Material Consumption Rate

The document outlines material consumption rate standards or norms for various construction items. It provides the unit of measurement, material components, and quantity of each component required per unit of the work item. Some examples given include 1.25 cubic meters of fill material required per cubic meter of excavation and earth work fill. For concrete work, it specifies the cement, sand, and aggregate quantities in kilograms or cubic meters needed per cubic meter of various concrete grades. The document also provides norms for formwork, reinforcement, masonry work, hollow concrete blocks, brick walls, roofing and cladding, and carpentry items.

Uploaded by

Million Gemechu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
1K views13 pages

Material Consumption Rate

The document outlines material consumption rate standards or norms for various construction items. It provides the unit of measurement, material components, and quantity of each component required per unit of the work item. Some examples given include 1.25 cubic meters of fill material required per cubic meter of excavation and earth work fill. For concrete work, it specifies the cement, sand, and aggregate quantities in kilograms or cubic meters needed per cubic meter of various concrete grades. The document also provides norms for formwork, reinforcement, masonry work, hollow concrete blocks, brick walls, roofing and cladding, and carpentry items.

Uploaded by

Million Gemechu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 13

Material Consumption Rate Standards or Norms

Item Material Component For


Work Item Unit Unit Qty
No. Unit Work Item

02. EXCAVATION AND EARTH


WORK
FILL
1 Fill material sub-base m3 m3 1.25
2 Hard core, 200mm thick m2 Stone m3 0.25
3 Hard core, 200mm thick m2 Crushed stone m3 0.03
Stone m3 0.31
Crushed stone m3 0.04

0.3 CONCRETE WORK IN SITU


CONCRETE
Plain building concrete
1 C-5 m3 Cement kg 150.0
Sand m3 0.48
Aggregate m3 0.72

Reinforced concrete
2 C-10 m3 Cement kg 240.0
Sand m3 0.52
Aggregate m3 1.03

3 C-15 m3 Cement kg 280.0


Sand m3 0.45
Aggregate m3 0.90

4 C-20 m3 Cement kg 280.0


Sand m3 0.45
Aggregate m3 0.90

5 C-25 m3 Cement kg 360.0


Sand m3 0.52
Aggregate m3 0.78

6 C-30 m3 Cement kg 400.0


Sand m3 0.51
Aggregate m3 0.71

7 Light weight concrete m3 Cement kg 250


Pumice m3 1.24

1/13
Material Consumption Rate Standards or Norms

Item Material Component For


Work Item Unit Unit Qty
No. Unit Work Item
Form Work
8 For beams and columns m2 Boards m3 0.013
Batten m3 0.006
Eucalyptus m3 1.05
Nail kg 0.3

9 For Slab m2 Board m3 0.013


Batten m3 0.006
Beams m3 0.005
Props (eucalyptus) ml 1.5
Brace (eucalyptus) ml 1.0
Nail. kg 0.22

10 Reinforcement kg Reinforecement bar kg 1.05


Tying wire kg 0.02

04. MASONRY WORK STONE WALL

1 Concealed form view m3 Stone m3 1.30


Mortar (1:4) m3 0.33
Cement qtls 0.92
Sand m3 0.26
Mortar (1:3) m3 0.33
Cement qtls 1.15
Sand m3 0.25

2 Exposed face (one side)


left for further finish m3 Stone m3 1.40
Mortar (1:4) m3 0.33
Cement qtls 0.92
Sand m3 0.26
Mortar (1:3) m3 0.33
Cement qtls 1.15
Sand m3 0.25

3 Exposed face (both sides)


left for further finish m3 Stone m3 1.50
Mortar (1:4) m3 0.33
Cement qtls 0.92
Sand m3 0.26
Mortar (1:3) m3 0.33
Cement qtls 1.15
Sand m3 0.25

2/13
Material Consumption Rate Standards or Norms

Item Material Component For


Work Item Unit Unit Qty
No. Unit Work Item

HOLOW CONCRETE BLOCK WORK


4 200mm thick m2 H.C.B No. 12.3
Mortar (1:2:9) m3 0.014
Cement qtls 0.0163
Lime qtls 0.044
Sand m3 0.011

5 150mm thick m2 HCB No. 12.3


Mortar (1:2:9) m3 0.011
Cement qtls 0.13
Lime qtls 0.034
Sand m3 0.01

6 100mm thick m2 HCB No. 12.30


Mortar (1:2:9) m3 0.0074
Cement qtls 0.0086
Lime qtls 0.023
Sand m3 0.01

Brick Walls
7 120mm thick m2 Bricks No. 57.70
Mortar (1:2:9) m3 0.0258
Cement qtls 0.03
Lime qtls 0.082
Sand m3 0.019

