Te Ii, Bput 1
Te Ii, Bput 1
TRANSPORTATION ENGINEERING-II
COURSE CODE-PCCI5304
CREDIT: 3-0-0
Branch- Civil Engineering
Semester:- 6th
2
PREAMBLE
• Ability to design the Railway Geometric Elements for
different conditions
3
SYLLABUS
Module-I
History of Indian railways, component parts of railway track, problems of multi gauge
system, coning of wheels, alignments and survey, permanent way track components ,
Type of rail sections ,creep of rails, wear and failure in rails , Ballast requirements,
sleeper requirements, types of sleepers, various train resistances
Module-II
Geometric design: Gradients and grade compensation, various speeds on a railway track,
super-elevation, horizontal and vertical curves,
Points and crossings, Design of simple turn-out, Signaling and interlocking,
Module-III
Airport site selection, Air craft characteristics, various surface of an airport, Wind rose
diagram, Geometric elements of run way and taxiway , holding apron, parking
configuration , terminal building , visual aids, air traffic control, airport marking and
lighting.
Reference Books:
1. A text book of railway engineering , By S.C.Saxena and M.G.Arora
2. Air-port Engineering by S.K.Khanna and M.G.Arora
3. Railway Engineering by Satish Chandra & MM Agrawal, Oxford University Press.
4
LESSON PLAN
• Lecture-1: Introduction
• Lecture-2: History of Indian Railways
• Lecture-3:alignment & Surveys
• Lecture-4: Permanent Way
• Lecture-5: Gauges In Railway Track, Conning of Wheel
• Lecture-6: Rails
• Lecture-7: Selection of Rail, Wear on Rails
• Lecture-8: Tractive Resistances
• Lecture-9: Rail Joints
• Lecture-10: Welding of Rails, Creep of Rail
• Lecture-11: Sleeper
• Lecture-12: Ballast
• Lecture-13: Stress in the Railway Track
• Lecture-1 4: Track Fittings & Fastenings
• Lecture-15: Introduction to Geometric Design, Gradient
5
LESSON PLAN
• Lecture-16: Speed of The Train on Curve
• Lecture-17: Superelevation or Cant
• Lecture-18: Cant Deficiency, Negative Superelevation
• Lecture-19: Curves, Widening of Gauge on Curve
• Lecture-20: Transition Curve
• Lecture-21: Introduction to Point and Crossing, Turnout
• Lecture-22:Crossings
• Lecture-23:Signaling and Interlocking
• Lecture-24:Aircraft characteristics and Airport site selection
• Lecture-25:Airport obstruction
• Lecture-26:Wind rose diagram
• Lecture-27:Runway design
• Lecture-28:Taxiway design
• Lecture-29:Visual Aids 6
*Under Revision
Lecture-1
INTRODUCTION
• Transportation engineering is the application of technology and
scientific principles to the planning, functional design, operation and
management of facilities for any mode of transportation in order to
provide for the safe, efficient, rapid, comfortable, convenient,
economical, and environmentally compatible movement of people and
goods from one place to other.
• Basic mode of transportation are:
Land
• Roadway
• railway
Water
Air
7
*Under Revision
Airways
Waterways
• slowest among all other modes
• It needs minimum energy to haul unit load through unit distance.
• This can be possible between ports on the sea routes or along the
river
• economical
8
*Under Revision
Railways
• The transportation along the railways track could be advantageous by railways
between the stations both for the passengers and goods, particularly for long
distance.
• It depends upon the road transport i.e. road could serve as a feeder system.
• Energy require to haul a unit load through unit distance by the railway is only ¼
to 1/5 of that required by road.
• Safety
Highways
• It gives the maximum service to one and all
• It gives maximum flexibility for travel with reference to route, direction, time
and speed of travel
• It provide door to door service
• Other modes are depend on it
• It requires small investment for the government
• Motor vehicles are cheaper than other carriers like rail locomotive and wagons
• It saves the time for short distance
• High degree of accident due to flexibility of movement
9
*Under Revision
Classification according to means of communication
• Road transport
• Animal transport
• Rail transport
• Air transport
• Water transport
• Pipeline transport
• Conveyor transport
• Human porter
10
*Under Revision
Classification based on the freedom to move laterally and vertically
• One degree of freedom: (vehicles are vertically and laterally
restrained), Ex- railway , pipeline , conveyor, cableways.
• Two degree freedom: (restrained only vertically), Ex- highway , ships
and boat.
• Three degree freedom: (to move in any plane), Ex- Aeroplane and
underwater vehicle.
Classification according to energy used for movement:
• Human energy
• Animal energy
• Petrol and diesel energy
• Steam energy
• Electrical energy
• Solar energy
• Atomic energy 11
*Under Revision
Advantage of Indian railway
Political advantage
• Railway have united the people of different castes, religions customs and
traditions.
• With the adequate network of railways, the central administration has
become more easy and effective.
• During emergency it mobilising troops and war equipment very
significantly.
• Railway have helped in the mass migration of the population.
Social advantage:
• The feeling of the isolation has been removed from the inhabitants of the
Indian village.
• By travelling together into the compartment without any restriction of
caste, the feeling of the cast difference has disappeared considerably.
• Railway has made it easier to reach places of religious importance.
• It provide a convenient and safe mode of transport for the country. 12
*Under Revision
Economic advantage
• Mobility of people has increased, thereby the congested area can be
relieved of congestion.
• During the famines , railway have played vital role in transportation of
raw materials.
• Growth of industry due to transportation of raw materials through
railway.
• It provide employment to millions of people thus solving the
unemployment problem.
• Land value has been increase due to industrial development.
Techno- Economic advantage
• Cost saving in transportation of long haul bulk traffic.
• Energy efficiency (railway consume one-seventh of fuel used by the
road sector).
• Environment friendliness.
• Higher safety
13
*Under Revision
Lecture-2
HISTORY OF INDIAN RAILWAYS
• Indian Railways is an Indian state owned enterprise, owned and
operated by the Government of India through the Ministry of Railways.
It is one of the world's largest railway networks comprising 115,000 km
(71,000 mi) of track over a route of 65,436 km (40,660 mi) and 7,172
stations In 2014-15.
• The first public railway in the world was opened to traffic on 27
September 1825 between Stockton and Darlington in the UK.
• In 1844, The first proposal for the construction of railways, in India
were submitted to East India Company by Mr. R. M. Stephenson.
• In 16th April 1853, the first railway line between Bombay to Thana(32
km stretch) was opened, it had 14 coaches and was driven by three
engines.
• 1905, railway board was established with one president and two member
under the department of commerce and industry.
