Primavera Project Planner Primavera Project Planner Sample Project Sample Project

The document summarizes a sample construction project plan using Primavera Project Planner. It includes 8 activities with durations, predecessors, resources needed, and a progress update showing the status of activities as of January 18, 2007. Resources required include equipment, materials, and personnel. Engineers are assigned responsibility for overseeing different activities. The document requests updating the schedule based on the progress and answering questions about project end date, total cost, actual cost to date and cost variance.

Uploaded by

khan103
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
36 views

Primavera Project Planner Primavera Project Planner Sample Project Sample Project

The document summarizes a sample construction project plan using Primavera Project Planner. It includes 8 activities with durations, predecessors, resources needed, and a progress update showing the status of activities as of January 18, 2007. Resources required include equipment, materials, and personnel. Engineers are assigned responsibility for overseeing different activities. The document requests updating the schedule based on the progress and answering questions about project end date, total cost, actual cost to date and cost variance.

Uploaded by

khan103
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Primavera Project Planner

Sample Project
Prepared by: Luay Dwaikat,
MSc. Construction Management

1) Project information:

Schedule the following project using Primavera Project Planner considering that the project will start on 1 Jan. 07 without any day off.

Activity Resource Material


I.D Description Duration Predecessor Resources Qty. Material Quantity unit
(Units/day) (Budgeted)

1 Excavation 1 -- Excavator 1 -- -- --
helper 8
2 leveling 9 1 Helper 9 -- -- --
mason 5
3 anti termite 5 1 Helper 7 Termite Material 200 M2
Helper 5 Concrete 30 M3
4 Foundation 5 2,3 Steel fixer 5 Steel 5 Ton
Carpenter 5
Mason 5
5 inspection 4 3 Helper 4 -- -- --

3
Helper 8 Concrete 5 M
6 Ground slab 4 4,5 Steel fixer 5 Steel 1 Ton
Carpenter 5
Mason 5
7 Plumbing 6 5 Helper 2 4” PVC Pipes 15 M
Plumber  2
3
Helper 4 Concrete 2 M
8 Columns 1 6,7 Steel fixer 5 Steel 1 ton
Carpenter 5
Mason 5
Luay Dwaikat 1

2) The following prices could be applied to the resources:

S. Resource Unit price


N. ($)
1 excavator 40 / hr
2 helper 7 / day
3 Steel fixer 10 / day
4 Carpenter 11 / day
5 Mason 10 / day
6 Plumber 3 /hr
7 4” PVC pipes 2/m
3
8 Concrete 40 / m
9 steel 200 / ton
10 termite 2 / m2

3) Three engineers are available and they will be responsible as follows:

S.n Engineer Responsible for


2) The following prices could be applied to the resources:

S. Resource Unit price


N. ($)
1 excavator 40 / hr
2 helper 7 / day
3 Steel fixer 10 / day
4 Carpenter 11 / day
5 Mason 10 / day
6 Plumber 3 /hr
7 4” PVC pipes 2/m
3
8 Concrete 40 / m
9 steel 200 / ton
10 termite 2 / m2

3) Three engineers are available and they will be responsible as follows:

S.n Engineer Responsible for

1 Ahmad – site engineer Foundation


Inspection
Ground slab
Columns
2 Ali – excavation engineer Excavation
Leveling
Anti-termite
3 Sami – mechanical engineer Plumbing

Using Ms project 2007, answer the followings:

1) When will the project end?


2) What is the total project cost?
3) What is the total concrete cost in the project?
4) What is the total steel cost in the project?
th
5) How many helpers should be available at site in 5  of Jan.?
6) Assume that you have just 10 helpers in the site, what would be changed in the
 project?

Luay Dwaikat 2
4) Progress Update:
th
The site feedback indicates the following activities status in 18 of Jan 2007:

S. Activity Original Remained Pct Notes


N. Description Duration Duration
1 Excavation 1 0 100 % Started & finished on time
2 leveling 9 0 100 % Started & finished on time
rd 
3 anti termite 5 0 100 % Started on 3  of Jan. and Delayed tow
days
th
4 Foundation 5 0 100 % Started on 12  of Jan. and Delayed one
days
th
5 inspection 4 0 100 % Started on 8  of Jan
th
6 Ground slab 4 4 0% Started on 18  of Jan
7 Plumbing 6 0 100 % Started & finished on time
8 Columns 1 1 0% --

Using Primavera Project Planner, update your schedule and answer the
followings:

1) When will the project end?


2) What is you project total cost?
3) What is your actual cost (ACWP) up to date?
4) How much is your cost variance (CV)? and WHY?

Luay Dwaikat 3