MS - BMS
MS - BMS
Date
B & C). RLR-MS-ELE-009 0 24-Nov-2018
METHOD STATEMENT
FOR
INSTALLATION OF BUILDING MANAGEMENT
SYSTEM
Contractor:
RLR
Sub-Contractor:
OMEGA ENGINEERING W.L.L.
Revision History
INDEX SHEET
1.0 PURPOSE.........................................................................................................................3
2.0 SCOPE..............................................................................................................................3
3.0 REFERENCES..................................................................................................................3
4.0 ABBREVIATIONS.............................................................................................................3
5.0 RESOURCES....................................................................................................................4
7.0 PERMITS AND LICENSES...............................................................................................7
8.0 SEQUENCE OF ACTIVITIES............................................................................................7
9.0 QUALITY.........................................................................................................................17
10.0 HSE ISSUES, RISK ASSESSMENT AND HAZARD ANALYSIS..................................17
1.0 PURPOSE
The purpose of this Method Statement is to describe the methodology of carrying out the
construction, quality control and safety aspects related to the installation BMS of Package 1A, 1B
& 1C - Fit out of Cluster (A, B & C), with respect to project specifications and specific scope of
works undertaken under the contractual obligations of the contract.
1.1 This Method Statement is developed based on the detailed design drawings “Issued for
Construction”.
2.0 SCOPE
The scope of this Method Statement is to define the procedures of the Contractor to adopt the
Installation, of “Building Management System (BMS)” as required by the project Package 1A, 1B &
1C - Fit out of Cluster (A, B & C).. The installation procedure shall follow the execution of actual
work at site in accordance with IFC drawings, QCS 2014, project specifications and manufacturer’s
recommended Installation.
3.0 REFERENCES
3.1 Qatar Construction Standards 2014
3.2 Issued For Construction (IFC) Drawings
3.3 Approved Shop Drawings
3.4 British Standards and other applicable standards
4.0 ABBREVIATIONS
4.1 QP - Qatar Petroleum ( Client)
4.2 IFC - Issued for Construction
4.3 ITP - Inspection & Test Plan
4.4 MS - Method Statement
4.5 HSE - Health, Safety and Environment
4.6 PPE - Personal Protective Equipment
4.7 QA/QC - Quality Assurance/Quality Control
4.8 QCS - Qatar Construction Standards
4.9 LV - Low Voltage
4.10 IR - Inspection Request
4.11 MIR - Material Inspection Request
5.0 RESOURCES
5.1 Tools and Equipment
The requirements that will be engaged for installation of Building Management system
works will be as follows:
a. Cable Cutters, Splicers / Strippers
b. Measuring Steel Tape, Ruler Water Level
c. Electrical Tape, Masking Tape,
d. Labeling/Tagging
e. Marker / Chalk
f. Compression Connectors/Terminal Lugs
g. Multi-Tester
h. Screw Drivers, Pliers
i. Lifting Equipment
j. PPE
5.2 Supervision/Manpower
• Project Manager
• QA/QC Engineer
• QC Inspector
• Safety Officer
• Site Electrical Engineer
• Site Electrical Supervisor / Foreman
• Skilled Workers / Helpers.
6.0 RESPONSIBILITIES
6.1 Project Manager
6.1.1 To ensure fulfillment of time and efficient use of company resources, cost target for
project to achieve the completion date within reasonable time.
6.1.2 Responsible under command responsibility for safety and proper planning of
resources at the project site for the welfare of the personnel under his management
involved at the jobsite.
6.1.3 Performs project management functions.
6.1.4 Attend Coordination meeting with Main Contractor as required for the completion of
the project.
6.1.5 Implementation of company procedures and policies at project site.
6.1.6 To ensure fulfillment of allotted time and cost effective target for project.
6.1.7 Shall perform other jobs as maybe required by Top Management.
6.2 QA/QC Engineer QA/QC is part of the quality management, focused on providing the
quality requirements per standards fulfilled with quality of workmanship.
6.2.1 Responsible for the inspections, testing and /or review of test data and quality audit
based on project documentation requirements.
6.2.2 Shall carry out periodic inspection of completed work, review of testing and
commissioning in coordination with the submitted data by site engineer, shall comply
with the project documentation requirements.
6.2.3 Shall perform coordination with the Engineer, Project Manager, Site Engineers, and
Safety Officers for the implementation and compliance with the Safety, Quality
Management System and work standard requirements.
