JBIC - Wastewater RPT
JBIC - Wastewater RPT
Final Report
February 2006
Chemonics Egypt
Ahmad Gaber and Associates
Engineering and Management Consultants
Executive Summary 1
EXECUTIVE SUMMARY
The Egyptian Government considers the water supply and sanitation issue of high
priority due to its valuable social and economic return. The total investments spent on
water and wastewater services during the period 1982-2005 amounted to about LE 60
billion. Inspite of the steady increase of population during this period, the water per
capita share was duplicated, and the wastewater services per capita share was
increased to 6 times. Nevertheless, there still exist problems facing the sector, which
limit the ultimate benefit from these investments; this was reflected on the level of
service delivered. The growing population of Egypt, reaching about 72 million in the
year 2005, generates a great pressure on the water and wastewater sector to face the
increasing demand on these two services.
In recognition of the importance f the wastewater sector in Egypt, the Japan Bank for
International Cooperation (JBIC) has requested Chemonics Egypt to conduct a study
on the wastewater sector in Greater Cairo for potential cooperation in this sector. The
data and information provided in the study were collected from reports and interviews
with concerned authorities. Although the study focused on the wastewater services in
Greater Cairo, an overview of the developments in the wastewater sector nationwide
was also included.
The wastewater affairs in Egypt are viewed as a part of the water and sanitation
sector. This sector is starting to take steps to decentralize management nationwide
and devote financial planning and management to the governorate levels through
water/wastewater companies under the umbrella of the holding Company for Water
and Wastewater (HCWW). There are several emerging issues in the wastewater
sector at present. These include construction of new wastewater facilities and
expansion of existing ones. Such facilities include sewer networks, pumping stations,
treatment plants and disposal works. Sustainable financing will be needed to fund
such projects. The National Organization for Potable Water and Sanitary Drainage
(NOPWASD) will continue to fund and construct capital investment projects. Since
new projects in wastewater are very costly, and NOPWASD budget will not cover
required projects all over the country. Egypt will seek additional, foreign funds to
those allocated through the state.
Also, it is planned that all newly established water companies under the umbrella of
the HCWW (14 companies) should cover all their operating expenses initially as well
as their investment projects in the near future. These companies will have to resort to
non-governmental financing schemes for their investment projects. Therefore,
financing of capital investment projects in the wastewater sector is one of the major
issues to be considered for developing any national and/or local investment plans.
Financial planning for the sector requires the availability of reliable financial
information.
The people of Egypt suffer from disparities in the coverage of services. Although
much attention was directed towards provision of safe water supply, sanitation, on the
other hand, received less attention and gaps in coverage of services were created.
According to the 2005 UNDP human development report, only 78.2% of households
in Egypt have access to sanitation services compared to 97.5% receiving piped water
in the year 2004.
Moreover, coverage with sanitation services varies among regions throughout Egypt
with the least coverage reported in rural areas of Upper Egypt. Lack of sanitation
services in Egypt has created many environmental and public health problems.
Heavily populated areas such as Greater Cairo, where almost 25% of Egypt’s
population exist, are targeted for their contribution to pollution of the River Nile
through discharge of huge quantities of untreated or inadequately treated wastewater
into water canals and agricultural drains. Pollution of the River Nile is a disaster since
the river is the main source for surface water, and the leaking river water is the main
source for groundwater in Egypt.
The Greater Cairo Wastewater Project is one of the largest wastewater projects in the
world; it is serving a population of 20 million occupying an area of about 1100 square
kilometer. It includes a large conveyance system, major pumping stations and huge
treatment plants, that raised the capacity for Cairo wastewater system from 1.4 million
m3/day to 5.24 million m3/day and has significant impact on the wastewater services
in Cairo. This mega project was divided into three major subprojects according to the
geographic location of districts served in Greater Cairo along the banks of the River
Nile as follows:
The area served by the Greater Cairo Wastewater Project lies in three main
governorates: Cairo, Giza and Qalubiya. The project efforts also include the
rehabilitation of the old pumping stations, treatment plants, and the drainage
improvement of the old sewers.
Construction of new projects within the three districts of Greater Cairo has been
proposed to improve service standards of local population, cope with population
increase, and improve environmental conditions of the River Nile. Some of these
projects is currently stagnant due to lack of financial resources. The local funds are
mainly directed to the construction of sewer networks where local technology exists
but construction of pumping stations and treatment facilities, which involves import
of foreign technology and equipment, requires financing by foreign funding
institutions.
In order to select projects on sound basis for possible funding by JBIC, the following
four principles were considered in settling rules for developing priority wastewater
projects:
Units
m meter
m3/d cubic meter per day
Mm3/d million cubic meter per day
km kilometer
kg kilogram
lcd Litre per capita per day
gcd gram per capita per day
ha hectare
mg/l milligram per litre
ppm parts per million
Consultants
Executive Summary
List of Abbreviations
1. Introduction
1.1 Background
1.2 Objectives and Scope
1
3.4 Economic and Financial Information
3.4.1 Cost Recovery and Tariffs
3.4.2 Tariff Amendments
3.4.3 Current Tariff
2
6.8 USAID (U.S.A.)
Annexes
Annex (A)
The Environmental Law No. 4/1994
Annex (B)
Law No. 48/1982
3
List of Tables
4
List of Tables
5
List of Figures
Figure (3.1) Organization Structure for the Holding Company for Water and
Wastewater (HCWW)
Figure (4.1 a) Main Components of the Greater Cairo Wastewater Project
(East and West Bank)
Figure (4.1 b) Main Components of the Greater Cairo Wastewater Project
(Helwan)
Figure (4.2) Development of the Wastewater System Capacity in Greater
Cairo (Years 1914-2005)
Figure (4.3) East Bank Schematic Flow Diagram (2005)
Figure (4.4) East Bank Projects Map
Figure (4.5) East Bank Contracts
Figure (4.6) West Bank Wastewater Project
Figure (4.7) West Project: Current Flow/Year 2005
Figure (4.8) Helwan Wastewater Project
Figure (4.9) Helwan Contract
Figure (4.10) Greater Cairo Wastewater Treatment Plants
Figure (5.1) Masterplan of 1978 for the East Bank of Greater Cairo
Figure (5.2) Sewered Areas
Figure (5.3) Proposed Connection between Ain-Shams and Gabal Al-Asfar
Figure (5.4) GCWWP Facilities Location Plan
Figure (5.5) West Bank Projects
Figure (5.6) Service Areas 1995
6
1: Introduction
Introduction 1-1
1. INTRODUCTION
Water supply and sanitation is an issue of high priority in Egypt due to its valuable
social and economic return. Despite the progress in providing water supply and
sanitation services during the last 20 years, the quality and sustainability of this
coverage is inadequate. Coverage of such services varies among regions nationwide,
and from urban areas to rural areas. This chapter presents an overview of the water
supply and sanitation in Egypt along with the objectives and scope of this study.
1.1 Background
Egypt had suffered for a long time from inadequate infrastructure up till the early
1980’s as the economic resources of the country were mainly directed to the armed
forces since the country was engaged in a number of wars which exhausted the
country’s resources. This was reflected in the water and sanitation sector where
people suffer from disparities in the coverage of services. Although much attention
was directed towards provision of safe water supply, sanitation on the other hand
received less attention and gaps in coverage of services were created. In fact, Egypt is
ranked among the highest developing countries concerning the coverage gaps between
water supply and sanitation in the year 1993 but the gaps was reduced in the year
2004 as shown in Table 1.1. Moreover, coverage of sanitation services varies among
regions all over Egypt, and also varies from urban areas to rural areas. About 21.7%
of the total number of buildings in Egypt are connected to wastewater networks, and
63.3% dispose of wastewater through other alternatives, while the remaining 15% are
deprived of sanitation services (Chemonics Egypt – UNICEF Report, 2005). On the
other hand, it has been also shown that, in rural areas only 6% of Egyptian Villages
are provided with sanitation services, and 7% shall be served after completing the
sanitation projects under construction, while the remaining 87% are deprived of
sanitation services.
The Egyptian Government and Parliament councils think carefully and deeply over
the water and wastewater issue. Provision of safe water and sanitation services is
considered essential rights for citizens which should be emphasized, while assuring
good quality of water and limiting its contamination. The Egyptian Government is
acting to reduce the gap between urban and rural areas nationwide, as regards water
supply and sanitation services by concentrating efforts on Upper Egypt governorates
and raising the percentage of water and wastewater coverage. The population of
Egyptian governorates by urban and rural sectors is presented in Table 1.2 according
to the 1996 census records.
There is a steady increase of population in Egypt reaching about 72 million in the year
2005. The increase of population generates a great pressure on the water and
wastewater sector to face the increasing demand on these two services. The Egyptian
Government considered the water supply and sanitation issue of high priority due to
its valuable social and economic return. The total investments spent on water and
wastewater services during the period 1982-2005 amounted to LE 60 billion. In spite
of the steady increase of population during this period, the water per capita share was
duplicated, and the wastewater services per capita share was increased to 6 times.
Nevertheless, there still exist problems facing the sector which limit the ultimate
benefit from these investments, this was reflected on the level of service delivered.
The studies and reports on water and wastewater problems in Egypt indicated the
necessity of collaborating the efforts of different ministries and authorities to solve
and overcome the problems facing the water and wastewater sector. The apparent
variation in service delivery between urban and rural areas in Egypt has a great effect
in policy development and investment plans to reduce the gap between rural and
urban areas in this regard. Despite the progress in providing water supply and
sanitation services during the last 20 years, the quality and sustainability of this
coverage is threatened by problems related to institutional structure and support.
Under the current trend to reform the sector and solve the problems and constraints
facing this vital sector, significant steps were taken and Presidential and Ministerial
Decrees were issued towards sector reform and cost recovery. The existing water and
wastewater authorities are currently under transformation into autonomous
companies.
The data and information provided in the study are collected from reports and
interviews with concerned authorities. Although the study is focused on the
wastewater services in Greater Cairo, an overview of the developments in the
wastewater sector nationwide is also included.
Sources: WHO, Water Supply and Sanitation Collaborative Council and UNICEF, Water Supply and
Sanitation Sector Monitoring Report: 1996.
Urban
Rural Population Urban Population Total Population Population /Total
Governorate
Population
Males Females Total Males Females Total Males Females Total
Cairo 0 0 0 3,835,131 3,661,997 7,497,128 3,835,131 3,661,997 7,497,128 100
Giza 1,128,781 1,060,319 2,189,100 1,674,917 1,562,775 3,237,692 2,803,698 2,623,094 5,426,792 59.66
Qalubiya 1,054,772 987,405 2,042,177 870,079 819,228 1,689,307 1,924,851 1,806,633 3,731,484 45.27
Alexandria 0 0 0 1,885,206 1,806,053 3,691,259 1,885,206 1,806,053 3,691,259 100
Beheira 1,761,018 1,697,952 3,458,970 539,338 516,726 1,056,064 2,300,356 2,214,678 4,515,034 23.39
Matrouh 64,858 57,313 122,171 69,329 63,424 132,753 134,187 120,737 254,924 52.08
Menufiya 1,277,608 1,201,836 2,479,444 324,479 308,495 632,974 1,602,087 1,510,331 3,112,418 20.34
Gharbiya 1,312,968 1,288,794 2,601,762 603,845 586,508 1,190,353 1,916,813 1,875,302 3,792,115 31.39
Kafr El-Sheikh 964,807 947,161 1,911,968 288,501 291,923 580,424 1,253,308 1,239,084 2,492,392 23.29
Damietta 381,666 363,413 745,079 147,678 143,457 291,135 529,344 505,870 1,035,214 28.12
Daqahliya 1,751,965 1,682,669 3,434,634 666,516 645,083 1,311,599 2,418,481 2,327,752 4,746,233 27.63
North Sinai 62,944 60,483 123,427 90,661 80,830 171,491 153,605 141,313 294,918 58.15
South Sinai 17,263 14,232 31,495 20,472 10,294 30,766 37,735 24,526 62,261 49.41
Port Said 0 0 0 267,360 254,189 521,549 267,360 254,189 521,549 100
Ismailia 211,018 200,581 411,599 210,867 202,898 413,765 421,885 403,479 825,364 50.13
Suez 0 0 0 240,238 229,038 469,276 240,238 229,038 469,276 100
Sharqiya 1,953,036 1,843,358 3,796,394 569,647 540,355 1,110,002 2,522,683 2,383,713 4,906,396 22.62
Beni Suef 847,193 807,855 1,655,048 257,226 249,462 506,688 1,104,419 1,057,317 2,161,736 23.44
Minya 1,600,749 1,530,793 3,131,542 381,114 361,993 743,107 1,981,863 1,892,786 3,874,649 19.18
Fayoum 936,408 867,802 1,804,210 268,134 248,564 516,698 1,204,542 1,116,366 2,320,908 22.26
Assyout 1,224,072 1,171,010 2,395,082 459,913 425,906 885,819 1,683,985 1,596,916 3,280,901 27
New Valley 42,816 40,880 83,696 41,577 37,400 78,977 84,393 78,280 162,673 48.55
Sohag 1,467,745 1,403,487 2,871,232 402,021 381,342 783,363 1,869,766 1,784,829 3,654,595 21.44
Qena 1,112,571 1,107,729 2,220,300 304,681 292,176 596,857 1,417,252 1,399,905 2,817,157 21.19
Asswan 308,068 312,842 620,910 231,559 224,753 456,312 539,627 537,595 1,077,222 42.36
Red Sea 27,820 18,139 45,959 73,816 59,048 132,864 101,636 77,187 178,823 74.3
Luxor City 110,482 106,934 217,416 98,058 91,434 189,492 208,540 198,368 406,908 46.57
Total 19,620,628 18,772,987 38,393,615 14,822,363 14,095,351 28,917,714 34,442,991 32,867,338 67,310,329 42.96
Source: Data of Ministry of Local Development , based on estimation of Central Agency for Public Mobilization and Statistics (CAPMAS), 2003
2.1 Introduction
This chapter presents the national development plan for Egypt as well as the specific
plans to develop the water resources, wastewater, and environmental management in the
country. Such plans outline the main features of development in each sector.
1. Expanding the scope of development to the whole country, trying to explore wealth
and new resources, get out of the narrow valley that constitutes only 5.5% of
Egypt’s territory, and expand the residential zone to 25% of the total area.
