PROJECT MANAGEMENT - Module
PROJECT MANAGEMENT - Module
Learning Outcomes
• After studying this chapter, students should be able to:
• Define what a project is
• List and discuss the attributes of a project
• Explain what is meant by project objective
• Define what is meant by project deliverable
• Provide examples of projects
• Discuss project constraints
• Describe the phases of the project life cycle
• Define and apply project management
• Discuss the steps of the planning process
• Identify the three elements of the executing process
Project Attributes
A project is an endeavor to accomplish a specific objective through a unique set of interrelated tasks and
the effective utilization of resources. The following attributes help define a project:
• A project has a clear objective that establishes what is to be accomplished. It is the tangible end
product that the project team must produce and deliver. The project objective is usually defined
in terms of end product or deliverable, schedule, and budget. Furthermore, it is expected that
the work scope will be accomplished in a quality manner and to the customer’s satisfaction.
• A project is carried out through a series of interdependent tasks in a certain sequence in order
to achieve the project objective.
• A project utilizes various resources to carry out the tasks.
• A project has a specific time frame, or finite life span - a start time and a date by which the
objective must be accomplished.
• A project may be a unique or one-time endeavor such as developing a new product, building a
house, or planning a wedding.
• A project has a sponsor or customer that provides the funds necessary to accomplish the
project. In a business setting, the customer can be internal or external to your organization.
• Finally, a project involves a degree of uncertainty and is based on certain assumptions and
estimates for the project budget, schedule, and work scope.
Planning Phase
• The planning phase is the second phase of the project life cycle, It includes defining the project
scope, identifying resources, developing a schedule and budget, and identifying risks, all of
which make up the baseline plan for doing the project work.
• Shows how the project scope will be accomplished within budget and on schedule
• Plan the work and work the plan
• The detailed plan results in a baseline plan
• What needs to be done— scope, deliverable
• How it will get done– activities, sequence
• Who will do it– resources, responsibilities
• How long it will take– durations, schedule
• How much it will cost— budget
• What the risks are
• Benchmark the baseline plan to allow for comparison with actual progress.
• Include the people that will actually do the work in the planning process.
• They have knowledge of detailed activities to be done.
• Participation also builds commitment.
Performing Phase
• In the performing phase, the project plan is executed and work tasks are carried out to produce
all the project deliverables and to accomplish the project objective.
• The project progress is monitored and controlled to assure the work remains on
schedule and within budget, the scope is fully completed according to specifications,
and all deliverables meet acceptance criteria.
• Any changes need to be documented, approved, and may be incorporated into an updated
baseline plan.
• This is the third phase of the project life cycle.
• The project manager leads the project team to complete the project.
• The pace of the project increases as more and various resources are involved in the
project.
• It is necessary to monitor and control the project's progress by comparing
accomplishments to the baseline plan.
• Corrective actions are taken if a project is off track.
• Changes are managed and controlled through documentation, approval, and
communication with agreement between the sponsor and the contractor.
• Some change is trivial
• The end of the phase, customer satisfaction, is achieved when the work and deliverables
are accepted by the customer and the project objective is accomplished.
• Several alternative actions may be evaluated to determine the best approach to bring the
project back within the scope, schedule, and budget constraints of the project.
• Determine if any sacrifices to scope, budget, schedule, or quality are necessary to accomplish
the project.
• The costs of changes vary with the timing in the project– generally, the later in the project that
changes are identified, the greater their effect on accomplishing the project objective.
Closing Phase
In the closing phase, project evaluations are conducted, lessons learned are identified and documented
to help improve performance on future projects, and project documents are organized and archived.
• This is the final phase of the project life cycle
• It includes a variety of actions such as:
• Collecting and making final payments
• Staff recognition and evaluation
• Conducting a post project evaluation
• Documenting lessons learned
• Archiving project documents
• Using a knowledge base to record lessons learned and post-project evaluation
• A knowledge base is helpful to retrieve the lessons and information that can help with
doing business with the customer or other customers in the future.
Learning Outcomes
After studying this chapter, students should be able to:
• Establish a clear project objective
• Prepare a project scope document
• Discuss the importance and elements of a project quality plan
• Develop a work breakdown structure
• Prepare a responsibility assignment matrix
• Describe how to define specific activities
• Create a network diagram
WBS
• The top figure depicts the WBS for the consumer market study project example. This project is
also the example used in the Microsoft Project appendices.
• Have students examine the relationship between this figure and the entries in the
Microsoft Project task list.
• The bottom figure depicts an indentured list for the work breakdown structure.
• For each of the work packages, the deliverable is listed.
• This format is helpful for large projects where a diagram would become too large and
unwieldy.
