Numerical Investigation of The Failure of A Shotcrete Lining
Numerical Investigation of The Failure of A Shotcrete Lining
)
© 2006 Taylor & Francis Group, London, ISBN 0-415-40822-9
R. Pöttler
ILF Consulting Engineers, Rum/Innsbruck, Austria
ABSTRACT: In the course of a 7-km-long railway tunnel, which is situated mainly in weathered chalk marl,
covered by Tertiary over a length of about 500 m, the tunnel traverses a transition zone of chalk marl, weathered
chalk marl and Tertiary. In a specific area with a length of 100 m, the deformation during tunnel drive did not cease
and exceeded the predicted values considerably. About one year after the installation of the primary lining, cracks
occurred in the shotcrete lining of the invert. Many different geotechnical models have been discussed to explain
this special ground behaviour and the failure. Numerical calculations based on extensive geotechnical investiga-
tions were performed, aiming at detecting the cause of this failure. It was only when the real ground behaviour and
reasons of failure had been understood that the secondary lining could be designed in an optimised way.
313
Table 1. Geotechnical parameters for numerical analyses
prior to excavation.
E Load E Unload cu wu g
[MN/m2] [MN/m2] [MN/m2] [°] [MN/m3]
314
at that distance (Figure 6). As the geotechnical param-
eters of the weathered rock mass have been assumed
to be almost the same as for the Tertiary, from a geot-
echnical point of view the ground behaviour could not
be explained. Additional support measures had to be
installed based on engineering judgement to prevent a
collapse of the tunnel. In a 1st step these consisted of
enlarging the shotcrete lining at the footing, in a 2nd
step of installing vertical anchors at the basement and in
a 3rd step a temporary invert of the heading, 5 m wide
and at a distance of 15 m. The 1st and 2nd step did not
have any influence on the deformation behaviour of
the heading. Thus the numerical investigations done at
the beginning, showing no major influence of these
support measures, have been proved. Deformations only
ceased after installing, in the relevant section, a tem-
porary invert arch in a 3rd step. Excavation of bench
Figure 6. Measured displacements. and invert had to be done close to the excavation of
the heading. Also, in the invert a shotcrete lining with
a thickness of 250 mm was installed.
Table 2. Geotechnical parameters for adopted numerical
analyses.
TER1 6 18 0.010 25 0.020 After the shotcrete invert had been placed, the work
TER2 16 48 0.015 25 0.021 on site was stopped for about 1.5 years. During this
TER3 80 240 0.015 25 0.021 time additional ground investigations were per-
RM 50 100 0.030 25 0.022 formed. As the tunnel was situated in karst, geologi-
cal anomalies due to karst phenomena located in the
Enlargement of the shotcrete lining has only minor vicinity of the tunnel had to be detected, which may
influence on the stress-strain behaviour of the tunnel. have an influence on the permanent stability and ser-
The same investigation was done for the placement of viceability of tunnel for a service life of 100 years.
additional vertical anchors at the footing. This addi- These investigation were done by geophysical meas-
tional support measure also had no major influence urements and drilling in an area of about 15 m around
on the overall stability of the heading. Therefore there the tunnel (Pöttler 2004).
was no reason to carry out both support measures Using these investigations, it was possible to gen-
from an engineering point of view. erate a realistic geological 3D model. The 3D model
In the course of the tunnel driving, the measured of the area under discussion is shown in Figure 7. A
displacements became bigger than the calculated dis- major discrepancy between the geological model in
placements (Figure 6). This was mainly because the the prognosis stage and reality is evident. A main dis-
transition zone of Tertiary and rock mass was located crepancy is that the weathered rock mass is not situ-
lower than in the prognosis. Numerical analyses with ated in the area of the heading but under the invert.
reduced values for the geotechnical parameters (Table The surface of the weathered rock mass is quite irreg-
2) resulted in higher allowable displacements. No dif- ular both in longitudinal and transversal direction.
ferentiation between RM1 and RM2 was done in the
numerical model.