2. Pushing the development growth rate from its current level of 4.8% to 6.8% during
the first 5- year plan and to 7.6% thereafter up to 2017.
3. Doubling the gross domestic product (GDP) every 10 years, i.e. reaching four times
the current GDP of LE 257 billion ($ 76 billion) by 2017.
4. Increasing the per capita share of GDP from its current level of LE 4,270 ($ 1,250)
to at least LE 13,750 ($ 4,100).
5. The accelerated development will reduce the deficit in trade balance and achieve
remarkable surplus by the end of the 6th five-year plan and big surplus thereafter.
6. Developing a set of flexible economical, financial, and cash policies to suit
fluctuating situations and help in maintaining inflation as low as possible, so that it
keeps lower than 5% annually at any case.
7. Making effort to balance the general budget towards achieving gradual and
continuous increase in surplus within a frame of economic stability that provides the
correct atmosphere for productive development. This would lead to stability of
exchange rate for the Egyptian currency against foreign currency.
8. Generating about 550 thousand new job opportunities annually. This would
compensate the population growth and reduce the current unemployment. This
would lead to stop unemployment by the 4th five-year plan (1997-2002) and increase
the labor force from 15.8 million currently to 26.8 million by the end of the 7th five-
year plan 2017.
investment sum represents at least 25% of the GDP. To obtain this amount of
investments, the strategic development plan recommends directing efforts to:
The growing population of Egypt and related urban, industrial and agricultural activities
have increased and will further increase the demand for water to a level that reaches the
limits of the available supply. Moreover, pollution of the water is threatening public
health and reduces the amount of good quality water even more. The Government of
Egypt recognized these problems since long and has initiated major programs to
improve the performance of the water resources system. The current water resources are
presented in Table 2.1. The amount of water used for drinking is estimated to be about
8.8 billion m3/year and the rest is used for irrigating agricultural land.
The national development plan, up to 2017, is aiming at increasing the water resources
and saving in the water used for agriculture through changing the crops-structure by
reducing the crops requiring high water duties and optimizing water irrigation systems
Study of Wastewater Sector in Greater Cairo Final Report
Chemonics Egypt February 2006
Outline of National Plans for Water Resources, Environmental and Wastewater Management 2-3
and water use in general. Reuse of treated wastewater in agriculture is viable and could
add an additional three billion m3 of water yearly for expanding the agricultural land.
Deep groundwater in Sinai and the Western and Eastern Deserts have a good potential
of adding more than three billion m3 of water annually.
The Ministry of Water Resources and Irrigation (MWRI) plays a key-role in the
development and management of the water system in the country. The present policy of
the ministry tries to achieve the national objectives by developing new water resources,
improving the efficiency of the present use, and protecting the environment and health
through preventing pollution to reach watercourses. Some of these objectives are
achieved through cooperation with other ministries such as the Ministry of Agriculture
and Land Reclamation (MALR), the Ministry of Housing, Utilities and New
Communities (MHUNC), the Ministry of Health and Population (MHP), the Ministry of
Local Development (MLD) and The Ministry of Environment (ME).
The water resources policy is based on the draft strategy “Facing the Challenge” and
employs the concept of Integrated Water Resources Management (IWRM) and takes
into account all national policy objectives. Such strategy was presented by the Planning
Sector, Ministry of Water Resources and Irrigation (MWRI) in July 2002. The draft
strategy “Facing the Challenge” call for an integrated strategy, consisting of a coherent
set of measures. The measures are grouped into three main categories:
a) A more efficient use of the available water resources
b) Development of additional water resources, and
c) Improvement of water quality to protect public health and environment
A more efficient use of the available water resources would entail improvement of the
irrigation systems; installation of tile drainage systems and rehabilitation of old drainage
network; rehabilitation of irrigation and drainage pumping stations; replacement and
rehabilitation of the existing barrages and structures on the Nile and main canals; and
introduction of new varieties as early maturing and salt tolerant crops.
In terms of new water resources, it is fair to admit that the possibilities to develop
additional resources are limited. Deep groundwater withdrawal in the Western Desert
can be developed up to an amount of 3.5Billion m3/ year, but this is not a sustainable
solution and should be carefully monitored. Small amounts can be developed from
rainfall and flash flood harvesting in addition to the use of brackish groundwater. Thus,
cooperation with the Nile Basin riparian countries is carried out through joint
agreements to develop river-shared resources.
MWRI is taking preventive measures and long-term policies to protect water quality
and control pollution. The long term policies to control pollution include: coverage of
open conveyance system passing through urban system to closed conduits; coordination
committee with other concerned ministries were formulated to put priorities for
wastewater treatment plants due to budget limitation; and the introduction of
environmentally safe weed control methods (mechanical, biological and manual) and
banning the use of chemical herbicides.
Measures aiming at a better use of existing resources focus mainly on improving the
efficiency of the water resources system. The draft strategy presented by MWRI
includes a careful re-evaluation of planned horizontal expansion projects and
recommends considering a possible reduction in the area of horizontal expansion in
relation to the availability of water (realistic approach). The same applies to the
cultivation of high water consuming crops such as rice and sugarcane. The activities of
the Irrigation Improvement Projects (IIP) should continue among other measures to
improve water use efficiency. Applying intermediate reuse of drainage water allowing a
higher permissible salinity. Moreover, a different water allocation and distribution
system that will be based on equity to decrease the losses in the system should be
considered. Improving water resources system requires improving the operation and
maintenance of the system through good institutional structure with strong Water
Boards and Water Users Associations. A mix of infrastructural and financial measures
can improve the municipal and industrial water use efficiency.
The strategy to protect the environment and public health includes several packages of
combined infrastructural, financial and institutional measures. Priority is given to
measures, which first prevent and then alleviate pollution. This includes promoting and
supporting cleaner production technology, clean products, and reallocation of certain
industries. Encouraging the use of more environmentally friendly methods and agro-
chemicals in agriculture. Treatment of municipal wastewater and consider a reliable
approach for rural sanitation. The last resort is to control the pollution by diverting it
away from urban and important ecological sites, and sensitive areas such as
groundwater wells and intakes of public water supply. Raising public awareness should
be considered also as an effective mean of reducing negative environmental impacts.
The MWRI strategy also includes a number of institutional measures. The initial
process of decentralization and private sector participation should be strengthened.
Restructuring the MWRI by establishing integrated inspectorates to enhance the role of
the ministry should be considered. Cost sharing and pricing mechanisms have to be
implemented to make the changes sustainable, at least with respect to operation and
maintenance. Improving data and information exchange-system with different related
authorities and coordinating investment activities are important measures. Involving
stakeholders, with particular attention to the role of women, in the various water
management tasks and strengthening their ownership feelings towards public property
should be enhanced.
Beyond 2017, when Egypt is successful in implementing the above measures, several
national objectives will be achieved. The GDP and employment in agriculture will
increase substantially, and the drinking water supply and sanitation situation will
improve. Further development, after 2017, may require that some drastic policy
decisions to be taken, at the national level, e.g. in relation to reducing the role of
agriculture in the Egyptian economy and increasing developments in the industrial
sector.
Among the opportunities and threats to the development in Egypt are the changes in the
external environment: liberalization of trade, formation of economic blocks, and the
rapid advancement in communication and information technology. The position of the
country in the global arena determines whether such changes become threats or
opportunities. Egypt has successfully implemented a program for economic reform and
structural adjustment. Among the outcomes of economic reform are reasonably stable
exchange rates, reforms in the financial sectors, and establishing an active stock market.
Direct foreign and local investments have increased in several economic sectors,
particularly agriculture, industry and tourism. The expansion of these economic sectors
has put pressure on limited resources and added more burdens in managing resulting
wastes. The high population growth rate is another pressure transforming the internal
environment. Despite that national education and awareness programs led to 1%
reduction in growth rate, according to 1996 census almost 38% of the population are
under 15 years of age, i.e. it is considered a young society. Resources to meet the needs
of this growing population are extremely limited and strained and thus threatening the
sustainable development.
• Major environmental issues and concerns, which challenge Egypt today cover the
degradation of land, air, and water resources; and the pressing need to preserve the
cultural heritage and natural biodiversity.
• Air pollution in major cities has reached levels that affect public health, cause
economic losses, and also damage historical sites.
• Egypt has limited natural fresh water, mainly the river Nile. As the river flows from
Aswan down to the Mediterranean Sea, many land-based and point sources of
Study of Wastewater Sector in Greater Cairo Final Report
Chemonics Egypt February 2006
Outline of National Plans for Water Resources, Environmental and Wastewater Management 2-6
pollution reach the Nile through drainage canals. The sources of pollution include
agricultural run-off, raw or partially treated wastewater, and industrial effluents.
This process was achieved in three stages. During the first stage, stakeholders including
NGOs, environmental and gender experts, members of national universities, business
community representatives, labor-force representatives, youth, and media were invited
to workshops sessions aiming at problem identification and prioritization. During the
second stage, issue-specific working groups developed strategic framework that led,
after discussions, to formal plan. The third stage has the objective of allocating the
required finance and resource mobilization and that is open-ended.
Driving forces creating pressures on the environment in Egypt are numerous. One of the
major environmental problems is the rapid population growth and informal human
settlements. The agricultural sector and associated activities, which result in about 18%
of total GDP and 20% of commodity exports, contribute to significant environmental
pressures. Fishing activities serving a traditional and important component of the
Egyptian diet has resulted in overexploitation of all Egyptian water bodies.
Manufacturing and mining, which employ about 20% of the active labor power and
contribute to 30% of the GDP is the major user of both renewable and nonrenewable
natural resources and also considered a significant source of air and water pollution. The
increasing consumption and demands for energy from conventional resources to serve
expanding industry, which is the main pillar of economic development, is a driving
force creating pressure on the environment. Transportation is the second most energy-
demanding economic sector following manufacturing. Its impact on environment is
quite significant and clear. Tourism relies on the utilization of natural, historic, cultural,
and human resources in the local environment. This can lead to a considerable pressure
on the environment that attracts tourists.
Environmental degradation has its cost. Pollution is closely associated with health
problems, which impact negatively the economy and threatens the sustainability of the
development in Egypt.
a) Water
The major challenges facing the water sector in Egypt is to close the gab between the
limited water resources and the escalating demand for water, while ensuring the
sustainable use of water resources. To face this challenge, Egypt is initiating programs
aiming at optimizing the use of conventional resources and making use of non-
conventional resources more feasible.
The Ministry of Water Resources and Irrigation (MWRI) is responsible to provide all
other sectors in Egypt with their needs of fresh water in due time. The MWRI is
mandated to construct, supervise, operate and maintain all irrigation structures and
drainage networks, and also to control and manage all fresh water resources in Egypt.
The Environmental Law No. 4/1994 has been issued to protect the environment in
Egypt in general, see Annex A. The law refers to Law 48/1982 (Annex B) that deals
with pollution abatement in all water resources in Egypt.
b) Air
The Government of Egypt (GOE), through the Ministry of State for Environmental
Affairs (MSEA) and Egyptian Environmental Affairs Agency (EEAA) and relevant
ministries such as Ministry of Transportation (MT) is currently adopting various
measures to control air pollution sources and recommended programs to be
implemented by 2017 with regard to ambient air quality:
Forming a strategy for controlling pollution and preventing smog episodes;
Managing auto exhausts and protecting air quality in urban and rural areas; and
Reducing pollution from industrial activities within human settlements and managing
and controlling air pollution from existing large industries and power plants
c) Land
The sustainable use of land means finding a balance that attains the greatest benefits for
social and economic development whilst still protecting and enhancing the environment.
The GOE has developed a National Spatial Strategy (NSS) through the Ministry of
Planning (MOP), with the support of UNDP for land uses and spatial economic
development. The strategy divides Egypt into seven planning regions. A land use map
was accordingly developed and presented as the Investment Map in the economic forum
held in Cairo during 1997.
Proper land management is necessary to protect biological diversity, utilize the land in a
sustainable way. Securing property rights, accounting for protected areas and habitats,
and the rights of local communities including the local indigenous groups is a necessary
part of reaching sustainable uses of land. Sound environmental management of
agriculture and rural development as well as implementing environmentally sound
management of urban settlements are the two key elements considered by the GOE for
land management leading to sustainable land use.
With the passing of Law 4/1994 for managing and protecting the environment, the
EEAA has the authority to coordinate national coastal zone management activities. The
EEAA established also a national committee to develop an Integrated Coastal Zone
Management Program (ICZMP). A major component of the program is protecting
coastal water from pollution.
h) Emerging issues
There are several emerging issues at present, which have to be considered in
environmental plans such as biosafety, risks associated with the release of
biotechnology products, and release of genetically modified organisms (GMO). In 2000,
the EEAA, with financial support from UNEP, produced a framework for a national
biosafety instrument, including draft legislation, which has been reviewed by the
Ministry of Foreign Affairs (MOFA) and Ministry of Justice (MOJ), but still needs
further review and refinement before being considered as legislation by the MSEA.
Environmental degradation impacts some social classes more directly than others, either
because of their nature, race, ages, social and cultural aspects, or their intimate relation
with the environmental problems. Special programs are tailored within the NEAP for
sub-population groups, particularly children, youth, women, elderly, physically
disabled, and marginalized people.
6- Institutional requirements
7- International cooperation
Egypt has signed and ratified most of the international and regional environmental
agreements since 1933, the year of signing the London agreement for the protection of
Study of Wastewater Sector in Greater Cairo Final Report
Chemonics Egypt February 2006
Outline of National Plans for Water Resources, Environmental and Wastewater Management 2-11
the flora and fauna of Africa. Egyptian scientists and scholars have made substantial
contribution as leader of international organizations and as architects of international
agreements for the protection of the global environment. Egypt was present in the
formal meetings of the sixth session of the Conference of Parties of the Climate Change
Convection in the Hague, November 2000. As one of the developing countries and one
of the Group of 77, Egypt is stressing that all parties should have a real voice in
negotiations, that priorities of developing countries must take a front seat and that
parties have to reach an agreement at the next meeting on a comprehensive package of
decisions on all issues covered by the Buenos Aires Plan of Action.
Egypt has an obligation to sign and ratify international and regional environmental
agreements, which are seen to be of potential benefit to the country. The NEAP needs to
take into consideration all these international agreements and incorporate into its
proposed actions their inherent obligations. The most emerging global/regional issues
that are addressed in the NEAP are the problem of climate change, regional cooperation
concerning Mediterranean Action Plan and bilateral and international cooperation
programs.
