SmartACU2000D Smart Array Controller Quick Guide (With No PID Module)
SmartACU2000D Smart Array Controller Quick Guide (With No PID Module)
Issue: 03
Part Number: 31500BWD
Date: 2020-09-22
1 Product Overview
Name Model Voltage Level Configuration
Cabinet Dimensions
2
SmartACU2000D-D-02 Components
For simplicity purposes, the following figure shows only the components that you need to operate
and reserved installation positions.
(2) Position for the 24 V DC power module (U02) (12) Position for the PoE module (POE)
(3) AC input terminal of the 24 V power module
(JX02) (13) ATB (Access Terminal Box)
(4) Single-phase surge protective device (SPD)
(F03) (14) Single-phase input switch (QF03)
(5) Three-phase SPD 1 (F01) (15) Three-phase input switch 2 (FU02)
(6) Three-phase SPD 2 (F02) (16) Three-phase input switch 1 (FU01)
(7) Position for the Ethernet switch (SWITCH) (17) RS485 communications terminal (JX01)
(18) Position for the SmartModule1000A01
(8) SmartMBUS CCO (MBUS CCO) (SmartModule)
(9) SmartLogger3000 (SmartLogger) (19) PE bar
(10) Optical fiber adapter (OFA01, OFA02)
3
SmartACU2000D-D-00 and SmartACU2000D-D-05CN Components
For simplicity purposes, the following figure shows only the components that you need to
operate and reserved installation positions.
(1) SmartLogger power adapter (U01) (10) Position for the PoE SPD
(2) Position for the 24 V DC power module
(U02) (11) Position for the PoE module (POE)
(3) AC input terminal of the 24 V power module
(JX02) (12) ATB (Access Terminal Box)
(4) Single-phase SPD (F03) (13) Single-phase input switch (QF03)
(5) Three-phase SPD (F01) (14) Three-phase input switch (FU01)
(6) Position for the Ethernet switch (SWITCH) (15) RS485 communications terminal (JX01)
(7) Position for the SmartMBUS CCO (MBUS (16) Position for the SmartModule1000A01
CCO) (SmartModule)
4
2 Configurations in Typical Scenarios
Fiber Ring Network
Components in dashed-line boxes are optional. To highlight the involved area, the figure does
not show all factory-installed components and cables.
5
The following table describes the components to be configured in the fiber ring network scenario.
Recommended Model or Component
Position Component Quantity
Specifications Source
(Optional)
SmartModule1000A01 1
SmartModule
(Optional) Ethernet
UT-H605 or ES1000 1
switch
Smart array (Optional) 24 V power Purchased
N/A 1
controller supply from Huawei
Fitting bag Optical
N/A 2
for optical module
ring Optical
switchinga N/A 8
jumper
Recommended rated
Miniature circuit breaker
current: 32 A; number of 1
(MCB)
poles: 2
• When the rated AC
voltage on the low-
voltage (LV) side of
the transformer
station is less than or
equal to 600 V, the
rated voltage of the
knife fuse switch
should be greater than
or equal to 600 V.
• When the rated AC
Transforme voltage on the LV side Prepared by • Scenario with a
r station of the transformer the customer double-column
Three-phase
Knife fuse station is greater than transformer: 1
power
switch 600 V and less than or • Scenario with a
switch
equal to 800 V, the dual-split
rated voltage of the transformer: 2
knife fuse switch
should be greater than
or equal to 800 V.
• Recommended rated
current of the fuse: 32
A; rated current of the
knife fuse switch box:
≥ 32 A; number of
poles: 3 (three fuses
for each knife fuse
switch box)
Note a: There are two types of fitting bags for fiber ring switching: with 100M optical modules or
with 1000M optical modules. You can purchase a fitting bag based on the specifications of the
optical modules used on the fiber channel (FC) switch.
6
The following table describes the cables to be prepared by yourself in the fiber ring network
scenario.