14
*Under Revision
Organization of Indian Railway
Name or Railways Date of Headquarters Divisions
Establishment
Central Railway (CR) 05 November 1951 Mumbai Mumbai CST, Bhusawal, Pune, Solapur and Nagpur
Eastern Railway (ER) 14 April 1952 Kolkata Howrah, Sealdah, Asansol and Malda
East Central (ECR) 01 October 2002 Hajipur Danapur, Dhanbad, Mughalsarai, Samastipur and Sonpur
East Cost (ECoR) 01 April 2003 Bhubaneswar Khurda Road, Sambalpur and Waltair
Northern Railway (NR) 14 April 1952 Delhi Delhi, Ambala, Firozpur, Lucknow, Moradabad and Udhampur
North Central (NCR) 01 April 2003 Allahabaad Allahabad, Agra and Jhansi
North – Eastern Railway (NER) 14 April 1952 Gorakhpur Izzatnagar, Lucknow and Varanasi
Northeast Frontier Railway (NFR) 15 January 1958 Guwahati Alipurduar, Katihar, Rangia, Lumding and Tinsukia
North Western (NWR) 01 October 2002 Jaipur Jaipur, Ajmer, Bikaner and Jodhpur
Southern Railway (SR) 14 April 1951 Chennai Chennai, Tiruchirappalli, Madurai and Salem, Palakkad,
Thiruvananthapuram
South – Central Railway (SCR) 02 October 1966 Secunderabad Vijayawada, Secunderabad,Guntakal, Guntur, Hyderabad,
Parbhani and Nanded
South – Eastern Railway (SER) 1955 Howrah Adra, Chakradharpur, Kharagpur and Ranchi
South East Central (SECR) 01 April 2003 Bilaspur Bilaspur, Raipur and Nagpur
South Western Railway (SWR) 01 April 2003 Hubli Hubli, Bangalore and Mysore
Western Railway (WR) 05 November 1951 Mumbai Mumbai Central, Ratlam, Ahmedabad, Rajkot, Bhavnagar
and Vadodara
West Central (WCR) 01 April 2003 Jabalpur Jabalpur, Bhopal and Kota
15
*Under Revision
Classification of Indian Railways
Trunk route
• Maximum permissible speed 120 kmph for BG and 80 kmph for MG, rail
section 52 kg/m and 37.2 kg/m for BG and MG respectivelly.
Main line
• Maximum permissible speed 100 kmph for BG and 75 kmph for MG, rail
section 52 kg/m and 37.2 kg/m for BG and MG respectivelly.
Branch line
• Maximum permissible speed less than100 kmph for BG and less than 75
kmph for MG, rail section 52 kg/m and 37.2 kg/m for BG and MG
respectivelly.
16
*Under Revision
Classification of Indian railway based on speed
criteria
• Group „A‟ line: speed 160 kmph or more, Ex- new Delhi to
Howrah by Rajdhani route.
• Group „B‟ line: maximum sanction speed is 130 kmph, Ex-
Kharagpur to Vijayaward
• Group „C‟ line: all suburban routes of Mumbai, Calcutta and Delhi
• Group „D‟ line: all other routes of the country where maximum
permissible speed is 100 kmph
• Group „E‟ line: all other routes and branch line where the
permissible speed limit is less than 100 kmph.
17
*Under Revision
Lecture-3
ALIGNMENT & SURVEYS
• In a railway project from beginning till its construction, four
• Reconnaissance survey
• Preliminary survey
18
*Under Revision
Traffic survey & Map study
• The object of traffic survey is to make accurate determination of the
potential of available traffic. this is essential both for existing and new
line. For conducting the traffic survey the fallowing factors should be
considered.
Census of population, their density and distribution.
General resources of production like agricultural and industrial
goods.
General character of lands.
General information of fairs, business, religious festivals….etc
should be collected which can attract the traffic.
The nature and volume of export and import, with centre of their
original destination.
Maps are needed i.e. topographical maps, agricultural map and
Industrial maps
19
*Under Revision
Reconnaissance survey
• This is a rough and rapid inspection, both visual and instrumental of
various physical characteristics of the area to determine the suitability of
different alignment from the map study. The objectives of this survey are:
25
*Under Revision
*Under Revision 26
*Under Revision 27
Requirements of an ideal permanent way
• The gauge should be correct and uniform.
• The rails should be in proper level. In a straight track two rails must be
at the same level. On curves the outer rail should have proper super
elevation .
• The alignment should be correct, i.e., it should be free from
irregularities.
• The gradient should be uniform as gentle as possible. Any change of
gradient should be followed by a smooth vertical curve, to give smooth
riding quality.
• The track should be resilient and elastic in order to absorb shocks and
vibrations of running track.
• The track should have enough lateral strength.
28
*Under Revision
Cont…
• The radii and super elevation on curves should be properly designed and
maintained.
• Drainage system must be perfect for enhancing safety and durability of track.
• Joints, including points and crossing which are regarded to be weakest point of
the railway track, should be properly designed and maintained.
• The various components of the track, i.e. , the rails, fittings, sleepers, ballast and
formation must fully satisfy the requirements for which they have been
provided.
• The track structure should be strong, low in initial cost as well as maintenance
cost.
29
*Under Revision
Lecture-5
GAUGES IN RAILWAY TRACK
• It is define as the clear distance between inner or running faces of
two rails.
• Volume and nature of traffic: for heavier loads and high speed, the
wider gauge are required.
*Under Revision 34
Conning of wheel
• The distance between the inside edges of wheel flanges is
generally kept less than the gauge of the track. So there is a gap
between the wheel flanges and running edges of the rails, nearly
equal to 1cm.(3/8”) on either side. Normally, the tread of wheels
is absolutely dead centre of the head of the rail, as the wheels
coned to keep in this central position automatically. These wheels
are coned at a slope of 1 in 20.
35
*Under Revision
Cont…
• The advantages of conning the wheels are:
To reduce the wear and tear of the wheel flanges and rails, which
in due to rubbing action of flanges with inside faces of the rail
head.
To prevent possibility of lateral movement of the axle with its
wheels.
To prevent the wheels from slipping to some extent.
• The disadvantages of coning the wheels t the curve are:
Pressure on outer rail is more while on inner rail it is less, this
result in wear of outer rail.
Due to centrifugal force, the horizontal components tend to turn
the rail out and gauge has widening tendency.
• In order to eliminate or minimise the above demerits “tilting of rails”
is done, in tilting of rails, the base plate or sleeper is not horizontal
but at a slope of 1in 20 inwards. This is known as adzing of sleepers.
36
*Under Revision
*Under Revision 37
Lecture-6
RAILS
• The rails on the track can be considered as steel girders for the
purpose of carrying axle loads. They are made of high carbon
steel to withstand wear and tear.
