Studying The Requirements of (TPM) Total Productive Maintenance in Production System
Studying The Requirements of (TPM) Total Productive Maintenance in Production System
net/publication/319881719
CITATIONS READS
2 2,953
1 author:
Mohanad Sahib
University of Technology, Iraq
2 PUBLICATIONS 2 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Mohanad Sahib on 04 June 2018.
BY
Mohanad A. Sahib
M.Sc. Industrial Engineering
Supervised by
I
CONTENT
Abstract I
Content II
List of Figures VI
List of Tables VIII
List of Abbreviations IX
List of Symbols X
Chapter One
Background and Research Objectives
1.1 Introduction 1
1.2 Research Environment 4
1.3 Research Objectives 6
1.4 Thesis Organization 6
Chapter Two
Framework of TPM Strategy, Literature Survey and
Methodology
2.1 Introduction 9
2.2 Definitions of TPM 9
2.3 TPM Goals and Benefits 10
2.4 TPM Pillars 11
2.4.1 5S 12
2.4.2 Autonomous Maintenance 13
2.4.3 KaiZen 15
2.4.4 Planned Maintenance 16
2.4.5 Quality Maintenance 17
2.4.6 Training 18
II
2.4.7 Office TPM 19
2.4.8 Safety, Health and Environment 19
2.6 Comparison of JIT, TQM and TPM 20
2.6 TPM Tools/ Metrices 22
2.6.1 Overall Equipment Effectiveness (OEE) 22
2.6.2 Overall Resource Effectiveness (ORE) 24
2.6.2.1 Readiness (R) 26
2.6.2.2 Availability of facility (Af) 26
2.6.2.3 Changeover Efficiency (C) 27
2.6.2.4 Availability of material (Am) 27
2.6.2.5 Availability of manpower (Amp) 28
2.6.2.6 Performance Efficiency (P) 28
2.6.2.7 Quality Rate (Q) 28
2.7 TPM Implementation Phases 29
2.7.1 Awareness Phase 29
2.7.2 Organization Phase 30
2.7.3 Planning Phase 30
2.7.4 Implementation Phase 31
2.7.5 Assessment Phase 32
2.8 Challenges and Success factors of TPM Implementation 33
2.9 Literature Survey 34
2.10 Research Limitations 40
2.11 Proposed TPM Methodology 41
2.12 Concluding Remarks 42
Chapter Three
Case Study: Application of The Proposed Methodology
3.1 Introduction 44
III
3.2 Production Line No. Five/ Al-Forat Factory 44
3.3Analysis of Maintenance Activities for Production Line Five 49
3.4 Production Line No. Five Breakdowns 50
3.1 Concluding Remarks 51
Chapter Four
Analysis of Results and Discussion
4.1 Introduction 53
4.3 Analysis of Production Line Five 53
4.4 Employing TPM Tools for Production Line Five: 61
4.4.1 OEE Tool for Line Five 62
4.4.2 PRE Tool for Line Five 70
4.4.2.1 Readiness (R) Value 70
4.4.2.2 Availability of Facility (Af) Value 70
4.4.2.3 Changeover Efficiency (C) Value 71
4.4.2.4 Availability of Material (Am) Value 72
4.4.2.5 Availability of Manpower (Amp) Value 73
4.4.2.6 Performance Rate (P) Value 73
4.4.2.7 Quality Rate (Q) Value 73
4.5 OEE Software 79
4.5.1 OEE Software Input 79
4.5.1.1 Data Validation Sheet 79
4.5.1.2 Log Sheet 80
4.5.2 OEE Software Output 81
4.5.2.1 OEE Data Sheet 81
4.5.2.2 Dash Board Sheet 82
4.6 Proposed TPM Implementation 83
4.7 Concluding Remarks 86
IV
Chapter Five
Conclusions and Recommendations for Future Work
5.1 Introduction 89
5.2 Research Summary 89
5.3 Conclusions 89
5.4 Recommendations for Future Work 90
References 93
List of Figures
Figure Page
Figure
Number No.
Figure (1-1) Evolution of Different Maintenance Strategies 3
Figure (2-1) Eight Pillars of TPM 12
Figure (2-2) 5Ss Method 13
Relationships between TPM and Lean Manufacturing
Figure (2-3) 20
building blocks
Figure (2-4) OEE based on six major production losses 24
Figure (2-6) TPM Implementation Phases 29
Figure (2-7) I operate and I fix flow chart 33
Figure (2-8) Proposed TPM Methodology 41
Flow Diagram for Production Line No. Five/ Al-Forat
Figure (3-1) 47
Factory
Figure (3-2) Production Line Machines in 3D 48
Figure (3-3) Detailed Planned Maintenance Activities Time Line 49
Figure (3-4) Pareto Chart for production line breakdowns (Jan – May) 50
V
Figure (4-1) Production data During 2015 56
Difference Between Planned and Breakdown Times on
Figure (4-2) 57
2014
Difference Between Planned and Breakdown Times on
Figure (4-3) 57
2015
Differences Between Designed operating and Actual
Figure (4-4) 58
production Times on 2014
Differences Between Designed operating and Actual
Figure (4-5) 58
production Times on 2015
Figure (4-6) Actual Production and Defective Products in 2014 59
Figure (4-7) Actual Production and Defective Products in 2015 60
Categories of Defective Products According to Process
Figure (4-8) 61
(Jan – May) 2015
Figure (4-9) OEE Factors in 2014 65
Figure (4-10) OEE Factors in 2015 65
Figure (4-11) OEE for Two Operational Speeds in 2014 67
Figure (4-12) OEE values for high speed during (2014) and (2015) years 68
Figure (4-13) Total OEE percentage during 2014 and 2015 69
Figure (4-14) Set-Up time during (2014) and (2015) years 72
Figure (4-15) ORE values during 2014 76
Figure (4-16) ORE values during 2015 77
Figure (4-17) OEE and ORE in 2014 78
Figure (4-18) OEE and ORE in 2015 78
Figure (4-19) Sample of Log Sheet Data of OEE Software 80
Figure (4-20) OEE Data Window of OEE Software 81
Figure (4-21) Sample of OEE software charts 82
Figure (4-22) Sample of Waterfall Chart for August 2014 83
Figure (4-23) Proposed TPM Implementation 84
VI
List of Tables
Page
Table No. Table
No.
Table (1-1) Comparison Between Maintenance Strategies 5
Table (2-1) Direct and Indirect Benefits of TPM 11
Table (2-2) Autonomous Maintenance steps 15
Required Ability from operator and maintenance
Table (2-3) 18
workers
Table (2-4) Comparison among JIT, TQM, and TPM 21
Table (2-5) Classifications of ORE losses 25
Detailed production processes of line five / Al-Forat
Table (3-1) 46
factory
Table (4-1) Production Data during (2014) and (2015) years 54
Table (4-2) OEE Values for Production Line Five During 2014 63
Table (4-3) OEE Values for Production Line Five During 2015 64
Comparison Between OEE World Class and the
Table (4-4) 70
Resulted Values for Line Five
Table (4-5) Set-Up Time for (2014) and (2015) years 71
Table (4-6) ORE Values of (2014) year 74
Table (4-7) ORE Values of (2015) year 74
Effect of AM and 5Ss implementation on production
Table (4-8) 86
line five
VII
List of Abbreviations
Af Availability of facility
AM Autonomous Maintenance
Am Availability of materials
Amp Availability of manpower
API Active Pharmaceutical Ingredient
CBM Condition Based Maintenance
CMMS Computerized Maintenance Management System
JIPM Japan Institute of Plant Maintenance
JIT Just-In-Time
MTBF Mean Time Between Failure
MTTR Mean Time To Repair
OEE Overall Equipment Effectiveness
OPE Overall Plant Efficiency
ORE Overall Resource Effectiveness
P Performance
PLC Programmable Logic Control
PM Planned Maintenance
Q Quality
QC Quality Control
R Readiness
RBM Reliability Based Maintenance
SHE Safety, Health, Environment
SMDP Semi-Markov Decision Process
SMED Single Minute Exchange of Die
TA Technical Availability
TEEP Total Effective Equipment Performance
TPM Total Productive Maintenance
VIII
TQM Total Quality Maintenance
UOM Unit of Measure
List of Symbols
A Morning shift
B Night shift
CO2 Carbon Dioxide
hr. Hour
L Litter
Max. Maximum
Min. Minimum
ml Milliliter
IX
Chapter One
Background and Research Objectives
1.1 Introduction
The purpose of this chapter is to outline a general overview
about TPM and maintenance. Describe the environment of
implementation and specify the objectives that needs to be
accomplished to solve the research problems.
After the improvements in production strategies and the
flexibility of production lines, it becomes important to find better
maintenance strategy especially in the areas of automation and large-
scale mechanization [1, 2]. Therefore, manufacturing organizations
employed several strategies to improve maintenance effectiveness,
such as Total Productive Maintenance (TPM) [3]. Decreasing
maintenance cost is one of TPM goals and the traditional maintenance
could represent 15% to 40% of the production cost [4].
TΡM implementation strategy delivers organizations with a
guide to fundamentally convert their shop floor by participating
process, technology and culture [5]. The impression is to acquire
competitive advantage by eliminating all stoppages in the processes,
predicting potential breakdowns, insulating them and including
operators with maintenance team in preventive maintenance activities
[6, 7].
The benefits realized throughout effective TPM implementation
strategy encompassed Overall Equipment Effectiveness (OEE)
advancements by 14˗45 %, inventory decrease by 45 ˗ 58 % and
improvement in workshop productivity by 22 ˗ 41%. For example,
Nissan Motor decreased breakdowns by 80%, defects by 85% and
inventory by 55% during the first three years of TPM implementation
[1].
