This document provides instructions for a project management tutorial session. It includes 3 questions to help students practice drawing project networks, computing early and late dates, and determining the critical path. Students are asked to draw a network for a garage building project and determine if they would receive a bonus or penalty based on the project completion date.

Uploaded by

GarethNg
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
95 views2 pages

Tutorial 3 F2F PDF PDF

This document provides instructions for a project management tutorial session. It includes 3 questions to help students practice drawing project networks, computing early and late dates, and determining the critical path. Students are asked to draw a network for a garage building project and determine if they would receive a bonus or penalty based on the project completion date.

Uploaded by

GarethNg
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

COURSE CODE WIX2002

COURSE NAME PROJECT MANAGEMENT


SEMESTER 1
SESSION 2022/2023
LECTURER Dr. Hema Subramaniam
Dr. Mohd Hairul Nizam Md. Nasir
TUTORIAL 3
TENTATIVE Week 5 – Tutorial Session (1 Hour)

TUTORIAL INSTRUCTIONS

1. Draw a project network from the following information. Which activity is a burst activity?
Which activity is a merge activity? (Lecture Notes 4 and 5)

ID Description Predecessor Time (days)


A Identify Topic None 1
B Research Topic A 5
C Draft paper B 3
D Edit paper C 2
E Create Graphics C 1
F References C 1
G Final Draft D, E, F 1

2. Given the following information, draw the project network. Compute the early, late, and
slack times for each activity. (Lecture Notes 4 and 5)

ID Duration Finish-to- Finish-to- Additional Lag Relationships Lag


(Day) Start Start Lag
Predecessor
A 5 None 0 None 0
B 10 A 0 None 0
C 15 A 0 Start-to-Finish C to D 20
D 5 B 5 Start-to-Start D to E 5
Finish-to-Finish D to E 25
E 20 B 0 Finish-to-Finish E to F 0
F 15 D 0 None 0
G 10 C 10 Finish-to-Finish G to F 10
H 20 F 0 None 0

3. Explain the relationship between WBS and project networks linked. (Lecture Notes
4 and 5)

This study source was downloaded by 100000856648151 from CourseHero.com on 11-16-2022 02:34:11 GMT -06:00

https://www.coursehero.com/file/178215674/3-TUTORIAL-3-F2F-PDFpdf/
4. You have signed a contract to build a garage for UM. You will receive a RM500 bonus
for completing the project within 15 working days. The contract also contains a penalty
clause in which you will lose RM100 for each day the project takes longer than 15
working days.
Draw a project network given the information below. Complete the forward and
backward pass, compute the activity slack, and identify the critical path. Do you expect
to receive a bonus or a penalty on this project? (Lecture Notes 4 and 5)

ID Description Predecessor Time


(days)
A Pour foundation None 3
B Erect frame A 4
C Roof B 4
D Windows B 1
E Doors B 1
F Electrical B 3
G Rough-in-frame C, D, E, F 2
H Door opener E,F 1
I Paint G, H 2
J Cleanup I 1

-END OF INSTRUCTION-

This study source was downloaded by 100000856648151 from CourseHero.com on 11-16-2022 02:34:11 GMT -06:00

https://www.coursehero.com/file/178215674/3-TUTORIAL-3-F2F-PDFpdf/
Powered by TCPDF (www.tcpdf.org)

You might also like