Sec 2 Completion Design
Sec 2 Completion Design
1. COMPLETION DESIGN
1.1 INTRODUCTION
In simple terms, the term ‘well completion’ refers to the methods by which a newly drilled
well can be finalised so that reservoir fluids can be produced to surface production facilities
efficiently and safely. In general, the process of completing a well includes the following:
• A method of providing satisfactory communication between the reservoir and the
borehole
• The design of the tubulars (casing and tubing) which will be installed in the well
• An appropriate method of raising reservoir fluids to the surface
• The design, and the installation in the well of the various components used to
allow efficient production, pressure integrity testing, emergency containment of
reservoir fluids, reservoir monitoring, barrier placement, well maintenance and
well kill
• The installation of safety devices and equipment which will automatically shut a
well in the event of a disaster.
In general, a well is the communication link between the surface and the reservoir and it
represents a large percentage of the expenditure in the development of an oil or gas field. It is
of utmost importance that the well be ‘completed’ correctly at the onset, in order that
maximum overall productivity of the field may be obtained. The ideal completion is the lowest
cost completion which will meet the demands placed on it during its producing lifetime.
MECHANICAL CONSIDERATIONS
• Functional requirements
• Operating conditions
• Component design
• Component reliability
• Safety.
Figure 1 shows an example of a north sea drilling and casing schedule the main features are as
follows:
1. The installation of a 30 ins conductor to approx 500 ft. Conductor pipe provides
structural strength, covers soft formations just below the sea bed and is the largest
diameter pipe installed in a well. The hole required to accommodate conductor pipe can
be drilled (onshore) of pile driven (offshore).
2. The installation of 20 ins surface casing which terminates at 1,000 ft total vertical depth.
Surface casing pipe provides protection against shallow gas, seals off shallow water
bearing sands, and provides a base for the BOP stack and the wellhead assembly.
Surface casing is always cemented back to surface.
3. The installation of 133/8 ins intermediate casing which terminates at 4,000 ft total
vertical depth. Intermediate casing pipe is used to protect weak formations; helps
prevent lost circulation of drilling fluids, and hole caving. (In a deep well, more than one
intermediate casing string may be set.) Intermediate casing is usually cemented to a few
hundred feet above the casing shoe of the surface casing string.
4. The installation of 95/8 ins production casing which terminates approx 7,500 ft total
vertical depth. Production casing pipe is used to provide control of the completed well
and is the main string that reaches down to the producing interval(s). Production casing
is usually cemented to a few hundred feet above the casing shoe of the intermediate
casing string.
NOTE: Drilling operations may be resumed to deepen the well and liner casing
installed and hung off from the lower end of the production casing.
Bottom Hole
Completion Advantages Disadvantages
Technique
• No perforating, no production • Liable to ‘sand out’
casing, no cementing expense • No selectivity for production or
• Minimum rig time stimulation
Open Hole • Full diameter hole in the pay • Ability to isolate is limited to the
zone improves productivity lower part of the hole.
• No critical log interpretation is
required.
• No perforating or cementing •
No selectivity for production or
expense for the production stimulation
casing • Cost of slotted liner or pre-
• Assists in preventing sand packed screen
Slotted Liner
production • Difficult to isolate zones for
• No critical log interpretation is production control
required. • Slightly longer completion time
than for open hole completion.
• Introduces flexibility allowing • Requires critical log
isolation of zones and selection interpretation to specify actual
of zones for production or perforation zone
Cased and
Cemented
injection. • Cost of casing/liner and
cementation
• Cost of rig time for longer
completion period.
Table 1 - Bottom Hole Completion Techniques - Advantages And Disadvantages
1.4 PERFORATING
It will be necessary in most cases to perforate a hydrocarbon bearing zone in cased hole
completions in order to realise optimum production. Some wells can flow open-hole but,
where a formation is relatively unconsolidated, flow rates are expected to be high and for
reasons of safety, perforated cased hole completions are usually considered preferable.
Perforating is an operation whereby holes are made through the production casing (or liner)
and its cement sheath into the reservoir to permit oil or gas to flow into the wellbore.
Nowadays, virtually all perforating is performed with shaped charge perforators. Bullet
perforators are occasionally used for particular applications.
As far a completion design is concerned, the following comment cannot be overstated.
‘The fate of a well hinges on years of exploration, months of planning, and weeks of
drilling. But ultimately it depends on perforating the optimal completion, which begins
with the first millisecond of perforating. Profitability is strongly influenced by the critical
link between the reservoir and the wellbore.’
Perforations must provide a clean flow channel between the producing formation and the
wellbore with minimum damage to the producing formation. The ultimate test of the
effectiveness of a perforating system, however, is the well productivity. The productivity of a
perforated completion depends significantly on the geometry of the perforations. The major
geometrical factors (Refer to Figure 4) that determine the efficiency of flow in a perforated
completion are:
• Perforation length
• Shot density
• Angular phasing
• Perforation diameter.