1
Chapter One
Maintenance is defined as: “all activities aimed at keeping an
item in or restoring it to the physical state considered necessary for the
fulfillment of its production function”, while the maintenance concept
is “a set of maintenance policies and actions of various types and the
general decision structure in which these are planned and supported”
[1, 3]. Maintenance is evolved as shown in Fig. (1.1).
The evolution begins with “Reactive” maintenance where the
majority of labor hours are reactive in nature and the organization is in
constant firefighting behavior. It is also called breakdown or run to
failure maintenance. Then, the improvements process setting the
expectation that all maintenance actions should be “Planned”. Planned
maintenance is also called preventive maintenance that is
implemented at fixed intervals by repair, service or component change
[9].
Further improvements have been executed to reach “Predictive”
maintenance. This type focuses on assessing the condition of the asset
throughout the analysis of vibration, oil, voltages, quality, etc. It is
also referred to Condition Based Maintenance (CBM). While the
predictive maintenance employs condition monitoring to help in
predicting the failure occurrence, it doesn't always identify the root
cause of the failure. Maintenance strategies continue to mature
towards, “Proactive” strategy, which focuses on finding the root cause
of failure and aiming to eliminate its occurrence again by making
necessary changes in production, operation or construction. It is also
called Reliability Based Maintenance (RBM).
2
Chapter One
3
Chapter One
The best in class concept now reached the “strategic” or
“Enterprise” concept. “Enterprise" refers to the scope of the assets
across departments, locations, facilities and, potentially, business
units. It is helpful for those companies having multiple sites which a
shared vision of knowledge and coordination is required, such as
Total Productive Maintenance (TPM) that involves everyone in the
organization with overall view on maintenance and production
departments [10]. Detailed description of maintenance strategies and
their advantages, disadvantages and definitions is shown in Table
(1.1).
1.2 Research Environment
This study is a case study of TPM implementation at Baghdad
Company for Soft Drinks that investigate and analyze the efficiency
of production system. The study also offers a proposed methodology
for TPM implementation. The company works using continuous
production system and consists of two factories, each one includes
four production lines [8]. Some of the production lines are new and it
has been provided and installed by Germans “KRONES” Company
that is contracted with Baghdad Company for implementing the
planned maintenance.
In spite of mentioned, the process industry at the company was
facing many stoppages, breakdowns, losses and wastes especially in
Production Line Number Five in (Al-Forat factory) as it is the largest,
highest in productivity, most dependable and most recent production
line that launched its production in 2009 to produce different flavors
of soft drinks in a plastic bottles with a maximum production of
768,000 bottles a day.
4
Chapter One
Table (1.1) Comparison Between Maintenance Strategies
Maintenance
Definition Advantages Disadvantages
Strategy
-High production
-No condition downtime.
Reactive maintenance is repairs that
monitoring related -High cost of spare parts.
are employed when equipment’s are
Reactive costs. -High risk of secondary
already broken down (also known as
-Machines are not failure.
“breakdown maintenance”).
over maintained. -Inefficient use of staff
resources.
-Maintenance is
-There are still
performed in
unscheduled breakdowns.
Actions performed on a time or controlled manner.
-Machines are repaired
machine run based on schedule that -Increased equipment
Planned when there are no faults.
detect, prevent or reduce degradation life cycle.
- Potential for incidental
of component or system. -Reducing
damages in conducting
unexpected
unneeded maintenance.
machinery failures.
-unexpected
breakdowns are
reduced.
Measurements that detect the onset of
-Parts are ordered -Additional skills are
system degradation (lower functional
when needed. required.
state), thereby allowing causal
-Equipment life is -High investment in
Predictive stressors to be eliminated or
extended. diagnostic equipment.
controlled prior to any significant
-Decrease in costs for - High investment in staff
deterioration in the component
parts and labor. training.
physical state.
-Maintenance is
performed when
convenient.
-Reduce downtime.
Stabilizing the reliability of machines
-Improve equipment
or equipment. The purpose of
reliability. - Additional skills are
proactive maintenance is to view
Proactive -Equipment life is required.
machine failure and similar problems
extended. - High investment cost.
as something that can be anticipated
-Reduce overall
and dealt with before they occur.
maintenance cost.
5
Chapter One
1.3 Research Objectives
This research investigates the requirements of implementing
total productive maintenance in a production system with the aim of
increasing productivity and equipment availability throughout
following steps:
1- Exploring TPM pillars and tools and analyzing the requirements
for each one.
2- Diagnosing the current production and maintenance activities in
(Al-Forat factory) for the production line (No. five) as a case study
at Baghdad Company for soft drinks.
3- Specifying the deviation of production activities towards
improving equipment’s availability and increasing productivity.
4- Developing methodology towards TPM implementation in the
above mentioned production line.
6
Chapter One
Chapter Four: Developed TPM methodology is introduced.
Collected data for two consecutive years (2014, 2015) are analyzed
throughout TPM tools (OEE, ORE) and OEE software version 13.1 is
further employed. TPM implementation time line is proposed
throughout 32 months starting from January 2017.
7
Chapter Two
Framework of TPM Strategy, Literature
Survey and Methodology
2.1 Introduction
TPM is a Japanese strategy; that was developed based on the
productive maintenance concept in 1970’s by Nippon Denso Co. Ltd.
of Japan, a supplier of M/s Toyota Motor Company, aiming in
maximizing equipment effectiveness .TPM seeks to maximize the
overall effectiveness of production throughout engaging all functions
and levels in an organization. TPM endeavors to uncover the hidden
capacity of ineffective and reliable equipment’s. The highest priority
of TPM activities is to improve production by reducing unplanned
stoppages and improving equipment availability [1].
TPM focuses on addressing the six main losses and wastes
correlated with production systems through affecting uninterrupted
and systematic evaluations, which will have effect on significant
improvements in production facilities. The evaluation of TPM
efficiency can facilitate significantly enhanced organizational
capabilities across various dimensions [11].
2.2 Definitions of TPM
There are many different definitions for TPM and the reason
behind this diversity is found in the adoption way of this strategy,
since some industries focus on teams working more than equipment
management, while other focus on equipment effectiveness [14].
9
Chapter Two
Nakajima defined TPM “as an innovative approach to maintenance
that optimizes equipment effectiveness, eliminates breakdowns, and
promotes autonomous maintenance by operators through day-to-day
activities involving the total workforce” [12].
While Edward Willmott claims that: "TPM seeks to engender a
company-wide approach towards achieving a standard of performance
in manufacturing, in terms of the overall effectiveness of equipment,
machines and processes, which is truly world class" [7].
2.3 TPM Goals and Benefits
TPM is a key element for lean manufacturing, thus, the big goal of
TPM is to reduce the six big losses in the production and to operate
equipment according to its designed capability. TPM takes the quality
in consideration towards zero product defect rate, which means no
production scrap or defect, no breakdown, no accident, no waste in the
process running or changeover. Some of the major TPM goals are:
[14, 15, 16].
Improving Overall Equipment Effectiveness (OEE).
Improving maintenance efficiency and effectiveness by involving
operators in daily maintenance to achieve autonomous maintenance.
Educating and training personnel: through involving everyone in
the company.
Designing and managing equipment for maintenance prevention as
the suggestions of operators and maintenance technicians may help
engineering design to specify and procure more effective
equipment.
10
Chapter Two
The benefits gained from the implementation of TPM can be
classified and organized into direct and indirect benefits as shown in
Table (2.1).
Table (2.1) Direct and Indirect Benefits of TPM [7, 17, 18]
Direct Benefits Indirect Benefits
Reduction in breakdowns by (65-78) %. Higher confidence level among the
Reduction in defects and rework by (65- employees.
80) %.
Reduction in the manufacturing and Clean, neat and attractive work place.
maintenance cost (18-45) %.
Delivering the right quantity at the right
time, in the required quality).
Reduction in accidents by (90-98) %. Favorable change in the attitude of the
Reduction in energy costs by (8-27) %. operators and increase in employee
suggestions by (32-65) %.
Reduction in customer complaints by Enhancing job satisfaction by creating
(50-75) %. a pleasant work environment and a
Increase in productivity and OEE better employees’ involvement
(Overall Equipment Effectiveness) by (sharing knowledge and skills through
(14-45) %. team working).
11
Chapter Two
2.4.1 5Ss
5Ss is a Japanese foundation pillar of TPM including Seiri (sort,
organization), Seiton (set in order), Seiso (shine, cleaning), Seiketsu
(standardize the cleaning), and Shitsuke (sustain, discipline) and
referred to as the five keys to a total quality environment. 5Ss is a
systematic method to reduce waste and optimize productivity and
quality throughout maintaining an orderly workplace and using visual
signals to achieve more consistent operational results. 5Ss are used to
organize, order, clean, standardize the workplace and keep it that way
to achieve a serene environment in the work place involving the
employees with a commitment to sincerely implement and practice
housekeeping behavior. Cleaning and organizing the workplace helps
the team to uncover problems, making problems visible is the first
step of improvement. If 5Ss method is not taken up seriously, this will
12
Chapter Two
lead to 5D (Delay, Defect, Dissatisfied customers, Declining profit,
and Demoralized employees) [22, 23], Fig. (2.2) shows the 5Ss.
13
Chapter Two
lubrication, whereas more difficult problem can be fixed only by a
skilled operator. The operators employ small maintenance activities
that may avoid the equipment’s from decline [13, 14].