38
*Under Revision
*Under Revision 39
Functions Of Rails
• Rails provide a hard, smooth and unchanging surface for passage
of heavy moving loads with a minimum friction between the steel
rails and steel wheels.
• The rail material used is such that it gives minimum wear to avoid
replacement charges and failures of rails due to wear.
• Foot should be wide enough so that rails are stable against overturning
especially on curves. 42
*Under Revision
Cont…
• Bottom of the head and top of the foot of rails should be so shaped as to
enable the fish plates to transmit the vertical load efficiently from the
head to the foot at rail joints.
• The centre of gravity of the rail section must lie approximately at mid-
height so that maximum tensile and compressive stresses are equal.
• The tensile strength of the rail piece should not be less than 72 kg/m²
• The rails specimen should withstand the blow of “falling weight test or
tup test” as specified by Indian railway standards without fracture. 43
*Under Revision
Types Of Rail Sections
• Double headed rails ( D.H Rails )
• The shape of the rail was double headed. When the head was worn
out in coarse of time, the rail can be inverted and reused. But
experience showed that smooth running over that surface at the
top was impossible.
44
*Under Revision
*Under Revision 45
*Under Revision 46
*Under Revision 47
*Under Revision 48
Bull headed rails (B.H. Rails)
• The head was made a little thicker and stronger than the lower part.
• Merits:
They keep better alignment and give more solid and smoother track.
The heavy chairs with larger bearing on sleepers give longer life to
wooden sleepers and greater stability to the track.
• Demerits:
• Merits:
• Demerits:
Type of rail
*Under Revision
Details of standard rail section
• 52 MR (i.e. 52 kg/m) rails are suitable for used upto a speed of 130
kmph and traffic density of 20-25 GMT(gross metric tone).
• 60 MR (i.e. 60 kg/m) rails are suitable for used upto a speed of 160
kmph and traffic density of about 30 GMT(gross metric tone).
Rt1 0.0016w
• Where „w‟ weight in tones.
61
*Under Revision
Resistance dependent on speed(Rt2):
• Track irregularities
Rt 2 0.00008 wv
Atmospheric resistance(Rt3):
Rt 3 0.0000006 wv 2
Rg wg
• Resistance due to curve(Rc):
• For BG:
Rc 0.0004 w D
• For MG:
Rc 0.0003w D
• For NG:
Rc 0.0002 w D
Where ‘g’ is the gradient*Under
in Revision
% and ‘D’ is degree of curve
63
Resistance due to starting & Acceleration (RSA)
Resistance due to starting(Rs):
Rs 0.15w1 0.005w2
W1 is the weight of locomotives in tonnes
W2 is the weight of vehicle in tonnes
Resistance due to Acceleration(Ra):
(v2 v1 )
Ra 0.028 w
t
V1= speed in kmph at the beginning of acceleration.
V2= speed in kmph at the end of acceleration.
a= acceleration
t= time taken in seconds during acceleration for achieving the
speed v2 to v1.
w= total weight of train in tonnes.
64
*Under Revision
Wind resistance(Rw)
Rw 0.000017 av 2
• Total resistance:
RT RT 1 RT 2 RSA RW
65
*Under Revision
Hauling Capacity
• Hauling capacity of a locomotive is define as the product
of the coefficient of friction and weight on driving wheel.
• Hauling capacity = µ x w x n
• Where,
µ= coefficient of friction
W= weight on driving axle
N= no. of pair of driving wheels
Condition of rail surface Coefficient of friction
greasy 0.03
Average dampness 0.165
68
*Under Revision
Lecture-9
RAIL JOINTS
• The rail joint are necessary to hold together the adjoining end
of the rails in the correct position, both in horizontal and
vertical planes.
69
*Under Revision
Requirements of an ideal joint
• The two rail ends should remain true in line both laterally and
vertically to avoid wheel jumping.
• The rail joint should provide enough space for free expansion
contraction.
• The joint should full fill the above requirements with minimum of
initial and maintenance cost. 70
*Under Revision
Types of rail joints
Supported rail joint:
• When the rail ends rest on a single sleeper called supported joint.
Suspended rail joint:
• When the rail ends are projected beyond the sleepers called
suspended joint.
Bridge joint:
• When the suspended rail joint are connected by a flat or corrugated
plate called a „bridge plate‟, it is termed as bridge joint.
Base joint:
• It is similar to bridge joint, with the difference that the inner fish
plate are of bar type and outer fish plate are of special angle type.
Welded joint:
• These are the best joint as they full fill nearly all the requirements
of an ideal joint. 71
*Under Revision
Cont….
Staggered or broken joint:
• These joints are generally provided on curves, where the length of outer curved
track is greater than the length of inner curved track. in this type of joint, the
joints of one rail track are not directly opposite to the joint of the other rail track.
Square or even joint:
• This is generally used in straight track, in this type the joint of one rail track are
directly opposite to the joints of other rail track.
Compromise joint:
• When two different rail sections are required to be joined together, it is done by
means of fishplates. This is termed as compromise joint.
Insulated joint:
• When insulating medium is inserted in a rail joint to stop the flow of current
beyond the track circuited part.
Expansion joint:
• In bridge provision for expansion and contraction is kept for girder and rails. This
gap is 2.2 cm in case of “mitred” joint and 7.2 cm for “halved” joint
72
*Under Revision
Insulated joint Suspended joint
Supported
joint
Welded joint
*Under Revision 73
Staggered joint
*Under Revision 74
Lecture-10
WELDING OF RAILS
Purpose of welding:
75
*Under Revision
Advantage of welding rails
• It satisfies the condition of a perfect joint and hence increase the
life of the rail, also reduce the maintenance cost by 20-40%.
• Long length rail being heavier, which resist the vibration due to
moving loads.
Indications of creep:
• Closing of successive expansion spaces at rail joints in the direction of
creep and opening out of joints at the point where the creep is starts.
• Marks on flanges and web on the rail made by spike heads, by scratching
as the rail slide.
Theories of creep:
• Wave theory
• Percussion theory
78
*Under Revision
Wave theory
• The wheels push the wave with a tendency to force the rail in the direction of
traffic
• The wave action can be reduced by
Use of angular heavy ballast
Lesser sleeper spacing
Bigger section of rail
Percussion theory:
• it states that the creep is due to impact of wheels at the rail end ahead at joints.
The creep by this theory increases due to,
• Weak and loose fish bolts
• Loose packing of joints
• Wide expansion gap
• Heavy axle load moving at high speed
79
*Under Revision
Effect of creep
• Sleeper moves out of position, this affect the gauge and alignment of track.