8- Financial measures
Sustainable financing will be needed to finance the projects that constitute the NEAP.
Following the five-year plan financing guidelines, Egypt will seek additional funds to
those allocated through the state as part of stakeholder partnership. More effective
enforcement of current regulations, improved legislation based on the polluter pays
principle, and the use of economic instruments will encourage private investment in the
environment.
Programs and projects developed at the local and community level may be funded with
loans from the Environmental Fund or the Social Development Fund. Such activities
should wherever possible be self sustained through the development of cost recovery
mechanisms for the provision of whatever environmental service.
The NEAP proposed three sources for financing the environmental projects, namely,
state budget, using conventional financing tools such as banks, and non-conventional
institutions/sources such as Environmental Protection Fund, ecotourism, green credit
card, or individual and corporate donations.
Despite of the general policies taken by the GOE towards decentralization and
economic liberalization, the water and wastewater sector is only now starting to take
steps to decentralize management nationwide and devote financial planning and
management to the governorate levels through water / wastewater companies under the
umbrella of the Holding Company for Water and Wastewater (HCWW). Water supply
and sanitation services today are still charged at less than cost. Appropriate policies for
penalizing customers who do not pay are not in force, and government and public sector
premises as well as religious institutions are often not paying their bills.
There is a pronounced regional bias in water supply versus sanitation service coverage.
Cities in Upper Egypt have only recently begun to implement sewerage systems, and
water supply provision lags behind in the villages of this region. In some regions the
increase in water coverage has been made on the expense of the quality and reliability
of the system. There are frequent system breakdowns and many household-connections
to water systems suffer regular and often lengthy service interruptions. Despite of the
high population densities in the villages, there is no proper sewerage system in rural
areas.
In Egypt, more than 80% of the population in urban areas is connected to piped-system
water supply compared to about 90% for the metropolitan areas of Cairo and
Alexandria. Water coverage in urban areas in Upper Egypt reached now between 75 to
85%. A large number of rural areas are dependent on groundwater sources for their
domestic water supply. Since groundwater usually does not need treatment, both the
quality of groundwater and the method used to deliver this water are of real public
health concern, especially in areas with no sewerage system and local disposal practices
may lead to contamination of groundwater. Over-pumping of aquifers may also lead to
contamination of groundwater source, by creating negative pressure within the water-
bearing strata. Infiltration to the aquifer from sewage or saline water sources may then
occur. According to a study conducted in 1995 by Shafy and Fathalla, 30% of the wells
in Minufiya governorate are biologically contaminated. Coliform counts of more than
100/ ml have been reported in the rural Mostorod area of Cairo governorate, and
NOPWASD reported that the wells in Shrarqiya governorate have also high biological
contamination (Chemonics Egypt, Report UNC 6-01(E), March 2005). The WASH
study conducted for USAID (1988) provides additional information concerning the
bacteriological contamination of water from deep wells, shallow wells, and irrigation
canals. Deep wells were the safest source.
Despite the quality of water at the River Nile intakes in Upper Egypt is generally good,
the drinking water quality standards are not always met because of insufficient control
of the purification process at the water works and due to the leaking networks.
Unaccounted–for water is up to 50%, the majority of which is caused by leaking pipe
networks and house installations. This accounts for almost 3 billion m3 of treated water
wasted annually at a cost equivalent to about LE 1.5 billion a year (Sector program
support – Water and Sanitation, Egypt, by COWI and Chemonics Egypt, June 2000).
CARE conducted a comprehensive survey activity related to the rural water and
sanitation sector in Middle and Upper Egypt. The survey covered a number of donor-
assisted activities (FINNIDA and the Dutch). The report concluded that household
sanitary facilities in villages are exclusively on site. Where houses have latrines, the
majorities have no formal method of sullage disposal. Many sanitary facilities function
poorly due to poor design and construction or because of problems in the absorption of
sullage into the soil. Poor handling and unsanitary disposal of wastewater have been
cited as serious health related problems connected with on-site sanitation.
Although there has been considerable growth in the provision of sanitation, it is likely
that 40% of the population in rural Egypt will remain dependent on on-site sanitation by
the year 2020 (METAP report, 1997). This document provides also basic information
on different water supply and sanitation systems in rural Egypt with assessment of the
various components of each system.
Most recent reports on the assessment of water and sanitation in Egypt prepared for the
UNICEF (2005) it was concluded that 21.7% of the total number of buildings in Egypt
are connected to wastewater networks, and 63% dispose of wastewater through other
alternatives, while the remaining 15% are deprived of sanitation services.
1
Border governorates mean those governorates that lies on the borders of Egypt, such as North and South
Sinai, Marsa Matrouh, Red Sea, Aswan, New Vallye
Study of Wastewater Sector in Greater Cairo Final Report
Chemonics Egypt February 2006
Outline of National Plans for Water Resources, Environmental and Wastewater Management 2-14
Only 6% of Egyptian villages are provided with sanitation services, and 7% shall be
served after completing the sanitation projects under construction, while the remaining
87% are deprived of sanitation services. The villages deprived of sanitation services
include the villages of Assyout Governorate and Kafr El-Sheikh Governorate; 90% of
Qalubiya, Behera, Beni Suef, Minya, and Sohag Governorates; and 46% of Ismailia
Governorate. The state is giving top priority, at present, to the shortage of sanitation
services in rural Egypt (Chemonics Egypt, Report UNC 6-01(E), March 2005).
Most of the Egyptian villages suffer from high groundwater table except South Sinai,
North Sinai, and the Red Sea. This high groundwater table in villages is considered one
of the most important problems that should be integrated to sanitation solutions
developed for the villages.
The total design capacity of all treatment plants in Egypt is ranging between 10 to 12
million m3/d. The actual capacity, however, may range between 7-9 million m3/d. Table
2.3 presents a summary of existing and planned treatment plants including upgrading up
to the year 2017.
Plants Capacity
(Mm3/day)
Existing plants
Present capacity 6.09
Ongoing construction to increase capacity 1.08
Planned capacity increase (till 2017) 1.29
New plants
Ongoing construction 3.35
Planned capacity increase (till 2017) 1.92
Planned new plants 1.67
Total (existing, under construction and planned) 15.40
Source: Darwish survey 2000
By 2017, the total available capacity may reach 15.4 Mm3/day. The capacity increase
will not be sufficient to cope with the future increase in wastewater production from
municipal and industrial sources and therefore the pollution loads that will reach the
water system are expected to grow significantly in the coming years.
During the period from 1982 – 1997, 35 new plants entered the service as part of the
government efforts to raise the level of sanitation services in the Governorates. The total
design capacity of these new plants is 1,5 million m3/d, and the total construction costs
reached LE 2,205.8 million. The plants were financed by a local fund through
NOPWASD with the support of some grants from USAID and FINNIDA.
The technologies applied for the treatment of wastewater in rural Egypt vary between
simple on-site sanitation, complete treatment plants, or other traditional solutions such
as sanitary latrines, trenches and percolating pits. Complete wastewater treatment
technologies include conventional activated sludge, trickling filter, aerated lagoons,
stabilization ponds, and upflow anaerobic sludge blanket (UASB) reactor.
Table 2.4 presents the country’s investment in 20 years (from 1982 to 2002) in 19
governorates and Luxor city, for water and sanitation. The total investment according to
the Table is LE 20,321 billion. Despite of the large size of investment, the problem of
the sector is still persisting and the performance is unsatisfactory. Analyzing the data of
the table it is possible to put the following remarks:
• The period of implementing the projects is too long and may go up to 10 years.
• According to MOP, only 40% of the projects planned within 20 years are completed
and 60% construction is still on going. This increases the net cost of the projects.
• There is a clear difference in the size of investment and the per capita share of the
investments among the Governorates, and seems that there is no clear criteria for
investment priority.
• The revenues of the water and wastewater companies do not cover capital
investment and this adds an additional financial burden on the governmental budget.
• The amount of investments during the first three five-year plans (1982-1997)
represent only 35% of the total cost of the projects, while the amount of investments
during the last five year plan (1997-2002) represent 38% of the cost. This is an
indicator of the increasing interest of the country to improve the sector.
The required investments to complete projects are, for example in Port Said
Governorate 0.02% and in Damietta 2%, in Assyout 8.4%, in Daqahliya 9.9%, and in
Menufiya 10.4% of the project costs, respectively. This shows some sort of miss
planning and in prioritizing the expenditure with respect to available resources.
Table 2.4 National Investments in Water and Sanitation Sector* from 1982 - 2002
Period from 5-Year Plan Total Period Total Estimated CostRequired Addition Project Capacity Population Investment per
Governorate 1982-1997 1997-2002 1982-2002 1982-2002
for Funds to Complete Million(m3/day) in 103 Capita Share
Water Sanitation Water Sanitation Water Sanitation Projects Projects Water Sanitation (2001) (LE)
Damietta 173.1 373.3 101.7 188.9 274.8 562.2 837.0 988.7 151.7 320.0 230.0 998.0 838.7
Sharqiya 277.0 295.4 370.4 646.8 647.4 942.2 1,589.6 1,883.7 294.1 437.0 388.0 4,721.0 336.7
Daqahliya 557.1 336.4 376.8 829.9 933.9 1,166.3 2,100.2 2,844.7 744.5 870.0 547.0 4,580.0 458.6
Qalubiya(1) 81.1 436.6 107.9 262.3 189.0 698.9 887.9 1,350.9 463.0 452.0 285.0 3,621.0 245.2
Kafr El Sheikh 390.3 112.1 231.2 488.6 621.5 600.7 1,222.2 1,819.2 597.0 743.0 171.0 2,405.0 508.2
Gharbiya 108.6 444.3 108.3 509.4 216.9 953.7 1,170.6 1,823.8 653.2 348.0 442.0 3,688.0 317.4
Menufiya 60.1 400.5 138.9 604.2 199.0 1,004.7 1,203.7 1,987.9 784.1 263.0 296.0 2,996.0 401.8
Beheira 594.9 533.8 317.4 509.4 912.3 1,043.2 1,955.5 2,208.0 252.5 500.0 270.0 4,348.0 449.7
Port Said 240.0 597.9 100.0 235.3 340.0 833.2 1,173.2 1,175.4 2.2 290.0 170.0 507.0 2,314.0
Ismailia 197.1 610.4 129.6 430.5 326.7 1,040.9 1,367.6 1,574.3 206.7 289.0 132.0 790.0 1,731.1
Suez 42.5 540.5 39.1 128.0 81.6 668.5 750.1 903.7 153.6 121.0 200.0 452.0 1,659.5
Giza(2) 46.7 66.0 112.6 169.5 159.3 235.5 394.8 705.6 310.8 166.0 92.0 3,000.0 131.6
Fayoum 28.6 121.8 76.8 238.8 105.4 360.6 466.0 860.9 394.9 213.0 214.0 2,211.1 210.8
Beni Suef 227.7 78.1 201.9 197.4 429.6 275.5 705.1 1,013.5 308.4 200.0 140.0 2,065.0 341.5
El Minya 79.5 128.6 254.1 304.5 333.6 433.1 766.7 1,256.6 489.9 278.0 222.0 3,719.0 206.2
Assyout 67.5 57.6 99.3 331.2 166.8 388.8 555.6 1,186.0 630.4 236.0 480.0 3,150.0 176.4
Sohag 127.7 310.0 188.0 425.3 315.7 735.3 1,051.0 1,400.0 349.0 272.0 325.0 3,500.0 300.3
Qena 358.0 83.3 230.9 210.5 588.9 293.8 882.7 1,241.9 359.2 261.0 223.0 2,712.0 325.5
Asswan 298.8 145.0 220.8 318.4 519.6 463.4 983.0 1,227.4 244.4 262.0 120.0 1,050.0 936.2
Luxor City 36.7 64.2 69.8 87.6 106.5 151.8 258.3 388.0 129.7 68.0 48.0 394.0 655.6
Total 3,993.0 5,735.8 3,475.5 7,116.5 7,468.5 12,852.3 20,320.8 27,840.2 7,519.3 6,589.0 4,995.0 50,907.1
Source: Adapted from report on cities and villages with access to wastewater services, Ministry of Local Development, Caior, Egypt, May 2003
* Except for Cairo, Alexandria, Sinai, New Valley, Matrouh, and Red Sea Governorates
(1)
Does not include Shoubra El-Khima
(2)
Does not include Giza City
3.1 Introduction
This chapter presents information on the technical, institutional and economic
analysis of the water and wastewater sector in Egypt/Greater Cairo. It includes a
general description of the institutional set up in Egypt in terms of the wastewater
sector and specifically the organizational structure and tariff policy in Greater Cairo.
Since 1991, the GOE has undertaken a program of fundamental national economic
reforms. However, reforms in the water and wastewater sector have not been carried
out as vigorously as in other infrastructure sectors. The slower pace is largely due to
the political risks associated with:
• Increasing household tariff levels and enforcing payment; and
• Implementing civil service reforms and commercializing human resource
management policy and staffing; and
• Decentralization of an overly centralized and fragmented institutional structure
The water supply and sanitation sector is presently undergoing a restructuring. This
involves the provision of water and sanitation services as a commercial/economic
activity rather than a social service at present.
The sector reform takes place at national, governorate, district, and community levels.
At the national level the following major changes to the institutional framework are
proposed (this changes reflects the donors recommendations and both the donors and
GOE are involved in an extended dialogue regarding these changes):
The immediate requirement at the governorate level is for existing utility operations to
be transferred to new public economic authorities (PEAs).
The main feature of the above institutions policy is the retention of revenues for their
own activities rather than being budget-driven as at present. Furthermore, many of the
rigid governmental regulations on employment, organization and financial
management will be removed or eased. The above policies are seen to serve the
proposed strategies in the water supply and sanitation sector.