Assign Responsibility
• A responsibility assignment matrix (RAM) defines who will be responsible for the work. It is a
tool used to designate the individuals responsible for accomplishing the different work items in
the work breakdown structure (WBS).
• This figure depicts the RAM for the WBS in Figure 4.1, the community festival project.
• The RAM often uses a P to designate primary responsibility and an S to indicate support
responsibility for a specific work item.
• The RAM shows all the individuals associated with each work item in the WBS, as well as all the
work items associated with each individual.
• Only one individual should be designated as the lead, or primary, person responsible for each
work item.
Define Activities
• Using the WBS, the individual or team responsible for each work package must next define all
the specific activities that need to be performed to produce the end item, or deliverable.
• Breaking down each work package into its component activities reveals the level at
which each activity must be performed to produce the deliverable.
• Some activities may not be easily definable.
• When all the specific activities have been defined for all of the work packages, they should be
consolidated into a comprehensive activity list.
• Because of the allocation of resources, there may be wait time between the end of one
activity and the start of another one.
• This figure shows the work breakdown structure for a consumer market study project. It depicts
the specific activities that need to be performed for each work package.
• Have the students compare this list to the entries for the tasks in the Microsoft Project
appendix.
Sequence Activities
• A network diagram defines the sequence of how the activities will get done. It is a tool for
arranging the specific activities in the best sequence and defining their dependent relationships.
• The three most common techniques of network diagramming are program evaluation and
review technique (PERT), the critical path method (CPM), and the precedence diagramming
method (PDM).
• In the past, there were distinguishable methodological differences between PERT and
CPM. Today, however, when most people refer to a CPM diagram or PERT chart, they
mean a generic network diagram.
• The top figure shows a complete network diagram for a consumer market study project, with
the person responsible for each activity included on the diagram.
• The bottom figure shows a network diagram for a web-based reporting system project.
Network Principles
• Each activity is represented by a box in the network diagram and the description of the activity
is written within the box, as shown in this figure.
• Activities consume time, and their description usually begins with a verb (such as get, wash, and
dry in this example).
• Activities have a dependent relationship—that is, they are linked in a logical sequence in a
network diagram to show which activities must be finished before others can start.
• Certain activities have to be done in serial sequence.
• Some activities may be done concurrently.
Loops
• An illogical relationship among activities is known as a loop.
• In preparing a network diagram, drawing activities in a loop is not acceptable because it portrays
a path of activities that perpetually repeats itself.
Laddering
• Some projects have a set of activities that are repeated several times.
• The top figure shows a series of activities that must be done in serial sequence, which means
that, for an activity with three people, at any one time only one person is working while two
other people are waiting.
• The middle figure shows a set of activities that can be performed concurrently. However, it is
often not practical to perform the activities in this way because the organization would need
triple the experts– one for each room.
• The bottom figure shows a technique known as laddering. This approach allows the project to
be completed in the shortest possible time, while making the best use of available resources.
Create Network Diagram
• A network diagram is a drawing of the activities for a project, displayed in boxes in their logical
sequence and connected by arrows to indicate dependent relationships. The network diagram
shows how the project should be performed from start to completion.
• Three questions need to be answered regarding each activity. The network is based upon the
answers:
1. Which activities must be finished immediately before this activity can be started?
2. Which activities can be done concurrently with this activity?
3. Which activities cannot be started until immediately after this activity is finished?
• Guidelines for the level of detail in the network diagram are:
1. Based on the work breakdown structure for a project; specific activities should be
defined for each work package.
2. It may be preferable to draw a summary-level network first that depicts a small number
of higher level activities and then expand to a more detailed network.
3. The level of detail may be determined by certain obvious interface or transfer points
such as a change in responsibility or if there is a tangible output or product or
deliverable as a result of an activity.
4. Activities should not be longer in estimated duration than the project progress review.
• It is not unusual to progressively elaborate the network diagram as the project progresses and
more information becomes clear.
• Sub-networks can be used to represent similar projects for different customers. Certain portions
of projects may include the same types of activities in the same sequence and with the same
dependent relationships.
DEVELOPING THE SCHEDULE
Learning Outcomes
After studying this chapter, students should be able to:
• Estimate the resources required for activities
• Estimate the duration for an activity
• Determine the earliest start and finish times for activities
• Determine the latest start and finish times for activities
• Explain and determine total slack
• Prepare a project schedule
• Identify and explain the critical path
• Discuss the project control process
• Develop updated schedules based on actual progress and changes
• Discuss and apply approaches to control the project schedule
This figure depicts the network diagram for a consumer market study, with the estimated durations in
days for each activity.
• What are the realistic estimates for the activities shown?
• What happens if an activity is delayed and will be its impact on the project?
• What happens if an activity finishes early?
“Pilot-Test Questionnaire”
• When “Develop Draft Questionnaire” is finished on day 13, “Pilot-Test Questionnaire” can start.
