Contract Management Practices and Completion of Road
Contract Management Practices and Completion of Road
D53/NKU/PT/33337/2014
JULY, 2017
DECLARATION
This research project is my original work and has not been submitted for a degree
Gloria Mulinge
D53/NKU/PT/33337/2014
This research project has been submitted for examination with my approval as the
university supervisor.
ii
DEDICATION
I dedicate this research project to my family for their moral and financial support
iii
ACKNOWLEDGEMENT
I would like to acknowledge the efforts of my supervisor for the support and guidance
while writing this research project. My appreciation goes to my college colleagues
who also offered me encouragement and support during my studies. I give thanks To
God Almighty for His mercy and good health and the spirit for enabling me write this
project.
iv
TABLE OF CONTENTS
DECLARATION................................................................................................................. ii
DEDICATION.................................................................................................................... iii
ACKNOWLEDGEMENT ................................................................................................. iv
LIST OF TABLES ............................................................................................................ vii
LIST OF FIGURES ......................................................................................................... viii
ABBREVIATIONS AND ACRONYMS .......................................................................... ix
OPERATIONAL DEFINITION OF TERMS .................................................................. x
ABSTRACT ........................................................................................................................ xi
CHAPTER ONE ................................................................................................................. 1
INTRODUCTION............................................................................................................... 1
1.1 Background of the Study ........................................................................................ 1
1.2 Statement of the Problem ..................................................................................... 10
1.3 Research Objectives ............................................................................................. 11
1.4 Significance of the Study ..................................................................................... 12
1.5 Scope of the Study................................................................................................ 13
1.6 Limitations of the Study ....................................................................................... 13
CHAPTER TWO .............................................................................................................. 15
LITERATURE REVIEW ................................................................................................ 15
2.1 Introduction .......................................................................................................... 15
2.2 Theoretical Review .............................................................................................. 15
2.3 Empirical Literature ............................................................................................. 19
2.4 Summary of Literature Review and Gaps ............................................................ 29
2.5 Conceptual Framework ........................................................................................ 31
CHAPTER THREE .......................................................................................................... 32
RESEARCH METHODOGY .......................................................................................... 32
3.1 Introduction .......................................................................................................... 32
3.2 Research Design ................................................................................................... 32
3.3 Target Population ................................................................................................. 33
3.4 Sampling Techniques and Sample size ................................................................ 33
3.5 Data Collection Procedure ................................................................................... 35
3.6 Validity of Instruments......................................................................................... 36
3.7 Reliability of Instruments ..................................................................................... 36
3.8 Data Analysis Procedure and Presentation........................................................... 36
3.9 Ethical Considerations.......................................................................................... 38
CHAPTER FOUR ............................................................................................................. 41
RESEARCH FINDINGS AND ANALYSIS ................................................................... 41
4.1 Introduction .......................................................................................................... 41
4.2 Response Rate ...................................................................................................... 41
v
4.3 Respondent’s Characteristics ............................................................................... 42
4.4 Contractor Management Practices ....................................................................... 44
4.5 Contractor Prequalification .................................................................................. 49
4.6 Contractor Payment Methods ............................................................................... 52
4.7 Contract Change Management Practices.............................................................. 58
4.8 Road Projects Completion .................................................................................... 67
4.9 Regression Model ................................................................................................. 70
CHAPTER FIVE .............................................................................................................. 73
SUMMARY, CONCLUSIONS AND RECOMMEDATIONS ..................................... 73
5.1 Introduction .......................................................................................................... 73
5.2 Summary .............................................................................................................. 73
5.3 Conclusions .......................................................................................................... 75
5.4 Recommendations ................................................................................................ 76
5.5 Recommendations for Further Studies ................................................................. 77
REFERENCES .................................................................................................................. 78
APPENDIX ONE; INTRODUCTORY LETTER ......................................................... 71
APPENDIX TWO; QUESTIONNAIRE ......................................................................... 72
APPENDIX THREE; NACOSTI AUTHORIZATION LETTER ............................... 78
vi
LIST OF TABLES
Table 3.1:Sampling Frame ............................................................................................... 35
Table 3.2; Operational Definition of Variables ............................................................... 38
Table 4.1: Contract Management .................................................................................... 49
Table 4.2: Contractor Prequalification ............................................................................. 52
Table 4.3: Factors Affecting Payment to Contractors...................................................... 56
Table 4.4: Contractor Behaviour over Non-payment...................................................... 58
Table 4.5: Contract Change Management Practices ........................................................ 61
Table 4.6: Contract Change on Road Projects ................................................................. 64
Table 4.7: Supervision of contracts.................................................................................. 67
Table 4.8: Road Performance Metrics ............................................................................. 69
Table 4.9: Model Summary ............................................................................................. 70
Table 4.10: ANOVA ........................................................................................................ 70
Table 4.11: Linear Relationship Coefficients .................................................................. 72
vii
LIST OF FIGURES
Figure 2.1; Conceptual framework Source ...................................................................... 31
Figure 4.1: Employee Distribution by Gender................................................................. 42
Figure 4.2: Length of Time Employed ............................................................................ 43
Figure 4.3: Level of Employee Education ....................................................................... 44
Figure 4.4: Completion Rate of Contractors .................................................................... 45
Figure 4.5: County Government Supervision .................................................................. 46
Figure 4.6: Prequalification of Contractors...................................................................... 49
Figure 4.7: Reasons for Delay ......................................................................................... 52
Figure 4.8: Contract Change Management Practices....................................................... 59
Figure 4.9: County Supervision of Contractors ............................................................... 64
Figure 4.10: Rate of Completion ..................................................................................... 67
viii
ABBREVIATIONS AND ACRONYMS
ix
OPERATIONAL DEFINITION OF TERMS
x
ABSTRACT
There has been poor performance of road contract due to diverse challenges such as
poor management of funds and poor delivery of services to the road user. In addition,
the performance measurement systems aren’t efficient or effective to overcome this
problem. Road contractor’s performance problem appears in many aspects, ranging
from fail in time performance, cost performance and others fail in other performance
indicators. This study sought to establish and investigate the influence of contract
management practices on the completion of road projects by the County Government.
The specific objectives were the effect of contractor pre-qualification process,
contractors’ payment practices, contract change management practices and contractor
supervision activities on the completion of road projects by the County Government
of Machakos County. The completion of road projects was measured by time, cost,
quality, accuracy and speed. The county government has a total population of 458
staff who were the target respondents of this study. Sampling was done using
purposive sampling and stratified sampling to come up with a size of 145 respondents.
Data were collected using questionnaires deployed using drop and pick method. Data
were analyzed using descriptive techniques aided by SPSS software version 21. The
regression analysis results showed that Prequalification, Contractors’ payment
practices, Contract Change Management and Supervision statistically explained
completion of road construction in Machakos. All the independent variables were
found to have a positive linear correlation with the performance of road construction.
The findings of this research showed that the county government of Machakos was
successful in implementing some of the key factors required for effective and timely
completion of roads projects. Of the recommendations suggested in this study, the
most crucial one is the emphasis of professional ethics in contract awarding, contract
supervision and payment methods for continuing county contracts. From this study it
was clear that corruption still needs to be addressed with serious and effective
strategies that involve structural and social changes in approaching the vice. This
study found out that contactor prequalification is an important aspect in predicting
road completion. As was one of the significances of this study, the county government
ought to emphasize on contractor prequalification documentation. Payment practices
were found to have a strong linear correlation with completion of road project
outcomes. This implies that if contractor services are not compensated within the pre-
agreed time then road completion outcomes are bound to suffer. With that in mind, it
is important that the county officials ensure timely and competitive payment packages
that are also less bureaucratic. While contract change Management practices had a
significant role in the completion of roads, its overall effect on the regression model
was the least. However, the fact that contract Management practices is positively
correlated with completion of roads projects at county level, it is imperative that
county officials in charge of procurement stop premature contract termination and
other contract management issues in order to encourage road completion.
xi
CHAPTER ONE
INTRODUCTION
works are usually a major contributor to Gross Fixed Capital Formation, Gross
Domestic Product and National Employment (Oyewobi & Ogunsemi, 2010). The
concerns on performance of road construction and its effect on the economy continues
and Asia. For the past two decades the growth of the Nigerian construction industry
has indicated its success on the great contribution to the gross national product of the
country, which was 1.72 as per 2007(Federal Bureau of Statistics). Aminudin (2006)
indicated that up to 30% of construction is rework, labour being at only 40% to 60%
of efficiency in potential and at least 10% of materials get wasted. It is suggested that
rework costs could be ominously higher than figures reported in the previous
The road construction industry plays a major role towards the development and
and adds to about 10% of the gross national product, in industrialized countries
(Navon, 2005). There are numerous complexities associated with the construction
1
industries in its nature as it contains a large number of parties as consultants, cents,
and occurrence of unexpected events for instance wars and draughts , are considered
to the major factors towards poor performance of the projects more so in the
developing countries (Idoko, 2008), (Jekale, 2004), (Andersen, 2008). In many ways,
the pace of the economic growth of a given nation can be measured by physical
infrastructures development, for instance buildings, roads and bridges. The failure of
any construction project is mainly related to the problems and failure in performance
(Hough, 2007) Moreover, there are many reasons and factors that attribute to such
problems.