If the operators are trained to carry out these basic activities,
that will raise their skill degree, give them additional responsibility for
the operation of the tool, increases their job prospects, and frees up the
technicians to work on extra complex activities.
Adopting “clean and inspect” procedures, may teach them how
to recognize abnormal operation and identify problems. Over time, as
the operators’ skill increases, the AM teams will progress to further
complex maintenance and ensure optimum machines availability [24,
25].
AM could be implemented gradually in seven well-defined
steps as described in Table (2-2). These seven steps are taken over an
agreed and achievable time span.
The benefits realized from AM are; [26].
a- The operators experience a sense of pride and ownership of their
machines.
b- Safer and easier to work around machines and work areas.
c- Reducing breakdowns, defects and other losses.
d- Reducing cost of doing the job.
14
Chapter Two
Table (2.2) Autonomous Maintenance Steps [25, 26]
Steps Activities
Eliminating causes of
2- Carrying outer – measures the
contamination by dust, dirt, etc.
source of the problem.
Optimization of accessibility.
Development of behavioral
3- Developing and implementing standards which quickly assure
cleaning and lubrication standards. continues cleaning, greasing and
adjusting of machine parts.
Instruction and training in
inspection capabilities.
4- General inspection routines.
Identification and elimination of
minor abnormalities.
Production and appliance of
5- Autonomous inspection. control.
Sheets for Autonomous inspection.
Standardization of logistics, data
6- Organization and tidiness. recording, process quality, molds
and tools.
Continuous improvement of
7- Full autonomous maintenance.
machines.
2.4.3 KAІZEN
“Kai” is intended change, and “Zen” is intended good (towards
improvement), principally kaizen is introduced for minor
developments, but handled on continuous origin and should include
entire persons in the institute. Kaizen pillar is practice concept of zero
losses in every activity to achieve cost reduction target in all
resources, improve overall plant equipment effectiveness and focus on
easy handling of operators. Kaizen requires no or little investment
15
Chapter Two
through very large number of small improvements is more effective in
an organizational environment than few improvements of large value.
This pillar is intended to reduce losses in the workshop which
affect efficiency using kaizen tools. Kaizen improving actions are not
restricted to production areas but can also be applied in administrative
areas as well.
Tools used in Kaizen pillar are: Why-Why analysis, poka-Yoke (is
Japanese term means ‘mistake proofing’ or error prevention) [27].
16
Chapter Two
Supporting and guidance to AM by planning efficient and effective
preventive, predictive and time based maintenance over equipment
life cycle.
Establishing planned maintenance check sheets.
Increase Mean Time Between Failures (MTBF), Reduce Mean
Time to Repair (MTTR). MTBF is the average time that the system
or component functions between breakdowns. MTTR is the
average time required to troubleshoot and fix failed equipment and
get it back to its normal operating conditions.
Lubricating.
Cleaning of workplace, machines, tools etc.
Inspecting.
17
Chapter Two
2.4.6 Training
Training is an integral part of TΡM, operators and maintenance
workers training help to eliminate breakdowns that occurred due to
unavailability of skill. Training will allow operators to maintain their
machines and recognize failure occurrence and they may propose
methods to avoid the failure from happening again. The JIPM
encapsulates the ability that is necessary from the operator and the
maintenance workers as summarized in Table (2.3); [28].
Table (2.3) Required Ability from operator and maintenance workers [24]
18
Chapter Two
2.4.7 Office ƮPM
Office TPM pillar should learn and promote the strategy of the
organization to make an efficient working office that improves
productivity and eliminates losses. Office TPM aims to make the
production system effective throughout the entire structural activities.
It must deliver required support for production actions and other
sections in order to decrease cost, building up competitive control and
improve the synergy between various business functions.
The effective administration impetus is to create effective
administrative processes by focusing on addressing cost-related
issues, waste and also developing a work process that can handle
changes [12, 14].
19
Chapter Two
2.5 Comparison of JIT, TQM and TPM
TPM strategy originated from Japan to support its lean
manufacturing system, since reliable and operative equipment are
crucial pre-requısite for applying lean manufacturing system in
establishments. Fig (2.3) shows the associations between TPM and
lean manufacturing structure.
TPM is the corner stone activity for most of the lean
manufacturing strategies and can effectively contribute towards
success of lean manufacturing. 5S’s and Kaizen were the foundations
of JIT, TQM, and TPM, whereas Poka-yoke and preventive
maintenance are the basics of JIT and TPM. Kanban seemed to be the
key of JIT whereas visual control is essential for TPM. Lastly, QC
tools are the vital tools for TQM. [29].
20
Chapter Two
The factors supporting JIT, TQM, and TPM are quite similar.
They are administrator deployment, team employment, and employee
involvement. JIT extends the supporting factors to JIT flow and pull
system whereas TQM does education and TPM does maintenance
activities. There are seven Wastes in JIT, which are waste from
overproduction, waste of waiting time, transportation waste, inventory
waste, waste of motion, waste from product defects and waste of over
processing [30].
The main objectives of JIT, TQM, and TPM, which are quite similar,
are cost reduction and quality enhancement. Table (2.4) shows the
similarities and differences among JIT, TQM, and TPM [29].
Table (2.4) Comparison among JIT, TQM, and TPM
Characteristic JIT TQM TPM
-Zero inventory.
-Cost down and quality -Increase machine
-Lead time reduction.
Objective improvement. efficiency
-Defective rate
reduction.
-Machine and
Focus Operator Management Machine management
operator management
7 Wastes:
- Overproduction.
- Waiting time.
-Defects. -Machine breakdown.
- Transportation.
Waste -Inventory. -Set up time.
- Inventory.
-Defects.
- Motion.
- Product defects.
- Over processing.
-Multi skilled -Self-maintenance
-Educated workers.
workers. workers.
Employees -Employee
-Employee -Employee
involvement.
involvement. involvement.
21
Chapter Two
2.6 TPM Tools/ Metrics
There are a number of tools that are used in TPM evaluation
and selection of the right tool depends on the available requirements
of implementation. These tools are used to analyze, discover losses
and check the performance of the machines to propose solutions for
the effectiveness problems.
TPM uses the following tools/ Metrics to analyze and solve the
equipment and process related problems: Overall Equipment
Effectiveness (OEE), Overall Plant Efficiency (OPE), Overall
Resource Effectiveness (ORE), Single Minute Exchange Die
(SMED), Pareto Analysis, Statistical Process Control SΡC – Control
Charts, etc. problem solving techniques; Brainstorming, Cause and
Effect Diagrams and 5-M Approach. Team based problem solving;
Poka-Yoke Systems, Setup Time Reduction, Bottleneck Analysis,
Recognition and Reward Program and Simulation [1, 24].
22
Chapter Two
Creating cross-functional crews for solving the root reasons/problems
can initiate great developments and create real bottom-line earnings.
OEE is a productivity development process that begins with
management mindfulness of total productive manufacturing and their
promise to focus on the factory work force in training in teamwork
and cross-functional equipment problem solving [16, 24].
OEE is intended by gaining the availability of the equipment,
performance rate process efficiency and quality rate [16]. OEE can be
used as a benchmark for matching the initial and enhanced
performance of a manufacturing plant, thus quantifying the level of
improvement made [31]. The six big losses, which are counted
significant in dropping the production system efficiency, are;
equipment failure/breakdown, setup and adjustment, idling and minor
stoppage, reduced speed, defect and rework, and start-up losses [7,
24]. The calculation of OEE considering the impact of the six major
losses in production system is shown in Fig. (2.4).
–
Availability 100% (2-1)
/
Performance rate 100% (2-3)
23
Chapter Two
24
Chapter Two
Overall Equipment Effectiveness (OEE) is adjusted as “Overall
Resource Effectiveness” (ORE) meanwhile it reports the losses related
with the resources (man, machine, material, method) separately.
Inclusion of these new factors enables additional exhaustive and
stratified classification of the resource losses [36, 37]. Classification
of losses is shown in Table (2.5).
Table (2.5) Classifications of ORE Losses [36]
25
Chapter Two
companies are facing materials and parts absences like spare parts
[36].
Overall Resource Effectiveness (ORE) is the level of
effectiveness in which uses all the resources, equipment, operators,
technicians, floor management, and support systems [35].
ORE is calculated according to equation (2-7) below and the seven
ORE factors are; [36, 37];-
ORE = R × Af × Am × Amp × P × Q × C (2-7)
2.6.2.1 Readiness (R)
Readiness (R) factor “is related with the total time that the
system is not ready for operation because of planned downtime due to
preparatory/ planned activities”. Readiness indicates the ratio of
planned production time to the total time available.
Planned downtime includes; preliminary effort like cleaning, checkup
of machine, initial part inspection, lubrication, tightening, data
collection and updating meeting, audit, operator training. Readiness
could be calculated according equations below: [36]; -
Readiness R (2-8)
Where;
26
Chapter Two
and instruments, test rigs related to facility where it could be
calculated according to equations below; [37] ;-
Availability of Facility Af (2-10)
Where;
Where;
Operation time = Loading time - Setup and adjustments (2-13)
2.6.2.4 Availability of material (Am)
In manufacturing systems, occasionally, raw materials,
components and sub-assemblies are not available causing shortage of
materials. The availability of material (Am) measure is related with
the total time that the system is not operating due to material. Material
shortage include; non-availability of raw materials, consumables,
parts and sub-assemblies and non-availability of Work In Process
(WIP). Availability of material addresses the material shortage
separately to initiate action on the external and internal suppliers. Am
is calculated as shown below; [36, 37];-
Availability of Materials (A) = (2-14)
27
Chapter Two
Where;
Running Time = Operating Time – Materials Shortages (2-15)
2.6.2.5 Availability of manpower (Amp)
The operator(s) may not exist at work center due to absence,
discussions, etc. The Availability of manpower (Amp) is the total
time that the system is not operating because of manpower absence
which includes; permission, leave and absenteeism, discussion with
supervisor, team leader and medical related issues. These could be
measured to find the actual running time as shown in equations below;
[36, 37];-
Availability of Manpower (Amp) = (2-16)
Where;
Actual Running Time= Running Time– Manpower absence
Time (2-17)
2.6.2.6 Performance Efficiency (P)
Performance efficiency measures speed losses that include any
factors which cause the process to operate at less than its maximum
possible operating speed [34].
