Epoxy Data Rate Analysis

This document provides a cost estimate for tile grouting work over an area of 100 square meters. It estimates the materials, labor, and other costs. The materials include 22 kilograms of epoxy-based tile grout at a cost of Rs. 61,710. Labor costs of Rs. 14,493.96 include tile layers, manual laborers, and equipment hire charges. Other charges of Rs. 15,240.79 account for overheads and contractor profit. The total estimated cost is Rs. 91,444.75, which works out to a cost of Rs. 914 per square meter.

Uploaded by

hscl
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
2K views

Epoxy Data Rate Analysis

This document provides a cost estimate for tile grouting work over an area of 100 square meters. It estimates the materials, labor, and other costs. The materials include 22 kilograms of epoxy-based tile grout at a cost of Rs. 61,710. Labor costs of Rs. 14,493.96 include tile layers, manual laborers, and equipment hire charges. Other charges of Rs. 15,240.79 account for overheads and contractor profit. The total estimated cost is Rs. 91,444.75, which works out to a cost of Rs. 914 per square meter.

Uploaded by

hscl
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Data rate for epoxy based tile grouting

Assume an area of Tile grouting 100Sqm 100.00 Sqm

Roff Rainbow Tile mate Epoxy based - (Hardener, Base


& Filler) with a coverage of 0.22 Kgs/sqm 22.00 Kgs
A Material Component:-
Roff Rainbow Tile mate Epoxy based - (Hardener, Base
1 & Filler) Kgs 22.00 2,500.00 55,000.00
Total 55,000.00
Wastages at 10% on above towards quick setting Kgs 2.20 5,500.00
Total (A) 60,500.00
Loading and unloading charges from factory to workspot
charges @ 1% (A) 605.00
Transportation charges @1% (A) 605.00
Total Rs. 61,710.00

B Labour component:-
Tile layer (Sl No. 24/ page No. 1) No’s/day 6.00 486.22 2,917.32
Mazdoor (Heavy) (Sl. No. 5/ page No. 1) No’s/day 6.00 476.22 2,857.32
Mazdoor (Light) (Sl. No. 5/ page No. 1) No’s/day 6.00 476.22 2,857.32
Hire charges for cutting machine Sl. No.
53/1073/XXXXIX No’s/day 6.00 364.00 2,184.00
Hire charges for grout pump/ agitator machine Sl. No.
67/1088/XXXXIX No’s/day 6.00 613.00 3,678.00
Total Rs 14,493.96

C Other Charges:-
Add overheads @ 10% on (A + B) 7,620.40
Add Contractor profit @10% on (A + B) 7,620.40
Total Rs 15,240.79

ABSTRACT:-
A Material Component:- Rs 61,710.00
B Labour component:- Rs 14,493.96
C Other Charges:- Rs 15,240.79
Total Rs. 91,444.75

Total Amount Rs 91,444.75


Cost per Sqm Rs 914.45
Cost per Sqm - Rounding off Rs. 914.00