The challenges facing the construction industry can be grouped. The performance
identified that the performance problem is related to poor budgetary and time
regulation. Long et al (2004) observed that the performance problems arise in large
contractors, poor estimation and change management, social and technological issues,
site related issues and improper techniques and tools. Becerik (2004) stated that the
main performance problem can be divided into two major groups: these are the
2
unrealistic target planning, setting or causes originating from the definite construction
It is significant that the Kenyan road construction projects history is marked by ups
and downs with high performance by the national government being perceived today
and a decade ago as apprehended in the succeeding empirical studies. The Kenyan
construction industry has performed relatively well, not accidentally (Wels, 2007),
characteristics of the industry, for instance the wide dispersion of the flexibility in
of materials, of which some can be immense. Low quality capital demand for entry,
more so for crafted-based jobs (Chan, 2001). This study sought to establish how the
road construction and contract management practices are faring in the devolved
system of governance.
The significance of recognizing road construction performance is apparent all over the
world-wide markets, the results of which are to attract future investment, increase
share value and attract high caliber employees (Kumaraswamy, 2009). Consequently,
how it can be communicated to the wider market, that is, how can it be
comprehended and interpreted by the latent investors, customers and employees. The
basis of expressing performance indicators that attain the latter have been in action as
early as the beginning of our century, Creswell (2008). Equally, some of those
3
indicators have been evaded because as appraisals concentrate on finances Ibironke
(2008).
Good reputations of companies build by project success and also initiating new
expenditures via means of repair and rework, retest in the short term and re-
inspection. At the long term, deprived efficient can offend reputation. If the company
continues with the same trend it might have to close its shop as well for want of new
facets of their projects, they begin to reflect on the country’s reputation (Hyvari,
responsible for acquiring the desired efficient level success aspects and also to find
the attributes unpleasantly affecting the project efficient, has been the motivating
aspect behind this study. It is comprehended that intensification of the success factors
and minimization of failure aspects ensure the construction industry realizes its
efficient goals (Iyer and Jha, 2006). In Nyeri County, effectual construction projects
can deliver a solid platform for reviving the economy and for building a more balance
of such services, systems and institutions, however, has affected the efficient of life of
An effective project is delivered in time and has a right quality. There are several
4
quality. Nonetheless, measuring project success is a composite task since success is
tangible and can barely be agreed upon (Xiao & Proverbs, 2003). A comprehensive
project is a product of complex series of activities that integrate skills and knowledge
to produce a valuable result (Elger, 2008). Project completion has been well-defined
prearranged goals or objectives that form the project restraints (Ahmad, Ismail, Nasid,
control and maintenance, production management, supply chain, stores, safety and
health (Amin, 2011). It is the completion of a project that enables achievement of the
desired performance indicators in three key areas: scope, schedule and budget
(Alvarado, Silverman & Wilson, 2005). A project is fruitful if it contents all three legs
years extended this norms of success as: satisfies stakeholder groups, meets functional
necessities, meets quality requirements and prospects, within cost and deadline,
delivers continued and definite benefits and provides the team with skilled satisfaction
and learning.
Performance dimensions may have one or more indicators, and could be influenced
performance of road contractors is complex issues just like are the factors militating
against timely completion of road projects. This was corroborated by Kemps (2012)
who described project delivery as the world’s oldest documented profession with
5
challenges in project efficiency, road contractor’s performance metrics and other
developing countries. Most of the road projects fail in performance of time, others in
cost performance whereas other fail in other performance indicators. There are
feedback, and monitoring and leadership skills. In addition, cultural, economic and
political issues are three vital indicators correlated to failures of road projects'
Construction Firms in the developing countries is that, often they are thought to be
one-man enterprises, having low capital and financial base and also lacking the
such as Kenya’s Bundi(2011). Despite the shortfalls, the contractors in the developing
countries play a major role in the economy. It is contended that, given that these so-
called small firms provide a structural base to the economy and also determine the
and rural areas of the economy, their evaluation of the factors influencing effective
and efficient delivery of road construction projects would go a long way in helping to
(Ganessan, 2003).
Reworks contribute to time and cost overruns in projects. There are diverse
6
who described the main categories of constraints during construction process as
of rebuilding a process or activity that was erroneously applied in the first instance.
Rework can result from an array of factors such as omissions, failures, errors,
changes, poor coordination and communication and ultimately the profit margins as
well.
requirements in some form of contracts that require being managed (Kumar and
analysis for the purpose of exploiting financial and operational performance and
concept with many features. It refers the conformance of contractor or supplier with
Indicators and other elements of the commercial agreement (CIPS, 2012). You cannot
place. This is so because performance key outcome priority is cost, quality, speed and
flexibility which also inform contract management (Ketchen and Hult, 2006).
duty for operating company to ensure contractors perform their duties safely and
7
effective contract management has emerged as a crucial function to advance
2011).Contract management has attracted attention because while some risks can be
finishing a project, the ultimate risk still lies with the operating organization to convey
Ward (2009) commends that, the whole of procurement team should also be involved
risk management (Hotterbeekx, 2013). Studies have shown that organizations that
great deal in surplus savings and have a distinctive competitive advantage over their
contracts eventually lead to poor operational control, high risks, low customer
satisfaction and unwanted costs (Saxena, 2008). This study evaluated if this is the
Machakos County with a population of 1,084,129 million people has seen an un-
cater for the new devolved governments. This has seen the country commit up to 30%
8
of its budget to development, a big percentage of which is going to new roads.
master-plan that will ensure the face of the county lifted by the envisioned planned
Machakos City that provided at attractive lease terms to develop housing to cater for
Nairobi city and Konza techno city which is 15 Km from Machakos. Machakos is set
to become the dormitory for those two cities and therefore there is certainly a high
However, like any other part of the world Machakos County has had its own share of
challenges in meeting the time deadlines of its construction projects. Indeed most of
timeliness. Indeed most of the projects started in the last two years are way behind the
set time schedules they were meant to be completed (Department of public works and
Housing, 2014). Olatunji, (2010) avers that most projects are finally completed to
specification more or less, although they are seldom on time. Cokins, (2006), Chai
and Yusuf (2013), while stressing the importance of completing construction projects
on time and within budget contends that “time is essence” and that time is “revenue”.
This indicates that any delay in meeting the project completion time certainly
The local studies haven’t focused on factors influencing roads Construction Projects
provision in Machakos County. Musa (2012) sort out a study on the effects of total
the Inter build Company Limited. Musa (2012) found that resource management and
9
magnitude. Bundi (2011) did a survey on encounters in the management of
procurement facilities within the Kenya Urban Roads Authority. She found that
Nyamwaro (2011) did a study on the analysis of encounters facing the project
enactment a case study of Ministry of Roads Projects. The study comprehended that
lack of awareness and poor communication on POA used in the enactment of the
According to government of Kenya (2012) the poor performance of the road contracts
is due to poor management of funds and poor delivery of services to the road user. In
aspects, ranging from fail in time performance, cost performance and others fail in
other performance indicators. Ugwa and Haupt (2007). The performance and
mostly attributed to construction contractors. In the past, many road projects were
of the drawing and design, additional works, waiting the decision, variation order,
handing over, changes in Bill of Quantity and delay of getting the drawings
contract management and their efficacy was captured by an empirical study conducted
on the same subject in Nigeria which established that corruption in the contract
10
management practices by the government in the developing world resulting in poor
This has been reinforced by studies in the Kenyan construction industry that have
made findings to the effect that cost overrun, delayed completion period, conflicts in
and bribery, poor risk mitigation and poor quality work are the norm rather than
Muchungu, 2012; Cleland and Bidanda, 2009; Lepartobiko, 2012; Chuah et al., 2010).
completion of road projects, this study not only sought to fill the gap but, establishes
the contract management practices by the nascent county government with reference
to Machakos County.
The following are the general and specific research objectives of this study.
The study sought to investigate the effects of contract management practices on the
Kenya
11
ii. To find out the role of contractors’ payment practices on the completion of
Kenya
Kenya
ii) How do contractors’ payment practices affect the completion of road projects
The study findings and recommendations are helpful to many parties. The
necessary measures to ensure timely completion. The project also helps the
12
government understand the challenges and the needed critical success factors in order
to boost project completion rates and increase the number of customers, revenues and
profitability. The general public, who are the beneficiaries of the projects are likely to
get nuanced details and challenges affecting the construction of roads of in this
county. This study provides reference point to future researchers and academicians in
selected. Only tarmacked roads were considered that were constructed under the
practices by the County government and completion of road projects by virtue of the
factors that affect both the construction of roads and contract management practices
Challenges and limitations in data collection were faced in course of the research
since most of the relevant information required is usually protected due to its sensitive
nature. The researcher used an introductory letter from the university as well as
assuring the respondents that the information cannot be used for any other purpose
13
apart from the study. Most of the respondents might be expected to be busy
executives who might not have the time to respond to the research instruments in an
instance and so the study adopted a drop and pick method of collecting data using
14
CHAPTER TWO
LITERATURE REVIEW
2.1 Introduction
framework that outlines the theories to guide the study, an empirical review based on
variables and a summary of literature review that expose gaps to be filled by the
study.
