Schedule Development A Methodical Approach COS
Schedule Development A Methodical Approach COS
Chris Carson, PSP, CCM Director Project Controls Alpha Corporation John Potter, PSP Project Controls Manager Alpha Corporation
PMI-CoS College of Scheduling PMI Scheduling Excellence Initiative (SEI) project writing Best Practices and Guidelines Scheduling/Claims
Design or Development?
Refer to 2008 presentation at PMI-CoS national conference Schedule Design; Planning for Schedule Development Separate the two processes
Design first Development second Need to plan (Schedule Design) to create the schedule (Schedule Development)
Schedule Design
Why design a schedule?
A schedule meets the criteria for a project in itself A schedule is a guideline or plan for a project A schedule provides a a methodical approach for a project Keeps the schedule development on track Prevents rework due to late understanding of needs Allows buy-in from end users prior to Development Makes the schedule development session much more meaningful Documents the assumptions and intention of the schedule
For reviewer and approver For future reference To facilitate changes in schedulers Place to capture Lessons Learned
Schedule Design
Scope of Design vs. Development
Design Conceptualizing the schedule
Planning Starting with the end in mind Providing concept of final product Creating organizational structure to fulfill the concept
PMBOK 3rd Ed. The diagram to the right is a Project Time Management (Schedule) process flow diagram. This diagram gives us an idea about how integral the schedule is to the management of the entire project. The six sections related to schedule development are at the center of the diagram.
Every scheduler starts Schedule Development differently Using the basis from Schedule Design, the process can be defined and structured
Schedule Design
Technical Scheduling Components Design Activity Coding structure
Input Driven - Based on need to organize schedule
Look at Stages and Areas (as well as Phases) Stages: Foundations, Structure, Rough-ins Areas: Determined by expected progress Phases: Usually are repetitive sequence activities
Output Driven - Based on need to report to different stakeholders Based on need to filter & isolate
Develop functional Stages, then progress-rate Areas Review use of schedule Identify frequency of updates. Establish smallest activity duration range.
Schedule Design
Reporting
Define all reports Provide examples
Overview for superintendent to correlate his weekly bar chart which will be used for look-ahead schedules
Need monthly data, will update monthly
Important: All sections of the project within each Area should progress at a similar rate Note: The SME (Subject Matter Expert) for each Stage are typically different, but are combined in Areas
They wont be thinking about rate of progress
Schedule Development
Use Sequencing Plan from Design
You may need horizontal (or lateral) logic along with vertical (or linear) logic
Rough-in Inspections (linked floor to floor) are predecessor to Hang Drywall (linked side to side)
Use this Outline Schedule to identify the summary schedule and check for reasonableness Acts as a guideline during detailed development
Try to keep each the similar granularity within each Area (can base on durations)
Summarize to trades, look at count of activities in each trade; should be similar & reasonable Print Detailed Predecessor Report Have report in hand to check relationships
Look in Contract for specification requirements Submittal approval times specification or verify Consider re-submittal cycle for difficult or highly detailed activities Include all Owner scope of work (include permits, permanent telephone and other utilities, owner supplied equipment, other contracts, Health Department approvals, etc.)
Code Owner activities so they can be filtered and tracked
Any delays related to these activities should be captured accurately for the protection of both the Owner and the Contractor
Project Team
Who owns the schedule?
Project Manager? Superintendent? Scheduler? Project Team? It is absolutely imperative that someone on the Team has primary responsibility for maintaining the schedule in order for it to be successfully utilized.
Know the Contract Requirements Scope of the Work Basic CPM logic rules and how they are applied in the software Contractor means & methods Limitations & constraints of the Owner, Contractor, the Site & the Industry
Questions/Comments
45
PMI is a registered trade and service mark of the Project Management Institute, Inc.
Contact Information
Name Title Company Email Phone Name Title Company Email Phone John Potter, PSP Project Controls Manager Alpha Construction & Engineering Corporation [email protected] (O) 757-533-9368 Chris Carson, PSP Corporate Director of Project Controls Alpha Construction & Engineering Corporation [email protected] (O) 757-533-9368 (M) 757-342-5524
46
(M) 206-200-6833
PMI is a registered trade and service mark of the Project Management Institute, Inc.