2.6.2.7 Quality rate (Q)
Quality rate takes into account quality loss that produces
products which doesn’t meet quality standards including rework
products [35]. Both of the performance and quality factors are
calculated using the same equations of the OEE tool as shown
previously in equations (2-3) and (2-5).
28
Chapter Two
2.7 TPM Implementation Phases
TPM could be implemented in every organization (production,
health, management, service, etc.) depending on the size, type, people,
effort, management and the way of implementation. Some
organizations may not implement all TPM pillars but only specific
pillars depending on the available requirements of implementation.
The choice of the tool used in TPM implementation is selected
depending on many factors that could give the required results. The
evaluation of overall effectiveness before and after TPM
implementation is important to check the progress of the result. Five
phases are required to implement TPM which are shown in Fig. (2.6)
[4, 39];
Phase 1 Awareness
Phase 2: Organization
Phase 3: Planning
Phase 4: Implementation
29
Chapter Two
2.7.1 Awareness Phase
The objective of this phase is to present TPM strategy and basic
ideologies to the team management and get their promise and support
for the TPM activities. It aims to increase machines knowledge and
find problems which have not been found before. TPM awareness
program includes the following activities [3, 7];-
Unwanted things and equipment are eliminated.
Overall cleaning is achieved to eliminate dirt and dust
Joining meetings, workshops and discussions on TPM and making a
library of TPM books.
Literatures visiting companies which applied TPM, requesting
consultants and TPM specialists to lecture in the facility arranging
and supplying an in-house introductory course on TPM to the
management crew.
Careful grouping of senior equipment, process engineers assessing
the current status of the equipment management system, holding
staff discussions to detect problems and brainstorming potential
clarifications.
2.7.2 Organization Phase
The goal of this phase is to generate an organizational structure
that promotes, plans, implements, and supports TPM at all levels in
the organization. At this phase all the causes of infection, dirt and oil,
are removed. The places which are hard to clean and examine are
rearranged or re-assembled to allow access [39].
2.7.3 Planning Phase
In order to implement this phase, equipment’s conditions
should be dependable and the operating conditions are consistent.
30
Chapter Two
Equipment life span can be accurately estimated, mechanics and
operators can plan periodic inspections and renovations.
This phase begins to determine the best type and interval of
inspections and repairs. Decisions are made frequently in
organizations that establish a preventive maintenance program. In
addition, operators should be trained on the cause-and-effect
relationship between the process and product quality.
Then, on-line tracking of process characteristics allow the
operators to detect equipment’s deterioration before it creates product-
quality problems. This phase presents standards for cleaning, oiling
and maintenance to make sure that the cleaning is achieved
successfully. Problem areas are investigated to identify the areas
where lubrication is ineffective. The process will also be documented
for auditing purposes, and monitor the situation before and after
cleaning [4, 39].
2.7.4 Implementation Phase
In order to offer the organization with hands-on knowledge,
TPM council decides to initiate an implementation process throughout
TPM pilot team. This is a single team working on, perhaps a single
machine and completing all TPM activities to improve its
performance. Pilot team has to develop the right way to get things
done in its own organization. The main criteria used for selecting
equipment suitable for the pilot TPM strategy are [4, 20];-
Importance to the customers.
Capacity constraints.
Great breakdown frequency.
Pretty new no backup system in place level of difficulty reliable with
the rest of the production line high visibility within the organization.
31
Chapter Two
The skill acquired through the pilot project can be used to
adjust the planning process and define resources required for TPM
employment.
In addition, correct selection of equipment and team members in the
pilot project can result in significant development in equipment
performance within a relatively short period of time. At this phase the
personnel training and advisement in basic controlling functions of
machines will be done to make sure that employees have the ability in
performing easy maintenance tasks and they are aware about machine
functions that they are working with [39].
2.7.5 Assessment Phase
This phase amounts to the standards and learning attained by
training at the third and fourth phases of implementation and it’s the
time for operator to start implementing basic examination and
maintenance tasks autonomously. The objectives of the assessment
system are [4];-
Authenticate the evolution made in TPM improvement activities
against exact oak.
Calculate the level of TPM maturity in the organization.
Explain areas of strength and weakness in the implementation
process.
Integrate TPM improvement projects in the organization’s business
plan.
Assess institute readiness to apply for a Plant Maintenance award.
32
Chapter Two
That’s because this concept invites external maintenance staff to bring
the machine back to its operative condition [39, 40].
33
Chapter Two
No sufficient resources (people, money, time, etc.) and assistance
provided.
Lack of management support and understanding of the strategy.
Lack of sufficient training.
Lack of structure and relationship to strategic needs.
Lack of necessary mixture of skills and experienced in TPM team.
Typically, people show strong resistance to change.
34
Chapter Two
Result revealed improvements in; maintenance efficiency, operational
routines for planning of maintenance activities, work order system,
planning and routines for condition control, maintenance key
measurements and daily planning [2].
35
Chapter Two
cleaning standards was established and he clarified problems which
needed to be replaced or fixed [11].
36
Chapter Two
Singh, J. et al implemented TPM at automobile industry in
India. Four TPM pillars are employed in the research are; 5S,
autonomous maintenance, Kaizen; planned maintenance. OEE is
employed and results at the company showed (58.7%) value but after
one year of TPM implementation it was shown a progress until OEE
became (70%) value. This indicates increasing in equipment
availability, decrease in defectives and rework and increase in
performance rate [21].
37
Chapter Two
Maintenance, Education and Training pillars. They reported that after
one year of implementation significate improvements were observed
in; reduction in time loss by (50%), increase in availability by (13%),
increase in MTBF period and reduction in MTTR [45].
38
Chapter Two
months of implementation the company achieved (83.95%) in OEE.
They claimed that successful implementation of TPM needs two years
or more of effective time. They reported that TPM implementation
provided better communication among the different departments at all
levels that led to an increase in team working spirit among the
employees and healthy organizational environment [50].
39
Chapter Two
company achieved about (93%) in quality rate, (87%) in availability
and (87.5%) in performance efficiency [55].
40
Chapter Two
2.11 Proposed TPM Methodology
Fig. (2.8) shows the proposed methodology of implementing TPM,
since implementing TPM requires defining the production big losses in
TPM reveal tools there should be forward/backward information exchange
that could reveal the big losses as well as identifying the relevant pillar(s).
41
Chapter Two
2.11 Concluding Remarks
1- TPM is a strategic maintenance concept that improves the overall
production of any organization.
2- The big goal of TPM is to reduce the six big losses in the
production and to operate equipment according to its designed
capability.
3- Different tools are used to analyze, discover losses and check the
performance of the machines to propose solutions for the
effectiveness problems.
4- TPM could be implemented according to five phases using TPM
pillars and appropriate tools to evaluate the existing and improved
results.
5- Office TPM plays crucial role in providing the required support for
production activities and other departments and improve the
synergy between various business functions.
42
Chapter Three
Case Study: Application of The Proposed
Methodology
3.1 Introduction
Baghdad Company for Soft Drinks was established at 1989
with a capital investment of 70 Million Iraqi Dinars. The company
produces different flavors of soft drinks according to the
specifications of International PepsiCo Inc. The products are
produced in different types and volumes packed in plastic, glass or
cans depending on production line type and the market need. There
are eight production lines in this company in (Al- Forat and Dijlah
factories). Baghdad Company covers 85% of local market needs, see
Appendix C. The production is continuous and the company imports
raw materials from certain companies from inside and outside Iraq
according to International PepsiCo Inc. specifications requirements.
The raw materials include; chemical components, flavors, containers,
CO2, cans …etc. The company works in two shifts a day during 24
hours, 12 hour for each shift during seven days a week. Products
volumes are; 250ml, 355ml, 750ml, 2.25L and 1.75L [8].
44
Chapter Three
“KRONES” [German Company] throughout contract until year 2021.
This production line is the newest, largest in size and the highest in
productivity.
As shown in Fig. (3.1), the production line starts with the raw
materials (ampoules) and moves by mechanical conveyer. These
materials are stored beside the blowing machine. After that, the bottles
are moved using air pressure conveyor to reach the filling room; this
room consists of 3 inputs as shown in Fig. (3.1), first input is from the
hot blowing stage, second input is from the mixing machine that feeds
the filling machine according to the flavor type, and bottle top covers
are introduced into the machine through a mechanical conveyer. Then
the first inspection stage will check the filling level by using X-ray
inspection and the defected ones will by pushed away to a container
right away. Different arrows in Fig. (3.1) depict different
transportation media.
45
Chapter Three
Table (3.1) Detailed production processes of line five / Al-Forat factory
Inspection Stage No. one X-ray inspection for the filling level.