8 250mm thick m2 Brick No 115.40


Mortar (1:2:9) m3 0.062
Cement qtls 0.072
Lime qtls 0.19
Sand m3 0.05

0.6 ROOF AND WALL CLADDING

1 Roof /wall m2 Sheet m2 1.25


Nails kg 0.076

2 Roof ridge m Cover m 1.05


Nail kg 0.041

3 Gutter m Flat sheet m 1.05


Fixing bracket No 1.05

3/13
Material Consumption Rate Standards or Norms

Item Material Component For


Work Item Unit Unit Qty
No. Unit Work Item
4 Down pipe m Flat sheet m 1.05
Fixing strap No 1.05

0.7 CARPENTRY AND JOINERY

Carpentry
1 Truss No. Upper chord m 1.18
Lower chord m 1.00
Vertical and diagonals m 1.01
Nails kg 0.49

2 Purlin m Purlin m 1.05


Nails kg 0.07

3 Ceiling/soffit m2 Covering meter linear m2 1.05


Batten m 3.71
Eucalyptus braces m 1.23
Eucalyptus suspension m 1.23
Nail kg 0.17

4 Fascia board m Board m 1.10


Nail kg 0.03
Paint It. 0.06

5 Skirting, timber m Board m 1.10


Nail kg 0.05

6 Door No Door set No 1.05

0.9 STRUCTURAL STEEL


1 Truss kg Steel kg 1.05
2 Plates kg Plate kg 1.05
3 Angle ties kg Ties kg 1.05
4 Bolts No. Bolt No. 1.05

10. METAL WORK


1 Metal door ( single leaf) No Door set No. 1.05
Hinge No. 3.0
Key (lock) No. 1.05
Paint Its 0.14

2 Metal window No Window set No. 1.05


Hinge No. 3.0
Key (lock) No. 1.05
Paint Its 0.14

4/13
Material Consumption Rate Standards or Norms

Item Material Component For


Work Item Unit Unit Qty
No. Unit Work Item

11. PLASTER AND POINTING


Two coat of plaster
1 Compomortar m2 Cement qtls 0.056
Lime qtls 0.039
Sand m3 0.017

2 Cement plaster m2 Cement qtls 0.073


Sand m3 0.018

3 Fine coat lime plaster m2 Lime qtls 0.026


Sand m3 0.003

4 Fine coat gypsum plaster m2 Gypsum qtls 0.017


Lime qtls 0.058

5 Fine coat cement plaster m2 Cement qtls 0.019


Sand m3 0.003

6 Final render coat m2 Cement qtls 0.013


Lime qtls 0.032
Sand m3 0.005

Cement Pointing Mortar


Mix,1:3
7 Brick wall m2 Mortar m3 0.0027
Cement qtls 0.0095
Sand m3 0.002

8 Hollow Brick wall m2 Mortar m3 0.0011


Cement qtls 0.0039
Sand m3 0.001

9 Stone wall m2 Mortar m3 0.0036


Cement qtls 0.0126
Sand m3 0.0027

5/13
Material Consumption Rate Standards or Norms

Item Material Component For


Work Item Unit Unit Qty
No. Unit Work Item
12. FLOOR AND WALL FINISH
1 Cement /Terrazzo/ marble
flooring & steps. m2 Tile m2 1.02
Mortar m3 0.0204
Grouting m3 0.001
Cement qtls 0.085
Sand m3 0.015

2 Ceramic wall tile (150x150mm) m2 Tile No. 45.3


Mortar m3 0.0102
White cement grouting m3 0.001
Cement qtls 0.036
Sand m3 0.008

3 Mosaic Tile (27x2mm) m2 Tile m2 1.02


Mortar m3 0.0102
Grouting m3 0.001
Cement qtls 0.036
Sand m3 0.008

Cement Screed
4 Mix 1:2 m3 Mortar m3 1.26
Cement qtls 5.88
Sand m3 0.84

5 Mix 1:3 m3 Mortar m3 1.26


Cement qtls 4.41
Sand m3 0.95

6 Mix 1:4 m3 Mortar m3 1.26


Cement qtls 3.53
Sand m3 1.01

7 PVC tile flooring m2 Tile m2 1.02


Adhesive kg 0.15

Skirting
8 Cement/Terrazzo/ marble m Tile m 1.05
Morar m3 0.0013
Cement qtls 0.0046
Sand m3 0.001