• Rail joints are opened out of their limit and also battered at the ends due to excessive gap
at the joint.
• The point and crossing get disturbed and affect the gauge and alignment.
Measurement of creep:
• Creep indicator
• As per Indian Railway creep should be measured at an interval of 3-months.
• Creep should not be more than 150 mm.
Remedies or prevention of creep
• Pulling back the rails
• Provision of anchors or anticreepers:
Creep anchore should be strong enough to resist the movement of rails due
to creep
The anchore should be uniformly distrubuted over the entire rail length
• Use of steel sleeper
80
*Under Revision
81
*Under Revision
ANCHORS
82
*Under Revision
Lecture-11
SLEEPER
• Sleeper are members generally laid transverse to the rails on
which the rails are supported and fixed, to transfer the loads
from rails to the ballast and subgrade below.
*Under Revision 83
Functions of sleepers
• To hold the rails to correct gauge .
• To hold the rails in proper level or transverse tilt i.e., level in turnouts,
cross-overs, etc., and at 1 in 20 tilt in straight tracks, so as to provide a
firm and even support to rails.
• To act an elastic medium in between the ballast and rails to absorb the
blows and vibrations of moving loads.
• To distribute the load from the rails to the area of ballast underlying it or
to the girders in case of bridges.
*Under Revision 88
*Under Revision 89
Functions of ballast
• It transfers the load from the sleeper to the subgrade and then
distributes it uniformly over a larger area of the formation.
• It holds the sleepers in position and prevents the lateral and
longitudinal movement, due to dynamic loads and vibrations of
moving trains.
• It imparts some degree of elasticity to the track.
• It provides easy means of maintaining the correct levels of the two
levels of the track (i.e., level in straight portions and correct super-
elevation on curves) and for correcting track alignment.
• It provides good drained foundation immediately below the sleepers
and helps to protect the top surface of the formation. This is
achieved by providing coarse and rough aggregates with plenty of
90
voids. *Under Revision
Requirements of the good ballast
• It should be able to withstand hard-packing
• It should not make the track dusty or muddy due to powder under
dynamic wheel loads .
• It should allow for easy drainage with minimum soakage and the voids
should be large enough to prevent capillary action.
• It should not produce any chemical action with rail and metal sleepers.
Dimensions BG MG NG
Depth of ballast 20 to 25 cm 15 to 20 cm 15 cm
Track modulus:
• It is defined as the load per unit length of the rail required to
produce a unit depression in the track.
• It depends upon gauge, type of rail, sleeper density, type and
section of ballast and subgrade.
• It is used in the various equation for finding track stress.
94
*Under Revision
Track stress
Stress in the railway track are produced due to the following,
• The wheel load
• The dynamic effect of wheel load
• The hammer blow
• The horizontal thrust
• Pressure exerted by flanges of wheels on sides of the rail.
• Stress due to the irregularities in the track.
Stress in Sleeper:
• End bound sleeper & centre bound sleeper
• Follow the fig 4.3 and fig 4.4 of Saxena & Arora Book of Railway
Engg.
Stress in Ballast:
• Follow the fig 4.3 and fig 4.4 of Saxena & Arora Book of Railway
Engg. 95
*Under Revision
Stress in Rail
• The rails are continuous beam carried on the sleepers which provide elastic
support. The rail distributes the wheel load to a number of sleepers.
• Bending moment due to single wheel load, follow the fig. 4.1 of Saxena & Arora
Book of Railway Engg.
EI I
M max x 42.34 4
4
4.5
9.25W
d
M max 0.318Wx 4
I 3
• Where, x= Distance from the load to the point of contraflecture in cm.
• d = Deflection of track in cm.
• W= Isolated wheel load in tonnes.
• µ= Modulus of subgrade reaction.
• I= Moment of inertia in cm⁴. 96
*Under Revision
Lecture-14
TRACK FITTINGS & FASTENINGS
• Track fittings and rail fastenings are used to keep the rails in
the proper position and to set the points and crossings
properly. Important fittings commonly used in permanent way
are,
• Fish plate:
• Spikes:
Dog spikes
Screw spikes
Round spikes
Standard spikes
Elastic spikes
• Plates:
Bearing plate
Saddle plate 97
*Under Revision
Cont…
• Keys: • Blocks:
Wooden keys for C.I. chairs Heel blocks
*Under Revision
Track defect on Curve track:
Improper super elevation
Improper radius of the curve
Improper speed
Unequal distribution of loads on two rails
• If all the above elements are properly designed, the possibility
of derailments due to defect in track can be avoided.
Elements of railway track:
• Gradient and grade compensation
• Speed of train
• Radius and degree of curve
• Cant of superelevation
• Curves
• Widening of gauge on curves
105
*Under Revision
Gradient and grade compensation
Gradient:
• It is measured either:
Types of gradient:
• Types of gradient:
• Ruling gradient
• Momentum gradient
• Pusher gradient
107
*Under Revision
Ruling Gradient
• It is defined as the gradient which determines the maximum load that the engine
can haul on the section. it is the maximum gradient allowed on the section.
• Rising gradient must be fallowed by falling gradient.
• A train is able to climb a rising gradient more easily if this rising gradient follows
a falling gradient as the train has an opportunity of attaining high speed over the
falling gradient before reaching the rising gradient.
• Extra pull required = W x gradient
• In plane terrain - 1 in 150 to 1 in 200
• In hilly region – 1 in 100 to 1 in 150
Momentum gradient:
• The gradient which is more severe than the ruling gradient, do not determine the
maximum load of train but on account of their favourable position on track, the
train before approaching them acquires sufficient momentum to negotiate them
for a certain length of track is known as Momentum gradient.
• A necessary qualification for this gradient is that the train should not be stopped
in the territory where it acquires the sufficient momentum to negotiate. Due to
this no signals should be provided on that location. 108
*Under Revision
Pusher or Helper Gradient
• In case of mountainous terrain, instead of limiting the train load, it may be
operationally easy or even be economical to run the train on the basis of load
that the engine can carry on the remaining portion of track and arrange for an
assistant engine (pusher engine) for the portion where the gradient is severe.
Such gradient are known as pusher or helper gradient.
• Ex- On Western Ghats with B.G. track, pusher gradient of 1 in 37 and on
Darjeeling Railway with N.G. track, a gradient of 1 in 25 is provided.
Gradient in Station Yards
• The Gradient at station yards have to be sufficiently low due to the following
reasons;
To prevent the movement of standing vehicles on the track.
To prevent additional resistance due to grade on the starting vehicles.
A certain minimum gradient is required to be provided for drainage.
