1. The document provides a check list for installing an IP clock system, outlining key steps to ensure proper installation. 2. It includes checking shop drawings, layouts, and material submittals. Installing the IP clocks as per manufacturer recommendations and approved drawings. 3. Safety precautions like adequate lighting, barricades, and ensuring personnel have proper training are also outlined.

Uploaded by

Ammar Hadi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
161 views1 page

4266 - Checklist For Installation of IP Clock System

1. The document provides a check list for installing an IP clock system, outlining key steps to ensure proper installation. 2. It includes checking shop drawings, layouts, and material submittals. Installing the IP clocks as per manufacturer recommendations and approved drawings. 3. Safety precautions like adequate lighting, barricades, and ensuring personnel have proper training are also outlined.

Uploaded by

Ammar Hadi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

ADVANCED SYSTEMS LTD. CO.

CHECK LIST FOR


IP CLOCK SYSTEM INSTALLATION
Doc No: ASL/ELV/CL/4266/22 DATE: 04-APR-2022 REV: 01 ISSUE: 01

Check Approved Shop drawings/Layouts.


SETTING
OUT Check Level as per approved Coordination drawings.
Check that material as per approved material submittal.
MEP/CIVIL Check for civil clearance
1. Check the location of the Clock as per approved shop
drawings.
2. Check the Installation of the IP clock as per
Manufacturer recommendation and Approved shop
IP CLOCK System Installation

drawings.
3. Check that all cable & wires sizes and type as per
approved wiring diagram & approved schematic
drawing
4. Check that there are no damages for the Installed
Clock and its accessories.
5. Check that the IP clock panel installed as per
approved shop drawings.
6. Check that Identification inside the panels done as per
approved schematic diagram and specifications.
7. Check that no damages for the installed panels and its
accessories.
8. Check that no clashes between other services.
1. Adequate lights are provided in the Work Area prior to
installation.
2. All terminations cables have been checked for any
SAFETY PRECAUTIONS

damage or improper connections.


3. Ensure that barricade & warning boards on the area
are available prior to installation.

4. Ensure all supports have been properly installed.

5. Ensure no obstacles in the area. Maintain proper


housekeeping.
6. Ensure all personnel performing the installation shall
have proper training & experience.
7. Ensure all electrical tools to be used in the installation
are not damage.