Cross-sectional Area
Range of the Cable
No. Cable Recommended Model or Specifications
(Recommended
Value)
• Three-core (L1, L2, and L3) outdoor
armored copper cable
• When the rated AC voltage on the LV side
of the transformer station is less than or
equal to 600 V, the operating voltage
between the three-phase AC power cable
Three-phase AC and the ground should be greater than or • 8–10 mm2 (10 mm2)
1
power cable equal to 600 V. • 8 AWG
• When the rated AC voltage on the LV side
of the transformer station is greater than
600 V and less than or equal to 800 V, the
operating voltage between the three-
phase AC power cable and the ground
should be greater than or equal to 1000 V.
CAT 5E outdoor shielded network cable with
(Optional) an outer diameter less than 9 mm (0.35 in.)
2 Peripheral network and internal resistance less than or equal to N/A
cable 1.5 ohms/10 m (1.5 ohms/393.70 in.), as well
as shielded RJ45 connectors
Peripheral RS485 Computer cable (DJYP2VP2-22 2x2x1) or • 0.5–1 mm2 (1 mm2)
3 communications armored shielded twisted pair that can be • 20–18 AWG (18
cable used outdoors, as well as OT-M4 terminals AWG)
• 6–16 mm2 (16 mm2)
4 Cabinet PE cable Outdoor copper cable and OT-M6 terminals
• 10–6 AWG (6 AWG)
Four-core or eight-core single-mode armored
optical cable with a transmission wavelength
5 Optical fiber cable N/A
of 1310 nm and an outer diameter less than
or equal to 18 mm (0.71 in.)
• Standard connection: two-core outdoor
armored copper cable • 4–6 mm2 (4 mm2)
Single-phase AC
6 • Connection through a tube: single-core • 12–10 AWG (12
power cable
outdoor copper cable AWG)
• Operating voltage to the ground ≥ 300 V
• Standard connection: two-core outdoor
• 2.5–4 mm2 (2.5
armored copper cable
(Optional) 24 V DC mm2)
7 • Connection through a tube: single-core
output power cable • 14–12 AWG (14
outdoor copper cable
AWG)
• Operating voltage to the ground ≥ 300 V
7
4G LTE Network
Components in dashed-line boxes are optional. To highlight the involved area, the figure does
not show all factory-installed components and cables.
8
The following table describes the components to be configured in the 4G LTE network scenario.
9
The following table describes the cables to be prepared by yourself in the 4G LTE network
scenario.
Cross-sectional Area
No. Cable Recommended Model or Specifications Range of the Cable
(Recommended Value)
Three-core (L1, L2, and L3) outdoor
•
armored copper cable
• When the rated AC voltage on the LV
side of the transformer station is less
than or equal to 600 V, the operating
voltage between the three-phase AC
power cable and the ground should be
Three-phase AC power • 8–10 mm2 (10 mm2)
1 greater than or equal to 600 V.
cable • 8 AWG
• When the rated AC voltage on the LV
side of the transformer station is
greater than 600 V and less than or
equal to 800 V, the operating voltage
between the three-phase AC power
cable and the ground should be
greater than or equal to 1000 V.
Computer cable (DJYP2VP2-22 2x2x1) or
Peripheral RS485 armored shielded twisted pair that can be • 0.5–1 mm2 (1 mm2)
2
communications cable used outdoors, as well as OT-M4 • 20–18 AWG (18 AWG)
terminals
Outdoor copper cable and OT-M6 • 6–16 mm2 (16 mm2)
3 Cabinet PE cable
terminals • 10–6 AWG (6 AWG)
A 20 m (65.62 ft) long network cable
Network cable from delivered with Huawei CPE (If the length is
4 the PoE module to the insufficient, prepare a cable with the same N/A
CPE specifications as a peripheral network
cable.)
