Checklist No Issue No: 01
BCL02 Date: 29-06-2010 CHECK LIST FOR SETTING OUT OF BUILDINGS
Project Engineering Work Shop Building - Bus Depot at Kegalle Re-checked date Checking Event No:
Section/area Checked after rectification
Date of Check
Result of Rectification of
SL Item Inspection Defects Identified Defects
No
OK Not OK Not
1 Level of the site
2 Base Lines off sets from existing structure
3 Parallel/perpendicular to existing structure
4 Length/width
5 Diagonal checks
6 Cross Checking of dimensions @ 3-4 locations
7 Profile Boards concreted (pegs)
8 TBM (Nos…………)
9 TBM distance form building
10 TBM are fixed permanently (Cl 2.2.1.1 SCA /4/I)
Comments:
TO/WS SE