Introduction To C&I
Introduction To C&I
C&I DEPARTMENT
WELCOMES
YOU
Prepared/Presented By:
T. K. Seal
HEAD
C&I MAINT.
BTL 2008-09
2007-08
INDEX
RIPPING Synchronization TIME Duration
DATE Time Date (hrs) (hrs) REMARKS Details
Apr-07 1:59 10-Apr-07 4:59 3:00 Furnace Pressure High
Unit 4 tripped on furnace pr High on 1-05-07. Big slab of slag fallen and found in right side of
May-07 2:13 1-May-07 11:19 9:05 Furnace Pressure High bottom ash.
Unit 2 tripped on Total Flame Failure on 6-5-07. AC Scanner purge air fan discharge
May-07 4:41 6-May-07 7:02 2:21 Total Flame failure damper closed and DC fan took start. Dust went to the scanners
Sep-07 1:24 4-Sep-07 2:56 1:32 Drum level high Unit 2 tripped on drum level High on Mill Change over on 04-09-07
Oct-07 22:03 22-Oct-07 3:01 4:58 Generator interturn fault Unit 4 tripped on Generator inter-turn fault protection on 21 Oct 2007
Oct-07 11:19 21-Oct-07 15:23 4:04 LBB Protection Unit 4 tripped on LBB protection operation in ALD1 line on 21-Oct-07
Stage-I :SG
ID Protection:
Fan outboard & inboard oil pr low 2/3 logic
Fan coupling oil pr low 2/3 logic
Lub oil flow low 2/3 logic
# Lub oil flow data is not available (In remote)
FD Protection:
Motor outboard & inboard oil pr low 2/3 logic.
PA Protection:
Fan outboard & inboard oil pr low 2/3 logic
Lub oil flow low 2/3 logic
Motor inboard & outboard oil pr low 2/3 logic
# Lub oil flow data is not available.(In remote)
Stage-I :SG
BCP Protection:
Motor cavity temp 1/1 logic
Cooling water flow 1/1 logic
BCP D/P 2/2 logic
# No space available for mounting flow switches
cavity temp: T/C 1 for ACS, 1 FOR DAS & 1 local
gauge: no additional T/C provision in there in motor cavity.
flow switch: 1 permissive, 1 trip & other alarm
In new DCS this will be tried to make 2/2
Stage-I - SG & CW
Mill Protection:
Mill PA/seal air DP low 1/1 logic
PA flow low with mill in service 1/1 logic
As extra tapping point N/A
CW protection:
Pump brg flow 1/1 logic
Flushing water 1/1 logic
Flow, lub oil cooler flow 1/1 logic
Motor cooler flow low trip 1/1 logic
# No space available for mounting such flow switches
Reverse rotation 1/1 logic
Suction level 1/1 logic
# No space available for reverse rotation.
Suction level is immersion type ( position at -30 meter) level switch
( bestobell mobrey ). Alternate type to be tried.
Stage-I : BFP
BFP Protection:
Gland seal flow 1/1 logic
Cooling water flow 1/1 logic
# No space for additional flow switch
Lub oil pr low 1/2 logic
# Lub oil protection require additional relays which will be made 2/3 in
new DCS sys.
D/A level switches 1/1 logic
# To be made 2/3 in new DCS
Lub oil temp 1/1 logic
Working oil temp 1/1 logic
Balance return line temp 1/1 logic
# OS & Engg. To suggest suitable alternative for the above
protections so that same can be implemented in the DAS R&M
works, being executed by CC Engg group.
Stage-I :BFP Gauge Rack
Stage-I :BFP LEC
Stage-I :TG
TG Tripping :
Generator hydrogen gas temp high 2/2 logic
Stator water flow low 2/2 logic
FRF pr low 2/2 logic
Steam inlet pr low 2/2 logic
LP exh. Temp high 2/2 logic
# All logics are 2/2 with redundant trip channel.
# Os & engg. To suggest suitable alternative for the
above protections
# For all above protection cases ATRS/GOV R&M
being processed by CC R&M group
Stage-I :Control Desk
Stage-I :Governor Panel
Stage-I: Governor -Comp Ch (CC)
Stage-I :Interlock Panel
Stage-I : FRF Pr Low
Field Instruments
SG & TG Stage-I:
Field devices trip switches supplied by OEM ,Delta
make- temp switch, pressure switch etc which are still
working even after 20 years of operation.
All transmitters : Rosemount/Emerson
SG & TG Stage-II:
Field devices trip switches mostly supplied by BHEL are
of PS: Switzer make, TS: Indfoss make except
furnace/PA header : SOR make.
All Pr /DP transmitters : Yokogawa.
Problems of Field Instruments
SG & TG Stage-I: Nil.
SG & TG Stage-II:
TS: Indfoss make : set point : drifting problem
RTD: BFP thrust brg- sensor/cable cutting problem( quality to improve,
original RTD –M/s Weir make is very good).
Local TB & DCS- Push fit ( Wago) Terminals - getting loose. No screws are
provided ( in Electrical switch Gear push fit with screw tightening used).
Similar philosophy is used in St-I which are reliable.
Heat prone areas of SG & TG (Mill & Air heater) existing cable are getting
damaged. Steps taken
a) Layout of several location changed b) high temp cable being used
OS & Engg to look for using high temp armored cables in critical heat
prone location
Problems of Field Instruments
SG & TG Stage-II:
-Oxygen Probes – Flue gas O/L oxygen probes
getting eroded fast particularly in SAH A&B due
to duct design( failing within 3 months).
-T/C at same location also getting eroded
Step taken: extra shielding provided.
- Inferior quality sol. Should not be used in
important location: like Nucon, Avcon, Rotex.
Problems & Strategies adopted
to Maintain DCS (H/W, S/W & Network)
Problems: Data back up for trends, events &
configuration
Strategies adopted: in every months trends & events &
configuration : in every two months which are saved in
different network PC & DVD back up
maxDNA trouble shooting chart prepared for easy
diagnosis ( enclosed).
Network security at Rihand enclosed
OFC failure, disables the functioning of remote I/O
panels of CW pp house. In this situation-
No protection will be in service & CW pp will continue to run.
Whether DPU to be provided at local?
# OS/Engg may look for the provision.
Problems in DCS / PLC system
• Error in one port gets transmitted to all.
• CRE 18 & SBC panels always run in secondary,
problem could not be identified.
• maxDNA binary input having no open ckt
monitoring
• Electrical breaker commissioning prob before
commg of DCS.
• Availability of as-built logics print out at site in time.
• No provision of SOE for OFF site PLC.
• Integration of OFF site package( PLC) with main
DCS system
C&I Tripping
• 2007-08 till date: one no.: U4 tripped on 24 volt
charger output over voltage ( Amara Raja).
• Action plan: PE Engg/ Amara Raja are working for
designing a suitable protection for charger
• 2006-07: 02 no. Y adapter & mother rack failure in
PA fan panel of U4 led to trip .
• Action plan: Redundant analog output module
jumper setting change from ‘fail-to-reset’ from ‘fail-
to-hold’ is possible.
Analog Control DPU communication loss with I/O
modules should not cause unit trip if corresponding
protection DPU is in service.
Think Today For Better Tomorrow
THANK YOU