46
Chapter Three
Fig. (3.1) Flow Diagram for Production Line No. Five/ Al-Forat Factory
47
Chapter Three
The bottles are passed to a hot air fan blower in order to be
labeled in the next process; the labels are changed according to the
type of product. Then the bottles passed to the second stage of
inspection to check the alignment of the sticker by using X-ray
inspection. The bottles will be pocketed and inspected. For more
clarification about the production line diagram Fig. (3.2) shows the
types of production line machines in 3D.
48
Chapter Three
3.3 Analysis of Maintenance Activities for Production Line
Five
This line is served by Iraqi maintenance staff (eight persons) in
each shift that employs maintenance for the production line after
machine failure (Breakdown Maintenance). Implementation of
planned maintenance by KRONES Company takes about three weeks
to maintain and check and restart the machines after maintenance
completion. Throughout this research, two planned maintenances
were accomplished, the first one has been done in March 2015
according to the company request in spite of that the production line
didn’t reach the 5000 operating hours since last planned maintenance
in December 2014. The time line for implementing planned
maintenance in March 2015 is shown in Fig. (3.3) in detailed
activities.
4 Days Overall check for production line *
7 Days Changing all the defective parts of the machines
Activity
4 Days Lubrications, changing oil and filters *
Setting up the machines and test them 6 Days
Time
(Days)
49
Chapter Three
In the previous figure, all maintenance activities are done by
expert German staff to make an overhaul of all the production line.
The activities noted by star symbol are those kinds of activities that
could be done by Iraqi staff and will be discussed later in chapter four.
3.4 Production Line No. Five Breakdowns
Data are collected along two years in 2014 and 2015
respectively. Although the production lines are new; but a lot of
stoppages and losses occurred in these lines. The company [8]
claimed that production line number five in (Al-Forat factory) is
facing the highest stoppages and losses.
In spite of that the data are collected for the years 2014 and
2015 for this study but, the production line breakdowns are classified
throughout 2015 only. The production line suffers from many
breakdowns. These breakdowns vary where Pareto chart will clarify
each type as shown in Fig. (3.4);
186 60.0
200
167
50.0
150
118 40.0
93 30.0
100
20.0
50
10.0
0 0.0
Mechanical Measurments Material Manpower Methods Others
50
Chapter Three
From the previous Fig. it could be noticed that 50% of the
failures are due to mechanical and measurements causes.
51
Chapter Four
Analysis of Results and Discussion
4.1 Introduction
Each company, organization, production line, etc. in different
areas have requirements that should be cleared and investigated to see
which pillars needs to be implemented and how it can add value.
4.2 Analysis of Production Line Five
Actual production data are collected from the company during
2014 and 2015 for two shifts and both speeds (2333 bottle/hr. and
4000 bottle/hr.) which are shown in Table (4.1).
53
Chapter Four
Table (4.1) Production Data during (2014) and (2015) years
Actual Actual
Designed Planned
Breakdown Production Production Defects
Month Operating Downtime
Time (hr.) Time (hr.) Quantity (bottles)
Time (hr.) (hr.)
(bottles/hr.)
January 720 422 109.7 188.3 452837 7510
February 720 250 170 342.3 792392 13380
March 720 295 127.7 297.3 808618 15139
April 720 444 96 180 446309 9277
2014 May 720 343 197 180 1031792 16065
June 720 272 141 307 812994 12882
July 720 381 212 127 890014 17679
August 720 87 206 427 1098452 18984
September 720 113.5 246 360.5 1019091 16271
October 720 233.5 293 193.5 1041701 15013
November 720 189 260 271 753247 11425
December 168 82 39 47 158868 2790
Average 260 175 244 775526 13035
54
Chapter Four
Breakdown time is the time that the production line is down because
of failure.
Actual production time is the time that production line is producing
products.
Actual production is the amount of defective and non-defective
products.
55
Chapter Four
the planned is (8%) of the designed quantity. While Fig (4.1 B) shows
the percentage of the actual production times is about (28%).
34560000,
6873348, Production Quantity Production Times
11%
2%
Planned Production Designed OPERATING
for One Year TIME
Average Planned
Designed 381, 28% Downtime
Production for One Average Breackdown
Year 720, 52%
Time
27648000
0, 87% Avarage Production
Average Actual
for One Year
118, 8% Production Time
160, 12%
Fig. (4.1 A) Production Quantity Taxonomy in bottles Fig (4.1 B) Average of Production Times in hours
56
Chapter Four
600
550
500
450
400
350
Hours
300
250
200
150
100
50
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
600
550
500
450
400
Hours
350
300
250
200
150
100
50
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
57
Chapter Four
750
700
650
600
550
500
450
400
350
Hours
300
250
200
150
100
50
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fig. (4.4) Differences Between Designed operating and Actual production Times in 2014
750
700
650
600
550
500
Hours
450
400
350
300
250
200
150
100
50
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fig. (4.5) Differences Between Designed operating and Actual production Times in 2015
58
Chapter Four
Figs (4.6) and (4.7) below show a comparison between the
actual production and defective products for 2014 and 2015
respectively.
It can be seen in Fig. (4.7) that April 2015 has the maximum
production which is exactly after implementing the planned
maintenance in March and it has the maximum breakdown time for
the same year.
It can be seen that maximum defective products occurred during
summer season in August for 2014 and 2015 which are (18984
bottles) and (23596 bottles) respectively.
Annual defective rates are 1.5% in 2014 and 2% in 2015. While the
company defective threshold is 2% annually.
It should be mentioned that the defective products are increasing
whenever the production speed is increased.
1200000 1098452
1031792 10190911041701
1000000
890014
792392 808618 812994
753247
800000
Bottle
600000
452837 446309
400000
158868
200000
7510 13380 15139 9277 16065 12882 17679 18984 16271 15013 11425 2790
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
59
Chapter Four
1200000
1000000 951767
867154
480314
406082
400000
177148
200000 97010
10269 14899 10448 17883 8318 17061 14271 23596 12574 22339 5322 2546
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
60
Chapter Four
January February
15% 17%
5% Hot Blowing 11% Hot Blowing
8% Leabiling Leabiling
72% 64%
Packegeing Packegeing
8%
Inspection Inspection
March April
20% 17%
Hot Blowing Hot Blowing
15%
Leabiling Leabiling
56% 54%
15% Packegeing Packegeing
9% Inspection 14% Inspection
May
27% Hot Blowing
45%
Leabiling
Packegeing
16%
Inspection
12%
61
Chapter Four
are not covered by OEE to enable decision makers initiating
improvements actions according to the related losses.
62
Chapter Four
Table (4.2) OEE Values for Production Line Five During 2014
Availability Performance Quality OEE
Month Speed [bottle/hr.]
% % % %
4000 27 14 98 4
Jan.
2333 23 17 97 5.5
4000 40 19 97 7
Feb.
2333 29 33 97 9
4000 31 19 98 5
Mar.
2333 49 43 97 20
4000 18 10.5 97 1
Apr.
2333 43.5 36.5 97 15
4000 41 31.4 98 12.6
May.
2333 31 28.5 98 8
4000 33 23.3 98 7
Jun.
2014 2333 62.3 38.6 97.5 23.4
4000 36 28.2 97.5 9
Jul.
2333 20 15.5 97.5 3
4000 60 45.3 96 26.4
Aug.
2333 56.3 45.6 96 25
4000 48.7 34.5 98 16.4
Sep.
2333 50 40 97.5 19.5
4000 36.7 32 98 11.5
Oct.
2333 36 22 98 7
4000 29.3 24.6 97 6
Nov.
2333 37 29 97 10
4000 26 16 97 4
Dec.
2333 31 23 98 6
Average 37 28 97 11
63
Chapter Four
Table (4.3) OEE Values for Production Line Five During 2015
Availability Performance Quality OEE
Month Speed [bottle/hr.]
% % % %
4000 38.3 25.3 98 9
Jan.
2333 36 27 97 9
4000 31.2 25 97 7
Feb.
2333 45.6 30.3 97 13
Mar. 4000 23 26.4 98 5
Apr. 4000 39 27 98 10
2015 May. 4000 19.3 14.6 97 2
Jun 4000 32 22 97 7
July 4000 35 21 97 8
Aug. 4000 51 34 97 16
Sep. 4000 56 27 97 14
Oct. 4000 52 18 96 9
Nov. 4000 47 8 97 3
Dec. 4000 60 8 97 4
Average 40 22 97 9
64
Chapter Four
100
80
60 55
49
45 45
Percentage
39 38 37
40 34
32 32.5
27.5 29 29 29 29 27 28
26
23 23
20
20 15 16 15
0
Jan. Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
100
80
60
Percentage
60 56
51 52
47
37 38 39
40 35 34
32
26 27 26.4 27 27
23 22 21
19.3 18
20 14.6
8 8
0
Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec
65
Chapter Four
From these Figures it can be seen that the;
Quality rate in each month is almost stable which is not less than
96% in each month; that means that the quality rate at the company
is stable (although it is less than PepsiCo Inc. specifications of 99%).
Availability factor is always higher than performance, but still not
exceeding more than (60%) percentage throughout the two
consecutive years of the study (2014, 2015) of an average value of
(37%) in 2014 and (40%) in 2015.
Performance rate throughout these two years do not exceed 45%
value. Although this line is working at two different operational
speeds that directly affect performance rate, but this line suffers
from critical performance issues.
Maximum performance rates are in August 2014 and 2015 which are
(45% and 34%) respectively, knowing that the highest defect rate
was in the same months.
66
Chapter Four
30
25
20
OEE Percentage
15 Operating Speed
4000 bottle/hr.
10 2333 bottle/hr.
