0% found this document useful (0 votes)
39 views3 pages

End PM 10-02-2021

The document is an end semester exam for a project management course. It contains 4 questions assessing key project management concepts. Question 1 involves creating an activity on node network diagram and calculating project duration, start/finish times, and slack. Question 2 analyzes resource loading and constraints. Question 3 calculates monthly budgets and draws a project S-curve. Question 4 involves completing a table with budget and schedule data and calculating earned value, schedule and cost variances. The exam tests concepts like scheduling, resource management, budgeting and earned value analysis over 40 marks in 2 hours and 45 minutes.

Uploaded by

Aleena Nasir
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
39 views3 pages

End PM 10-02-2021

The document is an end semester exam for a project management course. It contains 4 questions assessing key project management concepts. Question 1 involves creating an activity on node network diagram and calculating project duration, start/finish times, and slack. Question 2 analyzes resource loading and constraints. Question 3 calculates monthly budgets and draws a project S-curve. Question 4 involves completing a table with budget and schedule data and calculating earned value, schedule and cost variances. The exam tests concepts like scheduling, resource management, budgeting and earned value analysis over 40 marks in 2 hours and 45 minutes.

Uploaded by

Aleena Nasir
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

End Semester Exam (Fall 2020) 10-FEB-2021 2017-Computer (7th Semester)

Project Management
Max Marks: 40 Time Allowed (02 HRS : 45 MINS)

Sr. # Questions Marks CLO


1. Apply the following given information and create an AON network activity diagram. 7
Calculate each activity TE (rounding to the nearest integer); the project's total duration;
its early start, early finish, late start, and late finish times; and the slack for each activity.
Finally, show the project’s critical path.

3
10

2. Consider the partial resource-loading chart shown below. Suppose that you can commit
a maximum of 8 resource hours per day;
a. Choose the dates on which project resources are overallocated? 2
b. How should the resource-loading table be manipulated to correct for this 3
overallocation?
c. Now suppose that the maximum number of resource hours per day you can commit
is reduced to six. How would you reconfigure and construct the resource-loading 5
table to adjust for this number? What would be the new project completion date?

10

Department of Computer Engineering


End Semester Exam (Fall 2020) 10-FEB-2021 2017-Computer (7th Semester)
Project Management
Max Marks: 40 Time Allowed (02 HRS : 45 MINS)

Assume the following information. (Figures are in thousands.)


3.
Budgeted Costs for Sample Project
Duration (in weeks)
5 10 15 20 25 30 35 40 45 Total
Design 6 2 1
Engineer 5 10 12 6
Install 7 15 30 8 5 4
Test 1 5 8 5 2
Total Monthly Cumul.

a. Calculate the monthly budget and the monthly cumulative budgets for the project. 2.5

b. Draw a project S-curve identifying the relationship between the project’s budget 2.5
baseline and its schedule.
4. Make use of the data in the table below and complete the table by calculating The
cumulative planned and cumulative actual monthly budgets through the end of June. 5
Complete the earned value column on the right. Assume that the project is planned for
a 12-month duration and a $250,000 budget.

4
15

Department of Computer Engineering


End Semester Exam (Fall 2020) 10-FEB-2021 2017-Computer (7th Semester)
Project Management
Max Marks: 40 Time Allowed (02 HRS : 45 MINS)

After calculating all the missing information as asked in the above table, calculate the
following as well;

1. Schedule variances
Planned value (PV)
Earned Value (EV) 5
Schedule Performance Index (SPI)
Estimated Time to Completion
2. Cost Variances
Actual Cost of Work Performed (AC)
Earned Value (EV) 5
Cost Performance Index (CPI)
Estimated Cost of Completion

Grading Criteria
Q’s
1 Create AON and calculate all the relevant fields in each node 07
Find the critical path length 03
2 the dates on which project resources are overallocated? 02
correct for this overallocation in the resource loading table 03
Reconfigure the table with the constraint on 6 resources max per day 05
3 Calculate monthly budget and monthly cumulative budget 2.5
Draw a project S-curve identifying the relationship between the project’s 2.5
budget baseline and its schedule.
4 Complete the missing values in the given table 05
Calculate Schedule variances 05
Calculate cost variances 05

Checked and verified by Member


Subject Team

Department of Computer Engineering

You might also like