ID Task Task Name Duration Start Finish Feb '18 Mar '18 Apr '18 May '18 Jun
Finish Feb '18 Mar '18 Apr '18 May '18 Jun '18 Jul '18 Aug '18
Mode 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26
1 Engineering & Commercial Work 117 days 2/5/18 6/1/18
2 Submission of shop Drawings 14 days 2/5/18 2/18/18
3 Submission of Material submission 30 days 2/9/18 3/10/18
4 Submission of method statement 30 days 5/3/18 6/1/18
5 Price Variations Confirmation 30 days 4/30/18 5/29/18
6 Preperation 488 days 3/1/18 7/1/19
7 Check Concrete Openings 365 days 3/1/18 2/28/19
8 Building 2 10 days 3/1/18 3/10/18
9 Building 1 3 days 8/30/18 9/1/18
10 Building 3 3 days 2/26/19 2/28/19
11 Manufacturing Confirmation 355 days 3/10/18 2/28/19
12 Building 2 0 days 3/10/18 3/10/18 3/10
13 Building 1 0 days 9/1/18 9/1/18
14 Building 3 0 days 2/28/19 2/28/19
15 Manufacturing 445 days 3/11/18 5/29/19
16 Shipment 1 (Bd 2 A) 80 days 3/11/18 5/29/18
17 Shipment 2 (BD 2 B) 90 days 3/11/18 6/8/18
18 Shipment 3 90 days 9/2/18 11/30/18
19 Shipment 4 90 days 3/1/19 5/29/19
20 Voyage 395 days 5/30/18 6/28/19
21 Shipment 1 30 days 5/30/18 6/28/18
22 Shipment 2 30 days 6/9/18 7/8/18
23 Shipment 3 30 days 12/1/18 12/30/18
24 Shipment 4 30 days 5/30/19 6/28/19
25 Clearing and Delivery to the site 368 days 6/29/18 7/1/19
26 Shipment 1 3 days 6/29/18 7/1/18
27 Shipment 2 3 days 7/9/18 7/11/18
28 Shipment 3 3 days 12/31/18 1/2/19
29 Shipment 4 3 days 6/29/19 7/1/19
30 Prepare escalator Transport Path 369 days 6/25/18 6/28/19
31 ES 1.3a/b 4 days 6/25/19 6/28/19
32 ES 1.4a/b 4 days 6/25/19 6/28/19
33 ES 2.1a/b 4 days 7/5/18 7/8/18
34 ES 2.2 4 days 7/5/18 7/8/18
35 ES 2.3a/b 4 days 7/5/18 7/8/18
36 ES 2.4a/b 4 days 7/5/18 7/8/18
37 ES 2.6a/b 4 days 6/25/18 6/28/18
38 ES 2.7a/b 4 days 6/25/18 6/28/18
39 ES 3.1a/b 4 days 12/27/18 12/30/18
40 ES 3.2a/b 4 days 12/27/18 12/30/18
41 ES 3.3a/b 4 days 12/27/18 12/30/18
Task Project Summary Manual Task Start-only Deadline
Project: Procurement Schedule Split Inactive Task Duration-only Finish-only Progress
Date: 2/3/18 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Summary Inactive Summary Manual Summary External Milestone
Page 1
ID Task Task Name Duration Start Finish Feb '18 Mar '18 Apr '18 May '18 Jun '18 Jul '18 Aug '18
Mode 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26
42 Delivery to the site 365 days 7/1/18 7/1/19
43 ES 1.3a/b 0 days 7/1/19 7/1/19
44 ES 1.4a/b 0 days 7/1/19 7/1/19
45 ES 2.1a/b 0 days 7/11/18 7/11/18 7/11
46 ES 2.2 0 days 7/11/18 7/11/18 7/11
47 ES 2.3a/b 0 days 7/11/18 7/11/18 7/11
48 ES 2.4a/b 0 days 7/11/18 7/11/18 7/11
49 ES 2.6a/b 0 days 7/1/18 7/1/18 7/1
50 ES 2.7a/b 0 days 7/1/18 7/1/18 7/1
51 ES 3.1a/b 0 days 1/2/19 1/2/19
52 ES 3.2a/b 0 days 1/2/19 1/2/19
53 ES 3.3a/b 0 days 1/2/19 1/2/19
54 Installation
55 ES 1.3a/b 60 days 7/2/19 8/30/19
56 ES 1.4a/b 60 days 7/2/19 8/30/19
57 ES 2.1a/b 60 days 9/2/18 10/31/18
58 ES 2.2 60 days 9/2/18 10/31/18
59 ES 2.3a/b 60 days 9/2/18 10/31/18
60 ES 2.4a/b 60 days 9/2/18 10/31/18
61 ES 2.6a/b 60 days 7/2/18 8/30/18
62 ES 2.7a/b 60 days 7/2/18 8/30/18
63 ES 3.1a/b 60 days 1/3/19 3/3/19
64 ES 3.2a/b 60 days 1/3/19 3/3/19
65 ES 3.3a/b 60 days 1/3/19 3/3/19
Task Project Summary Manual Task Start-only Deadline
Project: Procurement Schedule Split Inactive Task Duration-only Finish-only Progress
Date: 2/3/18 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Summary Inactive Summary Manual Summary External Milestone
Page 2
Sep '18 Oct '18 Nov '18 Dec '18 Jan '19 Feb '19 Mar '19 Apr '19 May '19 Jun '19 Jul '19 Aug '19 Sep '19
26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1
9/1
2/28
Task Project Summary Manual Task Start-only Deadline
Project: Procurement Schedule Split Inactive Task Duration-only Finish-only Progress
Date: 2/3/18 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Summary Inactive Summary Manual Summary External Milestone
Page 3
Sep '18 Oct '18 Nov '18 Dec '18 Jan '19 Feb '19 Mar '19 Apr '19 May '19 Jun '19 Jul '19 Aug '19 Sep '19
26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1
7/1
7/1
1/2
1/2
1/2
Task Project Summary Manual Task Start-only Deadline
Project: Procurement Schedule Split Inactive Task Duration-only Finish-only Progress
Date: 2/3/18 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Summary Inactive Summary Manual Summary External Milestone