2014
67
Chapter Four
Since the company used only the high speed starting from
March 2015, a comparison between the high speed in 2014 and 2015
has been made to analyze the fluctuating data as shown in Fig (4.12)
below.
30
25
20
OEE Percentage
15
2014
10 2015
Fig. (4.12) OEE values at high operating speed during (2014) and
(2015) years.
It can be seen from the comparison between the above Fig. and
Fig. (4.11), that OEE values in 2014 for the high speed are greater
than in 2015. On the other hand, Fig. (4.13) shows the total OEE
values for each month in 2014 and 2015.
68
Chapter Four
30
25
24
20
18
16 16
Percentage
15
14 14
2014
9 9 10 10
10 2015
9 9 9
8
7
5 7 6
5
3.5 5 4
3
2
0
69
Chapter Four
Table (4-4) Comparison Between OEE World Class and the Resulting
Values for Line Five
Company Company
OEE Factor World Class
OEE for 2014 OEE for 2015
Availability 37% 40% 90%
Performance 28% 22% 95%
Quality 97% 97% 99%
OEE 11% 9% 85%
70
Chapter Four
4.4.2.3 Changeover efficiency (C) for Line Five;
From Table (4.5) below, the set-up and adjustments time for
January is (15.5 hr.). Fig. (4.14) shows line chart to clarify the
fluctuations in time. Changeover efficiency could be calculated using
equations (2-12) and (2-13).
Operating time = 188 – 15.5 = 172.5 hr.
C = 172.5 / 188 = 0.91 = 91%
Table (4.5) Set-Up Time for (2014) and (2015) years
71
Chapter Four
100
90
80
70
60
50
Hours
40 2014
30 2015
20
10
0
72
Chapter Four
Running time = 172.5 – 1 = 171.5 hr.
Am = 172.5 / 172.5 = 99%
Thus this factor is almost negligible throughout research duration.
4.4.2.5 Availability of Manpower (Amp) for Line Five;
There is no absence of the manpower since this production
line is fully automated and the operator most always exists to monitor
and perform certain activity. The delays that could happen for
example sometimes the machines need from operator to perform an
activity to continue working, so, the Absence of operator is assumed
to be 1hr. per month. Availability of manpower could be calculated
according to equations (2-16) and (2-17).
Actual running time = 172.5 – 1 = 171.5hr.
Amp = 171.5 / 172.5 = 99%
4.4.2.6 Performance efficiency (P) for Line Five;
Performance efficiency could be calculated according to the
same equation used for OEE tool and its value showed in Tables (4.2)
and (4.3).
P = 15% for January 2014
4.4.2.7 Quality Rate (Q) for line five;
Quality rate could be calculated according to the same equation
used for OEE tool and its value showed in Tables (4.2) and (4.3).
Q = 97% for January 2014
Tables (4.6) and (4.7) show the whole calculations of ORE tool during
(2014) and (2015) respectively.
73
Chapter Four
Table (4-6) ORE Values of (2014) year
Availability
Changeover Availability Performance Quality
Readiness Availability of ORE
Month Efficiency of Materials Rate Rate
% of Facility % Manpower %
% % % %
%
January 41 63 91 99 99 15 97 2.7
February 65 63 92 99 99 27.5 97 10.2
March 59 69 90 99 99 29 98 10.4
April 38 65 88 99 99 16 97 3.3
May 52 47 83 99 99 29 98 5.7
June 62 68 85 99 99 29 98 10.1
July 47 37 29 99 99 15 98 0.7
August 87 67 91 99 99 45 96 22.9
September 84 59 90 99 99 37 98 16.1
October 67 39 82 99 99 27 97 5.6
November 73 51 95 99 99 26 97 8.9
December 51 54 82 99 99 20 97 4.3
Average 61 57 83 99 99 26 97 8
Availability
Changeover Availability Performance Quality
Readiness Availability of ORE
Month Efficiency of Materials Rate Rate
% of Facility % Manpower %
% % % %
%
January 84 76 97 99 99 26 97 15
February 65 63 92 99 99 27 97 9
March 59 69 90 99 99 26.4 98 9
April 38 65 88 99 99 27 97 5
May 52 47 83 99 99 14.6 98 2
Jun 81 54 80 99 99 22 97 7
July 81 65 79 99 99 21 97 8
August 77 50 90 99 99 34 97 11
September 66 56 90 99 99 27 97 8
October 53 52 91 99 99 18 96 4
November 42 47 86 99 99 8 97 2
December 23 47 89 99 99 8 97 1
Average 60 58 88 99 99 22 97 7
74
Chapter Four
From Table (4.6) and (4-7) it can be seen that;
The average value of ORE for 2014 is (8%) and for 2015 is (7%),
this indicates decreasing in exploiting the production resources of
this relatively new line.
Readiness factor is fluctuating each month that is effected by
planned downtime and breakdown times.
In 2015 it can be seen that both the changeover efficiency and the
ORE results are decreasing in spite of that the company did the
planned maintenance in March then it gets increased in June and
July.
75
Chapter Four
Readiness Af
100 100
80 80
% 60
%
40 60
40
20 20
0 0
Nov
Apr
Jan
Oct
Feb
Jun
Sep
May
Mar
Jul
Aug
Dec
Nov
Jan
Oct
Feb
Jun
Sep
May
Mar
Aug
Apr
Jul
Dec
A B
Am C
100 100
80 80
60
%
60
%
40 40
20 20
0 0
Feb
Sep
Aug
Nov
Mar
Apr
Jul
Jan
Oct
Jun
Dec
May
Nov
Apr
Jul
Aug
Jan
Oct
Feb
Jun
Sep
Dec
May
Mar
C D
P Amp
100 100
80 80
60 60
%
%
40 40
20 20
0 0
Feb
Sep
Nov
Nov
Mar
Apr
Jul
Aug
Feb
Jun
Sep
Jan
Oct
Jun
Dec
May
May
Mar
Apr
Jul
Aug
Jan
Oct
Dec
E F
Q
100
80
%
60
40
20
0
Feb
Jun
Sep
May
Mar
Apr
Jul
Aug
Nov
Jan
Oct
Dec
G
(A; Readiness, B; Availability of facility, C; Avaliability of materials,
D; Changover effecincy, E; Performance Rate, F; Avaliability of
manpower, G; Quality Rate)
76
Chapter Four
Readiness Af
100 100
80 80
% 60
%
60
40 40
20 20
0 0
Aug
Nov
Apr
Octo
Jan
Feb
Sept
Dec
May
July
Mar
June
Nov
Apr
Jan
Oct
Feb
Sep
May
July
Mar
Aug
June
Dec
A B
Am C
100 100
80 80
60 60
%
%
40 40
20 20
0 0
Feb
Nov
Mar
Apr
July
Aug
Octo
Jan
Sept
Dec
May
June
Nov
Oct
Jan
Feb
Sep
May
July
Mar
Aug
Apr
June
Dec
C D
P Amp
100
%
100
80
%
80
60 60
40 40
20 20
0
0
M…
M…
Ju…
N…
Nov
Oct
Jan
Feb
Sep
May
July
Mar
Aug
Apr
June
Dec
Feb
Sep
Apr
July
Aug
Jan
Oct
Dec
E F
Q
100
80
%
60
40
20
0
Nov
Apr
Jan
Oct
Feb
Sep
Dec
May
July
Mar
Aug
June
G
77
Chapter Four
Also the same thing for Figure (4.16) it can be seen that the
factors (C, F, G) have no big effect on the productivity. The big losses
that happened and still decreasing without any improvement after
performing the planned maintenance is the performance factor that
shows big losses in both years. Figs. (4.17) and (4.18) shows the
variation of OEE and ORE for (2014) and (2015) respectively.
26
24
22
20
18
16
Percentage %
14
12
10
8
6
4
2
0
18
16
14
12
10
Percentage %
8
6
4
2
0
OEE ORE
78
Chapter Four
It can be seen from Fig. (4.17) and (4.18) that;
OEE and ORE are high in August for both years.
ORE in July 2014 is very low and that is an indicator for
management of necessity to make a decision to better utilize the
resources to increase these values.
4.5 OEE Software
In order to chase the fluctuations and support maintenance and
operation management, for decision makers at different operational
levels computer aided software is crucial to evaluate on real time
basis. Also this software may support TPM implementation through
reports that are needed to review the required operating information.
The OEE software is employed in this study and installed using
Systems2Win application that is compatible with Microsoft Excel,
version (13.8 Build B). This software offers multiple templates that
are compatible with Excel worksheets such as (Cause and Effect,
KaiZen, Pareto, etc.) [53].
4.5.1 OEE Software Input
OEE software input parameters are managed by two different
sheets according to user requirements which are;
4.5.1.1 Data Validation Sheet
Where user specified parameters include the Unit of Measure
(UOM), downtime threshold, lost time category, reject category, how
many shafts, and how many hours per shaft and product type or
family. These parameters could be edited by user.
4.5.1.2 Log Sheet
It is used for the daily event log in work center which all the
production data are introduced in this sheet as shown in Fig. (4.19)
where (A) is the morning shift and (B) is the night shift. These sheets
79
Chapter Four
may help operation manager to follow up issues across the whole
production line since it offers day by day follow up. Also this sheet
reveals the defective and acceptable (good) products according to
each shift / day.
80
Chapter Four
percentages as shown in Fig (4.20). From this Fig. it could be noticed
that the details offered in results shows different categories such as
performance loss, downtime loss, etc. that is much faster and specific
and cannot be calculated manually.
81
Chapter Four
or negative changes. It is sometimes called flying bricks chart or
Mario chart due to the apparent suspension of columns (bricks) in
mid-air [54].