•Standard connection: two-core outdoor
armored copper cable
Single-phase AC power • Connection through a tube: single-core • 4–6 mm2 (4 mm2)
5
cable outdoor copper cable • 12–10 AWG (12 AWG)
• Operating voltage to the ground ≥ 300
V
• Standard connection: two-core
outdoor armored copper cable
• 2.5–4 mm2 (2.5 mm2)
(Optional) 24 V DC • Connection through a tube: single-
6 • 14–12 AWG (14
output power cable core outdoor copper cable
AWG)
• Operating voltage to the ground ≥
300 V
10
4G Network
Components in dashed-line boxes are optional. To highlight the involved area, the figure does
not show all factory-installed components and cables.
11
The following table describes the components to be configured in the 4G network scenario.
Component
Position Component Recommended Model or Specifications Quantity
Source
(Optional)
SmartModule1000A01 1
SmartModule
Purchased
(Optional)
UT-H605 or ES1000 from 1
Ethernet switch
Huawei
Smart (Optional) 24
N/A 1
array V power supply
controlle Prepared by
r Standard SIM card of a local carrier (size:
SIM card the 1
25 mm x 15 mm)
customer
Delivered
4G antenna N/A with the 1
product
Miniature
circuit breaker Rated current: 32 A, number of poles: 2 1
(MCB)
• When the rated AC voltage on the LV
side of the transformer station is less
than or equal to 600 V, the rated
• Scenario
voltage of the knife fuse switch should
with a
be greater than or equal to 600 V.
Transfor Prepared by double-
• When the rated AC voltage on the LV
mer the column
Three- side of the transformer station is
station Knife customer transformer:
phase greater than 600 V and less than or
fuse 1
power equal to 800 V, the rated voltage of the
switch • Scenario
switch knife fuse switch should be greater
with a dual-
than or equal to 800 V.
split
• Recommended rated current of the
transformer:
fuse: 32 A; rated current of the knife
2
fuse switch box: ≥ 32 A; number of
poles: 3 (three fuses for each knife fuse
switch box)
12
The following table describes the cables to be prepared by yourself in the 4G network scenario.
Cross-sectional Area
No. Cable Recommended Model or Specifications Range of the Cable
(Recommended Value)
• Three-core (L1, L2, and L3) outdoor
armored copper cable
• When the rated AC voltage on the LV side
of the transformer station is less than or
equal to 600 V, the operating voltage
between the three-phase AC power cable
and the ground should be greater than or
Three-phase AC • 8–10 mm2 (10 mm2)
1 equal to 600 V.
power cable • 8 AWG
• When the rated AC voltage on the LV side
of the transformer station is greater than
600 V and less than or equal to 800 V, the
operating voltage between the three-
phase AC power cable and the ground
should be greater than or equal to 1000
V.
CAT 5E outdoor shielded network cable with
(Optional) an outer diameter less than 9 mm (0.35 in.)
2 Peripheral network and internal resistance less than or equal to N/A
cable 1.5 ohms/10 m (1.5 ohms/393.70 in.), as well
as shielded RJ45 connectors
Peripheral RS485 Computer cable (DJYP2VP2-22 2x2x1) or
• 0.5–1 mm2 (1 mm2)
3 communications armored shielded twisted pair that can be
• 20–18 AWG (18 AWG)
cable used outdoors, as well as OT-M4 terminals
• 6–16 mm2 (16 mm2)
4 Cabinet PE cable Outdoor copper cable and OT-M6 terminals
• 10–6 AWG (6 AWG)
• Standard connection: two-core outdoor
armored copper cable
Single-phase AC • 4–6 mm2 (4 mm2)
5 • Connection through a tube: single-core
power cable • 12–10 AWG (12 AWG)
outdoor copper cable
• Operating voltage to the ground ≥ 300 V
• Standard connection: two-core outdoor
armored copper cable • 2.5–4 mm2 (2.5 mm2)
(Optional) 24 V DC
6 • Connection through a tube: single-core • 14–12 AWG (14
output power cable
outdoor copper cable AWG)
• Operating voltage to the ground ≥ 300 V
13
3 Installing the Cabinet
3.1 Preparations
Installation Dimensions Marking-off Template
(Delivered with the Cabinet)
Bolts
• When the cabinet is installed on a wall, you need to prepare M12x60 stainless steel exploded
expansion bolts.