In summary, there are several potential scenarios for institutional reform in Egypt that
deserve attention. However, it is apparent that progress achieved in service coverage,
particularly in water supply domain, has not been accompanied by institutional
reform, capacity building, nor a program of cost recovery to assure sustainable
operations of the water and wastewater sector. The main problems may be
summarized according to the publication (Institutional Development Services for
Secondary Cities Project in Egypt – South Sinai Governorate – by Chemonics
International, CDM, Center of Financial Engineering in Development, Chemonics
Egypt, and Arab Software Engineering, 1996) as follows:
In order to achieve sustainability within the sector the following reforms should be
implemented:
MOHUUC is the lead ministry with primary responsibility for the water and
wastewater sector. It has the responsibility to formulating and implementing sector
policies. At the local level, MOHUUC provides services to the governorates, under
the supervision of the Governor. It has a wide range of responsibilities, including
urban planning, implementation of housing projects, and development and monitoring
of utilities. The principle function of MOHUUC at the local level is to provide
resources and expertise to implement and operate water supply and sanitation
facilities.
The EEAA is the highest authority in Egypt responsible for promoting and protecting
the environment. It was established in 1982, although its current scope of
responsibilities was not fully described until the enactment of law 4/1994. The head of
the agency reports to the Minister for Environmental affairs.
The EEAA through the Minister’s office prepares co-operation protocols with other
ministries, establishing frameworks for information flow, personnel exchange and
policy co-ordination. Protocols are in place with the Ministries of Labor, Health and
Population, Justice, Industry, Petroleum, and Tourism.
The MF prepares government budgets and financial statements and is responsible for
final distribution of funds for government’s salaries (Bab 1); operation and
maintenance (Bab 2); and investments (Bab 3). MF functions include the following:
The MF continues to subsidize water and wastewater activities by covering the gap
between O&M cost and revenues and by providing investment loans (low interest) for
new projects. These loans in practice, however, are not repaid. Disbursements for
domestic funds for investments are allocated under the 5 –year plans.
The MP is responsible for planning and approving the allocation of public sector
investments within the context of the 5-year planning process.
The MHP is responsible for setting water quality standards, monitoring water quality
and performing health and hygiene programs. The MHP has enforcement power and
can order the closure of facilities and cessation of production for both public and
private entities that violate the standards. The MHP is involved in the approval
process for projects involving effluent reuse, from the standpoint of workers exposure
(occupational health), and public health.
Under the authority of the MLD, ORDEV is responsible for ensuring the provision of
basic services, including water supply and sanitation, as well as co-ordination,
planning and implementation of projects in rural areas.
Under the jurisdiction of the MOFA, the MIC is responsible for the co-ordination of
project funding from international donor agencies.
The MALR together with the Ministry of Environmental Affairs (MEA) are leading
the effort to establish a new code for the reuse of treated effluent. The MALR is also
responsible for the allocation of the land required for wastewater treatment plants,
particularly in rural governorates.
Overlapping Responsibilities
The MLD through ORDEV is implementing rural water and sanitation projects under
Shorouk program (financed from the Social Fund) with overlaps with NOPWASD
work for mother villages (the village where the local rural unit is located- see next
section).
Sector operations and maintenance have been decentralized to the governorates and
district/municipal levels, and are implemented under various legal arrangements and
institutional settings. The responsibilities of the various local institutions are given
below:
2. Marakez: Marakez staff manages water and wastewater services in the urban
areas whereas in rural areas these are managed by a combination of village
council staff and line ministries employees.
3. City Council: The city or town is a regional subdivision of the marakez. The
city’s mayor is appointed by the prime minister, and is responsible for all city
services, including utilities, and infrastructure. The city council takes overall
responsibility for management of water supply and wastewater services, but
the human and physical resources required may come from a variety of
sources. The primary functions of the city council with respect to the sector
are:
• To provide staff for operation and maintenance of facilities, including
meter reading, billing and revenue collection, and to deposit collected
revenues in the account of the MF;
• To prepare budget applications for operation and maintenance,
replacement and extensions of the systems for submittal to the
governorate; and
• To prepare and manage contracts for small development projects.
Study of Wastewater Sector in Greater Cairo Final Report
Chemonics Egypt February 2006
Institutional Analysis of Water and Wastewater Sector in Egypt/Greater Cairo 3-7
NOPWASD employees are located at different physical places. The majority of the
employees are located in the 4 floors of the building in Orabi Street (13-16 floor). The
Central Department of Training is located at Mogameh El Tahrir. Some of
NOPWASD’s manpower is distributed at construction sites in the various
governorates to supervise construction of ongoing projects.
The laws and regulations relevant to water supply and sanitation sector are described
hereafter. These laws include several presidential decrees (PDs) establishing separate
water and wastewater utilities, and sector agencies and authorities. The PDs vary in
the degree of autonomy given to the utility, with the newer decrees providing greater
degree of autonomy in managing operations.
The laws and decrees corresponding to the various water and wastewater utilities are
presented in table 3.1.
Table 3.1 Laws and Decrees Concerning Water and Wastewater Utilities in
Egypt
Related environmental laws include law 48 of 1982 setting the standards for effluent
discharges in water bodies and recipients, and subsequent executive regulations
(Decree 8 of 1983), and its amendments (Decree 9 of 1989) substituted recently by
Decree No.44 of the year 2000 related to the protection of the Nile River.
Additionally, law 4 of 1994 governs the above utilities concerning the environment.
Concerning drinking water quality the guidelines for drinking water quality of the
World Health Organization (WHO, 1984) are recognized and respected with minor
differences, for more details see section on water quality.
• Presidential decree for Cairo, Alexandria, and Secondary Cities water and
wastewater organizations to become autonomous, 1994;
• Privatization of public sector companies initiated, 1995;
• Privatization of telecommunication and electricity distribution networks, 1997;
• Legal Institutional and Regulatory Reform of the Egyptian Water and
Wastewater Sector Project (LIRR) study, 1997/1998; and
• Proposed framework for water and wastewater sector reform in Egypt by the
LIRR project, 1998.
The framework for restructuring the sector has been outlined in the proposal for
reorganization of the water and wastewater sector by the MOHUUC in January 2000
as presented in this chapter (3.2).
The reform process is temporarily delayed, but there is an expectation that at least a
new regulatory agency and a new law on grant of concessions will be approved. The
delay has been attributed to foreign currency issues after floating the Egyptian pound.
The President apparently has stated that all BOT and BOOT projects should provide a
positive net inflow of foreign currency. Accordingly a Prime Minister Decree No.
695/2001 was issued establishing a Ministerial Committee and a Working Group to
regulate national and local BOT and BOOT projects.
The Minister of the MOHUUC has issued Decree No. 41 of 2001 establishing a
Central Department for Private Sector Projects in the Ministry’s Headquarters.
The latest draft of a memorandum presented to His Excellency the Prime Minster
from the office of the Minister of MOHUUC regarding the water and wastewater
sector reform is given in Annex F. The development in this respect was a letter from
the Cabinet of Ministers to the Minister of Local Development informing him that the
Cabinet in its meeting dated 7/5/2003 decided to agree on the implementation of the
proposed regulatory phases of the water and wastewater sector reform providing that
the Minister of MOHUUC shall be responsible for studying the details related to the
legal procedures of the reform process, coordinating with the Governors, defining the
prospective role of every supervisory body to be established later, and reviewing the
results with the Utilities Ministerial Committee.
On April 27, 2004, the Presidential Decree 135/2004 formed the Holding Company
for Water and Wastewater (HCWW) under Law 203 for 1991; this Holding Company
belongs to the Ministry of Housing, Utilities, and Urban Communities (MHUUC).
The Decree further mandated the transfer of the following utilities into Law 203
subsidiaries of the Holding Company:
This Decree transferred all of the assets of the 14 utilities to the Holding Company.
The Holding Company occupied temporary offices on Talat Harb street in downtown
Cairo and has contracted for the renovation of a site at the Rod El Farag water
treatment plant which will serve as permanent headquarters.
As indicated above, both the Holding Company and the subsidiaries were
incorporated under Egyptian Law 203. The incorporation process has involved the
following:
Once the Holding Company and subsidiary companies were incorporated began work
on laihas (Bylaws). The first set of subsidiary company laihas drafted covered
Board of Directors, personnel, procurement, finance, authorities and stores. The
strategy was to develop one set of laihas appropriate for all companies.
• The revised laihas were sent to the companies by the Holding Company for
approval by each Board of Directors, and the personnel laiha was sent to the
Labor Union for approval.
By July of 2005 six laihas had been approved by the Board of Directors for each
subsidiary company.
Once these three templates were completed, a team visited each of the subsidiary
companies to present and discuss the templates. Following these visits, formal
feedback was received from each company. That feedback was reviewed by Holding
Company management and revisions in the templates were made as necessary.
Holding Company management approved the draft templates and sent the drafts to the
subsidiaries for Boards of Director approval. All subsidiary company Boards of
Director approvals were completed in July of 2005.
Once the organizational structures were officially approved by the respective Boards
of Directors, a set of model job descriptions was developed and issued to all
companies for comment and adoption. Based upon the organizational structure work
has also started on the development of staffing norms for each company.
General Directorate for Information Systems General Directorate for Public Relations
and Media
Deputy Chairman for Technical Affairs Deputy Chairman for Administrative, Financial
and Legal Affairs
Manager of Technical Manager of Quality Assurance and Manager of Legal Manager of Administrative
Operations & Affairs Sector Monitoring Sector Affairs Sector and Financial Affairs Sector
Maintenance Sectors
Figure (3.1) Organization Structure of the Holding Company for Water & Wastewater (HCWW)
Institutional Analysis of Water and Wastewater Sector in Egypt/Greater Cairo 3-15
Cost recovery for water is a function of supply cost, tariff & billing and collection
efficiency. Supply costs are dependent on both fixed costs and efficiency of operation.
Because water and sanitation services have not been operated in Egypt as cost centers,
they typically have no hand on actual costs for providing customers with water and
sanitation services. The local administration institutional framework in particular is
very control oriented, which provides no incentives for effective and efficient
management of services. There are number of conditions, which have to exist in order
to recover cost, including and not limited to:
• Substantial improvement in personnel performance;
• Effective and regular leak detection program associated with remedial and
correction measures;
• Increasing the number of household connections;
• Reduction in public taps or stand pipes;
• Increasing production capacity and monitoring water quality;
• Better metering system of water; and
• Priority attention given to customer database, billing, and collection
efficiency.
Table 3.2 presents actual cost of water in five Egyptian governorates (UNICEF, 1995
for MLD). A study prepared by NOPWASD in 1996 concluded that the cost of
wastewater collection and treatment is LE 0.255/m3. A separate study by the Cairo
Greater Organization for Sanitary Drainage calculated a cost of LE 0.635/m3,
including debts and benefits.
Central and local governments set tariffs in Egypt. The role of local government is
often under-appreciated. A national tariff schedule is published periodically under the
direction of the MOHUUC through the High Consultative Committee on Utilities.
This committee is composed of the chairman of the Cairo and Alexandria general
authorities for water and wastewater, the chairman of NOPWASD, the chairman of
Greater Cairo Wastewater Organization, and the senior undersecretary and
undersecretary for public utilities of the MOHUUC. The committee’s
Study of Wastewater Sector in Greater Cairo Final Report
Chemonics Egypt February 2006
Institutional Analysis of Water and Wastewater Sector in Egypt/Greater Cairo 3-16
It is worth to mention, however, that several utilities started to use the atmosphere of
the ongoing reforms and initiated tariff studies financed by donors, mainly USAID,
with the objective of rescheduling a justifiable tariff rate based on actual cost data.
The studies are planned for four utilities including Beheira Water Company,
Alexandria Water Company, and Alexandria Wastewater Company. The studies are
aiming to develop a basic tariff-setting methodology, to adapt the basic model to a
range of situations, to assist the GOE to assess the tariff implications of various
assumptions regarding efficiency, affordability, and other regulatory concerns, and to
assess personnel and logistic requirements of the regulatory agency with respect to its
tariff analysis functions.
According to the Ministry of Local Development, the current tariff for residential
water and sanitary drainage as of January 2003 is shown in Table 3.4 for each
governorate in Egypt. The tariff differs from one governorate to the other but all
governorates charge for the sanitary drainage as a percentage of the water tariff except
for two governorates (New Valley and Matrouh) which do not have access to sanitary
drainage services. A detailed tariff for different water uses in Greater Cairo as of
September 2004 is presented in Table 3.5. Such tariff was originally implemented in
Alexandria Governorate and proved to be effective.
Table 3.4 Tariff for Residential Water and Sanitary Drainage in Egyptian
Governorates (January 2003)
Residential Use
Monthly Water Consumption Monthly Water Consumption
1 to 30 m3 > 30 m3
Governorate Sanitary Sanitary
Water Tariff** Drainage as Water Tariff Drainage as
P.T./m3 Percentage of P.T./m3 Percentage of
Water Tariff Water Tariff
Cairo 12 20% 16 20%
Alexandria 23 35% 30 35%
Port Said 16 50% 21 50%
Damietta 23 35% 27 35%
Daqahliya 23 35% 30 35%
Sharqiya 23 35% 30 35%
Qalubiya 18 35% 25 35%
Kafr El Sheikh 23 35% 23 35%
Gharbiya 23 35% 30 35%
Menufiya 23 35% 50 60%
Beheira 23** 35% 35** 35%
Ismailia 16 150 P.T./M 50 150 P.T./M
Giza 12 20% 16 20%
Beni Suef 23 35% 30 35%
Fayoum 23 35% 30 60%
Minya 23 35% 23 35%
Sohag 23 35% 30 35%
Qena 23 35% 30 35%
Aswan 23 35% 30 60%
Luxor 23 35% 30 35%
Red Sea 55 None 55 None
New Valley 23 35% 30 35%
Matrouh 48 None 48 None
North Sinai 23 50% 30 50%
South Sinai 18 50% 18 50%
** Up to 25 m3 ** > 25 m3
Table 3.5 Detailed Tariff for Different Water Uses and Sanitary Drainage in
Greater Cairo (September 2004)
Sanitary
Water Tariff* Drainage as %
No. Tariff Class
P.T. of Water
Tariff
Residential:
1 to 10 m3/month 23
1
11 to 30 m3/month 25 35%
> 31 m3/month 35
Buildings 80 70%
Flat Monthly Rate for Houses owned by
the Governorate (Public Houses)
1-bedroom apartment 300
2
2-bedroom apartment 360
35%
3-bedroom apartment 480
> 3-bedrom apartment 600
3 Syndicates and Political Party Offices 48 70%
4 Social & Religious 42 35%
5 Embassies 75 70%
6 Small Factories, Shops, Cafes,
70 70%
Restaurants
7 Big Factories, Gas Stations, Private
80 70%
Schools
8 Private Hospitals, Hotels 125 70%
9 Raw Water 19 No Drainage
10 NGO’s 42 35%
11 Small Sport Clubs 48 35%
12 Public Hospitals 70 70%
13 Large Sport Clubs 100 70%
14 Bakeries and Garages 70 70%
15 Raw Water for Free Zones 19 No Drainage
16 Clarified Water 22 No Drainage
17 Governmental Institutions – Public 65 70%
Industries – Local Authority Units
4.1 Introduction
Egypt had seriously suffered from negligence of the infrastructure projects during the
period, extending to late 1970’s, in which all of the efforts and resources of the
country were dedicated for defending and securing the Egyptian borders.