82
Chapter Four
800
700
87
600
206
500
400
Hours
720
300 234
200 427
100 193
0
Available Time Planned Downtime loss Net Operating Performance Productive Time
Downtime loss
83
Chapter Four
Assessment
5 Months
Implementati
on
5 Months
Planning
Phase
10 Months
Organization
6 Months
Awarness
6 Months
Nov
Apr
Nov
Apr
Nov
Apr
Jan
Feb
Oct
Jun
Sep
Jan
Feb
Oct
Oct
Jun
Sep
Jan
Feb
Oct
Jun
Sep
Jan
Feb
May
May
May
Mar
Jul
Aug
Mar
Jul
Aug
Mar
Jul
Aug
Dec
Dec
Dec
2017 2018 2019 2020
Time
84
Chapter Four
Predictive maintenance and diagnostic method.
Fixing and taking care of small maintenance tasks.
All the activities of planned maintenance pillar are done by the
German staff which mentioned earlier in Fig. (3.3); overall check of
the production line, lubrications, changing oil and filters are those
kinds of activities that could be done by Iraqi staff by using the core
pillars of TPM which are (Planned and Autonomous maintenance).
That’s to reduce time, reduce cost and increase operator’s
involvement and maintenance staff. Training of staff should also be
employed to the time proposed is six months.
Organization Phase:
This phase needs extra six months so as to develop plan that
conforms the production requirements and maintenance activities.
Also to locate contamination spots, and decide the appropriate
downtimes staff training and enhance machines performance.
Planning Phase:
This phase should last for 10 months in order to assess staff
maturity, plans for training that should improve productivity
through better resource utilization. Rewards and employee’s
encouragement should be launched.
Implementation Phase:
To be accomplished through five months where OEE software
is recommended to simplify, monitor, and decision making where
Line Five will be the pilot plan for factory toward the whole
company.
Assessment Phase:
Five months is recommended so as to define weakness and
strong implementation spots and results gained from this
implementation steps are evaluated in this phase.
85
Chapter Four
It is worth mentioning that six months for implementation
launch in January is needed for management commitment, budget and
maintenance staff preliminary training. The implementation of
autonomous maintenance and 5Ss pillars is assumed to decrease the
percentages of breakdowns as shown in Table (4.8). That will increase
the productivity by 20% and the availability by 35%. It should be
concluded that the major failures decreased from 50% to 25%.
86
Chapter Four
5- The quality factor is stable and represents an average of (96%), the
average of availability factor is not exceeding (40%) and the
average of performance factor is not exceeding (28%).
6- OEE software is very useful, easy to work with, powerful tool that
highlights the areas of weakness and extends the scope of analysis
since detailed (day by day) shift basis results are revealed.
7- Implementing these two pillars is assumed to increase productivity
by %20 and availability by 35%.
87
Chapter Five
Conclusions and Recommendations for
Future work
5.1 Introduction
This research has been conducted and written in relation to the
implementation of Total Productive Maintenance strategy at Baghdad
company for soft drinks. The study aims to increase both of the
productivity and availability of the production system.
5.2 Research Summary
Throughout this research, two important TPM metrics have
been used which are; OEE and ORE to reveal losses type and
allocation for the production system at Baghdad company. Developed
methodology and proposed implementation of TPM are also presented
in this research in order to raise up the production system efficiency.
5.3 Conclusions
1. Production Line Five is suffering from downtimes and defects
mainly due to mechanical and measurements shared by 50%.
2. Result analysis shows decrease in OEE and ORE for the two years
of this study, in 2014 they are (11%, 9%) respectively and for 2015
they are (8%, 7%) respectively. it has been found that following
aspects has the greatest effect on productivity;
Readiness.
Availability of Facility.
Changeover Efficiency.
Performance rate.
Planned and Breakdown times.
3. While the quality rate does not reach the world class values as its
average value is (97%) it is considered very acceptable and stable
89
Chapter Five
through 2014 and 2015 but still is less than that of PepsiCo Inc.
specification of (99%).
4. The company works using planned maintenance only which has
been implemented in December 2014 and March 2015 but it is not
enough to increase the productivity and eliminate losses because of
the inappropriate usage of resources.
5. Detailed analysis shows low performance rate that decreased from
(28%) in 2014 to (22%) in 2015.
5.4 Recommendations for Future Work
Following points are recommended for future work;
1- Developing office TPM as it is an important pillar that can boost
other TPM pillars.
2- Developing data base where all production data are kept inside.
This data base may be integrated with OEE software throughout
real time production in order to assess and follow up the progress of
productivity that may help decision makers to identify, assign
issues and areas of weakness so as to resolve them.
3- Employing other TPM tools such as Single Minute Exchange Die
(SMED), Statıstical Process Control (SΡC), Cause-Effect Diagrams,
Setup Time Reduction, Bottleneck Analysis, etc.
4- Tacquchi design of experiment could be conducted to identify the
noise factor(s) that are affecting production so as to identify best
production options (bottles size, speed, flavor, etc.).
5- Implementing TPM for Line five /Al-Forat Factory to improve
production line efficiency and increase productivity and to be a
starting point to implement TPM for the whole company.
90
References
93
[8] Baghdad Company for Soft Drinks – Al-Forat Factory.
94
Business, Engineering and Industrial Applications (ISBEIA),
IEEE Symposium, PP. 55-58.
[17] Arashpour, M. R., Enaghani, M. R., and Karimi, M. (2009), “The
Relationship between Lean and TPM”, MSc. Thesis, University
Of Borås, Sweden.
[21] Singh, J., Rastogi, V., and Sharma, R. (2013). “Total Productive
Maintenance Review: A Case Study in Automobile
Manufacturing Industry”, International Journal of Current
Engineering and Technology Vol. 3, No. 5, ISSN, 2277-4106.
95
[23] Bramstorp, O. (2011), “Implementation of the Focused
Improvement concept in outsourced production” MSc. Thesis,
LUND University, Sweden.
96
TPM” Sonklanakarin Journal of Science and Technology, Vol.
33, No. 1, PP, 101-106.
97
Modern Engineering Research (IJMER), Vol.2, Issue.1, PP, 442-
444, ISSN: 2249-6645.
[37] Kiran, M., Mathew, C., and Kuriakose, J. (2011), Root Cause
Analysis for Reducing Breakdowns in a Manufacturing Industry.
College of Engineering, Kothamagalam, Ernakulam, Kerala.
[41] Sharma, K., Gera, G., Kumar, R., Chaudhary, H. K., and Gupta,
S. K. (2012), “An empirical study approach on TPM
implementation in manufacturing industry”, International
Journal on Emerging Technologies, Vol. 3,No. 1, PP, 18-23.
98
[43] Oded Tal (2001), “Overall Resource Effectiveness; the Key for
Cycle Time Reduction and Capacity Improvements”, MAX
International Engineering Group – Operational, North Bergen
NJ 07020 USA.
[45] Iftekhar A., Sazedul K. and Md. Mosharraf H., (2012), “Effective
Implementation of Total Productive Maintenance and Its
Impacts on Breakdown, Repair and Setup Time”, Proceedings of
the Global Engineering, Science and Technology Conference,
Dhaka, Bangladesh.
[48] Kocher, G., Kumar, R., Singh, A., and Dhillon, S. S. (2012), “An
Approach for Total Productive Maintenance and Factors
Affecting its Implementation in Manufacturing Environment”,
99
International Journal on Emerging Technologies, Vol. 3, No. 1,
PP, 41-47.
[50] Dogra, M., Sharma, V. S., Sachdeva, A., and Dureja, J. S. (2011),
“TPM: A Key Strategy for Productivity Improvement in Process
Industry”, Journal of Engineering Science and Technology, Vol.
6, No. 1, PP, 1-16.
[54] Box, G., Bisgaard, S., Graves, S., Kulahci, M., Marko, K.,
James, J. and Wu, C. (2003), “Performance evaluation of
dynamic monitoring systems: the waterfall chart. Quality
Engineering”, Vol. 16, No. 2, PP, 183-191.
100
[56] Mahmoud, M.A., (1988), “Determination of Optimum Periods
for Maintaining Industrial Machinery”, MSc. Thesis, Production
Engineering and Metallurgy, University of Technology.