• When the cabinet is installed on a support or a pole, use the M12x40 bolt assemblies
delivered with the cabinet.
Wall-mounted Installation
Avoid drilling holes in the water pipes and power cables buried in the wall.
• To prevent dust inhalation or contact with eyes, wear safety goggles and an anti-dust mask
when drilling holes.
• Clean up any dust in and around the holes using a vacuum cleaner and measure the distance
between holes. If the holes are inaccurately positioned, drill holes again.
• Level the head of the expansion sleeve with the concrete wall after removing the bolt, spring
washer, and flat washer. Otherwise, the mounting plate will not be securely installed on the
concrete wall.
14
1. Determine the hole positions based on the
marking-off template, and then mark the 3. Secure the cabinet.
hole positions using a marker.
2. Install expansion bolts.
Support-mounted Installation
1. Determine the hole positions
based on the marking-off
template, and then mark the 3. Install bolt assemblies. 4. Secure the cabinet.
hole positions using a marker.
2. Drill holes. (You are advised
to apply anti-rust paint to the
holes.)
Pole-mounted Installation
• If you need to pole-mount the smart array controller, prepare pole mounting brackets
based on the dimensions of the smart array controller. You are advised to use M12 U-
shaped bolts to secure the pole-mounting brackets.
• The figure is for reference only. The actual pole and pole mounting brackets prevail.
15
1. Secure the pole mounting brackets. 2. Secure the cabinet. (For details, see
"Support-mounted Installation.")
• Before opening the cabinet door, turn off all upstream switches for the smart array
controller to power off the controller. If you have to operate an energized smart array
controller, wear insulation gloves and take preventive measures.
• If you need to open the cabinet door on rainy or snowy days, take protective measures to
prevent rain or snow from entering the cabinet. If it is impossible to take protective
measures, do not open the cabinet door on rainy or snowy days.
1. Remove the security torx wrench bound 2. Open the cabinet door and install the support
to the cabinet base and use the wrench bar.
to loosen security torx screws.
16
5 Installing Components
17
5. Connect the GE4 port on the SmartModule to the LAN port on the SmartLogger using the
network cable delivered with the SmartModule.
6. Connect the preinstalled RS485 cable to the COM port on the SmartLogger based on the
label.
7. Connect the preinstalled power cable to the 12V 1A port on the SmartModule based on the
cable label.
18
4. Connect the FE1 port on the Ethernet
switch to the WAN port on the
SmartLogger using the network
cable delivered with the Ethernet
switch.
5. Connect the preinstalled power cable
to the power port on the Ethernet
switch based on the label.
19
5.5 Installing the SIM Card and 4G Antenna
Installing the SIM Card
1. Remove the cables preinstalled on the SmartLogger and label them.
2. Take the SmartLogger out of the installation position.
3. Install the SIM card, reinstall the SmartLogger, and secure it.
4. Reconnect the cables based on the labels.
Secure the cable using the supplied cable clips. The cable is long and should be bound in the
cabinet after installation.
20
6 Connecting Cables
Connect cables in accordance with the installation laws and regulations of the country or region
where the project is located.
Common Connection
If you choose common connection, ensure
that an appropriate cable is available.
1. Remove the locking cap and plug from
the cable gland.
2. Route the cable through the locking
cap and then the cable gland.
3. Connect the cable.
4. Tighten the locking cap.
5. Check that the cable is connected
correctly and securely. Seal the cable
gland and cable hole using the
supplied firestop putty.
