Quiz 2 Question
Quiz 2 Question
Assignment = Quiz 2
Instructions
DO NOT copy the assignment, marks will be graded on originality of work, zero mark
will be for copied one. Assignment will be checked by Plagiarism software
Each question has 01 mark
Submission date is 19th April 2020 (Sunday)
Submit the assignment using MS Word individually. Image file is not acceptable.
Submit the assignment before closing date on Microsoft Teams.
Question 1:
Question 2:
Draw the ADN Diagram shown activities on arrows (AOA).
Question 3:
Activity Preceding Activity Normal Time (Days)
1-2 -- 20
1-3 -- 25
2-3 1-2 10
2-4 1-2 12
3-4 1-3 , 2-3 5
4-5 2-4 , 3-4 10
Question 4:
Activity Optimistic Time Mostly Likely Time Pessimistic Time
A 4 10 16
B 3 6 9
C 4 7 16
D 5 5 5
E 8 11 32
F 4 10 16
G 2 5 8
Calculate Expected Mean Duration, variance and Standard Deviation of each activity.
Question 5:
Activities Predecessors to tm tp
A -- 6 9 12
B A 14 17 20
C A 7 10 13
D A 3 5 9
E -- 4 7 8
F E 9 11 12
G C,F 10 14 16
H F,G 17 20 25
I C 12 15 18
J B 13 18 25
THE END