This study was based on the Critical chain project management theory. It is named
after the crucial element; the extended chain of dependent resourced errands in the
project. The goal of the solution is to safeguard the period or rather the duration of the
project, and thus completion date, beside the effects of individual task resource and
The outcome is a vigorous and reliable approach that permits teams to accomplish
projects on due time, every time, and most significantly within at most 75% of the
current period for single projects and much less for individual projects in multi-
marketplace to distinguish from competitors who deliver worse outcomes, and late at
15
deliver additional projects over all, in the same extent of time, and at no escalation in
operating expense, therefore significantly refining the bottom line (Youngman, 2009).
According to Chiappori and Salanie (2003) as cited by Salim (2013); and Oluka and
Basheka (2012) the underlying principle of the principal-agency theory is that there
should be a clear understanding of the needs of the principal and ability of the agent to
meet these needs to reinforce desired performance (Ketchen and Hult, 2006). This is
Indeed, when procurement contract is well defined and planned, the principal and
agents find it easy to meet needs of each other in an effectual way resulting to timely
theory can proudly be applied to this study with a case as a principal and contractors
study as it highlights the need for robust contract requirements and specifications as
requirements roles and responsibilities are well defined, the agents and principals find
it easy to meet needs of each other in a more effective way resulting to timely
This theory was propounded by Marx Weber in 1947 in order to explain the
16
evil. Weber’s bureaucratic approach which considers the organization as a portion of
and practical model to this study. Weber listed various preconditions for the
occurrence of bureaucracy. These include the growth in population and space being
ran, and the convolution growth of administrative tasks being carried out and the
administrative system.
resulted in demands that the new system delights everyone equally (Weber, 1947).
defined lines of authority in a stable area of activity, inaction taken on the grounds of
organization include the use of standard procedures and methods for performing work
17
entails high levels of specialized skills. The standard bureaucracy structure is based
identifying bureaucracy as the most effective form of organization, and even crucial
for the modern state, Weber, nonetheless saw it’s weakness being impersonal, rigid,
Subsequent to the above faults of the bureaucratic theory, modern theories are thus
process in which individuals interact for objectives (Hicks and gullet, 1975). The
diverse fields have funded to its development stressing on the dynamic nature of
interests. The structure of this study evaluates the role of both the County Government
and the contractors in their roles on completions of projects as defined by the study
Government has cut the red tape and adjusted the bureaucratic formalize tall structure
into a matrix project structure not only to accommodate the interests of the contractors
but also hasten completion of projects. The theory is important in assessing the
site visits, pre-qualification, supplier relations, stores management and appraisal and
payment of contractors.
18
2.3 Empirical Literature
factor and measure of project success. In the recent years, there has been a growing
organizations (Weiss & Potts, 2012). The achievement of any road construction
project is highly reliant on its completion time from start to delivery of results. This
has a straight or rather bearing on management decisions for instance budgets, targets
and standards (Seddon, 2008). There is available proof from literature on ways to use
projects for the controlling of organizational process to organize the organization for
its competitive survival and future (Cleland& Ireland, 2007). Today, project
management techniques are basically used as the principal means by which strategic
delivery which refers to producing work that is of high quality and recognized as
efficient (Cole, 2002). The long-term objective of any organization is to produce high
quality road construction projects measured against the traditional measures of time,
cost and scope (Basu, 2014). There are different dimensions of measuring the success
measured by time, cost and quality. Cookie and Davies (2002) distinguishes between
19
project management success and project success (measured against the objectives of
the project). He further distinguishes success criteria as the measures against which
success or failure of a project is measured while success factors are the inputs that
Construction works involve high daily expenses that can’t be met by the contractors
when progress payments by the owners are delayed. Hasseb et al., (2011) noted that a
road construction project’s success depends on meeting objectives within time and
budget limits. s a result of this, there are several road construction projects that are
delivered within time and budget but fail to meet the expectations of end users.
Equally, the challenge of timely road construction project delivery can take multiple
Frimpong et al., (2003) identified five factors as the major causes of delays to road
Delay in road construction project completion time can be can be caused by several
and poor site management have also been recognized as factors triggering a delay in
timely road construction project delivery, Samuel (2008) endorses that project time
management be an important or rather key priority for the contractors and that the
20
in the tendering process. Delays in road construction projects can be avoided by use
management because they are basically human, materials and logistics trinity.
According to Frimpong et al., (2003) major delay occur during road construction
due to poor reporting structures and prevalent corruption (DFID, 2013). This study
Contract initiation activities have many activities. Rendon (2010) explained that at pre
leadership and policies all of which have direct impact on resulting contractors’
Performance is the achievement of a given task measured against the present known
from all liabilities under the contract. It refers the conformance of contractor or
21
supplier with contract terms, specifications, service level agreements or Key
Performance Indicators (KPI) and other elements of the commercial agreement (CIPS,
2012). Performance key outcome priority is cost, quality, speed and flexibility
management include the following areas: Health Security Safety and Environment
construction project owners. Quite interesting are the criteria presented by the
Palaneeswaran and Kumaraswamy (2001). The following groups of criteria have been
obeying the law and complying with local government regulations, standards and
threats. Prichard (2000) offers that prequalification systems allow contractors and
competence and suitability. Nonetheless, previous research has tended to focus more
Holt and Jennings (1998), Mills (2005) and Minchin and Smith (2001) research
22
contractor sentimentality. Criteria can be followed in selection of contractors. Mills
(2005) found that the apparent importance of various selection criteria between
contractor and client diverges greatly. Furthermore, Ng, Skitmore and Smith (1999)
found that several consultants’ perceptions of which selection criteria were significant
differed ominously to each other and the client. As such, industry stakeholders were
This variety of thought should be valued. It also suggests that industry people
originating from different disciplines are possibly biased towards their own
Phillips (2008) suggest that prequalification can limit the number of available
times. Ngai, Drew, Lo and Skitmore (2002) say the two prime factors affecting the
degree of competition are the number of contractors able to tender a road construction
project and market conditions at the time. Larger contractors felt that prequalification
systems with stringent multi-criteria selection decision making improves their chances
of winning contracts. However they did also find that contractors are generally
assertion that there are good contractors who elect not to participate.
23
2.3.3 Contractors’ Payment Practices
A growing number of incomplete road construction projects have led many to pose
many questions as to what is behind the failure in providing such an extremely needed
commodity. One may wonder whether such a failure is in anyway concerned with
socio-economic platform of the society that is cost escalation and unethical practices
finalized within estimated budget. Abdullah, Aftab, Azis & Rahman, (2010) examined
that construction cost is one of the most important criteria of success of road
construction projects throughout the maturation of the road construction project and is
of high apprehension to those who take part in the construction industry. In order to
presented.
until recently an issue of severe concern, both to the client and project contractors.
Amusan, (2010) reported that cost deviation from initial cost plan, had been prevalent
on construction sites. Every year, large companies spend large sums on the research
and development about the most optimal amalgamation of production or the most
favorable function and feature of their products and services. Amin, (2011) examined
that the impact of poor quality on the price of products and organization earnings and
the expanse of cost should be paid for high quality has elevated many important issues
influencing quality control, cost accounting, repairs and maintenance, supply chain,
education .
24
It is always necessary to define ways and processes in the contract to penalize or
award on the basis of compliance with the agreement. Choy, Chow, Lee and Chan
(2007) state that conflicts regarding payments hinders an organization from practicing
and set actual acceptance standards. A study by Njie et al. (2005) reviews relevant
literature and recognizes several pricing and payment schemes used in the global
building industry. This research road construction project assumes payment systems
to refer to the method in which construction products and services are priced and paid
for. Standard forms of contracts for building works frequently require the client to
make intermittent payment of the sum agreed with the contractor. It is the principles
behind these contracts with respect to their tender/pricing and payment processes.
