0% found this document useful (0 votes)
72 views7 pages

3 Mnyuzi Boq

This document provides a bill of quantities for the proposed construction of a staff house at Mnyuzi Secondary School. It includes estimates for various construction works such as site clearance, substructure works including excavations and foundations, blockwork walls, reinforced concrete ring beams and slabs, roofing works with galvanized iron sheets, doors and windows. The total estimated cost is over 100 million Tanzanian shillings.

Uploaded by

Mwasamani Gunda
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
72 views7 pages

3 Mnyuzi Boq

This document provides a bill of quantities for the proposed construction of a staff house at Mnyuzi Secondary School. It includes estimates for various construction works such as site clearance, substructure works including excavations and foundations, blockwork walls, reinforced concrete ring beams and slabs, roofing works with galvanized iron sheets, doors and windows. The total estimated cost is over 100 million Tanzanian shillings.

Uploaded by

Mwasamani Gunda
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 7

BILL OF QUANTITIES FOR PROPOSED CONSTRUCTION OF STAFF HOUSE AT MNYUZI

SECONDARY SCHOOL IN KOROGWE DISTRICT COUNCIL

S/N WORKS DESCRIPTION UNIT QTY RATE AMOUNT


PRELIMINARIES
Allow for Contractor's establishment on site
Item 1 700,000.00 700,000.00

Site clearance m2 113 1,500.00 169,500.00


Setting out Item 1 250,000.00 250,000.00
-
SUBSTRUCTURE -
Excavations and Earthworks -
Excavate oversite 150mm deep average depth
and remove vegetable soil from site
m2 13 3,500.00 46,900.00

Excavate foundation trench commencing at


stripped level not exceeding 900mm deep
m3 56 5,000.00 278,500.00

Earth back filling well rammed and


consolidated in layers around foundation. m3 41 5,000.00 206,500.00

Imported filling material well rammed and


consolidated in layers not exceeding 150mm
thick to make up levels under floor m3 17 9,000.00 151,200.00

150mm thick hardcore Bed leveled and


blinded with 20mm layer of sand to receive
m2 112 35,000.00 3,920,000.00
DPM (Measured separetely)

Treat top of hardcore with approved anti -


termite solution applied strictly in accordance
with the manufacturer'ers instructions. m2 112 5,000.00 560,000.00

Ditto to backfilling to one side of wall on


perimeter of building 150mmx350mm deep
m2 21 5,000.00 105,000.00

Masonry works -
Construct stone masonry Foundation footing
wall using cement sand mortar in the ratio of m3 55 33,000.00 1,815,000.00
(1:4)

Concrete works -
Provide plain insitu concrete grade 15 100mm
thick floor slab concrete with formwork
m3 17 250,000.00 4,200,000.00
around the edges
S/N WORKS DESCRIPTION UNIT QTY RATE AMOUNT
Moisture control -
500mm gauge polythene damp proof
membrane laid over blinded hardcore m2 112 5,000.00 560,000.00

Hesian based bitumen damp damp proof


course to B.S 743 type 'A' 150mm wide laid
horizontally on concrete slab before erecting m 90 7,000.00 630,000.00
walls

-
SUPERSTRUCTURE -
Walling -
Solid sand cement Block thick wall bedded
and jointed in cement and sand (1:4) mortar
-

a)150mm thick wall m2 206 26,600.00 5,479,600.00


Concrete works -
Insitu Reinforced Concrete grade 20 tamped
around formwork -

a) 150 x230mm RC Ring beam m3 3 355,000.00 1,065,000.00


Formwork -
Sawn timber formwork to -
a) Soffits of the ring beam m 22 21,500.00 473,000.00
b) Horizontal sides of the beam m 2
45 9,000.00 405,000.00
Reinforcements -
High tensile round iron bars grade 460 to BS
4449;1964 -

a) 12mm diameter bars kg 948 4,500.00 4,266,000.00


b) 6mm diameter bars kg 948 4,500.00 4,266,000.00
-
ROOFING -
Roof structures and coverings sloping not
exceeding 25° from horizontal -

Supply and fixing of GCI Sheets 28G with


approved roofing nails m2 294 30,000.00 8,820,000.00

Supply and fixing of 28G Galvanised Iron


Sheets Ridge Caps Lm 14 10,000.00 140,000.00

Supply and fixing of softwood treated timber


-

i) Wall plate 50x150mm m 90 9,000.00 810,000.00


ii) Common Rafters,struts and posts
50x100mm m 300 7,500.00 2,250,000.00

iii) Purlins 50x75mm m 600 5,500.00 3,300,000.00


iv) Fascia board 25x200mm m 46 13,000.00 598,000.00
v) Tie beam 50x150mm m 20 9,000.00 180,000.00
S/N WORKS DESCRIPTION UNIT QTY RATE AMOUNT
Ceiling works -
Provide and fixing of ceiling board framework
and coverings -

a) S/w treated timber branderings 50 x50mm


at 600x600mm c/c spacings. m 810 5,000.00 4,050,000.00

b) Ceiling Covering - Gypsum board m2 125 22,000.00 2,750,000.00


c) Cornices m 100 3,500.00 350,000.00
-
DOORS -
Door frames 50x150mm H/W timber approved
by Engineer -