On Indian Railway, for all a gauges, the maximum gradient permitted in
station yards is 1 in 400 and a minimum gradient of 1 in 1000 is
recommended from drainage.
109
*Under Revision
Grade compensation
• The ruling gradient is the maximum gradient on a particular section,
but if a curve lies on a ruling gradient, the resistance of the track is
increased due to both gradient and curvature beyond the ruling
gradient. In order to avoid resistances beyond the allowable limits,
the gradient are reduced on curves and this reduction in gradients is
known as grade compensation for curves.
• In India, Compensation for curvature are,
For B.G. = 0.04% per degree of curve or 70/R
For M.G. = 0.03% per degree of curve or 52.5/R
For N.G. = 0.02% per degree of curve or 35/R
110
*Under Revision
Lecture-16
SPEED OF THE TRAIN ON CURVE
Case-1:(For transition curves)
• For B.G. and M.G.
V 4.35 R 67 OR V 4.4 R 70
• For N.G.
V 3.6 R 6.1 OR V 3.65 R 6
Case-2:(For non-transitioned curve)
• For B.G. and M.G.
• V = 4/5Th of speed calculated in case-1
• For N.G.
• V = 4/5Th of speed calculated in case-1 111
*Under Revision
Case-3(empirical formula given by Martin’s)
• On B.G. track:
V 0.27Ca Cd R
• On M.G. track:
V 0.347Ca Cd R
• On N.G. track:
Subjected to 50 kmph
V 3.65 R 6
• For high speed train
• Where, V 4.58 R
V= Maximum speed in kmph
Ca= Actual cant in mm
Cd= Cant deficiency permitted in mm
R= Radius in metre
112
*Under Revision
Radius or Degree of Curve
• The degree of the curve is defined as the angle subtended at
the centre by a chord of 100 feet or 30 metres length.
1720
D V=versini
R
V 12.65C 2
R
115
*Under Revision
Relationship of superelevation (e), with
Gauge(G), Speed(v) and Radius of curve(R)
e GV 2
127 R in m. or
e GV 2
1.27 R in cm.
• For B.G. (G= 1.676m)
V2
e 1.315
R In cm
• For M.G.(G= 1.0m)
V2
e 0.80
R in cm Where,
G= Gauge of the track in metres
• For N.G.(G= 0.762m)
V= Speed of the vehicle in kmph
V 2 In cm R = Radius of curve in metre
e 0.60
R 116
*Under Revision
Equilibrium cant
• When the lateral force and wheel loads are almost equal, the cant is
said to be in equilibrium. This equilibrium cant is provided on the
basis of average speed of the train.
• In Indian Railways provide superelevation for equilibrium speed or
average speed, as follows.
• Case-1(maximum sanction speed of the section is more than
50 kmph or Vmax > 50 kmph):
Average speed= ¾ x Vmax
• Case-2(Vmax = 50 kmph):
Average speed = Vmax
• Case-3(Weighted average): n
n v i j
Weighted average=
i , j 1
V n
n
i 1
i 117
*Under Revision
Maximum Superelevation
• The maximum superelevation have been prescribed in Indian
Railways varying from 1/10th to 1/12th of Gauge.
Gauge Maximum S.E. when V ≤ 100 Maximum S.E. for high speed
kmph i.e. V ≥ 120 kmph
Under ordinary Under special 120 kmph 160 kmph 200 kmph
condition (in cm) permission of Chief (in cm) (in cm) (in cm)
Engineer (in cm)
B.G. 14.0 16.5 16.5 18.5 18.5
118
*Under Revision
Lecture-18
CANT DEFICIENCY
• It is the difference between the equilibrium cant necessary for the
maximum permissible speed on a curve and the actual cant provided on
the basis of average speed of train.
M.G. 5.1 _
Example-6
• Calculate the maximum permissible speed on a curve of
high speed B.G. track having the following particulars.
Degree of curve= 1ᵒ
Amount of superelevation= 8.5 cm
Length of transition curve= 140 m
Maximum sanctioned speed= 160 kmph
124
*Under Revision
Lecture-19
CURVES
Necessity:
• To bypass the natural or artificial obstacles.
• To provide easier gradients by diversions from the straight
route.
• To balance the earth work in excavation and cutting.
Effect of curvature:
• Lateral bending of rails due to the rigid wheel base of
vehicles.
• Extra vertical load on the inner or outer rail depending on
the amount of superelevation and speed of the vehicle.
Due to above effects and objections to curvature use, it is
desirable to avoid the use of curve at bridge, tunnel, level-
crossings, steep gradients, deep cuttings, steep gradient and
station yards. 125
*Under Revision
Widening of Gauge on Curve
• Due to the rigidity of the wheel base, when the outer wheel of the
front axle strikes against the outer rail, the outer wheel of the inner
axle bears a gap with the outer rail. Provision should be made for
this gap, otherwise there is every possibility of tilting rails
outwards.
13B L
2
d
R
• Where,
B= Rigid wheel base in metres.
For B.G. Track, B=6 m
For M.G. Track, B=4.88 m
R= Radius of the curve in m.
L= Lap of flange in m.= L 0.02 h2 D.h
h= Depth of wheel flange below rail top level in cm
D= Diameter of wheel in cm.
126
*Under Revision
Lecture-20
TRANSITION CURVE
• It is defined as a curve of non-uniform radius which is introduce
between a straight and a circular curve for gradual introduction of
centrifugal force. Its radius raises from infinity to a selected
minimum in order to attain full superelevation and curvature
gradually.
Objects of providing transition curve:
• To decrease the radius of curve gradually from infinity at the
straight to that of circular curve of selected radius.
• To attain gradual rise for the desired superelevation.
• The gradual increase or decrease of the centrifugal force on the
vehicle.
• No sudden application of releasing of the force is encountered. 127
*Under Revision
Types of Transition Curve
• Spiral curve: it is an ideal curve and satisfies all the requirement of
transition curve. Radius of the curve is inversely proportional to the
length of the curve.
128
*Under Revision
Length of Transition Curve
• Indian Railways specify that greatest of the following
lengths should be taken as the length of the Transition
curve.
• Based on Arbitrary gradient:
L= 7.2 x e where e=actual superelevation in cm
• Based on rate of change of cant deficiency:
L= 0.073 x D x Vmax where, D= cant deficiency in cm
• Based on the rate of change of superelevation:
L= 0.073 x e x Vmax
• As per the Railway Code: (greatest of following)
L= 4.4 x ѴR where R= radius in m.
Rate of change of superelevation (1 cm for every 3.6 m)
Based on radial acceleration L 3.28 V
2
R 129
*Under Revision
Shift of the transition curve
L2
S
24 R
Example-1
• Determine the length of transition curve. Given that the design
speed of the train on the curve is 90 kmph on B.G. track.
