Quiz 2 Question

This document is a quiz assignment for a software project management course. It contains 5 questions asking students to draw network diagrams like AOA and ADN diagrams, identify time allocations on activities, and calculate expected mean durations and variances for activities in PERT diagrams. Students are instructed to submit original individual work in MS Word by a specified deadline on Microsoft Teams.
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
28 views

Quiz 2 Question

This document is a quiz assignment for a software project management course. It contains 5 questions asking students to draw network diagrams like AOA and ADN diagrams, identify time allocations on activities, and calculate expected mean durations and variances for activities in PERT diagrams. Students are instructed to submit original individual work in MS Word by a specified deadline on Microsoft Teams.
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Department of Computer Science, CUI Lahore Campus

Assignment = Quiz 2

Name: Section: Course Title: Software Project Management Date:


Reg.#: Instructor: Sana Rizwan Marks: 5 Class/Batch:

Instructions

 DO NOT copy the assignment, marks will be graded on originality of work, zero mark
will be for copied one. Assignment will be checked by Plagiarism software
 Each question has 01 mark
 Submission date is 19th April 2020 (Sunday)
 Submit the assignment using MS Word individually. Image file is not acceptable.
 Submit the assignment before closing date on Microsoft Teams.

Question 1:

Draw the Network Diagram shown activities on arrows (AOA).

Question 2:
Draw the ADN Diagram shown activities on arrows (AOA).

Question 3:
Activity Preceding Activity Normal Time (Days)
1-2 -- 20
1-3 -- 25
2-3 1-2 10
2-4 1-2 12
3-4 1-3 , 2-3 5
4-5 2-4 , 3-4 10

Draw activity network diagram and identify the time allocation.

Question 4:
Activity Optimistic Time Mostly Likely Time Pessimistic Time
A 4 10 16
B 3 6 9
C 4 7 16
D 5 5 5
E 8 11 32
F 4 10 16
G 2 5 8

Calculate Expected Mean Duration, variance and Standard Deviation of each activity.

Question 5:
Activities Predecessors to tm tp
A -- 6 9 12
B A 14 17 20
C A 7 10 13
D A 3 5 9
E -- 4 7 8
F E 9 11 12
G C,F 10 14 16
H F,G 17 20 25
I C 12 15 18
J B 13 18 25

a) Draw the ADN network diagram for Pert.


b) Find the Expected mean duration and variance for each activity

THE END