Njie et al. (2005) demonstrates the most common standard forms of building contracts
with their related existing payment systems. The original payment systems such as the
mobilization advance payment and the mechanic’s lien can be used with any
contracting system. Ordinary forms for civil engineering projects, notably the FIDIC
and ICE, use the same payment systems as their equivalent JCT contracts.
premature causes of contract terminations are anticipated in contracts like poor quality
works, health and safety incidents and late completion of works (Nassar & Salim
2013; Mturi 2013; Mkose 2012). On other hand, some members of the CM team
especially the end users, have not been taking ownership of the contract as the result
25
causes cost overrun and complains to contractors which could affect the relationship
and contractor’s performance. t has cited that the threat of contract termination
Grimsey and Lewis (2004) contract termination clauses can be defined as the
processes undertaken to maintain the integrity of the contract, and ensure that the
roles and responsibilities contractually demarcated are fully understood and carried
out to the contracted standard. Termination is the process that ensures that process
that safeguards that all involved parties to a contract fully meet their responsibilities,
in order to satisfy the strategic business goals and the operational objectives of the
Premature contract termination has gained frequency and traction in the construction
industry and several mitigating measures have been suggested. According to a study
do not fail to meet their obligations in order to convey the objectives obligatory from
the contract and are allowed to do so by the other party. It also involves building a
the life of a contract and entails managing proactively to anticipate future needs as
well as reacting to situations that rises. Rendon (2010) observes that the greatest guard
26
Effective change management process has to look into the cost, time and quality
practice that determine problems when change occurred in a road construction project
or lessen change that may occur and upset the movement of the road construction
project. Also Hwang and Low (2012) outlined the process of change management to
to implement changes and to learn from past experiences. In other words a change
management process should seek to anticipate possible change, identify change that is
before now occurred, arrange for preemptive measure and synchronize changes across
the entire project stakeholders, which can be achieve by an integrated solution for
construction projects. Aje, Odusami and Ogunsemi (2009) showed that contractors'
building projects. Wiguna and Scott (2005) showed the critical risks affecting both
project time and cost perceived by the building contractors were related. They were:
Regarding to time delays the most important causative factor for global road
construction projects was late delay in payments while for the stadia road construction
projects design-related factors caused the most delays (Baloyi & Bekker, 2011).
Iyagba (2010) identified the factors that contribute substantial negative effect to road
27
construction project performance, hence affecting the integrity of the construction
industry.
execution; it is the quality of the people, management system of the company and
contractor that are the best guarantor of success according to a study by (Bhardwaj,
indicators are used to track and evaluate the Contractor’s performance in conforming
that are relevant for the procurement environment. This is followed by identifying and
performance, and the particular indicators used differ in accordance to the contract
specifications, the level of risk associated with contract failure by the supplier, and the
worth of the procurement (Path, 2002). This has been supported by Miller (2005) who
observes that, just because everything can be measured doesn’t mean that everything
things for the right people at the right time. t’s about measuring what’s significant to
the business. t’s about the quality of the measures and not the quantity (Miller, 2005).
Building road construction projects are the fundamental factors influencing contractor
performance. Hatami and Behsan (2012) found that contractors are more compliant of
28
risks that are mentioned in contracts than of other types of risk. Contractor
Abbasnejad and Moud (2013) found that most road construction projects writhed
from delays, imposing major damage on contractors, and that these damages were
intolerable and deeply influenced the contractor performance, which has been found
Based on local studies that have been done in Kenya; most of them did not focus on
that influence success in large construction projects. Kigari and Wainaina, studied
emerging trends in economics and management sciences time and cost overruns in
power projects in Kenya by closely relating the factors to the various variables. From
these studies there is no a guideline for the contractors who want to correct their
previous mistakes and improve on their current situation. Therefore, this research
Business District which shall be used as a benchmarking for the contractors. Kibuchi
and Muchungu (2012) studied the involvement of human factors in the performance
in Kenya. Lepartobiko (2012) studied the factors that influence success in large
construction projects. From these studies that have been done on performance of
construction projects, there is a need for future studies to focus on the following areas:
29
The effects of construction project manager’s skills on projects performance. Find out
between public and private construction projects, which one has got higher
evaluate the most important factors as a case study of construction projects in Nairobi.
30
2.5 Conceptual Framework
Contract prequalification
process
Fairness
Capacity
Rules/policies
Workforce preparation
31
CHAPTER THREE
RESEARCH METHODOGY
3.1 Introduction
The study sought to assess the effects of contract management practices on the
Kenya. This chapter provides a framework of methodology that be used in the study.
It gives an insight into the research design, target population, sample size, data
constitutes the blue-print for the collection, measurement and data analysis (Cooper &
Schindler, 2008) hence a logical and systematic plan prepared for directing a research
study (Shajahan, 2005). The study adopted a descriptive survey design. Sekran (2007)
to a sample of individuals. The descriptive design was particularly ideal because all
the data on the indicators of contract management practices and completion of road
construction projects was in numerical form suitable for quantitative description. The
likert scale that was utilized provided quantitative data that was analyzed in a
quantitative manner.
Descriptive surveys are designed to obtain information about the current status of a
phenomenon or to answer questions like where, what, how, why, when, and who. The
study used descriptive research which refers to the investigation in which data is
32
collected and analyzed in order to describe the specific phenomena in its current
trends, current events and linkages between different factors at the current time
(Kothari, 2004). Descriptive research design was used because it enables the
researcher to generalize the findings to a larger population. The design not only
enables the description of activities that delay the completion of road construction
projects by the county government of Machakos, Kenya but also describe the exact
have one or more characteristics in common that are of interest to the researcher
(Saunders, 2008). The study was conducted in the area administratively delineated as
Machakos County. The study was conducted in the Machakos County because of
rapid urbanization, industrial activities and high population density. This enabled
government in the management cadre and with knowledge due to their work
experience on the completion of road construction projects forms the focus of this
study. The respondents included the staff of the County government. There are 458
Department, 2016).
33
3.4.1 Sampling Techniques
use stratified sampling and simple random sampling techniques. Stratified sampling
ensures that all categories of the study case are included in the sample (Kothari,
2004). Stratified sampling was used to ensure that officials from all the departments in
the county government that have a direct impact on completion of road construction
projects are included in the sample. This ensured that some comprehensive data on the
equitably represented from all the departments of the County government. Stratified
sampling ensured that members of staff from the projects department, finance
of the County government were represented in the sample. After the stratification,
simple random sampling based on the first letter on the names of the officials was
used to ensure objectivity and equal opportunity for participation in the study (Nondu,
2010). Simple random sampling was used to ensure that all the members of staff have
inition also encompasses the purpose of sampling frames, which is to provide a means
for choosing the particular members of the target population that are to be interviewed
in the survey. More than one set of materials may be necessary and this is generally
the case in a multiple survey with a multi-stage nature. Upagade and Shende (2012)
also refers to a sampling frame as a source list containing all names of the universe.
Specifying the sample frame is crucial as it itemizes all items in the population from
which a sample is obtained for analysis so as to test the research hypotheses. The
34
sample for this study was of size 145 respondents. The sample size represents a
Data was collected using interview schedules and questionnaires which was delivered
to each of the Respondents. The questionnaire were ideal just as they were appraised
reasonably quick space of time. Questionnaires are easy to administer, gives the
respondent sufficient time to arrive at a well thought response and are free from the
researcher’s bias. The drop and pick method was used where the respondent is very
departments to enable the researcher to collect even the detailed and qualitative data
35
3.6 Validity of Instruments
Face and content validity were administered on the questionnaires. Kothari (2004)
points out that validity is the degree to which a test measures what it is supposed to
measure. After piloting the questionnaires were edited to ensure that it measures up to
high degree of face and content validity. Additionally, the expert opinions of the
Reliability is the level of internal steadiness or stability of the measuring device over
steadily induce the same responses from respondents in a study. The ultimate
respondents. A pilot study was carried out to correct any mistakes in the measuring
tool. After the pilot study, the instruments were edited to eliminate inconsistencies,
ambiguities and other grey areas that might hinder the consistency of responses from
the instruments among the many respondents. Cronbach alpha co-efficient was used
deemed sufficient.
Zikmund (2003), define data analysis the whole process which starts immediately
after data collection and at the point of interpretation of results. It involves coding,
Primary data from the questionnaire was coded and entered into the computer for
36
computation of descriptive statistics which was analyzed with the support of
The descriptive analysis yielded tables, charts, mean and standard deviation to
describe the data and enable making of meaning from the data. Additional analysis
establishment of the exact strength of the association among the variables under
study. The model for the multiple regression analysis was as follows;
Where,
ε = Error term
Since both quantitative and qualitative data were collected and analyzed, quantitative
data was presented using tables, charts, and bar graphs and written discussions. Data
were presented in tables, charts, graphs and any other appropriate presentation
method.
