh concrete is then placed on
the bonding agent layer and the joint is thoroughly and systematically vibrated
penetrating the vibrator deep into the old layer of concrete.
7.5 Curing
a. Keep concrete surface continuously wet by covering with water.
b. Start initial curing after placing and finishing concrete as soon as free moisture has
disappeared from unformed concrete surfaces. Initial curing starts as soon as concrete
achieves initial set.
c. Covering concrete surface with specified absorptive cover,
Thoroughly for saturating cover with water and keeping continuously wet. Place
absorptive cover to provide coverage of Concrete surface and edges with 4” lap
over adjacent absorptive Covers.
d.Water shall be sweet water or applicable raw water. In no case water shall have total
dissolved solid not more than 1000 ppm as per Project specifications.
Note: Casting date shall be clearly marked / tagged on the cast item to ensure that the
minimum duration curing period (7 days) is maintained and achieved.
7.6 Surface preparation of concrete structure:
a. New concrete shall be cured according to ACI 308 and have sufficient time allowed for drying
b. Do not repair defects until concrete has been inspected by the Client.
c. Repair defects including, air voids and bug holes with a nominal diameter or depth greater
than 6 mm, honeycombed areas, visible construction joints, fins, burrs, color and texture
variations and other defects as determined by the Client. Make concrete repairs with an
approved material in accordance with project specification to produce a concrete surface
uniform in color and texture and free of all irregularities.
7.7 Coating application on concrete surface:
Page 12 of 15
Tabuk2 independent sewage treatment
plant
Mutlaq Al-Ghowairi Contracting Company
METHOD STATEMENT FOR CONCRETE WORK,
HANDLING AND PLACING, STEEL REINFORCEMENT
AND FIXING, FORM AND FORMWORK.
Document No:
Date: 20-Nov-22 Rev.0 Contract: SA10C2
10 HSE Requirements
Page 13 of 15
Tabuk2 independent sewage treatment
plant
Mutlaq Al-Ghowairi Contracting Company
METHOD STATEMENT FOR CONCRETE WORK,
HANDLING AND PLACING, STEEL REINFORCEMENT
AND FIXING, FORM AND FORMWORK.
Document No:
Date: 20-Nov-22 Rev.0 Contract: SA10C2
General Requirements
a. Complete guard rail system shall be provided to personnel working at heights more
than 1. 8 m (6 ft.), or personnel shall be provided and shall use a full body harness and
shock-absorbing lanyard attached to a lifeline or substantial anchorage.
b. Concrete or masonry structure shall not be loaded with construction loads unless
supervisor determines that the structure or portion of the structure is capable of
supporting the load.
c. All c o n c r e t e construction activities s h a l l be supervised by a c o m p e t e n t
person who is knowledgeable of the potential hazards and control measures.
Formwork
a. Form work shoring constructed of scaffolding materials and supporting an elevated concrete
slab/ deck more than 300 mm (12 inches) thick shall be considered as a special scaffold.
b. Minimum safety factor of four against failure from all dead and live loads shall be used for
design of tubular steel formwork shoring. Fabricated tubular frame scaffolding shall not be
used for formwork.
c. Formwork shoring, access platforms constructed of scaffolding material shall be erected under
the supervision of a Scaffold Supervisor.
d. Form work materials shall be inspected by an authorized person prior to use. Defective
and damaged materials shall not be used and shall be immediately removed from the site.
e. Concrete formwork shall be plumb in both directions, with the allowable maximum deviation
from the vertical not more than 3 mm/m (1/8 inch per 3 ft.).
f. Damaged erected shoring shall be immediately reinforced or restored. Restoring shall be
provided when necessary, to safely support concrete slabs and beams after stripping or where
members are subjected to extra loads.
g. Personnel shall not be allowed under or near formwork during concrete pouring operations.
All persons not involved in the concrete pouring operation shall not be allowed in the area.
h. Protruding reinforcing steel that presents impalement ha\rd. to personnel shall capped and
necessary protection shall be provided to prevent or limit personnel getting into contact with
the reinforcing steel.
Reinforcing Steel
a. Protruding reinforcing steel that presents impalement hazard to personnel shall capped and
necessary protection shall be provided to prevent or limit personnel getting into contact with
the reinforcing steel.
b. Erected reinforcing steel for walls, columns, piers and other vertical formwork structures shall
be braced and supported to prevent collapse due to possible wind load.
Concrete Placement
a. Concrete Pump and mixer trucks shall be guided by a flagman in maneuvering for concrete pouring.
b. Concrete Pump outriggers shall be in place and outrigger pads used. Outrigger pads shall be at least
three times larger than the outrigger float.
c. Personnel shall not be allowed to ride concrete buckets. Personnel shall not be allowed to work
under concrete buckets while buckets are being elevated or lowered into position.
d. Workers manning vibrator equipment shall not position or work under elevated concrete buckets
suspended from cranes.
e. Wheels of mixer trucks shall be blocked and the brakes engaged to prevent movement.
f. Proper protective equipment shall be worn at all times by all personnel involved in the concrete
Page 14 of 15
Tabuk2 independent sewage treatment
plant
Mutlaq Al-Ghowairi Contracting Company
METHOD STATEMENT FOR CONCRETE WORK,
HANDLING AND PLACING, STEEL REINFORCEMENT
AND FIXING, FORM AND FORMWORK.
Document No:
Date: 20-Nov-22 Rev.0 Contract: SA10C2
pouring operation.
g. Water for eye flushing shall be provided whenever concrete is being poured.
Page 15 of 15