Weekly Planning

The document contains weekly planning schedules for construction work at the CBD Thube Park site between August 10th and October 2nd. It outlines activities such as wall construction, reinforcement work, shuttering, and casting at different levels of the building over multiple weeks. Percentage completion updates are provided for many of the activities.

Uploaded by

Amrish Duri
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
93 views

Weekly Planning

The document contains weekly planning schedules for construction work at the CBD Thube Park site between August 10th and October 2nd. It outlines activities such as wall construction, reinforcement work, shuttering, and casting at different levels of the building over multiple weeks. Percentage completion updates are provided for many of the activities.

Uploaded by

Amrish Duri
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 7

TEJUS Infratech LLP

SITE NAME :- CBD,THUBE PARK


DATE:-10.08.022 TO 20.08.022
WEEKLY PLANNING
WEEK NO 02 & 03
SR.NO ACTIVITY START DATE END DATE DAYS REMARK
UPPER PARKING R. WALL 27M
1 UPTO 2.4MTR HEIGHT 12.08.022 17.08.022 6 100% COMPLETED
REINFORCEMENT
LIFT WALL SHUTTERING 2.4MTR
2 HEIGHT 11.08.022 16.08.022 6 100% COMPLETED

COLUMN W1,W2
3 W3,W4,W5,W6,W11,C5 ,C6 ,REINF 11.08.022 16.08.022 6 100% COMPLETED
ORCEMNT 2.4MTR HEIGHT
W7,W8 COL. 0.8 HEIGHT
4 SHUTTERING 14.08.022 16.08.022 3 100% COMPLETED

C5 & C6 SHUTTERING UP TO
5 2.4MTR HEIGHT 14.08.022 16.08.022 3 100% COMPLETED

6 R WALL RW4 SHUTTERING 17.08.022 20.08.022 4 100% COMPLETED


2.4MTR HEIGHT
7 RW10 WALL REINFORCEMENT 17.08.022 18.08.022 2 100% COMPLETED
TEJUS Infratech LLP
SITE NAME :- CBD,THUBE PARK
DATE:-21.08.022 TO 27.08.022
WEEKLY PLANNING
WEEK NO 04
SR.NO ACTIVITY START DATE END DATE DAYS REMARK

1 RW4 WALL DESHUTTERING WORK. 23.08.022 24.08.022 2 100% COMPLETED

2 BACKFILLING RAMP AREA 24.08.022 26.08.022 3 10% COMPLETED

RW4 2ND LIFT REINFORCEMENT


3 WORK 24.08.022 26.08.022 3 100% COMPLETED

LIFT WALL 2ND LIFT


4 REINFORCEMENT WORK 21.08.022 23.08.022 3 100% COMPLETED

5 C5 & C6 2ND LIFT REINFORCEMENT 21.08.022 22.08.022 2 100% COMPLETED


WORK.
MAIN STAIRCASE SHUTTERING & WORK IN
6 REINFORCEMENT WORK 1ST 22.08.022 27.08.022 6 PROGRESS
FLIGHT.
C5 & C6 2ND LIFT SHUTTERING
7 WORK. 22.08.022 24.08.022 3 C6 BALANCE
TEJUS Infratech LLP
SITE NAME :- CBD,THUBE PARK
DATE:-28.08.022 TO 03.09.022
WEEKLY PLANNING
WEEK NO 05
SR.NO ACTIVITY START DATE END DATE DAYS REMARK
RW4 WALL 2ND LIFT SHUTTERING
1 WORK. 23.08.022 24.08.022 2 100% COMPLETED

2 BACKFILLING RAMP AREA 26.08.022 1.09.022 7 50% COMPLETED

RW3 SHUTTERING & CASTING


3 28.08.022 31.8.2022 4 100% COMPLETED
WORK 1ST LIFT ABOVE 1.5 MTR

C6 2ND LIFT REINFORCEMENT &


4 SHUTTERING & CASTING 28.08.022 30.08.022 3 100% COMPLETED

STAIRCASE 1ST FLIGHT


5 SHUTTERING & REINFORCEMENT 26.08.022 01.09.022 7 100% COMPLETED
& CASTING

PIT PARKING DRESSING,MUCKING


6 & SIDE PCC 28.8.2022 29.8.2022 2 100% COMPLETED

7 PIT PARKING W12,13 FOOTING 30.8.2022 31.8.2022 2 100% COMPLETED


BELOW RAFT HDPE SHEET LAYING
PIT PARKING W12,13 FOOTING &
8 RETAINING WALL RW1 1.9.2022 6.9.2022 6 60% COMPLETED
REAINFORCEMENT
9 FIRE TANK PLUM CONCRETE 3.9.2022 6.9.2022 4
TEJUS Infratech LLP
SITE NAME :- CBD,THUBE PARK
DATE:-04.09.022 TO 10.09.022
WEEKLY PLANNING
WEEK NO 06
SR.NO ACTIVITY START DATE END DATE DAYS REMARK
Pit Parking W12,W13,RW1 & RW
1 10 Footing & Raft casting 9/6/2022 9/7/2022 2 100 % done