Example-2
• Find out the length of the curve for a B.G. curved track having 4ᵒ
curvature and a cant of 12 cm. the maximum permissible speed on
the curve is 85 kmph. Also find the shift of the curve
130
*Under Revision
Lecture-21
POINTS & CROSSINGS
• Points, crossing and turnouts are the arrangements by which
different routes either parallel or diverging are connected and afford
the means for trains to move from one route to another.
131
*Under Revision
Turnouts
• It is the simplest combination of point and crossings which
enables one track to take off from another track.
• The object of turnout is to provide facilities for safe movement of
trains in either direction on both the track.
Right-hand turnouts:- if a train from main track is diverted to the
right of the main route in the facing direction then this diversion
is known as Right-hand turnouts.
Left-hand turnouts:- if a train from main track is directed to the left
of the main route in the facing direction, then the diversion is
known as left-hand turnouts.
132
*Under Revision
Right-Hand Turnouts
133
*Under Revision
Left-Hand Turnouts
134
*Under Revision
*Under Revision 135
Terms related to points and crossings
• Check rail:- Checks rails are provided on the opposite side of the
crossing location for guiding one wheel of the vehicle and thus to
check the tendency of another wheel to climb over the crossing.
• Wing rail:- It helps in channelising the wheels in their proper routes
and direction meant for their movement. these rails guide the wheel
path for movement of trains.
• Tongue rail:- A tongue rail is tapered having toe at one end and heel
at other end. It is fixed at the heel end and can move or rotate about
this point.
• Stock rail:- The position of straight alignment against which the
tongue rail fits.
136
*Under Revision
Stretcher bar:-
• the toe of the two tongue rails are connected together by means of a
bar is known as stretcher bar, so that each tongue rail moves the
same distance on the gap while changing the points.
Flare:-
Lead rail:-
• lead rails are the length of rails from the heel of the tongue rail to
the toe of the crossing. 137
*Under Revision
Points of Switches
• The various component parts of the switches are:
• A pair of stock rails
• A pair of tongue rail
• Heel block or distance block
• Stretcher bars
• Switch tie plate or gauge tie plate
• Sliding chair or sliding plates
• Studs or stop
Heel clearance or heel divergence
• It is the distance between the running face of the stock rail and the
gauge face of the tongue rail when measured at the heel of the switch.
• For BG heel divergence is 13.7 to 13.3 cm
• For MG heel divergence is 12.1 to 11.7 cm
• For NG heel divergence is 9.8 cm
138
*Under Revision
Cont…
Flangeway depth:
• It is the vertical distance between the top surface of the running rail to
the top surface of the heel block used between the stock rail and the
check rail
Flangeway clearance:
• It is the distance between the adjacent faces of the stock rail and the
check rails.
Switch angle:
• It is the angle between the running faces of the stock rail and tongue
rail. This is also known as angle of switch divergence.
Types of switches:
• Stud switch
• Split switch
Loose heel type
Fixed heel type
Undercut switch
Over riding switch
Straight cut switch
139
*Under Revision
Lecture-22
CROSSINGS
• It is a device which provides two flangeways through which the wheels of
the flanges may move, when two rails intersect each other at an angle.
Component parts of crossing:
• A crossing or Vee piece
• Wing rails
• Point and splice rail
• Check rail
• Chairs at crossing, at toe and at heel
• Blocks at throat, at nose, at heel and distance block
Requirements of good crossings
• The assembly of crossing has to be rigid to stand against severe
vibrations.
• The wear on parts of the wing rails, opposite the nose and also of nose
itself must be protected.
• The crossing body should be as rigid as possible.
140
*Under Revision
Cont…
Types of crossings:
• On the basis of shape of crossing
Acute angle crossing or „V‟ crossing or frog
Obtuse angle crossing or diamond crossing
Square crossing
• On the basis of assembly of crossing
Spring or movable wing crossing
Ramped crossing
Acute angle crossing:
• When a left hand-rail of one track crosses right-hand rail of another
track or vice versa. If the angle of intersection of the approaching
rails is acute angle, it is termed as Acute angle crossing
141
*Under Revision
Obtuse angle crossing:
• When a left hand-rail of one track crosses right-hand rail of another track
or vice versa. If the angle of intersection of the approaching rails is a
obtuse angle, it is termed as Obtuse angle crossing.
Square crossing:
• When two straight track cross each other at right angle, they give rise to
square crossing.
Spring or movable crossing:
• One wing rail is movable and is held against the Vee of the crossing with
a strong helical spring.
Ramped crossing:
• The throat of the nose clearance is negotiated by use of special
manganese steel blocks over long distance. The wheel flanges roll over
this distance from a little beyond the throat to little beyond the nose.
The top level of these special blocks is so arranged that the tread of the
wheel is taken off the table by the wheel flange riding the blocks. This
type of crossing may be used for slow speed.
142
*Under Revision
Theoretical and actual nose crossing(TNC & ANC):
• The point rail is never manufactured to a well defined sharp point as it break off
under the dynamic action of moving traffic. So a blunt nose is provided for the
point rail. The thickness of blunt nose usually equal to the thickness of the web
of the rail.
• The sharp imaginary point where the two gauge faces in case of acute angle
crossing or the gauge face and sloping obtuse angle crossing would meet is
known as true or theoretical nose crossing
Number of crossing and Angle of crossing:
• Right angle or Cole‟s method: N= Cot α
• Centre line method: N= ½ Cot α/2
• Isosceles triangle method: N= ½ Cosec α/2
• Various crossing used in Indian Railway are
• 1 in 6 , used in symmetrical split
• 1 in 8 ½ , used in station yard where space is restricted
• 1 in 12, used in station yards of main line.
• I in 16 , used in very high speed turnout.
143
*Under Revision
Different methods of turnout design
Method-I (Cole‟s method)
• Curve lead(CL) = 2GN
• Radius(R) = R0 – G/2 , R0 1.5G 2GN
2
• Switch Lead(SL) = SL 2R d 0
• Heel Divergence(d) = d
( SL )
2R 0
• Radius(R) = R0 – G/2 , R0
Gd
cos cos
• Lead or crossing lead (L)= L (G d ) cot
2
144
*Under Revision
Method-III (IRS method)
• Radius(R) = R0 – G/2, G d x sin
R0
cos cos
Exampl-2
• On a straight BG track, a turnout takes off an angle of
5ᴼ35‟22”, switch angle is 1ᴼ45‟54”, heel divergence is 11.45
cm and length of straight arm is o.9 m.