It has an estimated duration of 20 days, so its ES is day 13 and its EF is day 33.
“Review Comments & Finalize Questionnaire”
• When “Pilot-Test Questionnaire” is finished on day 33, “Review Comments & Finalize
Questionnaire” can start. It has an estimated duration of 5 days, so its ES is day 33 and its EF is
day 38.
“Prepare Mailing Labels,” "Print Questionnaire," "Develop Data Analysis Software," and "Develop
Software Test Data"
• When “Review Comments & Finalize Questionnaire” is finished on day 38, “Prepare Mailing
Labels,” "Print Questionnaire," "Develop Data Analysis Software," and "Develop Software Test
Data" can all start.
• The ES for each activity is 38, but they each have different EFs.
• “Prepare Mailing Labels,” has an estimated duration of 2 days, so its EF is day 40.
• "Develop Data Analysis Software" has an estimated duration of 10 days, so its EF is day 48.
• "Develop Data Analysis Software" has an estimated duration of 12 days, so its EF is day 50.
• "Develop Software Test Data" has an estimated duration of 2 days, so its EF is day 40.
“Prepare Report”
• When “Analyze Results” is finished on day 128, “Prepare Report” can start.
• It has an estimated duration of 10 days, so its ES is day 128 and its EF is day 138.
• The required completion time for this entire project is 130 days. 138 days is 8 days beyond the
required completion time, therefore the project was not completed in the required time.
“Prepare Report”
Now let us look at how to set up the backward calculations for the consumer market study project we
just analyzed.
• The required completion time for the project is 130 working days.
• Therefore, the latest that “Prepare Report,” the last activity, can finish is day 130, and
the latest that it can start is day 120 because its estimated duration is 10 days.
• In order for “Prepare Report” to start on day 120, the latest that “Analyze Results” can finish is
day 120. If the LF for “Analyze Results” is day 120, then its LS is day 112 because its estimated
duration is 8 days.
“Analyze Results”
• In order for “Prepare Report” to start on day 120, the latest that “Analyze Results” can finish is
day 120.
If the LF for “Analyze Results” is day 120, then its LS is day 112 because its estimated duration is 8 days.
• In order for “Analyze Results” to start on day 112, the latest that “Input Response Data” can
finish is day 112.
Total Slack
• Total slack is sometimes called float.
• It is the difference between EF time of last activity and the project required completion
time.
• Total slack is calculated for each of the activities by finding the difference between the EF time
of the activity and the LF of the activity.
• You also look at the difference between the ES and LS of the activity.
• Negative slack indicates:
• A lack of slack over the entire project
• The amount of time an activity must be accelerated to complete the project by the
required completion time
• Positive slack indicates the maximum amount of time that the activities on a particular path can
be delayed without jeopardizing completion of the project by the required completion time.
• If the total slack is zero, the activities on the path do not need to be accelerated, but
cannot be delayed.
Critical Path
• The critical path is this longest path in the overall network diagram.
• One way to determine which activities make up the critical path is to find which ones have the
least amount of slack.
•
Critical Path Through a Project
• This table shows slack values for each activity in the consumer market study project we just
analyzed.
• Those with -8 as the total slack are the activities on the critical path.
• The figure on the bottom of the slide depicts the critical path through the network diagram for
the consumer market study project.
Change in Slack for Critical Path
This figure depicts the change in the critical path if the estimated duration of the Mail Questionnaire &
Get Responses task is reduced from 65 days to 55 days.
• Note that the tasks on the critical path now have a total slack of 2, the least amount slack in the
project.
Free Slack
Free slack is the amount of time a specific activity can be postponed without delaying the earliest start
time of its immediately succeeding activities.
Free slack is calculated by:
• Finding the lowest of the values of total slack for all the activities entering into a specific activity
• Then subtracting that value from the values of total slack for the other activities also entering
into that same activity
Control Schedule
Schedule control involves four steps:
1. Analyzing the schedule to determine which areas may need corrective action
2. Deciding what specific corrective actions should be taken
3. Revising the plan to incorporate the chosen corrective actions
4. Recalculating the schedule to evaluate the effects of the planned corrective actions
• If the planned corrective actions do not result in an acceptable schedule, these steps need to be
repeated.
• A concentrated effort to accelerate project progress must be applied to the paths with negative
slack.
• Activities that are near term (that is, that are in progress or to be started in the
immediate future)
• Activities that have long estimated durations
• The amount of slack should determine the priority with which these concentrated efforts are
applied.
• A change in the estimated duration of any activity on that path will cause a corresponding
change in the slack for that path and may shift the critical path.
• Eliminating negative slack by reducing durations of activities will involve a trade-off in the form
of an increase in costs or a reduction in the scope of the project.