9 PVC m Tile m 1.05

6/13
Material Consumption Rate Standards or Norms

Item Material Component For


Work Item Unit Unit Qty
No. Unit Work Item
Adhesive kg 0.015

10 Stone paving m3 Stone m2 1.05


Sand bed m3 0.105
Mortar m3 0.0378
Cement qtls 0.176
Sand m3 0.025

12. PAINTING
1 Oil paint m2 1st coat lts 0.06
2nd coat lts 0.055
3rd coat lts 0.045

2 Plastic paint. m2 1st coat lts 0.10


2nd coat lts 0.08
3rd coat lts 0.066

3 Synthetic enamel paint m2 Primer lts 0.05


2nd coat lts 0.07
3rd coat lts 0.055

13. GLAZING
1 Glass m2 Glass m2 1.10
Putty kg 0.40

14. SANITARY INSTALLATION


Pipes
1 Galvanized steel m Pipes m 1.05
Joint compound gram 12.0
Hemp gram 6.0
Accessories No. 0.20

2 PVC m Pipes m 1.05


Accessories No. 1.00
Adhesive kg 0.12

Precast Concrete
3 Diameter 100mm m Pipe m 1.05
Mortar, mix 1:2 m3 0.0005
Cement qtls 0.0025
Sand m3 0.001

4 Diameter 150mm m Pipe m 1.05

7/13
Material Consumption Rate Standards or Norms

Item Material Component For


Work Item Unit Unit Qty
No. Unit Work Item
Mortar m3 0.0012
Cement qtls 0.006
Sand m3 0.001

5 Diameter 200mm m Pipe m 1.05


Mortar m3 0.002
Cement qtls 0.009
Sand m3 0.001

6 Diameter 300mm m Pipe m 1.05


Mortar m3 0.003
Cement qtls 0.01
Sand m3 0.002

7 Diameter 400mm m Pipe m 1.05


Mortar m3 0.005
Cement qtls 0.02
Sand m3 0.003

8 Diameter 500mm m Pipe m 1.05


Mortar m3 0.007
Cement qtls 0.03
Sand m3 0.005

9 Diameter 600mm m Pipe m 1.05


Mortar m3 0.01
Cement qtls 0.05
Sand m3 0.007

10 Diameter 800mm m Pipe m 1.05


Mortar m3 0.02
Cement qtls 0.08
Sand m3 0.01

11 Diameter 1000mm m Pipe m 1.05


Mortar m3 0.03
Cement qtls 0.12
Sand m3 0.02

SANITARY FIXTURES

8/13
Material Consumption Rate Standards or Norms

Item Material Component For


Work Item Unit Unit Qty
No. Unit Work Item
12 WC/low flush No. WC No. 1.05
Flexible pipe No. 1.05
Stop cock No. 1.05

13 WC/high flush No. WC No. 1.05


Flexible pipe No. 1.05
Stop cock No. 1.05
Bracket for cistern No. 2.1
Fixer with plug No. 12.6
Hemp kg 0.21
Mortar m3 0.001

14 Squatting pan WC No. Pan No 1.05


Flush cistern with pipe No 1.05
Flexible pipe No 1.05
Stop cock No 1.05
Bracket for cistern No 2.1
Fixer with plug No 8.4
Hemp kg 0.21
Mortar m3 0.05

WASH HAND BASIN


15 WHB No WHB No 1.05
Rubber plug No 1.05
Chain with holder No 1.05
Bracket No 2.10
Fixer with plug No 8.40

16 WHB with pedstal No. WHB No 1.05


Pedestal No 1.05
Rubber plug No 1.05
Chain with holder No 1.05
Fixer with plug (floor) No 4.20
Fixer with plug (wall) No 2.10

17 Urinal No Uninal No 1.05


Fixer with plug 4.20

18 Bath tub No Tub No 1.05


Drain pipe and smell trap No 1.05
Chain, holder and plug No 1.05
Hemp kg 0.12

19 Water heater No Heater No 1.05

9/13
Material Consumption Rate Standards or Norms

Item Material Component For


Work Item Unit Unit Qty
No. Unit Work Item
Chock valve No 1.05
Closing valve No 1.05
Flexible pipe No 2.10
Nipple No 2.10
Hemp kg 0.03
Bolt No 4.20