146
*Under Revision
Lecture-23
SIGNALING
• It consist of system, devices and means by which trains are operated
efficiently and tracks are used to maximum extent, maintaining the safety of
the passangers.
Object of signaling
• To provide facilities for the efficient movement of the train
• To ensure safety between trains which cross or approaches each other‟s path
• To provide facilities for the maximum utility of the track.
• To guide the trains movement during maintenance.
• To safeguard the trains at converging junctions.
Classification and types of signals
a) Operating characteristics
b) Functional characteristics
c) Location characteristics
d) Special characteristics
147
*Under Revision
Cont..
a) Operating characteristics
I. Detonating signals(Fog or Audible signals)
II. Hand signals(visual indication signals)
III. Fixed signals(visual indication signals)
b) Functional characteristics
I. Stop or Semaphore type signals
II. Warner signals
III. Shunting signals(Disc or ground signals)
c) Location characteristics
I. Reception signals
Quoter signals
Home signals
II. Departure signals
Starter
Advanced starter
d) Special characteristics
I. Repeater or Co-acting signals
II. Routing signals
III. Calling on signals
IV. Point indicator
V. Modified lower quadrant semaphore signals
VI. Miscellaneous signals
148
*Under Revision
149
*Under Revision
150
*Under Revision
151
*Under Revision
152
*Under Revision
153
*Under Revision
Interlocking of signals and points
• It is define as the technique achieved through mechanical or electrical devices
or agencies by which it can be ensured that before a signal is taken to “OFF”
position, for the route, which the signal controls, is properly set and held, and
at the same time all the signals and points, the operation of which may lead to
conflicting movements, are locked against the feasibility of such conflicting
movement.
Necessity of interlocking:
• It is not possible to turn a signal “OFF” unless all the points for the line on
which the train is to be received are correctly set and all the facing points are
locked.
• The line should be fully isolated before the signal is turned “OFF”
• After the signal has been taken “OFF” , it should not be possible to make
adjustments in the points or locks on the route, including those in the isolated
line.
• It should not be possible to turn any two signals “OFF” at the same time.
• Wherever feasible the points should be so interlocked as to avoid any
conflicting movement.
154
*Under Revision
155
*Under Revision
Lecture-24
AIRCRAFT CHARACTERISTICS
• Aircraft characteristics are of prime importance to the
airport planner and designer, the following
characteristics are:
Types of propulsion
Size of aircraft
Minimum turning radius
Minimum circling radius
Speed of the aircraft
Capacity of aircraft
Aircraft weight and wheel configuration
Jet blast
Fuel spillage
noise 156
*Under Revision
AIRPORT ENGINEERING
• Meteorological survey
• Topographical survey
• Soil survey
• Drainage survey
• Material survey
167
*Under Revision
Airport classification
• The airport have been classified by various agencies:
Based on ESWL and the tire pressure, classification has been done by
using the numerical numbers i.e. 1 to 7
168
*Under Revision
Lecture-25
AIRPORT OBSTRUCTIONS
Zoning Laws:
• The site for airport should be so selected that it does not obstruct
the safe landing and take –off of aircraft. steps should be also be
taken to curb the possibility of developing any future obstruction.
Zoning ordinates regarding the permissible height of structures
and the land use within the airport boundary need implementation
as soon as the site is selected for airport development. The use of
land for manufacture of certain items which may result in smoke
nuisance, foul order..etc is also control by the zoning laws. 169
*Under Revision
Imaginary surfaces
• Approach surface
• Conical surface
• Transitional surface
170
*Under Revision
171
*Under Revision
172
*Under Revision
approach zone:
• During landing, the glide path of an aircraft varies from a steep to flat
slope. But during take-off, the rate of climb of aircraft is limited by its
wing loading and engine power, as such wide clearance areas known as
approach zone are required on either side of runway along the direction
of landing and take-off of aircraft. Over this area, the aircraft can safely
gain or loose altitude. The whole area should kept free of obstruction.
Clear zone:
• The inner most portion of approach zone which is critical portion from
obstruction view-point is known as clear zone. The purchase of land is
recommended for the effective implementation of zoning laws.
Turning zone:
• During take-off, if the engine fails or the pilot select to land for any
reason, the aircraft will have to take a turn and come in the line with
runway before landing. The area of airport other than approach area,
which is used for turning operation of aircraft is called turning zone.
173
*Under Revision
Lecture-26
WIND ROSE DIAGRAM
• The wind data i.e. direction, duration and intensity are
graphically represented by a diagram called wind rose.
• The wind data usually be collected for a period of at least 5 years
and preferably of 10 years, so as to obtained an average data with
sufficient accuracy
Wind rose diagrams can be plotted in two types:
• Type-I: showing direction and duration of wind
• Type-II: showing direction, duration and intensity of wind
Calm period:
• Percentage of time during which wind intensity, is less than 6.4
kmph is called calm period. It dies not influence the operation of
landing or take-off because low wind intensity.
174
*Under Revision
Runway orientation:
• Runway is usually oriented in the direction of prevailing winds. The
head wind i.e. the direction of wind opposite to the direction of
landing and take-off, provides greater lift on the wings of the aircraft
when it is taking-off. During landing, the head wind provides a
braking effect and the aircraft comes to a stop in a smaller length of
runway.
Cross wind component and wind coverage:
• The normal component of the wind is called cross wind component
and may interrupt the safe landing and take-off of the aircrafts.
• FAA recommends that for a small aircraft, the cross wind compnent
should not exceed 15 kmph and for mixed traffic it should not exceed
25 kmph
• For airport serving big aircrafts ICAO recommends that the cross
wind component should not exceed 35 kmph.
• The percentage of time in a year during which the cross wind
compnent within the limits as specified above is called wind
coverage.
175
*Under Revision
176
*Under Revision
177
*Under Revision
Lecture-27
RUNWAY DESIGN
• Runway geometric elements:
Runway length
Runway width
Transverse gradient
Sight distance
178
*Under Revision
Basic runway length
• It is the length of runway under the following assumed
conditions at the airport:
• Airport altitude is at sea level
• Temperature at the airport is standard i.e. 15⁰c
• Runway is levelled in the longitudinal direction
• No wind is blowing on runway
• Aircraft is loaded to its full loading capacity
• There is no wind blowing enroute to the destination
Correction for elevation, temperature and gradient:
• No correction is required if the runway is at mean sea level
elevation having standard temperature conditions. So necessary
correction are applied for any change in elevation, temperature
and gradient for actual site of construction.
179
*Under Revision
Correction for elevation
• As the elevation increases, the air density reduces, this is turn reduces
the lift on the wings of the aircraft and the aircraft requires greater
ground speed before it can rise into the air. To achieve the greater speed,
longer length of runway is required.