6. Clear foreign matter from the cabinet.
Prepare an appropriate tube based on the diameters of the cable holes at the bottom. It is
recommended that the tube specifications comply with the waterproof connector specifications.
For example, for a 3/4 in. waterproof connector, a 3/4 in. tube is recommended.
Nut Conduit
Fitting
21
1. Remove the locking cap and plug
from the waterproof connector, and
then remove the waterproof
connector.
2. Secure the tube fitting using the nut
provided with the tube.
3. Route the cable through the conduit
and then the fitting.
4. Connect the cable.
5. Secure the fitting to the conduit.
6. Check that the cable is connected
correctly and securely. Then take
appropriate measures to ensure that
the tube conduit and fitting are
secured reliably, and seal the cable
hole using supplied firestop putty.
7. Clear foreign matter from the
cabinet.
You can connect a peripheral cable to the smart array controller in common mode or through a
tube.
• The way of handling the bottom waterproof connector varies depending on the connection
method. For details, see section 6.1 "Selecting a Connection Method."
• Cables to the cabinet interior are connected in the same way irrespective of which connection
method is used. The following uses common connection as an example.
Insulation layer
• Avoid scratching the core
wire when stripping a cable. Core wire
Heat
• The cavity formed after the
shrink
conductor crimp strip of the
OT terminal is crimped must tubing
wrap the core wires
completely. The core wires
must contact the OT terminal
closely.
• Wrap the wire crimping area Crimping
with heat shrinkable tubing tool
or PVC insulation tape. The
heat shrink tubing is used as
an example. Heat
• When using a heat gun, gun
protect the devices from
being scorched.
22
6.4 Connecting the PE Cable
1. Crimp an OT terminal.
2. Secure the PE cable.
• Connect two optical cables in a ring optical network, and connect one optical cable in a star
optical network.
• As optical cables are hard, prepare optical cables before routing them into the cabinet.
• Only professionals are allowed to connect optical cables.
23
5. Connect one end of the optical
jumper to the fiber adapter.
6. Route the other end of the
optical jumper through the
cable hole on the side of the
ATB, and then connect the
cable to the ATB.
7. Connect the peripheral optical
cable to the ATB, splice the
optical cable and the optical
jumper, and then wind the
spliced cable around the fiber
spool on the ATB.
8. Check that the cables are
connected correctly and
securely. Then reinstall the
optical cable fastener and ATB
cover.
6.6 Connecting the 4G LTE Cable
1. Connect the factory-installed network cable to 2. Connect the CPE network cable to the PoE
the DATA port on the PoE module, and the port on the PoE module.
factory-installed power cable to the PoE
module.
24
• Connect the L1-1, L2-1, and L3-1
wires from the FU01 switch
respectively to ports A, B, and C on
the transformer station busbar 1
over a three-phase power switch.
• Connect the L1-2, L2-2, and L3-2
wires from the FU02 switch
respectively to ports A, B, and C on
the transformer station busbar 2
over a three-phase power switch.
• Ensure that the L1, L2, and L3 wires
are connected in correct phase
sequence.
Transformer station
Three-phase
power switch 1
Transform
er station
busbar 1
A/B/C
Three-phase
power switch 2
Transform
er station
busbar 2
A/B/C
Connect peripheral RS485 communications cables to the JX01 terminal block. All RS485
communications cables are connected in the same way. This section describes how to connect two
RS485 communications cables.
No. Port on the JX01 Terminal Block Definition
1 RS485-1 (+) RS485A, RS485 differential signal+
2 RS485-1 (–) RS485B, RS485 differential signal–
3 RS485-2 (+) RS485A, RS485 differential signal+
4 RS485-2 (–) RS485B, RS485 differential signal–
• For the smart array controller that supports the access of two MBUS routes, do not connect a
peripheral RS485 communications cable to the RS485-3 port (ports 5 and 6 on the JX01 terminal
block) because the MBUS CCO module communications cable has been connected to this port.
