Epoxy Data Rate Analysis
Epoxy Data Rate Analysis
B Labour component:-
Tile layer (Sl No. 24/ page No. 1) No’s/day 6.00 486.22 2,917.32
Mazdoor (Heavy) (Sl. No. 5/ page No. 1) No’s/day 6.00 476.22 2,857.32
Mazdoor (Light) (Sl. No. 5/ page No. 1) No’s/day 6.00 476.22 2,857.32
Hire charges for cutting machine Sl. No.
53/1073/XXXXIX No’s/day 6.00 364.00 2,184.00
Hire charges for grout pump/ agitator machine Sl. No.
67/1088/XXXXIX No’s/day 6.00 613.00 3,678.00
Total Rs 14,493.96
C Other Charges:-
Add overheads @ 10% on (A + B) 7,620.40
Add Contractor profit @10% on (A + B) 7,620.40
Total Rs 15,240.79
ABSTRACT:-
A Material Component:- Rs 61,710.00
B Labour component:- Rs 14,493.96
C Other Charges:- Rs 15,240.79
Total Rs. 91,444.75