20 Shower Unit No Shower No 1.05


Drain and smell trap No 1.05
Mortar m3 0.06
Hemp kg 0.12

Sink
21 Single bowl No Sink No 1.05
Chain, holder and plug No 1.05

22 Double bowl No Sink No 1.05


Chain, holder and plug No 2.10

23 Toilet paper holder No Holder No 1.05


Fixer with plug No 2.10

24 Towel Rail/Hook No Rail/Hook No 1.05


Fixer with plug No 2.10

25 Floor drain No Drain No. 1.05


Hemp kg 0.12
Lead kg 0.32

26 Concrete trough No Trough No 1.05


Drain with smell trap No 1.05
Hemp kg 0.12
Mortar m3 0.005
Chain, holder and plug No 0.05

27 Valve No Valve No 1.05


Joint compoung kg 0.04
Hemp kg 0.02

15. ELECTRICAL INSTALLATION

10/13
Material Consumption Rate Standards or Norms

Item Material Component For


Work Item Unit Unit Qty
No. Unit Work Item
Precast Concrete pipe
1 Diameter 100mm m Pipe m 1.05
Mortar, mix 1:2 m3 0.0005
Cement qtls 0.0005
Sand m3 0.001

2 Diameter 150mm m Pipe m 1.15


Mortar m3 0.0012
Cement qtls 0.006
Sand m3 0.001

3 Diameter 200mm ml Pipe m 1.05


Mortar m3 0.002
Cement qtls 0.009
Sand m3 0.001

4 Main distribution board m Box No 1.00


Circuit breaker, 1ph No *
Circuit breaker, 3ph No *
Tumbler switch No *

5 Sub-distribution board m Box No 1.00


Circuit breaker, 1ph No *
Circuit breaker, 3ph No *
Tumbler switch Mo *

6 PVC cable m Cable m 1.05


Conduit m 1.05

Light, Power and Socket outlet


Light, points
7 Residence /Dormitory/ Apartment No Conduit m 2.4
PVC conductors m 4.7
Junction box No 0.5
Connectors No 1.00

8 Workshop /Store/ No Conduit m 10.50


PVC conductors m 21.00
Junctin box No 1.00
Connectors No 1.00

9 Work shop/Store/Continuous No Conduit m 2.00

11/13
Material Consumption Rate Standards or Norms

Item Material Component For


Work Item Unit Unit Qty
No. Unit Work Item
PVC conductor m 4.00
Junction box No 1.00
Connector No 1.00

10 Office No Conduit m 3.70


PVC conductor m 7.70
Junction box No 1.00
Connector No 1.00

Switch
11 Residence/Dormitory/Apartment No Switch No 1.00
Conductor m 4.70
Conduit m 2.40

12 Work Shop /Store/ No Switch No 1.00


Conductor m 24.40
Conduit m 12.20

13 Work Shop /Store/ Continuous No Switch. No 1.00


Conductor m 13.70
Conduit m 6.85

14 Office No Switch No 1.00


Conductor m 3.70
Conduit m 2.00

Socket Outlet
15 Residence/Dormitory/Apartment No Outlet No 1.00
Conductor m 11.20
Conduit m 5.60
Junction box No 1.00

16 Workshop /Store/ No. Outlet No 1.00


Conductor m 33.00
Conduit m 16.50
Junction box No 1.00

17 Office No Outlet No 1.00


Conductor m 10.00
Conduits m 5.00
Junction box No 1.00

18 Bell point No Push button No 1.00

12/13
Material Consumption Rate Standards or Norms

Item Material Component For


Work Item Unit Unit Qty
No. Unit Work Item
Conductor m 4.70
Conduit m 2.40
Junction box No 0.33

19 Fan outlet No Switch No 1.00


Conductor m 5.00
Conduit m 4.00
Junction box No 1.00

20 Telephone outlet No. Switch box No 1.00


Conduit m 4.00

21 TV outlet No. Flat twin TV cable m 8.00


Conduit m 4.00
Junction box No 0.50

FIXTURES
22 Bell system No Buzzer No 1.00
Indicator No 1.00
Transformer No 1.00

23 Fans No Fan No 1.00

24 Air conditioner No Air conditioner No 1.00

25 Light fixtures No Fitting No 1.00

Poles

26 Wood No Wood pole No 1.00

27 Galvanized steel No Galvanized steel No 1.00

13/13