Procurement Schedule

This project schedule outlines the procurement of escalators for 3 buildings over 18 months. Key tasks include engineering and commercial work from February to June 2018, preparation from March 2018 to July 2019 including checking concrete openings for each building, manufacturing from March 2018 to May 2019 with shipments planned quarterly, voyage and delivery of each shipment, and installation of the escalators from July 2018 to March 2019 for different buildings.

Uploaded by

Lakshan Fonseka
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
86 views4 pages

Procurement Schedule

This project schedule outlines the procurement of escalators for 3 buildings over 18 months. Key tasks include engineering and commercial work from February to June 2018, preparation from March 2018 to July 2019 including checking concrete openings for each building, manufacturing from March 2018 to May 2019 with shipments planned quarterly, voyage and delivery of each shipment, and installation of the escalators from July 2018 to March 2019 for different buildings.

Uploaded by

Lakshan Fonseka
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

ID Task Task Name Duration Start Finish Feb '18 Mar '18 Apr '18 May '18 Jun

Finish Feb '18 Mar '18 Apr '18 May '18 Jun '18 Jul '18 Aug '18
Mode 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26
1 Engineering & Commercial Work 117 days 2/5/18 6/1/18
2 Submission of shop Drawings 14 days 2/5/18 2/18/18
3 Submission of Material submission 30 days 2/9/18 3/10/18
4 Submission of method statement 30 days 5/3/18 6/1/18
5 Price Variations Confirmation 30 days 4/30/18 5/29/18
6 Preperation 488 days 3/1/18 7/1/19
7 Check Concrete Openings 365 days 3/1/18 2/28/19
8 Building 2 10 days 3/1/18 3/10/18
9 Building 1 3 days 8/30/18 9/1/18
10 Building 3 3 days 2/26/19 2/28/19
11 Manufacturing Confirmation 355 days 3/10/18 2/28/19
12 Building 2 0 days 3/10/18 3/10/18 3/10
13 Building 1 0 days 9/1/18 9/1/18
14 Building 3 0 days 2/28/19 2/28/19
15 Manufacturing 445 days 3/11/18 5/29/19
16 Shipment 1 (Bd 2 A) 80 days 3/11/18 5/29/18
17 Shipment 2 (BD 2 B) 90 days 3/11/18 6/8/18
18 Shipment 3 90 days 9/2/18 11/30/18
19 Shipment 4 90 days 3/1/19 5/29/19
20 Voyage 395 days 5/30/18 6/28/19
21 Shipment 1 30 days 5/30/18 6/28/18
22 Shipment 2 30 days 6/9/18 7/8/18
23 Shipment 3 30 days 12/1/18 12/30/18
24 Shipment 4 30 days 5/30/19 6/28/19
25 Clearing and Delivery to the site 368 days 6/29/18 7/1/19
26 Shipment 1 3 days 6/29/18 7/1/18
27 Shipment 2 3 days 7/9/18 7/11/18
28 Shipment 3 3 days 12/31/18 1/2/19
29 Shipment 4 3 days 6/29/19 7/1/19
30 Prepare escalator Transport Path 369 days 6/25/18 6/28/19
31 ES 1.3a/b 4 days 6/25/19 6/28/19
32 ES 1.4a/b 4 days 6/25/19 6/28/19
33 ES 2.1a/b 4 days 7/5/18 7/8/18
34 ES 2.2 4 days 7/5/18 7/8/18
35 ES 2.3a/b 4 days 7/5/18 7/8/18
36 ES 2.4a/b 4 days 7/5/18 7/8/18
37 ES 2.6a/b 4 days 6/25/18 6/28/18
38 ES 2.7a/b 4 days 6/25/18 6/28/18
39 ES 3.1a/b 4 days 12/27/18 12/30/18
40 ES 3.2a/b 4 days 12/27/18 12/30/18
41 ES 3.3a/b 4 days 12/27/18 12/30/18

Task Project Summary Manual Task Start-only Deadline

Project: Procurement Schedule Split Inactive Task Duration-only Finish-only Progress


Date: 2/3/18 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
ID Task Task Name Duration Start Finish Feb '18 Mar '18 Apr '18 May '18 Jun '18 Jul '18 Aug '18
Mode 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26
42 Delivery to the site 365 days 7/1/18 7/1/19
43 ES 1.3a/b 0 days 7/1/19 7/1/19
44 ES 1.4a/b 0 days 7/1/19 7/1/19
45 ES 2.1a/b 0 days 7/11/18 7/11/18 7/11
46 ES 2.2 0 days 7/11/18 7/11/18 7/11
47 ES 2.3a/b 0 days 7/11/18 7/11/18 7/11
48 ES 2.4a/b 0 days 7/11/18 7/11/18 7/11
49 ES 2.6a/b 0 days 7/1/18 7/1/18 7/1
50 ES 2.7a/b 0 days 7/1/18 7/1/18 7/1
51 ES 3.1a/b 0 days 1/2/19 1/2/19
52 ES 3.2a/b 0 days 1/2/19 1/2/19
53 ES 3.3a/b 0 days 1/2/19 1/2/19
54 Installation
55 ES 1.3a/b 60 days 7/2/19 8/30/19
56 ES 1.4a/b 60 days 7/2/19 8/30/19
57 ES 2.1a/b 60 days 9/2/18 10/31/18
58 ES 2.2 60 days 9/2/18 10/31/18
59 ES 2.3a/b 60 days 9/2/18 10/31/18
60 ES 2.4a/b 60 days 9/2/18 10/31/18
61 ES 2.6a/b 60 days 7/2/18 8/30/18
62 ES 2.7a/b 60 days 7/2/18 8/30/18
63 ES 3.1a/b 60 days 1/3/19 3/3/19
64 ES 3.2a/b 60 days 1/3/19 3/3/19
65 ES 3.3a/b 60 days 1/3/19 3/3/19

Task Project Summary Manual Task Start-only Deadline

Project: Procurement Schedule Split Inactive Task Duration-only Finish-only Progress


Date: 2/3/18 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2
Sep '18 Oct '18 Nov '18 Dec '18 Jan '19 Feb '19 Mar '19 Apr '19 May '19 Jun '19 Jul '19 Aug '19 Sep '19
26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1

9/1
2/28

Task Project Summary Manual Task Start-only Deadline

Project: Procurement Schedule Split Inactive Task Duration-only Finish-only Progress


Date: 2/3/18 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 3
Sep '18 Oct '18 Nov '18 Dec '18 Jan '19 Feb '19 Mar '19 Apr '19 May '19 Jun '19 Jul '19 Aug '19 Sep '19
26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1

7/1
7/1

1/2
1/2
1/2

Task Project Summary Manual Task Start-only Deadline

Project: Procurement Schedule Split Inactive Task Duration-only Finish-only Progress


Date: 2/3/18 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 4