37
3.9 Operationalization of the Variables
38
To determine the effects of Contractors’ Promptness of Interval Descriptive -Frequency
contractors’ supervision activities on Supervision Supervision Measurement Analysis Distribution
the completion of road projects by the Activities Templates of Scale -Means
County Government of Machakos, supervision -Standard Deviations
Kenya Number/qualit -Correlation
y of Analysis
supervisors Inferential Regression Analysis
Contract Statistics
requirements
Completion of Time Interval Descriptive -Frequency
Road Projects Cost Measurement Analysis Distribution
Quality Scale -Means
Accuracy -Standard Deviations
Speed
Inferential Regression Analysis
Statistics
39
3.10 Ethical Considerations
For the purpose of this study, approval was sought from Kenyatta University and a
allow the researcher to carry out the research. The researcher further sought approval
from the management of county government where the officials are concerned to
carry out the study. The researcher explained the purpose of the study to the
respondents and assured them of confidentiality of their responses and identities. The
to voluntarily participate in the study. A verbal consent was sought from the
respondents before questionnaires were administered. The findings of the study were
not doctored to meet any preconceived or commercial ends. Materials and citations
40
CHAPTER FOUR
4.1 Introduction
This chapter examined the research findings and thereafter data analysis. The study
address the general research objective, three research objectives were formulated. The
County. The research findings were examined using descriptive statistics such as
frequency distribution, means and standard deviation. These results were presented in
pie charts, bar graphs and tables. In order to make conclusions on the relationship
between diverse variables then the inferential statistics were used. The inferential
The sample size of this study was 137 respondents and therefore 137 questionnaires
were distributed. The questionnaires that were returned were 113 therefore making a
response rate of 82.5%. This response rate was deemed sufficient in the context that
Orodho (2009) indicates that a response rate of over 85% being excellent, 70-85%
very good, 60-70% acceptable and below 50% not acceptable. The high response rate
was achieved due to the fact that the researcher engaged the respondents for the
purposes of reminding them to fill on the questionnaires. The high response rate
41
indicates that the results are sufficient for generalization as they can be considered a
The gender distribution results were illustrated through figure 4.1 below. The results
indicated that 55.80% of the respondents were male while 44.2% of the respondents
were female. The high number of the male respondents was attributed to the fact that
construction industry is often and generally male denominated. This is due to the
nature of work that makes it more attractive to the male gender. The gender aspect is
critical in the road construction projects completion rates in the sense that levels of
commitment and availability to supervise the road construction projects may vary
Gender
,0 ,0
Female, 44.20%
Male, 55.80% Male
Female
42
4.3.2 Length Worked at Machakos
In the context of the length of period worked at Machakos, the results were illustrated
using figure 4.2 below. The results indicated that 52.2%, 38.10%, 5.30% and 4.40%
of the respondents had worked for 0-2 years, 3-5 years, 6-8 years, and more than 8
years respectively. The length of the period worked in their respective institutions is
an indication of their experience levels in their functions and therefore the validity of
their results. The results indicated that slightly less than half of the respondents had
worked for more than 2 years and were therefore highly knowledgeable on the aspects
addressed by the research. It is also worth noting that the county governments have
only been in existence for a fairly short period of less than four years. The length of
time worked at Machakos County is critical for the completion of the road projects in
the county in the context that the persons who have stayed longer in the county are
well familiar with the road network in the county and have also networked with
diverse stakeholders.
60.00%
52.20%
50.00%
40.00% 38.10%
30.00%
Length of Period
20.00% Worked at The
Institution
10.00% 5.30% 4.40%
0.00%
0-2 Years 3-5 Years 6-8 Years More than 8 Years
Figure 4.2: Length of Time Employed
43
4.3.3 Education Level
The educational level was examined using figure 4.5 below. The results indicated that
4.4%, 16.8%, 54.0%, and 24.8% of the respondents had PhD, Masters, Degree and
Diploma level educational levels. The level of education is critical in ensuring that the
respondents have the required technical know-how on the aspects being asked. In this
context it was worth noting that 75.2% of the respondents had degree level education.
Education Level
PhD, 4.40%
PhD
Masters
Degree
The contract management levels were examined through use of completion rate of
44
4.4.1 Completion Rate of Roads
The results for the completion rates of roads were examined through figure 4.4 below.
The results indicated that 58.40% of the respondents agreed that there was delay in
The road constructions are often faced by diverse challenges that affect their
,0 ,0
No, 41.60%
In the context of supervision levels, the respondents were asked on the diverse levels
context, 9.7%, 8.8%, 43.4%, 18.6%, and 19.5% of the respondents indicated that there
45
and very close supervision respectively. Supervision of the contractors is a key
element of the work being completed on time as it ensures that the work
developmental milestones are met on time and with the required quality. Therefore,
supervision ensures on the timeliness of the work development as well the quality of
50.00%
43.40%
45.00%
40.00%
35.00%
30.00%
25.00%
18.60% 19.50%
20.00%
15.00% 9.70% How would you rate how the
8.80% county government of
10.00%
Machakos supervises road
5.00%
contractors?
0.00%
In the context of the delays in the payment of contractors, 7.1%, 19.5%, 32.7%, and
payment of contractors to a small extent, average extent, great extent and very great
extent respectively. The delays in the payment of the contractors have an effect of the
completion of the construction projects. This is due to the fact that contractors may go
slow or compromise the quality of work and then arm twist the county government to
pay them. In the context of the changing of contract documents, 17.7%, 38.9%,
46
29.2%, and 14.2% of the respondents indicated that county government of Machakos
changed contracts to a small extent, average extent, great extent and very great extent
respectively. Finally, 20.4%, 52.2%, and 27.4% of the respondents indicated that the
Upon the prompt that whether they engaged unqualified contractors, 49.6% responded
they never engaged them, 30.1% agreed they engaged them at small extent, while
20.4% agreed they averagely engaged unqualified contractors. None of the subjects
responded to engaging them to either a great extent or very great extent. On average
most respondents felt that project managers engaged unqualified contractors at a small
extent, with a mean score of 1.7080 and a deviation of .78696. The information in the
and Basheka, 2012). 38.9% of the respondents felt that the project managers
follows. The scores of the mean 1<µ<1.5,1.5< µ<2.5, 2.5<µ<3.5, 3.5<µ<4.5, and 4.5<µ≤5
to be interpreted as the respondents on average perceived that there was no extent, small
extent, average extent, great extent and very great extent of influence of the indicator on
road construction projects in relations to the given metric respectively. The standard deviation
(σX) scores; 0<σX<0.5, 0.5<σX<1, and σX≥1 to be interpreted as responses clustered around
the mean, responses moderately distributed around the mean, and responses widely
47
distributed around the mean implying high consensus, moderate consensus and lack of
The mean score for engaging unqualified contractors was 1.708, for delay in paying
contractors was 4.070, for changing of contract documents was 3.398, and for failure
to supervise contractors was 2.070. On average, the respondents perceived that delay
projects. On the other hand, the respondents on average perceived that changing of
construction projects was that to a small extent (1.5< µ<2.5), each indicator had an
In the context of distribution of responses around the mean and consensus levels, all
the metrics had moderately distributed responses around the mean. This implies that
there was moderate consensus (0.5<σX<1) on the extent of influence of each indicator
on road construction projects. The respective standard deviations were 0.78696 for
engaging unqualified contractors, 0.94223 for delay in paying contractors, 0.94055 for
48
Table 4.1: Contract Management
Percentages Mean Std.
1 2 3 4 5 Dev.
Engaging unqualified 49.6 30.1 20.4 0 0 1.708 .78696
contractors
Delay in paying 0.0 7.1 19.5 32.7 0 4.070 .94223
contractors
Changing of contract 0.0 17.7 38.9 29.2 0 3.398 .94055
documents
Failure to supervise 20.4 52.2 27.4 0 0 2.070 .69071
contractors
1. No extent 2. Small Extent 3. Average Extent. 4. Great extent 5. Very great
extent
Source: Research Data (2016)
The respondents were asked whether they thought the county government issued
contracts fairly based on the merit and qualifications brought forward to them. The
No, 47.80%
52.20% Yes
No
Figure 4.6
Fairness of Prequalification of Contractors
Source: Research Data (2016)
Half of the subjects of this study were of the opinion project managers emphasized on
the contractor’s training at 50.6%, while 41.6% thought project managers did so at a
small extent. Only 2.7% of the respondents felt the managers did so on rare occasions
as those who thought the managers did so at very great extent were represented by
49
1.7% of the respondents. 3.5% were of the opinion that training of the contractor was
Clearance with government bodies bore significant effect on the procuring entity as
none of the respondents thought it was not important or has very minimal importance.
45.1% of the respondents greatly thought clearance with government entities was
important, 31.9% thought they were important only on average and 23% thought very
crucial to have clearance with government entities. Machinery is also important to the
the subjects thought capacity of the contractor was either greatly important or very
greatly important to the procurer. Only 22.1% of the respondents felt that capacity of
the contractor was important to an average extent. Table 4.2 is a summary of the
percentages.
The study sought to find out the extent to which respondents on average perceived
undertaken as follows. The scores of the mean 1<µ<1.5, 1.5< µ<2.5, 2.5<µ<3.5,
that there was no extent, small extent, average extent, great extent and very great
The standard deviation (σX) scores; 0<σX<0.5, 0.5<σX<1, and σX≥1 to be interpreted
as responses clustered around the mean, responses moderately distributed around the
50
mean, and responses widely distributed around the mean implying high consensus,
The mean scores for training of the contractor, experience of the contractor, past
performance of the contractor, clearance with other government bodies (KRA, HELB,
PPOA) were 3.051, 3.384, 3.347 and 3.461 respectively. These mean scores were in
the range 2.5<µ<3.5, which implied that on average, the respondents’ perception was
of the contractor, past performance of the contractor, and clearance with other
The standard deviations for all the metrics on contractor prequalification were
projects. Similarly, there was moderate consensus on the extent of emphasis placed on
clearance with other government bodies like KRA, HELB, and PPOA which had a
51
standard deviation of 0.615, as well as capacity of the contractor (machinery owned)
Delayed payments are the money amount not delivered to the contractors in the pre-
Bureaucracy in the
government,
28.30%
Lack of Cash,
31.90%
Lack of Cash
Delay in inspecting roads
Delay in inspecting
roads, 39.80% Bureaucracy in the government
52
From the pie-chart in figure 4.7, the biggest contributing factor is delays in inspecting
the completed projects at 39.8% followed by unavailability of funds 31.9% and too
Factors affecting payments in the county governments include all issues that arise in
payment in full or as per the agreed upon installments corruption complaints among
other factors. The following table represents some of the factors and response
the delays in release of moneys by the central government hindered payments, while
24.8% agreed to an average extent. None of the respondents disagreed while 17.7% of
the respondents agreed to a “small extent” and 18.6% agreed to a “very great extent”.
the central government hinders payments with a score of 3.5841 and deviation of
.98856. The cycle of releasing monies by the central government falls under
organizational bureaucracy and laid down procedures of doing what is needed by the
While it would be expected that bribery by county officials would get great response
from the respondents those who agreed to a “very great extent” were only 4.4%
almost four times as smaller as those who completely disagreed at 16.8%. Most
respondents were of the opinion that the central government’s budgetary cycle created
a bottle neck in the payment processes as 41.6% of them agreed to a “very great
53
The study sought to find out the extent to which respondents on average perceived
interpretation was undertaken as follows. The scores of the mean 1<µ<1.5, 1.5<
small extent, average extent, great extent and very great extent in road construction
projects respectively. The standard deviation (σX) scores; 0<σX<0.5, 0.5<σX<1, and
distributed around the mean, and responses widely distributed around the mean
metric respectively.