Consequently, the wastewater system that served the Greater Cairo during that period
was in an extremely bad condition, most of the capital streets were flooded by the
excess wastewater flow.
In the year 1981, a new organization was established under the decree number “497”
of His Excellency the Minister of State for Reconstruction Housing and Land
Reclamation, to plan, design and construct a new wastewater project that save and
serve Greater Cairo. It was named the “Organization for Execution of the Greater
Cairo Wastewater Project”, know as CWO (Currently known as “the Organization of
the Greater Cairo and Alexandria Water and Wastewater Projects” (CAPWO)). Ever
since, CWO has played a great role in improving the environmental conditions and
regaining the bright full image of the country’s capital city.
The Greater Cairo Wastewater Project is one of the largest wastewater projects in the
world; it serves a population of 20 million occupying an area of about 1100 square
kilometer. It includes a large conveyance system, major pumping stations and huge
treatment plants, that raised the capacity of Cairo wastewater system from 1.4 million
m3/day to 5.24 million m3/day and has significant impact on the wastewater services
in Cairo. This mega project was divided into three major subprojects according to the
geographic location of districts served in Greater Cairo along the banks of the River
Nile as follows (Figure 4.1a & Figure 4.1b):
• East Bank Project
• West Bank Project
• Helwan Project (South of Cairo)
The area served by the Greater Cairo Wastewater Project lies in three main
governorates: Cairo, Giza and Qalubiya. The project efforts also include the
rehabilitation of the old pumping stations, treatment plants, and the drainage
improvement of the old sewers. The development of the wastewater system in
Greater Cairo is illustrated in Figure 4.2, featuring important data about the project as
follows:
8
6.84
7
Capacity (million m3/d)
6 5.4
5 4.3
4
3
1.85
2 1.4
1
1 0.35
0.05
0
2005 1998 1996 1992 1978 1970 1935 1914
This chapter presents data and information on the present situation of the wastewater
system in Greater Cairo.
Drain
2150 2000 500 600
To farm
2210 100
1500
100
150 Old Gabal Plant
500
100
Belbeis
El Gabel El-
Shebein El-Kanater
Emergency chanel
1500 Asfer WWTP
(1500)
El Khosos
Drain
Drain
Zero
By pass flow channel
from El- berka
1500 El-Berka
480
El-Kalag WWTP
Triple pipes
60 PS (500)
project
El- 160
Berka
290
50 El-Nahda city
El-Khosos
PS
PS
Shobra El- 150
Khema
1560 (2)
WWTP 200
(480) El Basha Emergency
60 100 160
Abo Ser 100 El
280
El mataria
Bahtem 55 Gamal
Zero Ain
PS El- Abd El
Shams 245
Ameri zero
PS
a PS
Emergency
chanels
1700
Shobra El-
Khema Culvert
Main
50
Tunnel
Masr El-Gdeda
• Flows by 1000 m3 & Nasr City
l t
Present Situation for Wastewater System in Greater Cairo 4-7
The main components of the project are shown in Figure 4.4, as follows:
• Main tunnel which expands from Maadi to Ameriya pump station of length
17.9 km, with diameters from 4 to 5 m.
• Branch tunnels of length 32 km, and micro tunnels of length 14.7 km, with
diameters from 1.2 to 2.5 m.
• Main collectors from Ameriya to Khossous of length 17.61 km and force
mains of length 3.65 km, with variable diameters.
• Gravity sewer lines of length 320.3 km, with variable diameters.
• Three main pumping stations along the tunnel and main collectors, with the
following capacities:
• Ameriya pumping station of average capacity 2.18 Mm3/d.
• Khossous pumping station of average capacity 1.88 Mm3/d.
• Kalag pumping station of average capacity 1.5 Mm3/d.
• A secondary treatment WWTP at Gabal El-Asfer occupying an area of about 2
Mm2, executed in stages reaching a total capacity of 3 Mm3/d by the year
2030. Its current capacity is 1.5 Mm3/d. This plant is the corner stone of the
project, being the largest WWTP in the Middle East.
Details of Completed Contracts for the Wastewater Project in the East Bank that has
been in Service, as of the year 2000, are as follows (Figure 4.5):
Table 4.1 (Cont’d): List of Tunnels, Culverts, Gravity Sewers Contracts under the
Project
Design Q Cost
Contract Length/
Description Section million (in million)
No. km
m3/d LE
14 Branch tunnel North Circular diameter
8.076 0.142 334.34
Shoubra and Rod El Farag. 0.6-1.8 m.
15 Branch tunnel in city Circular diameter
11 0.14 481
1.8-2.2 m
Gravity Gravity sewer serving the Circular 250-
sewer villages of Kalag, Marg, 1200 mm.
156.44 --- 87.3
Khousous, El Zohour, 23
July & Gabal El Asfar
LE = Egyptian Pound STR = Sterling Pound DK = German Mark
Source: Large steps towards better environment 1981-1998, The Organization for the Execution of the
Greater Cairo Wastewater Project, MHUUC, Cairo 1999.
Table 4.2: List of Lift Pump Stations Contracts under the Project
Contract Description Water Head No. of Design Q
No. M Pumps Million m3/d
1,2 Ameriya 24 8 Centrifuge 2.180
1,2 Ameriya 7 4 Screw 0.560
9 Khossous 7.5 12 Screw 1.880
Khossous 23” 4 Centrifuge 0.35
Kalag 7.5 10 Screw 1.5
16/1 Gabal El Asfer 9.6 10 1.73
Source: Large steps towards better environment 1981-1998, The Organization for the Execution of the
Greater Cairo Wastewater Project, MHUUC, Cairo 1999.
l
een E
Sheb
Proje
To Alexanderia
c t Ar
Gabal El-asfarWWTP
C 16-1, C16-2
ea B
ound
Be
l ba
ary
se
Shoubra El-Kheima D rai
n
C9 Berka WWTP
WWTP Khalag PS
ary
und
a Bo
ct Are C 8 Culvert
e
Proj C9 mailia
To Is
Qalioubya
Kossous PS
Governorat C7 International
Airport
culvert
C 6 Culvert
C 1, C2
C 5A Ameria P.S. Heliopolis
Branch Tunnel
C 3, C 3A
Main Spine Tunnel
C 14
Branch Tunnel Souk El-Samak To Suez
Abbasia
Central
C 15 Naser City
Branch Tunnels
Zamalek
Cairo
a Boundar
C4
Main SpineTunnel
Project Are
Abdeen
Cairo Governrate
Roda
C 12
Main Spine Tunnel
Ein El-Siera
C13
Rock Tunnel
Ring Road
The west bank project facilities are divided into two systems as follows:
Details of completed contracts for the wastewater project in the west bank which have
been in service as of the year 2000 are shown in tables (4.5 a), (4.5 b), (4.5 c), (4. 5 d),
(4.5 e), (4.5 f), (4.5 g) respectively.
Zaied City.
5,000m3/day
Kafr Gataty P.S.
10,000m3/day Zenein WWTP
285,000 m3/day El Geza P. S.
3 El Etehad P. S.
165,000m /day
10 St. P. S.
Pyramids P. S.
GOSD P. S. No. 6 Emergency
200,000m3/day
70,000m3/day
3
0 m /day Zenein P. S.
80,000 m3/day
GOSD P. S. No. 1
165,000m3/day
GOSD P. S. No. 5 West Bank Project
105,000m3/day * Current flow/ year 2005
Chaops P. S. * Future connections
25,000m3/day
Shabrament Prepared by
30,000 m3/day CWO Technical Office
Present Situation for Wastewater System in Greater Cairo 4-13
a) Collectors
Table 4.5 (a): Completed Contracts for the Wastewater Project in the West Bank
(Collectors)
Design Q Cost
Contract Length/
Description Section million Million
No. km
m3/d $
20 A Main collector at Embaba Circle dia. 0.8 –
18 620 107.1
2.75 m.
21 Main collector from Twin barrel
Embaba to Abu Rawash culvert each 10.4 650 29.73
3.00 x 2.00 m
23 A Release collector for Giza Circle dia. 1.2 –
5.5 850 20.42 LE
P.S. 2.5 m.
25 Main collector from Twin barrel
Pyramids P.S. to Junction culvert each 2.6 9 393 34.120
P.S. x 2.00 m
27 Drainage sewer network Circle dia. 0.8 –
collectors in the Pyramids 2.75 m 12.4 342 41.685
area
Source: Large steps towards better environment 1981-1998, The Organization for the Execution of the
Greater Cairo Wastewater Project, MHUUC, Cairo 1999.
Table 4.5 (b): Completed Contracts for the Wastewater Project in the West Bank
(Lift Pump Stations)
Design Q Cost
Contract Length/
Description Section million Million
No. km
m3/d $
22 Screw pump station 6.1
3 240
Embaba Boulak, South 8.5 – 8
4,4 624 44.64
Muheit 7.1 , 6.5
5,5 832
Junction, Abu Rawash
23 Zenein screw P.S. head 8.5 + 7.5 4
393 14.0
on 2 stages 4
26 Pyramids screw P.S. 8.5 3 416 9.364
28 Cheops screw P.S. 5.9 2 100 9.762
Source: Large steps towards better environment 1981-1998, The Organization for the Execution of the
Greater Cairo Wastewater Project, MHUUC, Cairo 1999.
c) Treatment Plants
Table 4.5 (c): Completed Contracts for the Wastewater Project in the West Bank
(Treatment Plants)
Contract Description Water Head No. of Design Q
No. M Pumps Million m3/d
29 Abu Rawash Primary 400 130.755
treatment plant
31 Rehabilitation of Primary + 330 74.152
existing Zenein Secondary
WWTP
Source: Large steps towards better environment 1981-1998, The Organization for the Execution of the
Greater Cairo Wastewater Project, MHUUC, Cairo 1999.
Study of Wastewater Sector in Greater Cairo Final Report
Chemonics Egypt February 2006
Present Situation for Wastewater System in Greater Cairo 4-14
Table 4.5 (d): Completed Contracts for the Wastewater Project in the West Bank
(Improvement of the drains)
Contract Design Q No. of
Description
No. Million m3/d Pumps
Improvement of Barakat, Abd El Rahman
30 A 1600
drains
43.00
Construction of twin Siphon under the
30 B 2000
Beheira canal
Source: Large steps towards better environment 1981-1998, The Organization for the Execution of the
Greater Cairo Wastewater Project, MHUUC, Cairo 1999.
Table 4.5 (e): Completed Contracts for the Wastewater Project in the West Bank
(Sludge Disposal Facilities)
Contract Description Type of Design flow Cost Million $
No. Treatment M3/d/1000
Sludge force main
33 A 33.6 24.372
and lagoon disposal
33 B Sludge Pump Station 33.7 7.83
Source: Large steps towards better environment 1981-1998, The Organization for the Execution of the
Greater Cairo Wastewater Project, MHUUC, Cairo 1999.
Table 4.5 (f): Completed Contracts for the Wastewater Project in the West Bank
(Dewatering Pilot WWTP)
Contract Description Type of Design flow Cost Million $
No. Treatment M3/d/1000
Testing pilot for Anaerobic
35 50 4.289
sludge treatment bacteria
Source: Large steps towards better environment 1981-1998, The Organization for the Execution of the
Greater Cairo Wastewater Project, MHUUC, Cairo 1999.
West bank unsewered areas are served by fixed amount reimbursable (FAR) program.
The FAR program was developed by USAID with the following major purposes:
• To provide sewers and house connection to residents in poor areas and
villages on the West Bank.
• To strengthen the ability and standard of Egyptian contractors. USAID
fund 79% of the program cost and the Egyptian Government fund 21%
of its cost.
Table 4.5 (g): Areas served by the Wastewater Project in the West Bank
No. approx. of
No. of Sewer Length Population
Served Area House
Contracts (km) Served
Connection
Embaba 27 282.305 64148 1137000
Pyramids 15 124.47 15085 250000
Saft El Laban 8 68.36 10034 196000
Abu Rawash 2 11.05 1280 40000
Kirdasa 9 60.77 8770 333000
Bani Magdoul 2 16.85 2210 44000
Maintenance 1 --- --- ---
Office
Total 64 563.805 83527
Source: Large steps towards better environment 1981-1998, The Organization for the Execution of the
Greater Cairo Wastewater Project, MHUUC, Cairo 1999.