• JX01 ports 7, 8, 9, 10, 11, and 12 can be connected to the RS485 cable only after the
SmartModule is installed.
25
1. Prepare a communications cable.
26
6.10 (Optional) Connecting the DC Output Power Cable to the 24 V Power
Module
1. Prepare a cable.
2. Connect the cable to the 24V OUT+ and 24V OUT- ports on the power module.
3. Bind the cable.
1. Prepare a cable.
2. Connect the cable to the
single-phase input switch.
27
7 Verifying the Installation
Yes □ No □ N/A
1. The cabinet and all components are installed properly.
□
2. All upstream switches for the cabinet and all switches inside the cabinet Yes □ No □ N/A
are OFF. □
3. All cables are connected correctly and securely, without exposed metal.
Cables are bound neatly, and cable ties are secured evenly and properly
Yes □ No □ N/A
in the same direction. There are no sharp edges at the cutting positions.
□
There are no sundries such as unnecessary adhesive tape or cable ties on
cables.
4. Routing for the power cables and signal cables meets the requirements
Yes □ No □ N/A
for routing strong-current and weak-current cables and complies with the
□
cable routing plan.
5. The locking caps on all waterproof connectors in use at the bottom of the
cabinet are tightened, or the cable routing pipes (if used) are secured to
Yes □ No □ N/A
the cabinet. All waterproof connectors or cable routing pipes in use are
□
applied with firestop putty. Idle cable holes at the bottom of the cabinet
are plugged and the locking caps are tightened.
6. The cover on the USB port is tightened, and the USB cable inside the Yes □ No □ N/A
cabinet is secure. □
Yes □ No □ N/A
7. The cabinet interior is clean, without dust, dirt, or foreign matter.
□
8. The paint on the cabinet exterior is intact. Immediately repaint the part Yes □ No □ N/A
where paint has fallen off to prevent corrosion. □
Ensure that the power voltage of the smart array controller is within the operating voltage
range, and the three-phase input voltage is within the MBUS module operating voltage range.
1. Turn on the single-phase power switch that controls the power supply from the remote
transformer station to the smart array controller.
2. Turn on the three-phase power switch that controls the power supply from the remote
transformer station to the smart array controller.
• If the smart array controller supports the access of one MBUS route, turn on the
corresponding three-phase power switch.
• If the smart array controller supports the access of two MBUS routes, turn on the
corresponding three-phase power switches.
3. Check that the input voltages of all switches of the smart array controller are within
appropriate operating voltage ranges using a multimeter.
4. Turn on the QF03 single-phase input switch in the smart array controller.
5. Turn on the three-phase input switch in the smart array controller.
• If the smart array controller supports the access of one MBUS route, turn on the FU01
three-phase input switch.
• If the smart array controller supports the access of two MBUS routes, turn on the FU01
and FU02 three-phase input switches.
28
• For details about the status of the energized SmartLogger and MBUS CCO
module as well as the commissioning procedure, see the SmartLogger3000 User
Manual. When the smart array controller communicates with the solar inverter
over MBUS, log in to the embedded WebUI of the SmartLogger3000, choose
Monitoring > MBUS > Networking Settings, and set Networking to Enable
(default value). When the smart array controller communicates with the solar
User Manual
inverter only over RS485, set Networking to Disable.
• The Ethernet switch can be directly put into use without commissioning after
power-on.
If a screw used for securing the cabinet door is lost, use the security torx screw in the fitting bag.
10 FAQ
10.1 How Do I Power Off the System Before Maintenance?
29
10.2 How Do I Determine an Unavailable Single-/Three-Phase SPD?
If an SPD is damaged or its indication window is red, the SPD is deemed unavailable.
30
Huawei Technologies Co., Ltd.
Huawei Industrial Base, Bantian, Longgang
Shenzhen 518129, People's Republic of China
www.huawei.com