Introduction Importance of Materials Testing
Introduction Importance of Materials Testing
GUEVARRA
Instructor IV
Project Engineer I, Materials Engineer II,
Safety Officer II
QUALITY CONTROL AND ITS SIGNIFICANT
HQ (M+W) = (HQ+E) S
MATERIALS TESTING
PHYSICAL CHEMICAL
COURSE OVERVIEW
OBJECTIVES
METHODOLOGIES
Cement
* Compressive Strength
* Specific Gravity
* Fineness
* Determination of Slump
Paints
MODULE IV
• Sampling and Testing of Asphaltic Materials and
Asphalt Mix
Asphaltic Materials
* Asphalt Cement
* Emulsified Asphalt
* Cutback Asphalt
Ascertain that all materials incorporated into the works pass the
requirements of DPWH Standard Specifications for Highways,
Bridges and Airports and strictly comply with the schedule of
Minimum Testing Requirements.
Submit test reports and other pertinent quality control reports within
the required time frame.
Selection of Materials
Materials shall be obtained from approved materials sources and should be
known in advance so that the required tests can be made to avoid delays in the
construction due possible rejection of unacceptable properties of materials so
that an approved corrective measures could be immediately implemented to
correct the quality of materials prior to its usage.
Information regarding the location of materials sources
that will be incorporated into the work may be
represented by the following:
a.Raw materials such as soil, sand and bank or river gravel
(with little or no processing).
b. Materials that are processed without basically changing
their properties, such as washed manufactured sand,
crushed rock and gravel, and etc.
c. Manufactured materials such as bituminous materials,
cement, paint, structural and reinforcing steel.
d. Combination of materials that may be partly or totally
manufactured, such as bituminous and Portland cement
concrete.
Materials to be procured or obtained from selected portions
of any area of materials sources such as mentioned above
should be known in advance so that the required test can
be made or arrangement for testing the materials involved
may be done to avoid unnecessary delays in construction
due to rejection of unacceptable quality of materials.
Handling and Storage of Materials
Is the process of selecting a part (sample), which will be used to judge the
whole (lot). Sampling of construction materials should be done on the
delivered materials at the project site and not in the place where it was
purchase.
Testing and Inspection in the construction works compliments with each other
and should be done both at the right time as the work progresses.
This practice shows that relationship of personnel in the project are in poor
situation. Construction and Materials personnel have no harmonious relation
and do not cooperate to each other during the implementation of the project.
• Incorporation of Materials into the works without Quality Tests
Construction materials are being incorporated into the works without the
benefit of quality tests.
Testing of materials were not timely done as the work progresses. Testing
are done as only compliance to the requirement of the project for billing
purposes.
Test Reports of materials are not authentic and contains doubtful results.
Materials samples of good quality were taken from good source and not
on the actual delivered materials on site.
Status of monthly test reports are bloated by reporting higher number of test
performed but not yet done just to comply to the required scheduled tests.