Details of completed contracts for the wastewater project in Helwan which have been
in service as of the year 2000 are as follows (Figure 4.9):
Table 4.6 (a): Completed Contracts under Helwan Project (Networks and Collectors)
Contract Description Cross Section Length Cost in
No. Km Million
1&2 Wastewater main Circular re-enforced 18.05 LE
collector concrete pipes dia. 10 53.45 DM
Between 3.4 m, 3 m 4.55 DFL
3 Gravity sewers Circular with dia. between
9 4.46 LE
800 mm & 1800 mm
4 Wastewater collector Horseshoe with dimension
between Helwan & between (2.4x2.6m) and 8 59.99 LE
Maasara (2.3x2.15 m)
5A Sludge drying beds 660 drying beds units
--- 6.21 LE
modification
7 Gravity sewers in Circular with dia. between
20
industrial area + P.S. 225-750 mm force main 7.24 LE
1,25
and force main dia. 400 mm
11 Main collector from Horseshoe with diam. of
6 38.33 LE
Maasara to Torah (2 m x 2.15 m)
12 Gravity sewers North Circular, dia. between 225
10 3.2 LE
of Helwan mm – 1000 mm
13 Gravity sewers North Circular, dia. between 225
37 3.99 LE
of Helwan mm – 120 mm
14 Main collector from Horseshoe with diam.
3.5 18.19 LE
Torah to South Maadi between (1.6 m x 1.72 m)
Study of Wastewater Sector in Greater Cairo Final Report
Chemonics Egypt February 2006
Present Situation for Wastewater System in Greater Cairo 4-17
Table 4.6 (a) (Cont’d): Completed Contracts under Helwan Project (Networks and
Collectors)
Contract Description Cross Section Length Cost in
No. Km Million
15, 16 Gravity sewers in Dia. between 225 mm –
70.00 LE
Helwan and Torah 600 mm 60
(estimated)
areas
21 Main collector to Horseshoe with gradual
serve Zahraa El- dia. from (0.9 x 1 m) –
4.5 27.103 LE
Maadi and central (1.6 m x 1.72 m)
Plateau
Shoubak Gravity sewers Dia. between 225 – 275
13.71 6.9 LE
& Minya m
Source: Updating Masterplan of Helwan Wastewater Project, October 2005
Table 4.6 (b): Completed Contracts under Helwan Project (Lift Pump Stations)
Contract Description Water No. of Units Design Cost in
3
No. Head m. m /sec Million
1 Pump station
No. 2 and its 6 4 screw 5.7 – 7.4 ---
force main
2 Pump station
No. 3 and its 6 3 screw 2–6 ---
force main
4 P.S. No. 4 6 2 screw 1.35 – 2.7 ---
8 Main P.S. and
4 centrifugal 350000 11.23 LE
twin force 40
2 centrifugal m3/d 15.85 DM
main
9 Irrigation P.S. 4 centrifugal 350000 3.51 LE
40
2 centrifugal m3/d 20.315 DM
Source: Updating Masterplan of Helwan Wastewater Project, October 2005
c) Wastewater Treatment
Table 4.6 (c): Completed Contracts under Helwan Project (Wastewater Treatment)
Contract Description Treatment Design Q Cost
No. 1000 m3/d/ in Million $
5, 6 WWTP Primary + 350 18032.56 Lit
Secondary 2.41 LE
Source: Updating Masterplan of Helwan Wastewater Project, October 2005
Capacity: First stage was commissioned in 1998 with a design capacity of 1 Mm3/d.
Second stage was operational as of October 2004 with a capacity of 500,000 m3/d.
Capacity: The first stage was commissioned in 1992 with an average capacity of
400,000 m3/d. The second stage will expand the capacity to 1.2 Mm3/d by the year
2010 with a final stage to increase the capacity to 2 Mm3/d.
Location: South east of Greater Cairo at Arab Saad. It serves Helwan, Torra, Maadi,
Basateen and Al Saf districts.
Capacity: The first stage was commissioned in 1978 with an average capacity of
250,000-m3/d and maximum capacity of 466,000 m3/d. The plant is currently
overloaded as the flow reached 420,000 m3/d. Plant expansion is required to increase
the capacity to 550,000 m3/d in a second stage and finally to 960,000 m3/d in a third
stage.
Capacity: Zenein WWTP was originally taken into operation in 1970 and extended to
the present capacity of 330,000 m3/day in 1978. In the beginning of 1990’s the
WWTP was rehabilitated to the present extent. Today the WWTP is located in the
middle of a housing area. During the time when it was originally constructed, it was
surrounded by agricultural fields.
The average flow (2001) to the WWTP is approximately 271,000 m3/day. The
influent sewage quality in terms of BOD5 and suspended solids concentrations are
about 240 mg/l. No major industrial discharges to collection system exist.
Helwan WWTP
As has been demonstrated in countries across the world, reclaimed wastewater can be
safely and economically used for: crop production; landscaping, recreational grounds
irrigation, industrial processes, cooling towers, air conditioning, stack gas scrubbing,
toilet flushing, construction, fire fighting, environmental enhancements (wetlands
preservation).
Water reuse has been practiced in Egypt for over 100 years, through government
sanctioned projects as well as unofficial practices. Water reuse has been used since
1915 at the government farm of Gabal El Asfr near Cairo. The Afforestation and
Environment Division of the Ministry of Agriculture and Land Reclamation has
developed 10 forest plantations across Egypt that are irrigated by treated sewage
water. In addition, farms in Ismailia, Helwan, Qena and Abu Rawash have been
officially operating on treated effluent. And in areas without sewerage, such as in the
Nile Delta, septic tanks are routinely emptied into agriculture drains, which are then
used as a source for irrigation during water shortages.
Very little study has been undertaken on the sanctioned effluent reuse schemes, with
the exception of the Gabel El Asfr scheme. This project is approximately 25 km
northeast of Cairo, on the edge of the Delta flood plain. The farm is 3000 feddans
(i.e. 1350 ha). Since 1915 the farm has been irrigated using effluent that has received
only basic sedimentation. In 1992, the average application rate was 80,000 m3/d of
effluent.
Salinity of the effluent was tested to be around 1000 mg/l. Chloride and sulfate
concentrations of 160 mg/l and 26-60 mg/l respectively were found in the effluent.
Average COD content was 470 mg/l. Average total-N content was about 14 to 60
mg/l with NH4 concentrations from 10 to 65 mg/l and NO concentrations ranging
from 25 to 45 mg/l. In addition, relatively high Boron concentrations of 0.7 to 2 mg/l
were found in the effluent. Groundwater studies in the area showed significant impact
on the groundwater table, with especially high nitrogen content, heavy metals and
fecal coliforms.
Egyptian standards and restrictions for the reuse of treated wastewater are set out in
Presidential Decree No. 44 (2000) and its precursor, Decree No. 16 (1995).
Microbiological standards applying to treated wastewater reuse in Egypt generally
follow the WHO (1989), and US EPA (1992) Guidelines. Recently, the MHUUC has
published the Egyptian Code for Reuse of Treated Wastewater Effluent in
Agriculture, Code EPC 501-2005.
The following two tables (4.7 and 4.8) from Decree 44 (2000) provide the required
parameters for effluent reuse:
Egypt’s Water Policy/Water Balance report: 1997 – 2017 set an expectation that 20.4
billion m3/y of water will be needed for reclamation projects by 2017. The expected
sources are 5.9 billion from groundwater, 5.5 billion from agricultural drainage water,
3 billion from crop substitution and 4 billion from improved irrigation practices. Also
included would be 2 billion from treated effluent: Current estimates are that .04
billion of treated effluent is being used per year.
It is important to note that the issue of what can be done with treated effluent is a
potential bottleneck. Discussions within the drafting groups include whether to make
reuse standards more restrictive than current guidelines under Decree 44/2000, (and
international guidelines such as FAO, EPA, EU).
The large possibilities for commercial use of the treated effluent should be seriously
taken into account in any decisions on the extent of secondary treatment facilities to
be built as part of the expansion of the WWTPs in Greater Cairo. The price to be paid
for establishing a secondary treatment system is likely to match that would be
required to clean the polluted river with the added benefit of reusing the secondary
treated effluent for producing crops for market.
According to the Egyptian Code (ECP 501-2005) published in 2005, three grades of
effluent quality namely grades A, B and C were specified for water reuse in irrigation
which require advanced treatment for Grade A, secondary treatment for Grade B, and
primary treatment for Grade C. While treated effluents satisfying the requirements for
Grades A and B could be used for irrigating agricultural lands, the reuse of treated
effluents with Grade C is limited to irrigation of forest lands (wooden trees) and some
plants for the production of industrial oils only. This in turn calls for the application of
secondary wastewater treatment plants as a minimal requirement for effective water
reuse programs.
5.1 Introduction
Some 20 years ago, one of the largest wastewater projects was launched in Greater Cairo. The
Organization for the Execution of the Greater Cairo Wastewater Project (CWO) undertook the
responsibility of preparing the necessary studies and implementing this project. The project
area has been, for practical reasons, divided into two sub-areas, the one covering the West
Bank of the Nile, the other the East Bank. In the south, the Helwan area was later added to the
Greater Cairo Wastewater Scheme. The initial masterplan for this project was produced in
1978. This involved evaluating existing wastewater installations, preparing plans for their
rehabilitation where appropriate and identifying the need for new facilities. Detailed proposals
were developed for an extensive collector system serving the greater part of Cairo city,
involving large-scale construction in tunnel on the east bank of the Nile. In 1984 detailed
engineering designs were completed for the scheme.
This chapter presents the existing wastewater system (sewer networks, pumping stations, and
wastewater treatment plants) in Greater Cairo for each of the three areas: East Bank, West
Bank, and Helwan. An analysis of the existing bottlenecks and the future plans required to
ease these bottlenecks are also presented in this chapter.
The East Bank area is divided into three zones: Central Cairo, Shoubra El-Kheima, and Nasr
City. The wastewater collection network has been upgraded several times since the
preparation of the master plan of the year 1978.
5.2.1 Background
The 1978 Masterplan has always been the reference document for CWO planning. The
strategy defined by the Masterplan was to divide the East Bank network into three main equal
size systems with transfer facilities to split the flows between those systems (Figure 5.1):
i) A separate collector system for the Shoubra El Kheima area (north of Ismailia Canal)
leading to a treatment plant discharging into the Shebeen El Kanater drain.
ii) A new conveyance tunnel aligned after the rout of the Emergency Canal to transfer to
Berka WWTP the wastewater of the relatively elevated areas of Mokattam, Nasr City and
Heliopolis on the eastern and northeastern fringes of the city.
iii) A main conveyance system from Ameriya to Gabal El Asfar to serve the remaining part of
the East Bank.
In order to use the treatment plants at their full capacity, it was planned to connect the main
culverts to Shoubra and Berka wastewater treatment plants by:
• Implementing two θ 1200 mm pipes and a transfer pumping station (TPS) in Khossous to
transfer flow from the main culvert to Shoubra El Kheima WWTP.
• Rehabilitating the old Pumping Stations no. 3 and 4 in Ameriya to deliver wastewater to
Berka treatment plant.
Figure 5.1: Master Plan of 1978 for the East Bank of Greater Cairo
g) The enlargement of the Gabal El Asfar drain to convey the flows up to 1,75 million
3
m /day to the Belbeis drain.
j) Culverting of the Emergency Canals and the new pumping station in Bridge no. 3
The scheme hereafter presents the present situation of the network (Figure 5.2).
Pumping Stations
Ameriya Tunnel PS
• 8 pumps can be with a capacity of 3600 l/s or 311,000 m3/d.
• 7 pumps can be operated simultaneously giving a total discharge of 2,200,000 m3/d.
Ameriya Collectors PS
• 4 Archimedean screws each with a capacity of 2,170 l/s or 187,000 m3/d.
• 3 Screws can be operated simultaneously giving a total discharge of 560,000 m3/d.
Khossous Screw PS
• 12 Archimedean screws each with a capacity of 2,170 l/s or 187,000 m3/d.
• 10 Screws can be operated simultaneously giving a total discharge of 1,875,000 m3/d.
Khossous Transfer PS
• 4 Pumps, each with a capacity of 1,350 l/s or 116,000 m3/d.
• 3 Pumps can be operated simultaneously giving a total discharge of 350,000 m3/d.
Kalag
• 10 Archimedean screws each with a capacity of 2,170 l/s or 187,000 m3/d.
• 8 Screws can be operated simultaneously giving a total discharge of 1,500,000 m3/d.
Bahtime PS
• 8 Pumps, each with a capacity of 1,200 l/s or 104,000 m3/d.
• 6 Pumps can be operated simultaneously giving a total discharge of 620,000 m3/d.
The civil works of this pumping station are designed for the installation of two additional
pumps to reach a capacity of 830,000 m3/d.
Length Capacity
Culvert Dimensions Slope
(m) (m3/d)
America – Urban Boundary 2 culverts
1/1900 2920 2,200,000
4mx3m
Urban Boundary – Khossous 3 culverts
1/2050 3140 2,250,000
3,5 m x 3 m
Khossous – Kalag 2 culverts
1/1900 5500 1,537,000
3mx3m
Kalag – Gabal El Asfar 2 culverts
1/1900 2300 1,537,000
3mx3m
Matariya Branch – Urban 1 culverts
1/1625 890 745,000
Boundary 2,75m x 3 m
Khossous – Shoubra El 2 x θ 1200 m Force main 1500 350,000
Kheima
b) Shoubra El Kheima
Length Capacity
Culvert Dimensions Slope
(m) (m3/d)
Factory – Collector 3250 mm Information
3900
not found
Bahtime – Shoubra El 2 x θ1500
Force main 2600 550,000
Kheima mm
c) Ein Shams
Length Capacity
Culvert Dimensions Slope
(m) (m3/d)
To old Gabal El Asfar θ 1200 mm
Forced main 12000 150,000
treatment plant
To Berka θ 1200 mm Forced main 9000 150,000
To Emergency Canals θ 1200 mm Forced main 1,800 150,000
By 2015, the total discharges conveyed to Berka WWTP will reach 651,000 m3/day and will
exceed the capacity of the Berka treatment plant.
Therefore, it is planned to divert the excess flows to Gabal El Asfar Wastewater Treatment
Plant by implementing a new culvert from Nasr City and by connecting the force main from
Ain Shams pumping station to Gabal El-Asfar WWTP (Figure 5.3).
Shoubra El Kheima WWTP treates the wastewater discharges from Shoubra El Kheima area.
These discharges vary from 300,000 m3/day in 1995 to 466,000 m3/day in 2015. Therefore,
the excess wastewater flows is planned to be pumped from Khossous through Khossous
Transfer Pump Station to ease the load over Shoubra El-Kheima WWTP, so that, finally, the
excess wastewater will be conveyed to Gabal El-Asfar WWTP.
.
Figure 5.3 Proposed Connection between Ein Shams and Gabal El Asfar
The existing facilities are sufficient to meet the needs up 2015. In Khossous, the networks
implemented by CWO should add an estimated discharge of 200,000 m3/d. Whether this flow
is to be discharged upstream or downstream, the capacity of Khossous Pumping Station
should vary between 2,1 millions m3/d and 2,4 millions m3/d by the year 2015. Thus, this
pumping station will then need to be extended with an additional 2 or 3 screws (standby not
included). Accordingly, the discharges in the different sections downstream Khossous
pumping station will be:
The conveyance system downstream Khossous pumping station will then be overloaded and
new facilities must be implemented. These facilities must be designed to transfer the flow
corresponding to the year 2015.