6.3 QC Inspector is part of the quality management, focused on providing the quality
requirements per standards fulfilled with quality of workmanship.
6.3.1 Responsible for the inspections of workmanship for the installation of Building
Management System Works.
6.3.2 Shall carry out day to day inspection of the on-going and completed works, review of
testing and commissioning in coordination with the submitted data by Electrical
Engineer, shall comply with the project documentation requirements.
6.3.3 Shall perform coordination with the QA/QC Engineer, Electrical Engineer, Supervisor
and Safety Officers for the implementation and compliance with the Safety, Quality
Management System and work standard requirements.
6.4 Safety Officer
6.4.1 All safety measures implemented at the job site for handling, transporting,
installations, dismantling, etc. Hazards and risk assessment shall be prepared and
disseminated to all concern, to minimize the occurrence of untoward incident at
jobsite.
6.4.2 Coordination with project managers, QA/QC engineers, site engineers, foremen,
supervisors, workers, client’s representatives, etc. at job site on health and safety
issues.
6.4.3 Shall conduct the tool box meetings and on the spot inspection on daily activities at
jobsite of all personnel to prevent or minimize hazardous condition, unsafe practices,
etc.
6.4.4 Shall be responsible to implement safety rules and regulations and conduct
disciplinary action to those who has repeatedly made defiance to safety matters.
6.4.5 Shall be responsible for first aid treatment and shall coordinate with nearest hospital,
police and fire department in case of accident or emergency.
6.5 Site Electrical Engineer
6.5.1 Review this method statement and monitor its implementation.
6.5.2 Assist site Supervisor/ Foreman on executing the construction activities.
6.5.3 Responsible on overlooking the activities on the project and preparing work progress.
6.5.4 Responsible of implementing all activities that are required as per approved shop
drawings.
6.5.5 Responsible on all work safety during execution.
6.5.6 Conducting daily meeting with Construction team to organize work for the day/next
day.
6.5.7 Coordinate the activities to other trade contractor before implementing at the site.
6.6 Site Supervisor/Foreman
6.6.1 Shall be responsible for the tool box meetings with workers prior to start of work at
job site on day to day activities, the proper storage, handling, installations, cost
effective utilization of construction materials at job sites.
6.6.2 Responsible under command responsibility for the safety and welfare of his site
workers at project job site at every stage of work at job site.
6.6.3 Performs installation/construction of all works in accordance with approved shop
drawings, specifications, standards, Method Statements and quality workmanship.
6.6.4 Coordination with site workers for proper use of material resources and daily work at
the project job site.
6.6.5 Shall maintain good housekeeping at job site upon completion of work. All scrap
materials, rags, debris, etc., shall be properly disposed.
6.7 Skilled Workers/Helpers
6.7.1 Responsible for the safe and efficient performance/works at project job site and
proper utilization of materials. Minimize waste of materials at job site and use the
right tools for the job.
6.7.2 Performs installation/construction of all works in accordance with approved shop
drawings, specifications, standards, Method Statements with quality workmanship.
6.7.3 Coordination with helpers for joint efforts and use of all available resources and daily
activities for the project.
6.7.4 Shall follow all company rules, guidelines, procedures and policies at project site.
MS BUILDING MANAGEMENT SYSTEM Page 6 of 19
Project name : Package 1A, 1B & 1C - Fit out of Cluster (A, Doc. no Rev. no. Date
B & C). RLR-MS-ELE-009 0 24-Nov-2018
6.7.5 Site coordination works of related equipment with other trades at project job site to
ensure efficient use of resources.
6.7.6 Shall maintain good housekeeping at job site upon completion of work. All scrap
materials, rags, debris, etc., shall be properly disposed.
8.2.9 Material found not suitable for site use will be removed from site immediately.
Ensure that necessary containment works are completed before pulling the cables.
For the cable installation, all cables and cable type shall be followed as per approved cable
schedule of individual field device and panels.
Pull the cables in appropriate containment/ ELV tray for field devices and panels as per
approved layout drawing and grease for smooth pulling.
All bare shields should be taped or protected against accidental shorting against electronic
components.
All the cables shall be inspected after installation with approved layout drawing and cable
schedule.
Before installations all wires shall be tested for continuity and insulation resistance by using
multimeter / megger.
Continuity testing shall be done by shorting single core of cable with another core/ shield at
one end and checking the continuity at other open end for same core/shield.