101
A
B
BSDC Daily Sales Tracker
Month 2015 1 2 3 4 5 6 7 8 9 10 11 12
Container Brand Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
250ml RB Pepsi 50,550 57,503 81,000 100,700 89,101 107,450 112,200 121,700 159,425 111,208 89,874 43,100 1,123,811
24/case 7Up 17,550 30,650 31,500 51,200 41,451 34,700 39,900 59,400 57,300 37,850 19,633 12,100 433,234
Mirinda Orange 9,800 14,600 21,800 21,750 32,201 8,600 0 14,200 13,280 15,850 7,266 9,500 168,847
Total 77,900 102,753 134,300 173,650 162,753 150,750 152,100 195,300 230,005 164,908 116,773 64,700 1,725,892
250ml NRB Pepsi 24,091 36,102 38,629 27,805 53,583 58,839 60,193 63,795 41,879 40,329 18,608 14,802 478,655
24/case 7Up 10,538 18,082 19,773 26,999 19,470 24,667 17,408 34,015 39,799 18,038 9,536 7,630 245,955
7Up Lemo 0 0 0 0 14,791 12,331 4,725 26,103 0 0 62 1,794 59,806
Mirinda Orange 5,268 6,496 5,824 9,758 9,081 15,228 1 16,786 20,509 4,038 4,158 1,467 98,614
Mirinda Green Apple 0 0 0 0 0 0 0 0 0 0 0 0 0
Mirinda Lemon 0 0 0 0 0 0 0 0 0 0 0 0 0
Mountain Dew 17,143 23,858 16,069 38,310 10,869 33,942 57,357 121,539 56,786 55,217 24,082 2,808 457,980
Total 57,040 84,538 80,295 102,872 107,794 145,007 139,684 262,238 158,973 117,622 56,446 28,501 1,341,010
250ml Cans Pepsi 458,924 532,304 554,752 458,946 630,406 517,768 598,704 690,556 810,794 696,137 382,987 347,801 6,680,079
30/case Diet Pepsi 30,910 16,832 44,725 25,743 28,626 35,666 26,290 35,006 30,801 27,365 18,866 22,235 343,065
7Up 159,635 266,174 231,845 215,405 289,452 268,102 251,098 279,666 324,287 254,233 176,550 144,125 2,860,572
7Up Free 29,041 16,428 45,825 22,552 32,035 36,433 25,190 32,366 32,121 29,195 14,905 19,749 335,840
7Up Lemo 0 27,280 22,797 29,801 24,976 41,047 23,104 40,640 33,909 30,149 9,900 16,070 299,673
Mirinda Orange 65,456 50,766 85,558 80,139 79,779 75,175 89,281 110,365 97,769 102,382 51,140 48,145 935,955
Mirinda Green Apple 55,434 9,447 72,684 46,082 49,727 49,231 50,279 67,246 54,930 50,460 30,030 29,176 564,726
Mirinda Lemon 0 0 0 0 0 0 0 0 0 0 0 0 0
Mountain Dew 0 0 0 0 0 0 0 0 0 0 0 0 0
Shani 46,116 59,433 54,082 56,221 69,487 58,370 65,402 98,575 80,764 75,262 36,265 45,237 745,214
Sting Gold 1,750 0 0 0 0 0 0 0 0 0 0 0 1,750
Sting Grape 1,678 0 0 0 0 0 0 0 0 0 0 0 1,678
Total 848,944 978,664 1,112,268 934,889 1,204,488 1,081,792 1,129,348 1,354,420 1,465,375 1,265,183 720,643 672,538 12,768,552
330ml Can Pepsi 198,602 166,948 0 0 0 0 0 0 0 0 0 0 365,550
24/case Diet Pepsi 11,081 7,097 10,449 0 0 0 0 0 0 0 0 0 28,627
7Up 60,122 98,073 103,861 20,677 0 0 0 0 0 0 0 0 282,733
7Up Free 9,028 7,916 17,931 7,704 1,980 3,410 5,060 9,031 2,980 0 0 0 65,040
Mirinda Orange 26,498 26,613 0 0 0 0 0 0 0 0 0 0 53,111
Mirinda Green Apple 20,315 0 0 0 0 0 0 0 0 0 0 0 20,315
Total 325,646 306,647 132,241 28,381 1,980 3,410 5,060 9,031 2,980 0 0 0 815,376
355ml Can Pepsi 0 0 353,960 254,244 224,465 207,135 190,346 425,053 315,243 355,622 142,782 151,717 2,620,567
24/case Diet Pepsi 0 0 0 10,450 10,450 5,610 4,510 9,460 3,741 5,508 5,292 866 55,887
7Up 0 0 0 42,572 85,511 81,400 94,050 121,646 110,533 104,655 36,290 29,978 706,635
7Up Free 0 0 0 0 0 0 0 0 0 1,944 2,916 758 5,618
Mirinda Orange 0 0 43,442 37,516 33,811 25,630 34,980 49,304 39,410 39,701 12,960 8,538 325,292
Mirinda Green Apple 0 0 39,034 22,595 7,271 5,996 9,130 13,310 7,520 7,020 4,320 1,566 117,762
Mountain Dew 0 0 0 0 0 0 0 0 0 12,528 6,588 3,241 22,357
Total 0 0 436,436 367,377 361,508 325,771 333,016 618,773 476,447 526,978 211,148 196,664 3,854,118
750ml PET Pepsi 267,655 498,966 365,415 302,804 473,931 449,699 524,045 576,535 781,077 556,560 234,601 277,738 5,309,026
12/case 7Up 142,763 110,041 124,220 139,822 158,067 214,484 176,290 236,959 248,801 150,300 73,950 78,005 1,853,702
7Up Lemo 0 0 0 0 0 0 0 0 0 0 0 0 0
Mirinda Orange 31,705 51,255 57,290 72,946 84,746 98,729 97,495 106,108 117,810 93,134 35,955 44,733 891,906
Mirinda Green Apple 17,085 15,504 15,725 18,530 15,215 35,571 38,930 33,704 46,835 30,260 14,875 6,630 288,864
Mountain Dew 6,377 11,076 7,225 18,068 18,956 13,768 80,580 118,830 99,450 93,032 24,820 19,323 511,505
Shani 61,987 32,270 75,445 69,785 72,958 136,959 78,910 184,620 135,257 118,148 77,860 65,145 1,109,344
Total 527,572 719,112 645,320 621,955 823,873 949,210 996,250 1,256,756 1,429,230 1,041,434 462,061 491,574 9,964,347
1.25L PET Pepsi 4,664 3,033 0 0 0 0 0 0 0 0 0 0 7,697
6/case 7Up 3,872 170 0 0 0 0 0 0 0 0 0 0 4,042
Mirinda Orange 0 0 0 0 0 0 0 0 0 0 0 0 0
Mirinda Green Apple 0 0 0 0 0 0 0 0 0 0 0 0 0
Total 8,536 3,203 0 0 0 0 0 0 0 0 0 0 11,739
1.75L PET Pepsi 397,713 308,151 339,415 598,020 461,006 595,369 610,285 759,345 929,257 575,972 313,769 311,524 6,199,826
6/case 7Up 66,485 106,483 107,025 139,370 169,361 167,381 171,920 244,640 222,000 152,688 80,080 69,440 1,696,873
Mirinda Orange 31,818 47,920 40,544 53,353 65,841 79,290 45,532 86,565 22,571 71,402 51,920 21,360 618,116
Mirinda Green Apple 5,201 4,000 1,100 22,058 15,040 13,926 5,840 20,638 29,360 23,218 9,440 2,000 151,821
Shani 21,680 23,140 8,235 44,109 41,442 54,363 65,840 75,600 47,570 60,597 36,160 26,880 505,616
Total 522,897 489,694 496,319 856,910 752,690 910,329 899,417 1,186,788 1,250,758 883,877 491,369 431,204 9,172,252
2L PET Pepsi 0 2,697 0 0 0 0 0 0 0 0 0 0 2,697
6/case 7Up 0 0 0 0 0 0 0 0 0 0 0 0 0
Mirinda Green Apple 0 0 0 0 0 0 0 0 0 0 0 0 0
Total 0 2,697 0 0 0 0 0 0 0 0 0 0 2,697
2.25L PET Pepsi 86,104 75,446 20,240 115,609 114,364 92,039 122,191 199,482 100,959 110,624 39,821 43,247 1,120,126
6/case 7Up 22,212 17,115 0 40,339 37,742 15,744 43,173 37,294 31,873 20,876 5,766 5,972 278,106
Mirinda Orange 5,376 4,066 0 14,020 17,732 5,500 22,400 16,630 12,553 14,919 6,080 1,030 120,306
Shani 0 0 1,024 0 0 0 0 0 0 0 0 0 1,024
Total 113,692 96,627 21,264 169,968 169,838 113,283 187,764 253,406 145,385 146,419 51,667 50,249 1,519,562
2.5L PET Pepsi 0 30,720 124,967 0 0 52,224 0 0 0 0 0 0 207,911
6/case 7Up 0 0 41,604 0 0 16,711 0 0 0 0 0 0 58,315
Mirinda Orange 0 0 20,503 0 0 0 0 0 0 0 0 0 20,503
Total 0 30,720 187,074 0 0 68,935 0 0 0 0 0 0 286,729
BIB 10 L Pepsi 0 0 0 0 0 0 0 0 0 0 0 0 0
Diet Pepsi 0 34 37 33 50 0 37 47 0 50 0 23 311
7Up 0 0 0 0 0 0 54 49 22 90 37 29 281
7Up Free 0 32 27 29 0 0 0 0 50 0 0 22 160
Mirinda Orange 54 30 44 35 44 31 50 102 0 54 101 0 545
Total 54 96 108 97 94 31 141 198 72 194 138 74 1,297
BIB 20 L Pepsi 589 812 612 608 613 723 892 1,081 1,193 699 421 1,035 9,278
7Up 43 25 30 35 30 33 26 0 0 0 0 0 222
Total 632 837 642 643 643 756 918 1,081 1,193 699 421 1,035 9,500
0.33 Aquafina 18,888 21,600 12,784 15,358 14,350 1,843 43 0 2,773 158 43 36,364 124,204
0.6 Aquafina 12,560 9,320 8,340 10,017 12,183 15,640 1,805 55 5,465 0 0 23,733 99,118
Total Raw 2,514,361 2,846,508 3,267,391 3,282,117 3,612,194 3,766,757 3,845,546 5,138,046 5,168,656 4,147,472 2,110,709 1,996,636 41,696,393
Total 8oz 3,870,650 4,351,896 5,071,102 5,150,351 5,585,807 5,932,394 6,021,092 8,027,839 8,032,741 6,410,810 3,226,056 3,103,003 64,783,739
Target 2015 8oz
% #DIV/0!
2014
Total 8oz 0
B/(W) % #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
View publication stats