By 2015, Gabal El Asfar WWTP will have a capacity of 2,000,000 m3/day (peak: 2,600,000
m3/day). Taking into account that 100,000 m3/day will come directly from Gabal El Asfar
village and Ain Shams, the transfer capacity of the system should be:
The sanitary sewerage system of the City of Cairo dates from 1914 and originally consisted of
a partially combined system serving the East Bank. Its main elements were a 50,000 cmd
treatment plant at Gabal El Asfar, approximately 25 km northeast of the city, and a main
collector served by 63 ejector stations. From 1925 through 1954, the collection system was
expanded and various pumping stations and relief collectors were added, as well as additional
sedimentation tanks at Gabal El Asfar.
The initial West Bank system was commissioned in 1939. Its wastewater was pumped to a
treatment plant at Abu Rawash, located approximately 15 km west of the Nile River.
In the mind 1960s, the “One Hundred Days Scheme” added new primary treatment facilities
at Nahya on the West Bank (80,000 cmd) and at Khossous on the East Bank (150,000 cmd),
as well as relief and pumping facilities to divert southern East Bank flows to the West Bank
through an inverted siphon that had been constructed under the Nile.
The West Bank treatment plant, at Zenien, was commissioned in 1970. This had an initial
design capacity of 220,000 cmd and in 1978 was under expansion to a total capacity of
330,000. By that time, lack of system capacity and the poor condition of many of the
facilities had lead to a situation in which sewage ponding was a normal occurrence in many
parts of the city and in which no effective secondary treatment was being given to any of the
collected wastewater.
In 1978-79, Taylor Binnie & Partners prepared a master plan for the Greater Cairo
Wastewater Project for the Ministry of Housing and Reconstruction. With the availability of
USA and UK funding assistance, AMBRIC was formed in 1979 to assist with the
implementation of the project.
The initial tasks of AMBRIC included preparing an Interim Development Plan Report. Part I
of this report, presented in June 1980, reviewed the master plan population projections in the
light of the 1976 census data, and made use of flow measurement, sampling and analysis data
to reassess overall flows and loads. It presented a staged development plan for design and
construction of first stage works. Part II of the Interim Development Plan Report, presented
in February 1981, proposed a major rehabilitation and upgrading effort for the Zenein
treatment works.
In June 1981 AMBRIC submitted the Design Inception Report (DIR). This report refined the
population, flow and load projections based on the same data as used in the Interim
Development Plan Report and presented revised facility planning criteria applicable up to the
year 2000 and the planning horizon (saturation development). It reduced the level of
treatment proposed at Abu Rawash from tertiary to secondary but otherwise introduced only
minor changes from the Interim Development Plan Report proposals. It also presented design
criteria and construction packaging for the first stage works.
In the period 1982-84, first stage detailed designs and construction documents were prepared
for CWO by AMBRIC.
Rehabilitation of existing conveyance facilities took place from 1983-86. Rehabilitation of the
Zenein wastewater treatment plant began in 1987 and it is now in operation. Construction of
the GCWWP facilities shown on (Figure 5.8) began on the East Bank in 1984 and on the
West Bank in 1985. Major West Bank conveyance works, effluent drain improvements, and a
new 400,000 cmd primary treatment plant at Abu Rawash have been completed and are
operational. Construction of some of the West Bank local sewer system under FARA
contracts will continue into 1995, as will the construction of sludge conveyance and disposal
facilities.
Pump station (by 1997). Options for possible expansion of the Zenein treatment plant were
considered, but any final decision was deferred pending more detailed investigations.
Planning proposals for major West Bank wastewater conveyance and treatment facilities were
prepared, which were estimated to cost $655 million through 1995 and $1,550 million
through 2010 (at 1990 price levels). The costs for local sewers and house connections on the
West Bank were estimated at an average of about $50 million per year through the year 2010.
5.3.2.1 Introduction
Since its beginning in 1984, the Cairo Sewerage II Project has resulted in the design and
construction of several significant projects which now comprise the major components of the
West Bank wastewater collection, conveyance, treatment and disposal facilities. These
facilities are shown in Figure 5.9.
Drain and the Muheit Drain under the canal, and discharge ultimately into the Rosetta
branch of the Nile River.
• Contract 31 – The rehabilitation of the existing Zenein WWTP was completed under
this contract, and the facility was placed into service in September 1990.
• Contracts 33A and 33B – These contracts are for the Western Desert Sludge Disposal
Facilities. A sludge pumping station (Contract 33B) pumps sludge from the Abu
Rawash WWTP, through a force main to the Western Desert Lagoon Disposal
Facilities (Contract 33A).
• Contract 35 – This contract, for the construction of a Pilot Mechanical Sludge
Dewatering Facility at the Zenein WWTP.
In addition to the major contracts described above, AID participated in the funding of 43
contracts for the construction of sewers and house connections in the Embaba, Saft El Labban
(Zenein) and Pyramids areas of the West Bank.
In addition, another pumping station was constructed at the GOSD Pump Station No. 1 site.
The flow is pumped to either the Zenein WWTP or the Contract 25 collector, and then to the
Abu Rawash WWTP, thus allowing GOSD the opportunity of selecting which plant the flows
will be sent to, and the proportionate amount sent.
The Zenein WWTP, a full secondary treatment facility, was designed to have an average
capacity of 330,000 m3/day, and a peak capacity of 429,000 m3/day. However, because of
hydraulic constraints in the modules, it has been found that only about 360,000 m3/day can be
carried through the plant without overflowing the conveyance channels. A by-pass facility is
incorporated into the influent structure of the treatment and excess flows are directed to a
Preliminary Treatment Facility, for grit removal, and the flows are then diverted into the
Nahya Drain.
Although not yet produced, GOSD plans to install four pumps, each rated at 1.2 m3/sec, in the
expansion of the GOSD P.S. No. 1. It is intended that two pumps will normally operate,
discharging to the 1500 dia force main to the Pyramids culvert. With three pumps in
operation, this facility would have a peak discharge of about 310,000 m3/day, and the velocity
in the discharge main would be about 2.04 m/sec. Since the proposed pumps only have a
head of 20 meters, the peak pumping capacity may not be reached.
GOSD P.S. No. 6. Four pumps, each rated at 450 liers/sec will be installed at this station.
Assuming one pump as a standby, the remaining three pumps can discharge 116,600 m3/day.
As discussed in a later chapter, this is sufficient capacity to meet projected flows beyond the
planning horizon of the year 2005.
Culverts
The basis of design for the two major culverts which convey wastewater flows to Junction
Pump Station and the Abu Rawash WWTP assumed that, over time, there would be a build-
up of detritus in the culvert, to a depth of 20 cm. This would reduce the flow area available,
and the flow velocity.
Based upon the design criteria used, the maximum flow in each barrel of the culvert from
Boulaq to Abu Rawash would be 443,500 m3/day, or a total of 887,000 m3/day. The
maximum flow in each barrel of the Pyramids to Junction culvert would be 369,000 m3/day,
or a total of 738,000 m3/day.
Major Collectors
The basis of design for the major collectors, (Contracts 20A, 23A and 27) was the same as
that for the culverts, in that a build-up of detritus was assumed to occur to a depth of one-
tenth of the diameter of the pipe. Further, the collectors were sized to carry the projected peak
flows, based upon ultimate (saturation) populations tributary to the collectors.
At the time, wastewater collection services will be available to the residents of Embaba,
Mohandessin, Dokki, Zamalek, Road Island, Saft El Labban, all of the Pyramids Area west of
the Mariouteyah Drain, and Giza City, north of King Faisal Road to south of Pyramids Road,
as well as Monib and Tersa in the south, along with the villages of Ghatati, Kirdasa, Bani
Magdoul and Abu Rawash.
The Helwan area is one of the industrial heartlands of Egypt, where a wide range of products,
from iron and steel to textiles, and from cars to chemicals are manufactured. Up to the
1960’s, Helwan itself was well-known principally as a spa resort. The pace of both industrial
and residential development since that time has been spectacular and has resulted in
increasing demands being made on the existing infrastructures, particularly on the sewers and
sewage treatment facilities. Therefore, the Ministry of Housing, Utilities and Urban
Communities have constructed a great general wastewater drainage project via an
Egyptian/German joint-venture under the leadership of Dorsch Consult, Munich, Germany.
The Helwan Waste Water Project (HWWP) covers the southern part of the Greater Cairo
Area from El-Maadi to about 30 km to the south via Toura, El Maasara, Helwan, El Tebeen to
El Menia and Shoubak as well as the city of 15th May and the planned residential
communities along the Autostrade. All the industries in the area such as the iron and steel
factory, the coke, coal and chemical factory and the cement and textile companies are also
connected to the system.
The first stage of the project has been planned to serve one million inhabitant equivalents with
350,000 m3 of effluent per day, while the second stage is to serve one and half million
inhabitants equivalents with an effluent 550,000 m3 per day.
As the treated sewage was planned to be used for irrigation, and as a suitable irrigation area
was available to the south of the proposed scheme, the main sewer was designed to flow from
north to south. Because the areas adjacent to the Corniche Road near the Nile are almost
level, there was no need for any lifting stations between the proposed sewer networks and the
main sewer. However, three lifting stations were required to overcome the fall over the 28
km length of the main sewer. In order to avoid difficulties in connection with land acquisition
and considering environmental aspects, the treatment plant, previously planned to be located
at the end of the main sewer, was relocated to a desert area further away from the River Nile.
This measure has required an additional pumping station and an additional pressure line.
The treatment plant was designed as a classical mechanical biological treatment plant using
activated sludge. The effluent was planned to be reused for irrigation purposes, serving an
area of 30,000 feddans that equal to 12,600 hectares in the final stage. To accommodate this
purpose, it was decided to construct El Saff irrigation canal to receive the treated effluent via
a balancing reservoir to permit also maintenance works of the canal to be carried out.
• The irrigation pumping station within the site of the treatment plant, the rising main
and the balancing reservoir with the outlet to El Saff irrigation canal.
• All electrical and non-processing ancillaries for O&M of the plant.
The main sewers, collecting all wastewater coming from domestic areas and industrial
complexes was designed as horseshoe or circular cast-in-situ or precast concrete culverts
beginning with internal diameter of 1.60 m at Maadi and ending with diameter of 3.40 m at
the pumping station south of the industrial area near Tebeen. Due to a special proposal,
offering some financial savings, two lengths were carried out by laying circular prefabricated
concrete pipes with concrete footings. The internal diameter of these pipes varied between
3.00 m and 3.40 m. The latter was smaller than the original design due to handling and
transport requirements, but the hydraulic recalculation allowed for the reduction of the section
area by 5%.
The protection of the internal surface of the concrete against air and sewage is PVC lining. It
was fixed to the in-situ constructed pipes by adhesive and to the prefabricated pipes by burls
running parallel to the pipes. The PVC liners were jointed by welding and the whole lining
has been tested for water tightness.
Presented in Table 5.2 is the updated expected hydraulic capacity from the different districts
at the year 2017. As shown in this table, the expected population is 2,274,011 capita while
the expected flow is 998,789 m3/day including industrial wastewater and springs surcharge.
Table 5.2: Expected Hydraulic Capacities from the Different Districts of HWWP in the year 2017
Served Area Sewage Flow (l/c/d) Population (capita) Design Flow (m3/d)
Therefore, it was concluded that there are no upgrades except to release the excess
flows out of the original project to be treated in a new separate treatment plant. The
excess flow involves all the untreated industrial wastewater (that should be pre-
treated) and/or springs surcharges besides domestic sewage.
The upgrade comprises a very effective suggestion based on the availability of in-
hand features that can be used for the upgrade. The suggestions include the following:
1. Releasing the excess flow of the existing pumping station (PS4) from
upstream culverts to a new pumping station (PS4A) in the neighborhood from
which a force main will convey this excess flow over the path of the
embanked El-Khashab canal to another new pumping station (PS3A)
2. Releasing the excess flow of the existing pumping station (PS3) as well as the
excess flow of the existing pumping station (PS2) from upstream culverts of
(PS3) to the new pumping station (PS3A) which will be constructed at a site in
Omar Ibn Abdel-Aziz street
3. Conveying the flow of the new pumping station (PS3A) to another new
pumping station (PS3B) located at a corner on Autostrad faces the south of
15th May city. This station could receive also the excess flow produced from
the city of 15th May.
4. Construction of an emergency bypass of the existing plant at Arab Abu Saed
from the existing pumping station (PS1) by constructing a new pumping
station (PS1A) in the neighborhood that can handle up all the capacity of the
existing plant for conveying to the new pumping station (PS3B)
5. The new pumping station (PS3B) conveys the excess flow as well as
emergency flow, if any, to the east across the east boundary to the desert
where a site will be chosen for the new east treatment plant that will be of
capacity to handle the excess flow of the project area and provided with a
round periphery bypass channel for the emergency flow of the existing
treatment plant.
550,000 m3/day of the existing treatment plant to the new treatment plant at times of
emergency. Accordingly, it is recommended to upgrade the capacity of the new
treatment plant to 1 million m3/day.
The different treatment alternatives that can be reviewed for such new treatment plant:
1. Conventional Activate Sludge Process System
2. UASB (Anaerobic Sludge Bed) Reactor System
3. Oxidation Ponds System
4. Oxidation Ditch System
5. High-Rate Trickling Filter System
6. Chemical Precipitation System
On the other hand, the new plant will be provided with a by-pass channel connected to
the effluent channel of the treated sewage at the outlet of the new plant. The capacity
of this channel will also be 1 million m3/day. Both industrial and springs wastewater
should be pre-treated before reaching the treatment plant to comply with laws
regulating the discharge of wastewater to public sewers. This constrain would not be
considered, if a chemical precipitation system is used.
Connection of new housing areas to the wastewater system: New housing area has been
developed in the South Giza area of the West Bank Project (estimated population about
5,000) although the connection to the sewerage system has not yet been solved. CGOSD has
not given permission to this new housing area to be connected to the sewerage system
because it should be connected to a wastewater pumping station, which do not have sufficient
capacity to pump further the sewage and the force main of which already today caused serious
problems. Similar situations exist in areas in the East Bank and Helwan Projects.
