University Question Bank For PSP - Unit 03

This document contains 28 questions from a university question bank for a 6th semester electrical engineering course on hydro power stations. The questions cover a range of topics related to hydro power including: calculating available power given catchment area and rainfall data; explaining the working and utility of pumped storage hydroelectric plants; classifying different types of hydroelectric plants; reducing water hammer in hydro plants; defining and explaining hydrographs, mass curves, and flow duration curves; explaining components of hydro plants like surge tanks and spillways; calculating average power generation given effective head, catchment area, rainfall, and plant efficiency; explaining problems in hydro power development; and comparing turbines types like Francis, Kaplan, and Pelton and their applications.

Uploaded by

ptarwatkar123
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
167 views

University Question Bank For PSP - Unit 03

This document contains 28 questions from a university question bank for a 6th semester electrical engineering course on hydro power stations. The questions cover a range of topics related to hydro power including: calculating available power given catchment area and rainfall data; explaining the working and utility of pumped storage hydroelectric plants; classifying different types of hydroelectric plants; reducing water hammer in hydro plants; defining and explaining hydrographs, mass curves, and flow duration curves; explaining components of hydro plants like surge tanks and spillways; calculating average power generation given effective head, catchment area, rainfall, and plant efficiency; explaining problems in hydro power development; and comparing turbines types like Francis, Kaplan, and Pelton and their applications.

Uploaded by

ptarwatkar123
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

University Question Bank for Power Station Practice - 6th Sem EE

Unit - 03 Hydro Power Stations

Sr.
Question Statement Marks
No.
1 A hydroelectric power station has a catchment area of 500 sq.km. The average annual 7
rainfall in the area is 125 cm. The average available head in the reservoir is 300m.
Assuming plant efficiency as 85 %, and average run off is 70 %. Calculate the
available power.
2 Explain the working of pumped storage hydroelectric plant with the help of neat 6
diagram. Explain its utility.
3 Explain three different ways of classification of hydroelectric plants. 6
4 What is water hammer? How is it reduced in hydro power plants? 7
5 Define & Explain the importance of: - i) Hydrograph. ii) Mass curve. iii) Flow 7
duration curve.
6 Explain three different ways of classification of hydroelectric plants. 7
7 A proposed hydro power plant with an effective head of 125 m has a catchment area 7
of 600 Sq. Km, in which average rainfall is 150 cm per annum. only 65% of water is
available for power generation. Determine the average power that can be generated
throughout the year if the efficiency of turbine–generator is 75%.
8 Discuss turbines in power plants. 7
9 Define hydrology, flow duration curve and mass curve. Explain their uses with 6
respect to hydro power plant.
10 A hydro power station has a catchment area of 500 square km. The average annual 7
rainfall in the area is 125 cm. The average available head in the reservoir is 300
meters. Assuming plant efficiency of 85 % and an average run-off of 70 %, Calculate
the available power.
11 Explain the working of pumped storage hydroelectric plant with the help of neat 6
diagram. Explain its utility.
12 Explain the following components of hydro electric power plant. 7
i) Surge tank. ii) Spillway. iii) Tail Race
13 Define Hydrology, flow duration curve and mass curve with their uses. 6
14 A proposed hydro power plant with an effective head of 125 m has a catchment area 7
of 600 sq. K, in which average rainfall is 150 cm per year. Only 65 % of water is
available for power generation. Determine the average power that can be generated
throughout the year if the efficiency of turbine generator is 75 %.
15 Explain the working of Hydro power plant with the help of neat diagram. Explain its 7
utility.
16 Explain in details, the problems in hydro power development. 6
17 Explain the working of pumped storage hydroelectric plant with the help of neat 7
diagram. Explain its utility.
18 A proposed hydro station has a catchment area of 500 sq.km. With average rainfall of 6
200 cm. per year. Effective head of water on turbine is 120 cm. If the overall
efficiency of turbine and generator is 50 %, determine the electrical power that could
be generated from the project. Assume 70 % of the collected water is available to
power generation.
19 Discuss the difference between Kaplan, Francis and Pelton turbines and state the 6
types of power plant they are suitable for.
20 A hydro-electric station is supplied from a reservoir at ahead of 40 m. If the area of 7
the reservoir is 1.8 km2 and generating 24 MW power. Determine the rate at which the
level will fall in the reservoir. Take overall efficiency as 80 %
21 Explain three different ways of classification of hydroelectric power plants. 7
22 Define and explain the following terms referred to hydro power plants. 7
i) Run off ii) Hydrograph iii) Flow duration curve.
23 Plot hydro-graph & find the average inflow & the power that can be developed at an 6
effective head of 150m and a turbine–generator efficiency of 0.85. Find storage
capacity of reservoir based on data given & neglect losses.
The average rates of inflow during 12 months for a river are -
Jan 1000 Cu-m/Sec July 2400 Cu-m/sec
Feb 800 Cu-m/sec Aug 2400 Cu-m/sec
March 600 Cu-m/sec Sept. 1000 Cu-m/sec
April 400 Cu-m/sec Oct. 400 Cu-m/sec
May 400 Cu-m/sec Nov. 400 Cu-m/sec
June 1200 Cu-m/sec Dec. 1000 Cu-m/sec
24 Write short note on. i) Surge tank. ii) Spillway. 8
25 Give the classification of hydro power plant in details. 7
26 Explain construction and operation of different components of hydro power plants. 7
27 A proposed hydro plant with an effective head of 125 m has a catchment area of 600 7
sq. Km in which average rainfall is 150 cm per annum. only 65 % of water is available
for power generation. Determine the average power that can be generated throughout
the year if the efficiency of turbine. generator is 75 %
28 Compare Francis turbine, Kaplan turbine and Pelton turbine. Also state the 7
application of each of them.