All field devices to be installed in correct location and position as instructed in the shop
drawing & installation details of each instrument as well as instructions from supplier.
Cable Termination.
Prior to pulling of Building Management System Cables, ensure that all containment works
has been inspected and approved by the consultant.
Ensure the routes of Building Management System cables are to be mark based on
approved shop drawings and coordinated with other services.
Cable pulling through conduit manually by using spring wire.
Building Management System cable system wiring shall be done as per the approved cable
specification.
Ensure sufficient length of cable is maintained to connect to the device/panel as per the
approved shop drawings before cutting the cables on the both the sides of conduit.
All cables/wires, pull boxes covers shall be provided with approved cable identification tags
at both ends and labels, respectively.
The protection of cable glands shall be done by providing shrouds wherever required.
All earth wires where cable sheath is removed, yellow/green sleeve to be provided.
Use only appropriate cable crimp terminal lugs for all BMS cables terminated to panels,
devices, etc.
All enclosures and panels related to BMS shall be provided with identification labels.
Any change shall be Red Line in Approved shop drawings and change shall be reflected in
As-Built Drawings.
As per the project requirements after every stage of completion of work (Installation,
termination etc.) should be offered to consultant for inspection /Approval.
8.4.3 Installation of BMS Control Panel, Automation server, Controllers & Field Devices:
Appropriate method and approved material shall be used for holing and connect the
conduits to the panel.
All the labelling of devices and cables shall be in accordance with the approved BMS layout
drawing.
Fix the panel manually in the designated location, check the level and height before
marking.
Drill the marked location, with hummer fix the fisher inside the hole.
Fix the panel using a 10 mm screw with appropriate washer.
Where cables pass through a building structure such as a wall or column, the cables shall
be drawn through PVC sleeves inserted into the building structure.
Cut the cable as per required length with extra allowance for cables at junction boxes and
make the minimum bend that will do termination and arranging inside panel, device
enclosure.
Identification labels shall also be fixed on cables at each entry and exit points.
DDC Enclosure
Figure 1: Figure 2:
Figure 3:
The transmitter is connected with a 2-wire cable. The current is proportional to the
measured humidity and it is measured over an external load resistance R L. The supply
voltage UM is a function of the voltage across the room transmitter UG and the voltage drop
across the load resistor and the wire resistances.
The transmitter is connected with a 3-wire cable. If another load is to be connected close to
the sensor, this should be made with a separate go, so that the measuring signal will not be
affected.
9.0 QUALITY
9.1 Inspection And Testing
9.1.1 The Inspection and Test Plan (ITP) for the installation of BMS materials layout works
summarizes various characteristics to be checked. The concerned Site Engineer will
be responsible to ensure stage wise compliance for these operations and the QA/QC
Engineer will carry out quality control checks and report the inspection results.
9.1.2 ITP will be submitted along with this method statement.
9.2 Documentation
9.2.1 The Site Inspection Request (IR) of various activities of BMS materials layout works
will be submitted to RLR in advance with adequate notice. Consultant Inspection
Requests Form shall be followed for all materials layout works activities.
9.2.2 Variance work activities will be checked and the QA/QC Engineer will be responsible
for completing Inspection Requests for these activities. Recorded in related
checklists.
10.4 Site Engineer will ensure that all involved personnel are briefed on the nature of work and
associated hazards, and to verify the compliance with the required Personal Protective
Equipment for the tasked works at all times during construction activities.
10.5 Regular compliance inspections by the Site Engineer and HSE department will take place
throughout the works.
10.6 Safety signs shall be provided to guide the movement of workers, & safety awareness to all.
10.7 During night works, a suitably trained supervisor will be on site throughout the work duration
and adequate lighting shall be provided.
10.8 All site activities involving worker, operators at exposed areas during hot weather season
shall adhere to the control measures as per the project heat stress programmed and local
regulation in state of Qatar.
10.9 Emergency response plan procedures shall be strictly followed in the applicable events; a
competent emergency responses coordinator will be nominated for the site; while first
aiders and fire wardens will be deployed, assembly and muster points shall be clearly
identified and fire drills will be conducted regularly.
10.10 Adequate rest shelters, cooled drinking water and toilet facilities shall be provided.
10.11 Work area to be completely barricaded and permits related to the work being done, and
to ensure that no works are performed unless the relevant permits are in place.
10.12 No specific environmental hazards identified outside the scope of the Construction
Environmental Management Plan.
10.13 The Site Specific Risk Assessment.