The average opinion on demand for bribes by county government officials as a source
of delayed or poor payment practices was 2.7788 with a deviation from the mean of
1.0668. The score falls in the bounds of “average extent” with there being no
consensus on the metric. The average perception of the respondents was that to a great
scores for the individual metrics were 3.5841 for release of monies by the central
government, 3.6991 for bureaucracy in the finance department, 4.0354 for the
obligations.
54
While no response was recorded for “No Extent” in the questionnaire prompt of
whether disagreements over contractual obligations, the average opinion on the matter
was “great extent” marked by a mean of 3.8319 and deviation of 0.9811. Going by
amount of study. Bottle necks in the government budgetary allocations and too much
bureaucracy are some of the issues that rock payments of contractors (Nguyen, 2013).
The responses for bureaucracy in the finance department (σX=1.328) and the
government budgetary circle (σX=1.008) were widely distributed around the mean
which implied that there was no consensus (σX≥1) amongst respondents on the extent
On the other hand, responses for release of monies by the government (σX=0.9885),
distributed around the mean. This implied that there was moderate consensus
The respondents on average perceived that the demand for bribes by county
construction projects. This is beacause the metric had a mean score of 2.7788 which
was in the range 2.5<µ<3.5. The responses on the demand for bribes by county
government officials were widely distributed around the mean (σX=1.066) which
implied there was no consensus amongst respondents on the extent of effect that this
only seen in the government contracts but also in the almost every arm of the
government. While it is expected that demand for bribes would affect allocation to a
55
great extent, even a moderate extent is not good enough in ensuring contracts are
carried to term.
This subsection of this paper gives the actions taken by the contractors when their
payments are either delayed, completely not paid or other complaints by the
contractors. From the Table 4.4, most contractors (38.9%) “Never” pursue legal
options when procurers fail to pay them, sharply contrasting the .9% of the
respondents who “ lways” use legal means to get their pay. Most respondents on
average felt that contractors “usually” pursued litigation over non-payment issues
with an average score of 3.3805 out of 5 and a deviation from the mean of 1.0633.
payments at 40.7%, while those who “Never” or “Rarely” complain were represented
by 2.7%. The respondents also reported that those who “always” complained over
delayed payments were at 24.8%, 4.4% higher than those who “Usually” complain.
56
The study sought to find out how frequently the respondents perceived litigation by
contractors over non payment, complains by contractors over delayed payment, and
complaints by contractors over the amount to be paid occurred. The means (denoted
systems were calculated. The interpretation was undertaken as follows. The scores of
the mean 1<µ<1.5, 1.5< µ<2.5, 2.5<µ<3.5, 3.5<µ<4.5, and 4.5<µ≤5 to be interpreted
respectively. The standard deviation (σX) scores; 0<σX<0.5, 0.5<σX<1, and σX≥1 to be
around the mean, and responses widely distributed around the mean implying high
The average feeling about contractors complaining over delayed payments was that
over the amount to be paid occurred regularly as indicated by a mean score of 3.8319
which was in the range (3.5<µ<4.5). The responses for complains by contractors over
delayed payment and complaints by contractors over the amount to be paid were
moderately distributed around the mean with standard deviations of 0.92804 and
0.95340 respectively. This implied that there was moderate consensus (0<σX<0.5) that
complains by contractors over delayed payment and over the amount to be paid
occurred regularly in the road construction projects. The respondents on average felt
that litigation by contractors over non payment usually occurred (2.5<µ<3.5) in the
road construction projects as it had a mean score of 3.3805. However, there was no
57
consensus (0<σX<0.5) amongst respondents that litigation by contractors over non
1 2 3 4 5
Litigation by contractors 38.9 27.4 18.6 14.2 0.9 3.3805 1.0633
over non payment
Complains by contractors 2.7 2.7 29.2 40.7 24.8 3.8230 .92804
over delayed payment
Complaints by contractors 0.0 11.5 20.4 41.6 26.5 3.8319 .95340
over the amount to be paid
1. Never 2. Rarely 3. Usually 4. Regularly 5. Always
However, the frequency of changing contractors is what draws the most attention. The
Most respondents felt that contracts were changed “Regularly” at 36.3%. Those who
felt that the contracts were changed “usually” were represented by 26.5%, “Rarely”
58
Changes in the Contracts
Always, 18.60% Rarely, 18.60%
Rarely
Usually, Usually
Regularly, 26.50%
36.30% Regularly
Always
In the below table the main variables in the processes of changing contracts were
posed to the respondents. 36.3% of the respondents were of the opinion that adequate
provisions in contract document for change are used at both “great extent” and “very
great extent”. 19.5% of the subjects responded at “average extent”, 6.2% at “small
extent” and 1.8% at “no extent” as summarized in the table below. Generally,
documents for change were included at an average score of 3.9912 and a mean of
of goods, very little has been documented on the causes contract change when the
client is a government. The reasons highlighted here therefore add to the existing
literature of the factors that influence contract termination at local government levels.
59
The study sought to find out the extent to which respondents on average perceived
due diligence is conducted to ascertain the authenticity of change, the government and
contractor agree on the cost of change, and there are adequate provisions in contract
document for change done during the contract change process. The means (denoted
process were calculated. The interpretation was undertaken as follows. The scores of
the mean 1<µ<1.5, 1.5< µ<2.5, 2.5<µ<3.5, 3.5<µ<4.5, and 4.5<µ≤5 to be interpreted
extent, great extent and very great extent is the respective metric done during the
The standard deviation (σX) scores; 0<σX<0.5, 0.5<σX<1, and σX≥1 to be interpreted
as responses clustered around the mean, responses moderately distributed around the
mean, and responses widely distributed around the mean implying high consensus,
All the indicators on the contract change process in road construction projects had
mean scores in the range of 3.5<µ<4.5. This implied that on average the respondents
felt that to a great extent, due diligence is conducted to ascertain the authenticity of
change (µ=3.7611), the government and contractor agree on the cost of change
(µ=3.6726), and there are adequate provisions in contract document for change
(µ=3.9912).
provisions in contract document for change as the standard deviation was 0.9864. This
60
implied that there was moderate consensus (0.5<σX<1) amongst respondents that to a
great extent there are adequate provisions in contract document for change during the
extent
On the other hand, the responses for due diligence is conducted to ascertain the
authenticity of change (σX=1.028) and the government and contractor agree on the
cost of change (σX=1.012) were widely distributed around the mean. This implied that
there was no consensus (σX≥1) whether due diligence is conducted to ascertain the
authenticity of change and the government and contractor agree on the cost of change
The following are the potential responses to effects of contract change in cost of roads
projects and the corresponding responses. 0.0% of the respondents felt that contract
changes had no effect on cost of roads projects as compared to 52.2% who thought that
contract changes “Regularly” changes the cost of roads projects. 23.9% of the respondents
61
chose to say that contract changes “always” bring about changes in cost of roads projects,
8% chose “rarely” while 15.95 felt that contract changes “usually” altered the cost of road
change in cost of roads projects at a mean Likert score of 3.9204 with a standard deviation
of .84665. The degree of pinch in terms of cost, time for completion, quality of work done
documented. Aje, Odusami and Ogunsemi (2009), strengthen the evidence that change in
contract management definitely affects the time taken to complete the project as well as
An equal percentage of respondents were of the opinion that contract changes altered
completion time of road projects “ lways’ and “Never” respectively at 8%. Most
respondents believed that contract changes “always” altered the quality of roads
projects at 38.1%, while 29.2% believed the changes “Regularly” changed the quality
of roads projects.. 25.7% of the respondents thought that the changes in contract
The study sought to find out how frequently the respondents perceived change in cost
road projects, and termination of contractors work occurred during contract change
The interpretation was undertaken as follows. The scores of the mean 1<µ<1.5, 1.5<
average perceived the indicators never, rarely, usually, regularly, always occurred
62
The standard deviation (σX) scores; 0<σX<0.5, 0.5<σX<1, and σX≥1 to be interpreted
as responses clustered around the mean, responses moderately distributed around the
mean, and responses widely distributed around the mean implying high consensus,
On average, the respondents tended to think that change in cost of roads project
contractors work (µ=3.7522), regularly occur during contract change process in road
construction projects. This is because their mean scores were in the range of
change in cost of roads project (σX= 0.84665), change in quality of road projects (σX=
0.96346), and termination of contractors work (σX= 0.92129), regularly occur during
contract change process in road construction projects. This is because the responses
On the other hand, there was no consensus (σX≥1) on the average perception of
(2.5<µ<3.5) during contract change process in road construction projects. This is due
to the high standard deviation of 1.1361 which meant responses were widely
distributed around the mean for this metric as well as a mean score of 2.9381.
