Document 5

The document is a checklist for testing a process gas compressor. It contains 28 steps to commission the compressor, including reassembling parts, checking systems, starting the compressor, monitoring pressures and temperatures, delivering gas to the client line, and final safety and documentation tasks.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
26 views2 pages

Document 5

The document is a checklist for testing a process gas compressor. It contains 28 steps to commission the compressor, including reassembling parts, checking systems, starting the compressor, monitoring pressures and temperatures, delivering gas to the client line, and final safety and documentation tasks.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

SIAD Macchine Impianti S.p.A.

Società unipersonale soggetta all’attività di


direzione e coordinamento di SIAD S.p.A.
24126 Bergamo, Italy - Via Canovine, 2/4
Tel. +39 035 327611 - Fax +39 035 316131
www.siadmi.com - [email protected]
Capitale Sociale - Share Capital € 25.000.000 i.v. - paid up
P. IVA, C. F., Reg. Impr. Bg - VAT and Fiscal Nr.: (IT) 00228420162
R.E.A. BG-72619 - Export: BG 006107

K33033/10A Project: :
M5 - PROC - PROCESS GAS Compiled 14/12/2021 by Paglialunga

Description Ok Note
1 - REASSEMBLE THE FRONT WINDOW
ON THE DISTANCE PIECE AFTER
PROPER CLEANING
2 - CHECK LUBE OIL SYSTEM - LUBE OIL
LEVEL AND RUN MANUAL OIL PUMP IF
ANY
3 - CHECK THAT THE WATER PUMP IS
RUNNING AND THAT THE WATER IS
CIRCULATING CORRECTLY
4 - CHECK THAT SUCTION GAS VALVE
IS CLOSED
5 - CHECK THAT COMPRESSOR VALVE
DELIVERY VALVE TO THE CLIENT IS
CLOSED
6 - CHECK RECYCLE VALVE IS FULLY
OPEN AND IN MANUAL OR THAT THE
UNLOADERS ARE IN UNLOAD POSITION
7 - CHECK THAT THE VENT VALVE IS
CLOSED AND IN AUTOMATIC
8 - REMOVE THE BY-PASS ON THE LOW
SUCTION PRESSURE ALARM IF BY-
PASSED DURING PREVIOUS TEST
9 - CHECK PERSONNEL ARE NOT
WORKING ON OR AROUND THE
COMPRESSOR
10 - ISOLATE THE NITROGEN SUPPLY
LINE
11 - OPEN SLOWLY THE SUCTION
VALVE AND PRESSURIZE THE
COMPRESSOR AT THE DESIGN
SUCTION VALUE
12 - CHECK FOR LEAKAGE ALL AROUND
THE COMPRESSOR AND PIPING. IF
NECESSARY CORRECT LEAKAGE.
13 - START THE COMPRESSOR WITH
BY-PASS FULLY OPEN. VERIFY THE OIL
PRESSURE REACH THE DESIGN VALUE.
14 - ENSURE THERE ARE NO
ABNORMAL NOISES COMING FROM
THE COMPRESSOR
15 - RUN THE COMPRESSOR WITH BY-
PASS FULLY OPEN AND KEEP
PRESSURES AND TEMPERATURES
SURVEIED
16 - CHECK FOR LEAKAGE ON GAS AND
WATER PIPING. IF NECESSARY TIGHT
FLANGES AND CONNECTIONS.
17 - CLOSE MANUALLY AND
GRADUALLY THE BY-PASS VALVE TILL
THE DESIGN DELIVERY PRESSURE IS
REACHED
1/2
SIAD Macchine Impianti S.p.A.
Società unipersonale soggetta all’attività di
direzione e coordinamento di SIAD S.p.A.
24126 Bergamo, Italy - Via Canovine, 2/4
Tel. +39 035 327611 - Fax +39 035 316131
www.siadmi.com - [email protected]
Capitale Sociale - Share Capital € 25.000.000 i.v. - paid up
P. IVA, C. F., Reg. Impr. Bg - VAT and Fiscal Nr.: (IT) 00228420162
R.E.A. BG-72619 - Export: BG 006107

18 - CHECK TEMPERATURES OF THE


RODS AND PRESENCE OF OIL LEAK
TROUGH THE OIL SCRAPER RINGS.
19 - AGREED WITH THE CLIENT ABOUT
PROCEDURE IN ORDER TO START TO
DELIVER PROCESS GAS TO THE LINE
20 - START TO DELIVER GAS TO THE
CLIENT OPENING GRADUALLY THE
DELIVERY VALVE. A PREVIOUS PERIOD
OF VENT COULD BE NECESSARY TO
VENT THE NITROGEN - PROCESS GAS
MIX AND THEN DELIVER TO THE
CLIENT ONLY PURE PROCESS GAS.
KEEP PRESSURES AND
TEMPERATURES SURVEYED FOR 4
HOURS.
21 - ADJUST INTERCOOLER AND
AFTERCOOLER WATER OUTLET VALVES
TO REACH THE DESIGN WATER AND
GAS TEMPERATURE
22 - CHECK AGAIN FOR LEAKAGE ON
THE PIPING DURING ALL THE RUN AT
DESIGN PRESSURE. IF ANY CORRECT IT.
23 - RECORD ON THE A9 PRESSURES,
TEMPERATURES AND ALL THE
AVAILABLE DATA
24 - STOP THE COMPRESSOR
25 - MAKE THE COMPRESSOR SAFE.
ISOLATE ALL THE PROCESS GAS
CONNECTIONS AND OPEN AGAIN THE
NITROGEN SUPPLY LINE.
26 - CORRECT ANY DEFECTS FOUND
DURING TEST
27 - CUT OFF POWER AND RECECK
BELT TENSIONING
28 - CHECK CONDITION OF WATER
FILTER AND IF NECESSARY CLEAN IT. IF
WATER IS VERY DIRTY INFORM THE
CLIENT THAT WATER QUALITY IS NOT
GOOD. PURIFICATION SYSTEM MUST
BE INSTALLED.

2/2