Sewerage Systems
Lack of O&M database: In the sewerage system the biggest operation and maintenance
problems are caused by sand deposition into sewers, poor condition of force mains,
insufficient capacity of some collectors and lack of spare parts. Sand deposition into sewers
is a serious problem, which requires continuous maintenance of sewers. Partly the
maintenance equipment used by CGOSD is inefficient and old-fashioned slowing the
maintenance works and requiring more personnel. In case the sewer collector has at the same
time capacity problems the required cleaning frequency is shorter. As already mentioned in
Giza Square area maintenance of sewers is required almost each night. In order to create
better circumstances for reducing the maintenance problems it is recommended to establish a
database, in which all maintenance works and all deficiencies in the sewerage system will be
recorded. This data can in the future be used for preparation of annual replacement schemes
and longer-term development plans. Furthermore, the database can in the future be connected
to a GIS-system, which is also considered important because as-built maps are not or only few
of them are available. In order to reduce the maintenance works more efficient and modern
equipment is recommended to be purchases. As CGOSD does not have sufficient funds for
the replacement investments it is recommended to use the capital investment funds for
reconstruction of sewerage system.
Lack of spare parts is also considered as a problem. The sewage pumps used are in many
cases manufactured in Western Europe and CGOSD do not have enough fund for purchasing
spare parts to them. Therefore they have stored all the broken pumps and utilize those parts
of the pumps, which still are in operational condition.
Some operational problems have been recognized in major WWTPs in Greater Cairo. These
problems are related to existing equipment, which is considered to represent old technology
and should be replaced with modern equipment simultaneously with the extension works.
Unsuitable sludge pumping facilities at Zenein WWTP: At Zenein WWTP, the most
serious operation problem is caused by the effluent sludge pumping station. The pumping
station is provided with four pumps and the pumps are used two in series to reach the
sufficient head needed. The excess sludge from the WWTP is discharged from the process
together with the primary sludge; however, due to the unsuitable sludge pumps, the primary
sludge has to be diluted to 0.5% TS. Although the sludge is diluted still the seals of the
Study of Wastewater Sector in Greater Cairo Final Report
Chemonics Egypt February 2006
Assessment of Existing Infrastructure in Greater Cairo and Analysis of Bottlenecks 5-26
pumps are leaking causing maintenance problems. Furthermore, the pressure sewers from
Zenein to Abu Rawash (2 DN 500, 14 km) are badly corroded because of unfavourable soil
conditions. CGOSD has reserved LE30 million for replacement of the pipelines. Before the
final decision on the replacement is made, CGOSD will carry out pilot tests at Zenein WWTP
to dewater the sludge at the site. In case of successful test results, final comparison between
rehabilitation of pressure sewers and sludge pumping station and sludge dewatering at the site
will be made.
Energy savings and reduction of operation personnel could be obtained at both WWTPs by
provision of modern equipment, field instruments and automation. In case of Abu Rawash
WWTP these issues have to be taken into account when the WWTP will be extended but in
Zenein the feasibility of these actions should b calculated case by case.
6.1 Introduction
Donors rank Egypt as a lower middle-income country, with annual per capita
income in 2000 of US$ 1500 (€ 1286), according to the current exchange rate.
Since 1982 and up to the year 2001 a total amount of more than US$ 8.8 billion (€
7.5 billion) was invested by the donors group to improve and support the water
and wastewater sector in Egypt (Donor Assistance Group meeting –DAG- in
December 2001). To achieve 100% coverage of water and wastewater services by
2017 would require an additional estimated investment of US$ 19.2 billion (€
16.46 billion), of which US$ 4 billion (€ 3.43 billion) are needed urgently to
maintain current levels of service. The DAG meeting also concludes that donor
support in water and wastewater sector focuses on better and equitable access to
improved facilities, economic management and greater autonomy.
The major donor agencies operating in Egypt (chronologically ordered) are the
following (METAP Study: Wastewater Project for Cairo, by JAAKKO POYRY
INFRA, May 2002):
• African Development Fund
• Canadian International Development Agency (CIDA)
• Danish International Development Agency (DANIDA)
• Dutch International Development Agency (DGIS)
• European Investment Bank (EIB) / EU
• Finish International Development Agency (FINNIDA)
• French Government
• German International Development Agency (KfW and GTZ)
• Islamic Development Bank
• Japanese International Development Agency (JICA)
• Kuwait Fund
• Nordic Investment Bank
• Saudi Arabian Development Fund
• Spanish Government
• United States of America’s International Development
Agency (USAID)
The donors from the EU coordinate regularly their activities through holding bi-
monthly sub-committee meetings to revise and monitor the support to Egypt.
In March 2001, the protocol for the cooperation program in the coming 7 years
was signed between Egypt and DANIDA, focusing on supporting the following:
• National sector reform & capacity development, DKK 15
millions for preparation and DKK 17 millions for phase 1
• Aswan water supply and sanitation, DKK 205 millions,
DANIDA 60%, GOE 31%, and consumers 9%
• Qena water supply and sanitation, DKK 368 millions,
DANIDA grant is 63%, GOE is 29%, and consumers 8%
1
Donor Assistance Group meeting –DAG- December 2001
Study of Sewerage Sector in Greater Cairo Final Report
Chemonics Egypt February 2006
Donors Activities in the Wastewater Sector in Egypt 6-3
The Cairo sewerage project was designed to improve and ensure proper
arrangement of the wastewater collection and treatment systems on Cairo’s West
Bank in addition to operations and maintenance technical assistance. USAID
provided technical and capital technical assistance to the Cairo General
Organization for Sanitary Drainage (CGOSD) (currently: Cairo Wastewater
Company) under four components described below. Installation of sewerage
networks and removal of high groundwater table were implemented in Old Cairo
area. This groundwater problem presented a health hazard and threatened religious
monuments in the area.
All of the major facilities were completed and handed over to the Government of
Egypt (GOE) by the end of FY 1996
The unsewered areas program completed in 1998, funded sewer service and house
connections in low-income west bank neighborhoods. The 62 contracts, totaling
L.E. 338.7 million, funded construction of about 500 km of sewer lines, 25,000
manholes, 74,000 connection chambers, 568 km of service connections and
training of 290 local engineers in sewerage system design and construction
inspection
In 1998, the project was extended to support initiatives that would protect several
ancient, culturally significant religious monuments and improve infrastructure and
services for about 140,000 residents of Old Cairo. This included that construction
of gravity sewer lines and house connections in poor areas of Old Cairo and the
installation of perforated pipes (drain line network) to lower the groundwater table
that threatens the structural integrity of the sites themselves.
The Secondary Cities project was designed to address the need to provide water
and wastewater services to meet growing demand and to enhance the autonomy of
local institutions and ensure the sustainability of existing and new water and
wastewater infrastructure.
National-Level Sector Policy Reform: USAID policy dialogue with the Ministry
of Housing, Utilities, and Urban Communities on the need for a shift in the role of
central government from water and wastewater (W/WW) service provider to a
regulator and facilitator of services led to the development of a draft
concession/regulation law that authorizes creation of a W/WW regulatory agency
and repeals restrictions on private sector participation. Two pre-feasibility studies
for a five-year $8 million management contract for water/wastewater facilities in
Sixth of October/Sheikh Zayed new communities, and a 30-year $60 million
Build-Own-Operate-Transfer (BOOT) agreement to finance new water supply
facilities in Southern Beheira Governorate were completed. Four tariff rate case
studies were initiated and completed by June 2002. A debt restructuring study
was, also, completed. And finally, guidance on tariff reform and private sector
participation, prepared under the program, was disseminated to local utilities
through a second, year-long Development Training 2 (DT2)-funded national
training program, which began in April 2002.
Middle Egypt Utilities: USAID assisted the Economic General Authorities for
Water Supply and Sanitary Drainage in Fayoum, Beni Suef and Minya to
complete the transition from subsidized service providers to autonomous public
enterprise capable of meeting customer needs. The program combined
institutional development with master planning, a large-scale construction
Study of Sewerage Sector in Greater Cairo Final Report
Chemonics Egypt February 2006
Donors Activities in the Wastewater Sector in Egypt 6-7
Alexandria Water General Authority: While USAID has invested over $600
million in Alexandria to construct two new wastewater treatment plants and
expand sewage collection networks throughout the city; the current program is the
first USAID assistance program for the Alexandria utility responsible for water
supply services. The current program also combines institutional strengthening
activities with master planning and construction. Investments are concentrated on
network expansions and system improvements in existing treatment plants.
The recommendation in this report was prepared by Chemonics Egypt and does not
represent any opinion and decision of JBIC and the Egyptian government authorities.
The following recommendations are made for JBIC on the possibility of cooperation
to develop and upgrade the sewerage sector in Egypt, with particular emphasis on
Greater Cairo.
• Fund the governorates in Egypt for conversion of the water and wastewater
authorities into water and wastewater companies and integrate them with
the Holding company of Water and Wastewater (HCWW).
• Provide financial assistance to the HCWW to improve their facilities to
manage the wastewater sector and support its programs for the
development and operation of the wastewater projects nationwide.
• Fund the sanitation projects of the unserved and deprived area of the
regionalized city and village sanitation as well as rural village sanitation.
• Participate in the P3 (public private participation) program and the BOT
(Build, operate, and transfer) program in association with international
water companies.
Project Title: Ameriya Pumping Station, Second Stage Main Conveyance System, East
Bank Wastewater Project.
Description:
Cost Estimate:
Justification:
Priority Rank: 1
Project Title: Third Stage of Expansion of Gabal El-Asfar Wastewater Treatment Plant,
East Bank Wastewater Project.
Description:
Components: Inlet pumping station, distribution chambers, screens, grit removal tanks,
primary sedimentation tanks, aeration tanks, secondary sedimentation tanks,
emergency bypass, chlorine tanks, sludge thickening tanks, anaerobic sludge
digestion tanks, mechanical dewatering units, dual fuel system, digester gas
holders, and service buildings.
Cost Estimate:
Justification:
Priority Rank: 2
Project Title: Second Stage of Expansion of Abu Rawash Wastewater Treatment Plant,
West Bank Wastewater Project.
Location: Abu Rawash, North West of Greater Cairo at the 24th km East of
Cairo/Alexandria Desert Road.
Description:
Components: Pumping station, emergency by-pass channel, screens, grit removal tanks,
primary sedimentation tanks, chlorination tanks, sludge thickeners, sludge
lagoons.
Cost Estimate:
Justification:
Priority Rank: 3
Description:
Population served: 2 million persons
Additional capacity provided: 200,000 m3/d
Plant area allocated for expansion will be in the desert
Construction of facilities for primary and secondary treatment
Construction of facilities for sludge treatment
Components: Inlet pumping station, distribution chambers, screens, grit removal tanks,
primary sedimentation tanks, aeration tanks, secondary sedimentation tanks,
emergency bypass, chlorine tanks, sludge drying beds, irrigation pumping
station
Cost Estimate:
Justification:
Priority Rank: 4
Additional Projects
Description:
1. Population served: 2 million persons
2. Additional capacity provided: 338,000 m3/d of
primary treatment and 800,000 m3/d of secondary
treatment
3. Area allocated for expansion: 46 feddan (190,000
m2 )
4. Construction of additional primary and secondary
treatment facilities for wastewater
5. Construction of additional facilities for sludge
treatment and drying
Components: Pumping station, screens, grit removal tanks, primary sedimentation tanks,
aeration tanks, secondary sedimentation tanks, chlorination tanks, and sludge
pumping.
Cost Estimate:
Justification:
Priority Rank: 1
Description:
1. Population Served: 2 million persons
2. Additional capacity provided: 193,000 m3/d
(primary treatment) and 800,000 m3/d secondary
treatment
3. Area allocated for expansion: 23 feddan (95,000 m2)
4. Construction of additional primary and secondary
treatment facilities for wastewater
Components: Pumping station, screens, grit removal tanks, primary sedimentation tanks,
aeration tanks, secondary sedimentation tanks, chlorination tanks and sludge
pumping
Cost Estimate:
Justification:
Priority Rank: 2
Cost Estimates
Rank Project Location Justification Total Cost Required
Foreign Funding
1 Ameria Pumping Station, El Ameria, North To increase the capacity of the pumping
Second Stage Main East of Greater station from 1.7 Mm3/d to 2.18 Mm3/d as to
Conveyance System, East Cairo deliver the required capacity to the Gabl El- Euro 38 M Euro 28 M
Bank Wastewater Project Asfar WWTP after expansion, in order to
cope with the population increase.
2 Third Stage Expansion of Gabl El-Asfar To increase the capacity of Gabal El-Asfar LE 1200 M Euro 100 M
Gabal El-Asfar Wastewater North East of WWTP by 0.5 Mm3/d to match the
Treatment Plant – East Bank Greater Cairo, population needs, cope with environmental
Wastewater Project Khanka Markaz laws, and protect the public health and
environment. This includes facilities for
secondary biological treatment of
wastewater and for sludge treatment.
3 Second Stage Expansion of Abu Rawash, North To increase the capacity of Abu Rawash LE 700 M Euro 50 M
Abu Rawash Wastewater West of Greater WWTP by 0.8 Mm3/d to match the
Treatment Plant – West Bank Cairo, 20 km East population needs. This includes facilities
Wastewater Project of Cairo/Alexandria for primary treatment of wastewater and for
Desert Road sludge disposal.
4 Expansion of Helwan Helwan, South East To increase the capacity of Helwan WWTP
Wastewater Treatment Plant, of Greater Cairo by 0.41 Mm3/d to match the population
Updating of Master Plan, needs, cope with environmental laws and
Helwan Project protect the public health and environment.
LE 580 M Euro 50 M
This includes transfer to a new desert
location and construction of facilities for
secondary biological treatment and for
sludge treatment.
Cost Estimates
Rank Project Location Justification Total Cost Required
Foreign Funding
1 Expansion of the Eastern Abees, To construct additional primary facilities of
Wastewater Treatment Plant in Alexandria capacity 0.6 Mm3/d and secondary facilities
Alexandria Governorate of 0.8 Mm3/d. This is required to match the
LE 1200 M Euro 90 M
population needs, cope with environmental
laws, and protect the public health and
environment.
2 Expansion of the Western Karmooz, To construct additional primary treatment LE 1400 M Euro 100 M
Wastewater Treatment Plant in Alexandria facilities of capacity 0.338 Mm3/d and
Alexandria Governorate secondary treatment facilities of 0.8 Mm3/d.
This is required to match the population
needs, cope with environmental laws, and
protect the public health and environment.