63
Table 4.6: Contract Change on Road Projects
Percentages Mean Std. Dev.
1 2 3 4 5
Change in cost of 0.0 8.0 15.9 52.2 23.9 3.9204 .84665
roads project
Change in completion 8.0 35.4 19.5 29.2 8.0 2.9381 1.1361
time of roads projects
Change in quality of 0.0 7.1 25.7 29.2 38.1 3.9823 .96346
road projects
Termination of 0.0 12.4 20.4 46.9 20.4 3.7522 .92129
contractors work
1. Never 2. Rarely 3. Usually 4. Regularly 5. Always
Source: Research Data (2016)
4.7.4 Engineers Supervision of Contracts
More respondents felt that the county governments did not have enough engineers to
supervise contractors as compared to those were for the opinion that county
Yes, 35.40%
No
No, 64.60%
Yes
The number who felt that corruption “Never” (8.8%) affected supervision of
contractors was double that which felt corruption “always” (4.4%) affected
supervision of contractors. Those who were of the opinion that corruption “usually”
affected supervision of the contractors was 7% less than the number of people who
64
felt that corruption “rarely” (21.2%) affected supervision of contractors. 36.3% of the
None of the respondents felt that lack of enabling structures for supervision “never”
affects supervision, while 10.6% thinks that lack of enabling structures “Rarely”
affect supervision. Finally, 37.2% of the respondents were of the opinion that lack of
and lack of enabling structures for supervision were both on average voted as “
regular” stumbling blocks to affecting supervision with averages of 3.735 and 3.9735
The study sought to find out how frequently the respondents perceived a lack of
and lack of other enabling structures for supervision affect supervision of contractor
(denoted by σX) of indicators of contract change process were calculated. The mean
projects respectively. The standard deviation (σX) scores; 0<σX<0.5, 0.5<σX<1, and
distributed around the mean, and responses widely distributed around the mean
65
implying high consensus, moderate consensus and lack of consensus on a given
metric respectively.
contractor in road construction projects. This is beacase their mean scores were
between 3.5 and 4.5. Additionally, in repect to the three metrics, there was moderate
consensus on their effect on (µ=3.6283) This is because the responses for the three
metrics were moderately distributed aroound the mean as their standard deviations
were 0.98375 for lack of resources to monitor contractors, 0.96379 for lack of policies
on contractor supervision and 0.99517 for lack of other enabling structures for
On the other hand, the respondents on average felt that corruption usually (2.5<µ<3.5)
affects supervision of contractor in road construction projects as the mean score was
2.9823. Responses for corruption were widely distributed around the mean which
implied ther was no consensus (σX≥1) that corruption usually affects supervision of
66
Table 4.7: Supervision of contracts
Percentages Mean Std. Dev.
1 2 3 4 5
Lack of resources to 3.5 9.7 23.0 47.8 15.9 3.6283 .98375
monitor contractors
Corruption 8.8 29.2 21.2 36.3 4.4 2.9823 1.0936
Lack of policies on 1.8 11.5 17.7 49.6 19.5 3.7345 .96379
contractor supervision
Lack of other enabling 0.0 10.6 18.6 33.6 37.2 3.9735 .99517
structures for
supervision
1. Never 2. Rarely 3. Usually 4. Regularly 5. Always
rated higher in the time it took to complete road construction projects as is discussed
below.
The county government was rated as better placed to complete roads constructions as
opposed to the central government with 51.3% and 48.7% respectively. The
,
Completion Rates0of Road Projects
by County Government
,0 Compared
to Central Government
No, 48.70%
Yes, 51.30%
Yes
No
67
4.8.2 Roads Performance Metrics in County Government
15.9% of the respondents felt that the priority of roads built affected performance to a
“very great extent”, 5.3% felt it was to no extent, 23.7% felt it was to a “small extent”,
35.4% were of the opinion it was to a “great extent” and 19.5% thought it was to an
“average extent”. The general reaction of those interviewed when asked whether
priority of the roads built contributed to performance was that it actually contributed
to an average extent with a likert mean score of 3.3274 and deviation of 1.1606. Of
those who responded, 29.2% believed that cost of construction affected performance
of roads both to a “great extent” and to a “very great extent”, 15.9% thought cost of
construction and inputted “small extent” and 24.8% inputted “average extent”. Only
.9% of the respondents thought cost of construction had no extent on the performance
of the roads.
The study sought to find out the extent to which priority of roads built, time taken to
complete roads, cost of constructing road, and quality of roads constructed has
changed under the county government. The means (denoted by µ) and standard
deviations (denoted by σX) of indicators of has changed under the county government
4.5<µ≤5 were interpreted as the respondents on average perceived that there was no
extent, small extent, average extent, great extent and very great extent of change of a
given metric under the county government road construction projects respectively.
The standard deviation (σX) scores; 0<σX<0.5, 0.5<σX<1, and σX≥1 to be interpreted
as responses clustered around the mean, responses moderately distributed around the
mean, and responses widely distributed around the mean implying high consensus,
68
The respondents on average perceived to a great extent (3.5<µ<4.5) cost of
changed under the county government. There was however different levels of
respondents on the extent of change in cost of constructing roads (σX =1.0846), but
there was moderate consensus amongst respondents on the extent of change in quality
(2.5<µ<3.5) the priority of roads built (µ=3.3274) and time taken to complete roads
(µ=3.4602) have changed under the county government. However, the responses on
the priority of roads built under the county government were widely distributed
around the mean which implied there was no consensus (σX≥1) amongst the
respondents on the extent of change (σX=1.1606). The responses on the time taken to
complete roads under the county government were moderately distributed around the
mean which implied there was no consensus (0.5<σX<1) amongst the respondents on
69
4.9 Regression Model
The regression model was utilized for the purposes of examining the influence of the
four independent variables on the dependent variable. The multiple linear regression
coefficient of 0.842 indicated that there was a positive correlation between the four
independent variables and the dependent variable.The adjusted R Square Statistic was
0.696. Thus, 69.6% of the total variation in the values of Completion of Road Projects
Practices. The rest is due to chance or factors beyond this model. 62.9% value of
The ANOVA statistics were used to determine on whether the regression was a good
fit for data. In this case since p value is 0.000 which is less than 0.05 then the
70
Where X1 is the contractor’s prequalification, X2 is the contractors’ payment practices
likely to cause a .289 unit increase in Completion of roads for every unit increase in
component in ensuring that the contractors with the right qualifications are sourced.
These contractors should have the right qualifications and technical expertise as well
While holding Prequalification, supervision and CMP constant, a unit increase in CPP
Practices was seen to give a positive influence on the completion of the road projects
since the payment practices influences the quality of roads undertaken. The
contractors who have not been paid their dues are likely to abandon work half way for
nonpayment of services.
Contract Management Practices are critical in ensuring that the contract is executed as
per scope of work in regards to timelines and quality of work. This aspects influence
roads with the other independent variables kept constant. Supervision is key in the
execution of the projects in the sense that it ensures that road contract scope of work
progresses as planned.
