PICM Change Request BRFplus Application
PICM Change Request BRFplus Application
BRFplus Application
This document contains help to understand how BRFplus application works behind the change request
approval process in Project Issue and Change Management.
In the standard system, SAP delivers the following activity categories for the definition of
approval activity types and activity templates:
• Approval activity
• Cost planning activity
Process
1. Create a cost estimation alternative to plan costs for the change request (type CRC).
2. Create a cost planning activity (activity type CR1).
3. Plan the details of the change in the change planning workbook of the Project Cost and
Revenue Planning application.
4. Mark the status of the cost estimation alternative as ready for approval.
Note
o When multiple cost estimation alternatives exist for a change request, you can
only mark one as ready for approval.
o The cost of the change corresponding to the cost estimation alternative marked as
ready for approval, is the value that is considered in the Pending Costs column in
the Project Cost Status report.
5. Mark the status of the cost planning activity as complete.
6. Upon saving the object, the system automatically creates an internal approval activity for
the change request and assigns an employee responsible according to the rules defined in
Business Rule Framework plus (BRFplus).
7. The system sends an e-mail notification to the employee responsible.
8. The employee responsible approves the internal approval activity.
9. Upon saving the object, the system creates an external approval activity for the change
request and assigns an employee responsible according to the rules defined in BRFplus.
10. The system sends an e-mail notification to the employee responsible.
Note
Note
The cost of the change corresponding to the cost estimation alternative marked as
approved, is the value that is considered in the Approved Costs column in the Project
Cost Status report.
12. The system marks the change request as approved and also updates existing forecasts
with the approved quantities and costs.
13. If you have assigned any purchase order as a reference object to the change request, the
system updates the purchase order, if you have activated the Business Add-In BAdI:
Updating of Purchase Orders with Additional Quantities
(/PICM/BADI_UPDATE_DOCUMENT). This BAdI allows you to add material quantity
in existing purchase orders (POs) by using approved change requests. This BAdI checks
the PO for the original quantity, based on the reference object assigned to the change
request. For the addition of an approved material quantity, a new line item is added in the
PO.
1. Check if Cost Planning Activity is set to ‘In Process’; Set change request status to ‘In Process’.
2. Check if Internal Approval Activity is completed and External Activity does not exists; Set Cost
Estimation Alternative status to ‘Internally Approved’
3. Check if Internal Approval Activity is completed; Create External Approval Activity
4. Check if external activity status is approved; Set Cost Estimation Alternative status and Change
Request status to ‘Approved’.
5. If Internal Approval or External Approval activity is rejected; Set Cost Planning Activity status to
‘Rejected’ and Cost Estimation Alternative status to ‘In Process’.
In this rule set we are setting Cost Estimation Alternative to ‘In Process’ as soon as it is created.
This rule set contains Approval Matrix /PICM/APPROVAL_MATRIX for defining and processing business
rules.
If cost planning is done for Cost Estimation Alternative on change request screen matches the criteria
maintained in approval mattrix for Estaimated Cost and Estimated Margin; Associated Role ID will be
picked up and respective business partner will be assigned to the employee responsible of the approval
activity.