Last month (September) Activities:
HV – Electrical:
1. 33 KV MV cable laying & Termination works completed in SUT-1
2. 33KV MV Looping cable Termination works in capacitor bank COMPLETED
3. Capacitor Bank control cable pulling completed & Termination works ongoing
4. Capacitor bank Earthing works & Contact Resistance Test completed.
5. OHL clamp & conductor Installation works at AIS area.
6. MV cable Cleat installation works done
7. Diesel Generator accessories Installation works.
8. Auxilary transformer LV cable Termination works.
9. Auxiliary Transformer -1 &2 Cleat Fixing work Completed
10. Fire sealant works is ongoing at Basement.
11. CCTV installation work Indoor / outdoor.
12. Excavation & PVC pipe laying works for CCTV.
13. CCTV- Pole & JB Installation works.
14. Earthing cable dressing works all area.
15. Cable dressing & tagging work.
16. RFI comment rectification works.
17. Assisting ABB for Testing.
18. Housekeeping works at all area
Testing & Commissioning
1. Power Transformer-2, Testing and commissioning Works.
2. Power Transformer -3,Testing and commissioning Works.
3. 33kV Surge arrestor Test Completed (Witness)
4. 33kV GIS-Relay Testing
5. 33kV GIS-Modification
6. AIS Testing in progress.
7. Auxilary transformer Testing works
8. Earthing Transformer Testing works.
9. DC System testing in progress.
10. Capacitor bank testing In progress
11. MV cable Testing (VLF TEST) done in SUT-1.
12. Telecommunication panel configuration – HV side (internal) in progress.
13. Telecommunication panel configuration – ESF side (internal)in progress.
14. SCADA/DCS System Configuration and Signal Checks (Internal)
15. Cable Differential Protection Panel Testing.
16. Transformer Differential Protection Panel Testing.
17. AVR and LCC panel Testing in progress.
18. C14 station level check done – ESF side (Witness)
19. Tariff meter panel Configuration - ESF side (Internal)
20. Outstation panel Configuration -ESF side (Internal)
21. CKT-1 Energization preparation works.
22. Red mark-up preparation and submission.
23. SAT Procedure preparation & submission works.
24. SAT Report preparation & submission works.
Next month (October) activities:
1. 33 KV MV cable laying & Termination works will be completed From GIS to Capacitor Bank.
2. 33KV MV Looping cable Termination works in capacitor bank.
3. Capacitor Bank control cable Termination works.
4. OHL clamp & conductor Installation works at AIS area will be completed.
5. Diesel Generator accessories Installation works.
6. Earthing cable dressing works all area.
7. Cable dressing & tagging work.
8. RFI comment rectification works.
9. Assisting ABB for Testing.
10. CCTV installation work Indoor / outdoor.
11. Fire sealant installation works.
12. Housekeeping works at all area
Testing and commissioning (October month):
1. Power Transformer-1,2, Testing and Pre commissioning Works.
2. Power Transformer -3, Testing and Pre commissioning Works.
3. 33KV GIS Testing in progress.
4. SUT-1,2,3 Stability Test
5. AIS Testing in progress.
6. Auxilary transformer Testing works
7. Earthing Transformer Testing works.
8. FMS Channel Testing and input checks (Internal)
9. Capacitor bank testing works.
10. FMS Check Connection of Interface & FO cables (Internal)MV cable Testing (VLF TEST)
11. Telecommunication panel configuration – HV side (internal) in progress.
12. Telecommunication panel configuration – ESF side (internal) in progress.
13. SCADA/DCS System Configuration and Signal Checks (Internal)
14. AVR Panels Signal Checks (Internal)
15. Transformer Differential Protection Panel Testing.
16. AVR and LCC panel Testing in progress.
17. Diesel Generator Testing will be started.
18. CKT-1 Energization works.
19. SAT Procedure preparation & submission works.
20. SAT Report preparation & submission works.
21. Red mark-up preparation and submission.