71
Table 4.11: Linear Relationship Coefficients
B Std. Error t p-value
(Constant) -.267 .401 -.665 .508
Prequalification .289 .117 2.47 .016
Contractors’ Payment Practices .986 .122 8.057 .000
Contract-change Management Practices .0326 .140 .325 .0305
Supervision .050 .132 .379 .705
Source: Research Data (2016)
While each of the individual independent variables had a statistically significant linear
relationship with the response, some of them failed to pass the significance test in the
multiple-linear regression model. The p-value for prequalification was .016 which
was below the .05 level rendering Prequalification to be having a linear relationship
with the response. Contractors’ Payment practices had a proven linear relationship
.705 respectively with the latter exceeding 0.05 level. Contract Change Management
roads. This implies that contract change management practices had a significant effect
supervision was not seen to have significant influence on road completion of projects
72
CHAPTER FIVE
5.1 Introduction
This chapter examines the summary, conclusions and recommendations of the study
5.2 Summary
The aim of this study was to establish whether certain selected independent variables
County Tarmacked roads. Analysis of the dependent and independent variables was
done and the results interpreted that three independent variables (Prequalification,
Projects
road projects, the experience of the contractor was a significant component. None of
the respondents thought that the experience of the contractor was not useful. The
bodies bore significant effect on the procuring entity as none of the respondents
thought it was not important or has very minimal importance. The use of machinery
73
5.2.2 Contractors’ Payment Practices on the Completion of Road Projects
projects. Amongst the aspects that were found contributing to delays in payments
of funds and too much bureaucratic procedures in availing money to the contractors.
payment practices was found to affect the road completion to an average extent.
which is not only seen in the government contracts but also in the almost every arm of
the government. While it is expected that demand for bribes would affect allocation to
a great extent, even a moderate extent is not good enough in ensuring contracts are
carried to term. Bottle necks in the government budgetary allocations and too much
Projects
The influence of the contract change management practices was examined. The
respondents felt that the contracts were changed in an infrequent manner. On average,
subjects felt at a “great extent” that due diligence is conducted to ascertain the
caused a change in cost of roads projects. The degree of pinch in terms of cost, time
for completion, quality of work done and complete termination of contractor due to
74
5.2.4 Contractors’ Supervision Activities on the Completion of Road Projects
More respondents felt that the county governments did not have enough engineers to
supervise contractors as compared to those were for the opinion that county
measured and its overall impact on the project, the evidence presented in these results
clearly show that there is need for resource allocation for monitoring contractors.
of contractors.
5.3 Conclusions
In relations to completion of road projects, the study found that 45.3% of the
study also found that there was statistically significant relationship between
contractors’ prequalification process and the completion of road projects. From the
regression model, while holding all the other variables constant, prequalification has a
positive correlation with the response. Thus from our study contractor’s qualification
the study found that 64.1% of the variation in values of Completion of Road Projects
75
Practices. The study also found that contractors’ payment practices are statistically
significant to the completion of road projects. The simple linear regression model
indicated that 33.8% of the variance in completion of road projects was attributed to
In respect to contract change management practices, the study found that there was a
on the Completion of Road Projects. This was because the p value for regression
analysis was below 0.05 as the hypothesis was being tested at 5% level of
significance.
completion rates as the study they had p values greater than 0.05. The study therefore
concluded that the supervision on its own was not sufficient to influence on its own
5.4 Recommendations
The following are the recommendations as derived from the findings of this study.
predicting road completion. As was one of the significances of this study, the county
Payment practices were found to have a strong linear correlation with completion of
road project outcomes. This implies that if contractor services are not compensated
within the pre-agreed time then road completion outcomes are bound to suffer. With
76
that in mind, it is important that the county officials ensure timely and competitive
While contract change Management practices had a significant role in the completion
of roads, its overall effect on the regression model was the least. However, the fact
stop premature contract termination and other contract management issues in order to
The supervision activities on their own were not seen as significant predictor of
completition of road projects and therefore the county government should always
The study recommended for further studies an examination of the influence of the
government structure. The study also recommends for further studies the influence of
77
REFERENCES
Ashley, D.B. (1986). New trends in risk management, paper presented at the
Internet’s 10th International Expert Seminar on New Approaches in
Project Management, Zurich, 10-12 March.
Atkinson, A., Waterhouse, J., & Wells, R. (1997). A Stakeholder Approach to
Strategic Performance Measurement. Sloan Management Review.
Ambituuni, A., (2011). Causes Of Project Delay And Cost Overrun And Mitigation
Approach. Abardeen, U.K. Robert Gordon University
Brigham, E., & Ehrhardt, M., (2013). Financial management: Theory and practice.
Ohio, USA. Cengage learning publishers
Cleland, D.I. and Ireland, L.R. (2007). Project Management: Strategic Design and
Implementation. McGraw-Hill Company, New York.
78
DFID (2013). Education: Improving Learning, Expanding Opportunities.
Available:https://www.gov.uk/government/publications/education
improving earning expanding
Frimpong,Y., Oluwoye, J. and Crawford, L.(2003). Causes of delay and cost overruns
in construction of groundwater projects in developing countries; Ghana as a
case study. International Journal of Project Management: 321-326.
Kothari, C. R., (2004). Research Methodology Methods and Techniques, 2nd edition.
New Age International Publishers.
Kumar, R. &Markeset, T. (2007). Development of performance-based service
strategies for the oil and gas industry, a case study.Journal of Business &
Industrial Marketing, 22(4), 272-280
Li, S., Foulger, J. R, and Phillips, P. W. (2008) „ nalysis of the mpacts of the
Number of Bidders Upon Bid Values: Implications for Contractor
Prequalification and Project Timing and Bundling‟, Public Works
Management and Policy, 12 (3), 503-514.
Marshall, R. (2007). “The Contribution of Earned Value Management to Project
Success on Contracted Efforts: A Quantitative Statistics Approach within
the Population of Experienced Practitioners”. Journal of Contract
Management, 2007.
79
Mugenda.A.G. and Mugenda.O.M.(2003).Research methods; Qualitative and
quantitative Approaches.Nairobi: Kenya Acts Press
80
APPENDIX ONE; INTRODUCTORY LETTER
Gloria Mulinde
TEL:
EMAIL: [email protected]
BOX:
Information offered will be treated confidentially and used for the purpose of this
research only. The findings of the research will ultimately help improve the
Appreciation is offered as you aid in the creation of new knowledge to aid both the
Regards,
…………………..
Gloria Mulinge
71
APPENDIX TWO; QUESTIONNAIRE
BACKGROUND INFORMATION
ii. Masters ( )
iii. Degree ( )
iv. Diploma ( )
v. Any other ( )
Specify…………………………………………………………………………………
…………………………………………………………………………………………
………………………………
72
c) Related supervision ( )
d) Very related supervision ( )
e) No supervision ( )
6. State the extent to which the following contract management practices affect
road construction projects.
1 2 3 4 5
a) Engaging unqualified contractors
b) Delay in paying contractors
c) Changing of contract documents
d) Failure to supervise contractors
7. In your own opinion, what in what ways contract management practices can
be adjusted to improve completion of road construction?
…………………………………………………………………………………
…………………………………………………………………………………
…………………………………………………………………………………
………………………………………
Yes ( )
No ( )
Explain your answer
…………………………………………………………………………………
…………………………………………………………………………………
………………………
9. Indicate the extent to which the following is emphasized in the contractor
prequalification process using the following scale.
1. “very great extent” 2. Great extent 3. Average extent 4. Small extent 5.
No extent
1 2 3 4 5
a) Training of the contractor
b) Experience of the contractor
c) Past performance of the contractor
d) Clearance with other government
bodies. ( eg KRA, HELB, PPOA)
e) Capacity of the contractor ( machinery
owned )
73
10. State the reasons why some of the contractors are not prequalified by the
county government of Machakos.
…………………………………………………………………………………
…………………………………………………………………………………
…………………………
11. Tick on the reasons that mostly cause delayed payments to contractors.
a) Lack of cash ( )
b) Delay in inspecting roads ( )
c) Bureaucracy in the government ( )
12. Indicate the extent to which the following factors affect payment to
contractors.
1 2 3 4 5
a) Release of monies by the central
government
b) Bureaucracy in the finance department
c) Demand for bribes by county government
officials
d) The government budgetary circle
e) Disagreements over contractual obligations
13. State the frequency with which the following occurs using the scale provided
by contractors over no payment.
1. Never 2. Rarely 3. Usually 4. Regularly 5. Always
1 2 3 4 5
a) Litigation by contractors over non payment
b) Complains by contractors over delayed
payment
c) Complaints by contractors over the amount
to be paid
…………………………………………………………………………………
…………………………………………………………………………………
…………………………
74
PART FOUR: CONTRACT CHANGE MANAGEMENT PRACTICES
15. Tick appropriately to indicate the frequency with which changes are made in
this county.
18. Indicate the frequency the following occurs during contract change process
using the following scale.
1. Always 2. Regularly 3. Usually 4. Rarely 5. Never
1 2 3 4 5
a) Change in cost of roads project
b) Change in completion time of
roads projects
c) Change in quality of road
projects
d) Termination of contractors
work
75
PART FIVE: CONTRACTOR SUPERVISION ACTIVITIES
19. Do you think the county government has enough engineers to supervise
contractors?
Yes ( )
No ( )
20. Tick appropriately to indicate the extent to which the following factors affect
supervision of contractor using the scale provided.
1. Always 2. Regularly 3. Usually 4. Rarely 5. Never
1 2 3 4 5
a) Lack of resources to monitor
contractors
b) Corruption
c) Lack of policies on contractor
supervision
d) Lack of other enabling structures
for supervision
…………………………………………………………………………………
…………………………………………………………………………………
………………………..
22. Would you rate the completion of road projects by county government as
faster than central government?
Yes ( )
No ( )
23. Indicate the extent to which the following performance metrics in road
construction has changed under the county government.
1 2 3 4 5
a) Priority of roads built
b) Time taken to complete
76
roads
c) Cost of constructing
roads
d) Quality of roads
constructed
24. In your own opinion, list the factors that affect roads construction projects in
this area.
…………………………………………………………………………………
…………………………………………………………………………………
…………………………
77
APPENDIX THREE
78
79