• ICAO recommends that the basic runway length should be increased at
the rate of 7% per 300 m rise in elevation above the mean sea level
Correction for temperature:
T T
• Airport reference temperature= Ta m 3 a
• Where, Ta is the monthly mean of average daily temperature for the
hottest month of the year and Tm is the mean of the maximum daily
temperature.
• ICAO recommends that basic runway length after having been
correction corrected for elevation should be further increase at the rate
of 1% for every 1ºc rise in temperature.
• Standard atmospheric temperature at given elevation= 15º-(o.oo65 x
altitude above mean sea level) 180
*Under Revision
Total correction
• ICAO recommends that, the total correction for elevation plus
temperature should not exceed 35% of the basic runway length.
Correction for gradient:
• FAA recommends that the runway length after having been
corrected for elevation and temperature should be further
increased at the rate of 20% for every 1% of effective gradient.
Example-1
• the length of runway under standrad condition is 2000 m. the
airport site has an elevation of 300 m. its reference temperature is
35⁰c if the runway is to be constructed with an effective gradient
of 0.2 %, determine the corrected runway length as per ICAO
and FAA.
181
*Under Revision
Lecture-28
TAXIWAY DESIGN
• The main function of taxiway is to provide access to the aircraft
from the runways to the loading apron of service hanger and
back.
• Geometric elements of taxiway:
Length of taxiway
width of taxiway
Width of safety area
Transverse gradient
Longitudinal gradient
Rate of change of longitudinal gradient
Sight distance
Turning radius 182
*Under Revision
Turning radius:(maximum value of three cases)
1. Whenever there is a change in the direction of taxiway a
horizontal curve is provided. The curve is so designed that the
aircraft can negotiate it without significantly reducing the speed.
V2
R
125 f
0.388 W 2
2. According to “Horonjeef” R
T
S
2
Runway marking
Taxiway marking
Apron marking
Rotating beacon
Code beacon
Boundary lighting
Approach lighting
Threshold lighting
Runway lighting
Taxiway lighting
188
Sample question(Set-A)
Answer question No. 1 which is compulsory and any five from the rest.
Q. No.-1 (2x10=20)
a) Write any three requirements of an ideal sleeper.
b) Classify train resistance.
c) Name different gauges and specify their standard length.
d) What is grade compensation? What is the standard value of compensation
for curvature for Broad gauge?
e) What is Airport capacity?
f) What is cross wind component
g) What is “Kinks” of Rails
h) Define Calm period
i) Define end bound sleeper
j) What is the minimum size of ballast for wooden sleeper and steel
sleepers?
189
Q. No. 2
a) draw the schematic diagram of Right hand turn out and show its various
component parts. (5)
b) What are the requirements of an ideal rail joint? (5)
Q. No. 3
a) The length of runway under standard condition is 1620 m, the Airport site
has an elevation of 270 m. The reference temperature is 32°C,if the
runway is to be constructed with an effective gradient of 0.2%, determine
the corrected runway length. (5)
b) What are the different characteristics of aircraft? How they affect the
planning and design of design of aircraft. (5)
Q. No. 4
a) What will be the gradient for a BG track when the grade resistance
together with curve resistance due to a curve of 5° shall be equal to the
resistance due a rolling gradient of 1 in 150? (5)
b) Calculate maximum permissible train load that can be pulled by a
locomotive having 4 pairs of driving wheels carrying an axle load of 25 tons
each. The train has to run at a speed of 80 kmph on a straight BG track.
Also calculate the reduction speed if the train has to climb a gradient of 1
in 200. (5)
190
Q. No. 5
a) Compare between flat footed and bull headed rails. (5)
b) Discuss supported, Suspended and bridge joint in brief. (5)
Q. No. 6
a) Discuss different factors on which airport site selection
depends in brief. (5)
b) A taxiway is to be designed for an operating Boeing 707
which has the fallowing characteristics. Determine the turning
radius of taxiway, wheel base = 17.00 m, tread of main
loading gear = 6.5 m, turning speed = 40 kmph, co-efficient
of friction = 0.13. (5)
Q. No. 7 write short notes on the following. (2x5=10)
a) Preliminary Survey
b) Normal Take-off
c) Wind rose
d) Pusher gradient
e) Spikes 191
Sample question(Set-B)
Answer question No. 1 which is compulsory and any five from the rest.
Q. No.-1 (2x12=20)
a) Define Centre Bound Sleeper.
b) Mention various type of Rail section used in Indian Railways for B. G.
track.
c) What are the compositions of Rails?
d) What is the difference between Staggered joint and Square joint?
e) Write any two advantage of welding of Rails.
f) What is Negative Superelevation?
g) What is Wind Rose diagram?
h) What are FAA and DARA?
i) Define Track Modulus.
j) Write any two factors which affecting the choice of particular Gauge.
192
Q. No. 2
a) What would be the permissible speed on the curve, if on a 7ᵒ M.G.
track, the average speed of different trains is 55 kmph and allowable
cant deficiency is half that of maximum cant deficiency. (4)
b) Describe the requirements of Rail in a Railway track. (6)
Q. No. 3
a) If the wheel base of a vehicle moving on a M.G. track is 4.88 m, the
diameter of the wheel is 1.2 m and the depth of flange below the top of
the rail is 3.17 cm. Determine the extra width required to be provided
on gauge, if the radius of the curve is 150 m. (5)
b) Draw a typical cross-section of a B.G. track in embankment and briefly
explain the basic functions of its various components. (5)
Q. No. 4
a) Draw the schematic diagram of left hand Turn out and show its various
component parts. (5)
b) Define Creep of Rail. What are the effects of Creep? (5)
193
Q. No. 5
a) The length of the runway under standard conditions is 2000 m. The airport is to
be provided at elevation of 400 m above the mean sea level. The airport
reference temperature is 34ᵒc. Determine the length of runway with fallowing
data: (6)
End to end runway(m) Grade (%)
0-300 +1.00
300-900 -0.4
900-1500 +0.5
1500-1800 +0.8
1800-2100 -0.5
2100-2700 -0.3
2700-3000 +0.2
b) What are the imaginary surfaces? Explain briefly their significance. (4)
Q. No. 6
a) Explain with neat sketches the limiting heights of objects in the approach and
turning zone of an instrumental runway. (5)
b) What do you understand by the term visual aid in connection with airport?
Name the different visual aids. What is the necessity of visual aids? (5)
Q. No. 7 write short notes on the following. (2x5=10)
a) Grade compensation on curves
b) ICAO
c) Zoning Laws
d) Holding aprons
e) Turnout
194