For the excavation of the heading the following 4 UNPREDICTED EVENT
ranges of displacements were calculated:
During this period of no construction, regular inspec-
– Roof settlement (RS) 75 mm–85 mm
tions of the shotcrete lining were undertaken by the
– Horizontal convergence (HC) ⫺10 mm–60 mm
site management. One year after the construction
(- .. divergence)
works had been stopped, cracks appeared in the invert
– Settlement of footing (SF) 65 mm–80 mm
lining and additional settlements occurred (Figure 8).
It was assumed that the displacements would cease The settlements could only be stopped when the tunnel
1–2 diameters behind the face. But the results of the was partly refilled with material and wooden columns
measurements showed no abatement of displacements placed to support the shotcrete lining of the heading.
315
Figure 7. Geological situation in reality.
Due to the large settlements of up to 150 mm, the tun- geotechnical parameters as listed in Table 2 have been
nel lining had to be reconstructed to provide enough used for the numerical analyses. Taking account of the
space for installing the inner lining. Additional excavation sequence, the numerical analyses yielded
drilling had been performed to get even more infor- the same results in terms of displacements which were
mation on the ground in this area. The main questions measured (Table 3), therefore it could be assumed that
to be answered were: the ground behaviour and the excavation process were
modelled realistically.
– What is the reason for the unpredicted restart of
But the numerical analyses showed no failure of the
movements?
shotcrete lining in the invert section. The stresses in the
– What is the realistic load on the inner lining caused
shotcrete lining were considerably lower than the sus-
by shotcrete deterioration?
tainable stresses. The actual location of the geological
Different scenarios to explain the behaviour of the strata differed from the prognosis, but this could not
tunnel have been discussed: be the reason for the unpredicted event.
Scenario 1: Change of location of geological strata: Scenario 2: Influence of rock “peak”: As can be
The tunnel is situated in Tertiary and the weathered seen from Figure 4, the weathered rock mass forms a
rock mass is about 10 m below the invert. The same peak in the vicinity of the area where the crack in the
316
Figure 8. Cracks in the shotcrete lining of the invert.
317
5 CONCLUSION the process one had to become aware that, for the
present, the limit of understanding and numerical
The prognosis of the geological situation was done modelling has been reached. It becomes evident that
based on the well-known geological mapping and tunnelling in such ground conditions can be done
additional drillings spaced every 500 m over the only by an experienced team. The numerical analyses
course of the tunnel. After problems as described are helpful but not the only tool for success.
appear, “experts” may state that a greater number of There was no complete collapse of the tunnel and
ground investigations have to be carried out before no loss of life. This section of the tunnel was expen-
tunnel driving. It goes without saying that the better sive, but all in all economic with regard to other pos-
the ground investigations are before the construction sible and realistic scenarios. This was thanks to the
starts, the lower the risk of an unpredicted event. The proper work done on site by the client, construction
amount and quality of ground investigation represent- company, site supervision and designer.
ing the state of the art is found in the relevant stan-
dards. But even if the standard is met, like in the
described case study, unpredicted events may occur.
In this case study, the reason for the unpredicted event REFERENCES
could not be defined in a proper way, although a far
greater number of ground investigations were per- Pöttler, R. 1992. Die Standsicherheitsuntersuchung für die
Kaverne der englischen Überleitstelle im Kanaltunnel.
formed than ever done in a tunnelling project and Bautechnik 69: 602–617.
although the geological situation was well known. Pöttler, R. 2004. Die Beherrschung der Karst- und
As numerical analyses were used to a great extent, Erdfallproblematik bei Tunnelbauwerken. Veröffentlichung
and as there was time for a lot of discussion and meet- des Instituts für Geotechnik der Technischen Universität
ings after the completion of the tunnel, at the end of Bergakademie Freiberg. Freiberg.
318