50% done - BOBCAT


2 Backfilling Ramp & lift area 9/3/2022 9/10/2022 8 ISSUE
Footing W10,W9,W18 & raft
3 mucking, Pcc & Waterproofing 9/3/2022 9/10/2022 8 breaking not done
Work
not done due to
4 Fire tank plum Concrete 9/7/2022 9/10/2022 4 backfilling
obstruction

Ramp Slab Reinforcement &


5 casting 9/8/2022 9/10/2022 3 decision hold

UGWT W8 wall reinfrocement &


6 shuttering work 9/3/2022 9/10/2022 8 50 % done

7 Tie Beam Shuttering, 9/3/2022 9/10/2022 8 100 % done


Reinforcement

8 RW1, RW10 W12 & W13 9/7/2022 9/10/2022 4 100 % done


Shuttering work upto 2.4 mtr level
TEJUS Infratech LLP
SITE NAME :- CBD,THUBE PARK
DATE:- 17/10/2022 TO 21/10/2022
WEEKLY PLANNING
OCT 22 - 3rd WEEK
SR.NO ACTIVITY START DATE END DATE DAYS REMARK

RW 2 2ND LIFT STEEL


1 REINFORCEMENT , SHUTTERING 10/17/2022 10/19/2022 3
AND CASTING WORK

ABOVE FIRE TANK SLAB RW 3


2 AREA STEEL REINFORCEMENT 10/17/2022 10/21/2022 5
WORK AND CASTING WORK

W10,W18, COLUMN 2ND LIFT


3 SHUTTERING WORK AND CASTING 10/17/2022 10/19/2022 4
WORK

DOMESTIC TANK ABOVE RAFT


4 BOTTOM SLAB SHUTTERING WORK 10/18/2022 10/21/2022 4

RW 4 TO RW 3 AREA RAMP SLAB


5 STEEL REINFORCEMENT WORK 10/17/2022 10/21/2022 5
AND CASTING WORK
TEJUS Infratech LLP
SITE NAME :- CBD,THUBE PARK
DATE:-18.9.2022 TO 25.9.2022
WEEKLY PLANNING
SEP 22 - 4TH WEEK
SR.NO ACTIVITY START DATE END DATE DAYS REMARK

RW1,W12 & W13 2nd LAYER 100


1 SHUTTERING & CASTING 12.9.2022 23.9.2022 12 COMPLITED%

PIT PARKING PART 1 PLUM


2 CONCRETE WITH RUBBLE 19.9.2022 21.9.2022 3 100
COMPLITED%
SHIFTING

3 RW 4 NORTH SIDE CASTING & 20.9.2022 21.9.2022 2 100


DESHUTTERING COMPLITED%

FIRE TANK PLUM CONCRETE 2ND 100


4 LAYER 19.9.2022 21.9.2022 3 COMPLITED%
COMBINED FOOTING W10,W9 &
6 W18 PCC , WATER PROOFING & 20.9.2022 26.9.2022 6 50 COMPLITED
REAINFORCEMENT %

NEAR COMBINED FOOTING RAFT 100


7 AREA BREAKING 20.9.2022 24.9.2022 4 COMPLITED%

8 RAMP SLAB SHUTTERING 21.9.2022 24.9.2022 4 50%


COMPLITED
TEJUS Infratech LLP
SITE NAME :- CBD,THUBE PARK
DATE:-26.9.2022 TO 2.10.2022
WEEKLY PLANNING
SEP 22 - 5TH WEEK
SR.NO ACTIVITY START DATE END DATE DAYS REMARK
COMBINED FOOTING W10,W9 &
1 REAINFORCEMENT,SHUTTERING & 27.9.2022 1.10.2022 6 100%
CASTING

2 FIRE TANK RAMP SLAB 25.9.2022 28.9.2022 4 80%


SHUTTERING

3 RAMP SLAB REAINFORCEMENT 29.9.2022 1.9.2022 4 0%

4 RW1 & W12,13 COLUMN 3RD 26.9.2022 29.9.2022 4 100%


LAYER SHUTTERING & CASTING
W14 FOOTING AREA EXCAVATED
5 MATERIAL SHIFTING WORK BY 27.9.2022 1.9.2022 6 70%
MINI POCKLANE