a)900 x2600mm No 10 350,000.00 3,500,000.00


b)800 x 2600mm no 2 350,000.00 700,000.00
Doors shutters 40mm thick Batterned door
single or double leaf solid Hardwood complete
-

a)850 x255mm No 10 450,000.00 4,500,000.00


b)750 x 2555mm No 2 450,000.00 900,000.00
Supply and fixing of the following to doors
-

a) Mortice lockset;UNION ORIGINAL EX . No 12 120,000.00 1,440,000.00


UK;furniture;3 Lever -
b) Brass butt Hinges 100mm long No 36 2,500.00 90,000.00
c) 12.5 x45mm Architrave moulded m 20 10,000.00 200,000.00
d) 15x40mm door stop m 2 10,000.00 20,000.00
-
S/N WORKS DESCRIPTION UNIT QTY RATE AMOUNT
WINDOWS -
GRILL WORK -

Supply fabricate and fixing of windows grills -


complete with Hinges locks and Iron mongery
using 12mm diameter internal partition and
16mm bars for frame work painted red oxide
primer and finished with paint selected
a) 1200 x1700mm High No 10 254,000.00 2,540,000.00
b)900 x 450mm high no 2 58,600.00 117,200.00
c)800 x 450mm high no 2 53,200.00 106,400.00
d) Door vents for Mosquito and wire mesh
No 14 50,000.00 700,000.00

Supply and fixing of window 5mm thick -


clear glass
a) 1200 x1700mm High No 10 367,000.00 3,670,000.00
b)900 x 450mm high no 2 72,900.00 145,800.00
c)800 x 450mm high no 2 64,800.00 129,600.00
-
FINISHING -
Plastering -
a)15mm thick sand cement plastering to
internal walls of the building with lime
plaster or of other approved materials in two
coats steel trawelled to smooth finish m2 205 11,000.00 2,255,000.00

b)Apply sand cement plastering 15mm thick


to external walls of the building m2 112 11,000.00 1,232,000.00

c) Provide and apply 15mm cement and sand


1:4 external rendering to concrete or stone
m2 19 11,000.00 207,900.00
mansory footing

FLOORING -
Cement and sand (1;4) screeds and backings
-

a)40mm thick cement sand screed floor finish


in two coats steel trowelled to a smooth finish
m2 80 23,000.00 1,835,400.00

b)Supply and fixing ceramic floor tile 400mm


x 400mm x 6mm bedded in with adhesive and
joints finished with approved grout matching m2 4 40,000.00 168,000.00
the tiles

c)Ditto to ceramic wall tiles 300mm x 300mm


x 6mm m2 36 40,000.00 1,440,000.00
S/N WORKS DESCRIPTION UNIT QTY RATE AMOUNT
-
External rendering -
Tyrolean rendering in two coats with cement
finish to external walls of the building
m2 112 8,800.00 985,600.00

ELEMENT NO 8-DECORATION -
Painting work -
Prepare the surface and apply 3-coats of
emulsion paint to ceiling board m2 80 7,800.00 624,000.00

Prepare the surface and apply 3-coats of vinyl


silk emulsion paint to internal walls of the m2 205 11,000.00 2,255,000.00
building

Provide and apply 2 coats of bituminous paint


to plinth area of the building
m2 19 9,000.00 171,000.00

Prepare and apply one coat of wood primer


and two finishing coats of gloss oil paint to m 46 9,900.00 455,400.00
fascia board

-
ELELECTRICAL INSTALLATION -
a)Allow for the electrical installation sytem
complete with its fitting, conections and
accessories including builders work make sure
the system operates properly (NB, ALL
ELECTRICAL MATERIAL SHOULD BE
TRONIC PRODUCT. LS 1 4,325,000.00 4,325,000.00

-
PLUMBING AND SEWARAGE SYTEM
-

Plumbing work -
a)Allow for the plumbing sytem complete with
fitting, conections and accessories including
builders work make sure the system operates
properly Item 1 2,500,000.00 2,500,000.00

Supply and fixing of sanitary ware complete


with its fittings fittings connections and -
accessories

a) White vitreous china washing basin


complete no 2 170,000.00 340,000.00

b) white vitreous china W.C no 2 289,000.00 578,000.00


S/N WORKS DESCRIPTION UNIT QTY RATE AMOUNT
c)Stainless steal shower rose no 2 254,000.00 508,000.00
S/N WORKS DESCRIPTION UNIT QTY RATE AMOUNT
Drainage Work -
Supply and fixing of drainage pipe (waste
pipe) to all specified area with fitting,
conection and accessories complete. Make
sure the system operate properly Item 1 750,000.00 750,000.00

Construction of std soak away pit 3600mm


including finishing Item 1 3,789,000.00 3,789,000.00

Construction of std septic tank 3200 x


1500mm with 2400mm deep with all corvers
Item 1 2,800,000.00 2,800,000.00
and proper finishing

Construction of Std man holes and dully traps


Item 1 250,000.00 250,000.00

TOTAL 99,023,500.00
ADD 18% VAT 17,824,230.00
TOTAL GRAND 116,847,730.00

You might also like