Lecture 11 Electrification of Commercial Installation
Lecture 11 Electrification of Commercial Installation
1
LECTURE 11: ELECTRIFICATION OF COMMERCIAL INSTALLATION
Fundamental considerations for planning of an electrical installation system for commercial
building
Reception and Distribution of Main Supply
• There is always a circuit breaker or a linked switch with fuse on each live conductor of the
supply mains at the point of entry. The main switch is normally easily accessible and shall
be situated near to the termination of service line.
• Branch distribution board is always provided with a fuse or a miniature circuit breaker
(MCB) or both of adequate rating / setting.
• Light and fans may be wired on a common circuit. Such sub-circuit shall not have more
than a total of 10 points of light, fan and 5 A socket outlets. The load of such circuit shall be
restricted to 800 Watts. Power sub-circuit shall be designed according to the load but in no
case shall there be more than two 15 A outlets on each sub-circuit.
• The load on any low voltage sub circuit shall not exceed 3000 Watts. In case of new
installation, all circuits and sub-circuits shall be designed by making a provision of 20%
increase in load due to any future modification.
• The distribution fuse board shall be located as near as possible to the centre of the load.
These shall be fixed in suitable stanchion or wall and shall not be more than 2 m from the
floor level.
• All conductors have to be of copper or aluminium. Conductor for final sub-circuit of fan
and light wiring have a nominal cross sectional area not less than 1 Sq. mm copper and 1.5
Sq. mm aluminium. The cross sectional area for power wiring is not less than 2.5 Sq. mm
copper, 4 Sq. mm aluminium. The minimum cross sectional area of conductors of flexible
cord shall be 0.5 Sq. mm copper.
2
Design considerations of electrical installation system for commercial building
i. Load calculation and selection of size of service connection and nature of supply,
ii. Deciding the size of the cables, busbar and bus bar chambers
iii. Next step is finding Bus bar size.
Bus bar materials are:
• Aluminum or Aluminium alloy – working current density, 0.8 A/ Sq.mm
• Copper – working current density, 1.2 A/ Sq.mm
3
Mounting arrangements and positioning of switchboards,
distribution boards main switch
Switch boards in general are power distribution centers with SFUs/MCCBs/ACBs/OCBs for
controlling outlets and incomer. Unlike DBs, switch boards are specified by its total current
carrying capacity or incomer current rating. Where as in DBs current rating of the outlet is
the specified rating. Standard switch board ratings are 100 A, 200 A, 400 A, 800 A, 1200 A,
1600 A, 2000 A, 2500 A and 3200 A. If the incomer supply is controlled with an SFU, the
switch board is called switch fuse controlled board and if the incomer is ACB/ OCB
controlled, it is called breaker controlled board.
A switch board having three sections
• Outlet control gears
• Bus chamber
• Incomer control gear
The outlet switch, fuse and cable rating are decided by the load that has to be handled
through that feeder. If the number of loads is more, SSB is required, which is installed almost
at the load centers. In smaller set up SSB may not be necessary and MSB will be the only
switch board.
4
Earthing of the electrical installation
Design data on earth electrode
Standard earth electrodes are;
(a) Rod and pipe electrodes,
(b) Strip or conductor electrodes,
(c) Plate electrodes, and
(d) Cable sheaths
If motor loads are connected, for selection of isolator / SFU, the starting current has to be
taken in to account rather than continuous current. Eg:- 5 hp - 5Nos and 10 hp - 2Nos
motors are connected to a DB
Total connected load = 45hp MD = 1.545 =30 hp
Corresponding maximum current is 30 x 1.4 = 42 A. This current is the continuous maximum
current
When motors are started we have to account the starting inrush current of large motor in the
down stream. Starting current of DOL starting motor is 2.5 times the rated current and for
assisted starting (star delta), it is 1.5 times the rated current.
So the MD calculation in the above case is as follows:
• One 10 hp (one higher rating) kept aside
5
• Now only MD of 20 hp is existing
• Its maximum current = 20 x 1.4 = 28 A
• For one 10 hp alone, maximum current = 2.5 x (10 x 1.4) = 35 A
• Therefore MD of the DB = 28 + 35 = 63 A ie, incoming feeder, isolator/SFU of the DB
can be rated to 63 A
6
7