The relative importance of each of these factors on well productivity depends on the type of
completion, formation characteristics, and the extent of formation damage from drilling and
cementing operations. The method of perforating a well must be meticulously planned.
An example of VLP curves for various pipes IDs is shown in Figure 12.
Figure 12 - Typical Vertical Lift Performance (VLP) For Various Tubing Sizes
Matching the VLP curve to the IPR curve (nodal analysis) will identify which ID will be
appropriate for the production required from the well (Refer to Figure 13). Tubing selected on
this basis will optimise flow from the reservoir to production facilities. When depletion of a
reservoir occurs, VLP curves are utilised to determine the new conduit size to match its new
IPR curve.
A completion string that fulfils these functional requirements is illustrated in Figure 14. It is
important to realise this example design is only a solution and not the solution. This design is
called a single zone single string completion.
The completion design of Figure 14 also addresses the other functional requirements of:
• Suspension the tubing
• Compensation for expansion or contraction of the tubing
• Internal erosion of the tubing
• Protection of the reservoir during well kill operations
• Pumping operations for well kill
• Well intervention operations out of the lower end of the tubing
• Pressure integrity testing
• Reservoir monitoring
• Installation points for well barriers.
The component selection for this completion is shown in Table 2.
NOTE: This completion design utilises a permanent packer and tailpipe that will
be installed by wireline techniques or hydraulically via a work string, prior
to running the completion string. (Packer systems will be discussed later.)
Component Function
Tubing support
Tubing hanger Tubing to casing seal
Barrier installation point
Sub-surface safety valve (SSSV) Emergency containment
Flow couplings Tubing protection against internal erosion
Upper side pocket mandrels (SPMs) Unloading annulus liquids
Lowest side pocket mandrel (SPM) Point of gas injection
Tubing to annulus circulation
Sliding side door (SSD)
Barrier installation Point
Pressure testing of tubing string
Landing nipple
Barrier installation point
Protect the casing from well fluids
Retrievable packer
Ensure retrievability of all components
Pressure testing of tubing string
Landing nipple Barrier installation Point
Installation point for plug to set packer
Allows flow of fluid when monitoring reservoir
Perforated joint
performance
Installation point for pressure/temperature gauges
Landing nipple (No-Go)
Catches fallen well intervention tools
Allows unrestricted re-entry of well intervention
Re-entry guide
tools into the tubing
Table 3 - Component Selection For Completion Example 2
NOTE: This completion utilises a retrievable packer that will be run and set in
the casing by the application of pressure to the tubing. (Packer systems
will be discussed later.)
NOTE: In highly deviated wells, it may not be possible to use landing nipples at
inclinations greater than 70°. Wireline operators commonly use landing
nipples for depth references.
NOTE: As with all communication devices, the differential pressure across SSDs
should be known prior to opening.
NOTE: In some areas, the sealing systems between the concentric sleeves are
incompatible with the produced fluids and hence alternative methods of
producing tubing to annulus communication is used (e.g. side pocket
mandrel, tubing perforating).
NOTE: In multi-zone completions, blast joints are commonly used to prevent loss
of tubing string integrity due to external erosion resulting from the jetting
actions directly opposite producing formations.
In most oil operating areas the installation of a safety valve is governed by law.
There are numerous types of safety valves in field operation, but in our case we are going to
concentrate on only four types. Two subsurface controlled, and two surface controlled valves.
NOTE: Both examples are known as ‘Direct Acting’ valves and are classed as
pressure activated devices.
NOTE: Completion strings may also be set in tension to compensate for thermal
expansion of the tubing due to production. Setting a completion in
tension requires pulling the tubing in tension prior to production and
closing rams around a hanger nipple. The hanger nipple is run an
appropriate distance below a ram type tubing hanger (Refer to Figure 27)
and the tension applied to the tubing string to remove tubing from the
well equivalent to that expected from thermal expansion. Setting a
completion in tension requires that the tubing-to-packer arrangement be
appropriate. (Packer systems will be discussed later.)
NOTE: The Xmas Tree is normally connected directly to the tubing hanger spool
that sits on the uppermost casing head spool. The whole assemblage of
Xmas Tree, tubing hanger, and uppermost casing head spool is
sometimes referred to as the wellhead.
A Xmas Tree may be a composite collection of valves or, more commonly nowadays,
constructed from a single block (Refer to Figure 28). The solid block enables the unit to be
smaller and eliminates the danger of leakage from flanges.
Typically, from bottom to top, an Xmas Tree will contain the following valves:
Lower master gate valve Manually operated and used as a last resort to shut in a well.
Upper master gate valve Usually hydraulically operated and also used to shut in a well.
