HCI Cluster Deployment - Project Plan
HCI Cluster Deployment - Project Plan
Each project may include several milestones and span multiple Service Delivery Kits (SDKs).
Template Version 2022.01
HCI Cluster Deployme
Milestone/Task Description Role
Milestone 1 Predelivery
Gather requirements.
Create containers.
Configure SMTP forwarding.
(Optional) Configure remote sites
2 hours
1 hour
4 days
2 hours
10 minutes
4 hours
.5 hours
3.5 hours
10 minutes
5 minutes
5 minutes
5 minutes
10 minutes
1 hour
10 minutes
10 minutes
5 minutes
.5 hours
1 hour
9 hours
2 hours
2 hours
10 minutes
.5 hours
1 hour
.5 hours
10 minutes
2 hours
.5 hours
9 hours
4 hours
4 hours
1 hour
4 hours
1 hour
1 hour
2 hours
4 hours
2 hours
2 hours
1 day
4 hours
2 hours
Test plan 2 hours
2.5 hours
Project closeout slides,
1 hour
deployment guide
1 hour
5 minutes
Comments
Before you head out, have one last call to confirm with the
client that everything is ready. You can use the final checklist
in the predelivery questionnaire.
Use the Visio templates.
Instructions:
https://portal.nutanix.com/#/page/docs/details?
targetId=Physical_Installation_Guide-
NX1000_NX3050_NX6000_NX7000:setup_rack_mounting_c.
html
https://www.surveymonkey.com/r/NutanixConsultingServicesFeedback