Flow wing valve Manually operated to permit the passage of hydrocarbons to
the production choke.
Kill wing valve Manually operated to permit entry of kill fluid to into the
tubing.
Swab valve Manually operated and used to allow vertical access into the
tubing for well intervention work.
NOTE: Modern Xmas Tree valves are of the gate-valve type that allows full bore
access.
A typical surface wellhead and Xmas Tree are shown in Figure 29.
NOTE: By no means are all wells completed with production packers. However,
for the purposes of this course, only those packers used in well
completions will be discussed.
NOTE: Both the above methods provide a disconnect mechanism from the
setting device. The setting device is removed from the well after the
packer has been set. The completion string is then run into the well and a
seal assembly stabbed into the polished bore of the packer.
NOTE: The tubing may be disconnected from the packer by rotation of the latch
system or by utilising an expansion joint located in the completion
directly above the latch assembly.
NOTE: Seal assemblies of this type can be used without the locating No-Go
shoulder.
Locator seal assemblies do not permit the tubing to be landed in tension. At most the full
tubing weight can be hung off at the tubing hanger. However, when the well is producing, the
temperature of the tubing will increase and the tubing will expand longitudinally. With the
locator seated on the packer, and top of the tubing string fixed in the tubing hanger,
expansion can take place only at the expense of buckling. By using a series of seal subs below
the locator, the tubing can be pulled back a calculated distance (space-out) and then landed,
leaving the locator the same distance above the packer, but with the seal assembly still within
the packer bore. This will allow for tubing expansion or contraction. A completion string may
also be spaced out appropriately if overall cooling of the tubing string will occur e.g. in a water
injection well.
1.9.9 Tubing
Although tubing is the last string of tubulars to be run in the well, its requirements often
dictate the whole well design. Tubing is run mainly to serve as the flow conduit for the
produced fluids. It also serves to isolate these fluids from the ‘A’ (Production) annulus when it
is used in conjunction with a casing packer.
The basic tubing string design criteria are:
• Size, appropriate to producing operations
• Tensile strength
• Stress
• Corrosion resistance.
The American Petroleum Institute (API) identifies, assesses and develops standards for oil and
gas industry goods. Tubing is considered appropriate to API standard if the following
conform to certain specifications:
• Weight per foot
• Length ranges
• Outside diameter
• Wall thickness
• Steel grade
• Method of steel manufacture.
and API standards also specify:
• Physical dimensions of the thread connections
• Performance for burst, collapse and tensile strength of the pipe body and thread
connections.
An API type connection is shown in Figure 36.
API tubing steel grades are identified by letters and numbers which dictate various
characteristics of the steel. For each grade, the number designates the minimum yield strength.
Thus J-55 grade steel has a minimum yield strength of 55,000 psi. In other words, it can
support a stress of 55,000 psi with an elongation of less than 0.5%. The letter in conjunction
with the number designates parameters such as the maximum yield strength and the minimum
ultimate strength which for J-55 pipe is 80,000 psi and 75,000 psi respectively. Table 4 shows
the yield values for various API tubing grades:
Minimum Ultimate
Grade Minimum Yield (psi) Maximum Yield (psi)
Yield (psi)
H-40 40,000 80,000 60,000
J-55 55,000 80,000 75,000
C-75 75,000 90,000 95,000
L-80 80,000 95,000 95,000
N-80 80,000 110,000 100,000
P105 105,000 135,000 120,000
Table 4 - Yield Values For Various API Tubing Grades
Grade C-75 is for hydrogen sulphide service and where a higher strength than J-55 is required.
In addition to API grades, there are many proprietary steel grades which may conform to API
specifications, but which are used extensively for various applications requiring properties
such as:
• Very high tensile strength
• Disproportionately high collapse strength
• Resistance to sulphide stress cracking.
Many tubing strings are run which contain these non-API tubulars. This pipe is made to many
but not all API specifications, with variations in steel grade, wall thickness, outside diameter,
thread connections, and related upset. Due to these variations, the ratings of burst, collapse,
and tensile specifications are non-API.
The type of tubing connections selected for a completion will depend mainly on the well
characteristics. The connection must be able to contain the produced fluids safely and at the
maximum pressures anticipated. The basic requirements of a tubing string connection are:
• Strength compatible with the operational requirements of the string during, and
after running
• Sealing properties suitable for the fluid and pressures expected
• Ease of stabbing during make-up, and safe breakout when pulling the tubing
• Resistance to damage, corrosion, and erosion.
There are two types of thread connection, API and Premium.
Premium connections are proprietary connections that offer premium features not available
on API connections. Most offer a metal-to-metal seal for improved high pressure seal
integrity. Premium connections exist with features such as flush connections, recess free
bores, and special clearance. An example of a premium thread is shown in Figure 37.