SPICES
SPICES
ON
SPICE MILL
PROPRIETOR : XXXXX
ADDRESS OF THE PROPRIETOR : YYYYY
DIST............ STATE.................
CONSTITUTION : PROPRIETORSHIP
CATEGORY OF UNIT : MICRO UNIT
FATHER NAME : XXXXXX
DATE OF BIRTH : XX-YY-ZZZZ
CATEGORY OF THE PROPRIE TOR : XXXXXX
QUALIFICATION : XXXXXX
LOCATION OF UNIT : XXXXXX
Spices are very important and essential for adding and enhancing flavor, taste and
scent in preparation of food. They are also useful in preparation of certain medicine.
India is the largest producer, consumer and exporter of spices Andhra Pradesh,
Gujarat, Orissa, Rajasthan are major states producing varieties of spices. Spices are
heavily used in Indian household for preparing food. They give aroma, taste and
flavor to food. Curry powder, extensively used in Indian recipes, contains some time
more than 20 different spices. Even in foreign countries, Indian spices are
extensively used in preparation of food. Some of spices have medicinal properties
and can be used in preparation of medicines and ayurvedic & cosmetic products.
The promoter is reported to have good financial standing presently. The Promoters is
actively associated with the implementation of the project. Promoter is over all in
charge of the working of the unit.
India is largest consumer of spices and with the growth of population; there will be
huge demand of spices which is increasing. Moreover, the varied tastes and habits
of the people, there is even increasing demand for high quality spice and
curry/masala powder. Even there is a good scope for exporting spices to other
countries. There is a growing demand of pure/unadulterated grounded spices from
the customers who are increasingly informed these days. With various food
standards such as FSSAI, FSMS, ISI and ISO standards implementation, there can
be huge market growth for manufacturer for packed spice and curry powder. Raw
materials are easily available from the local market anywhere in India. Marketing of
spices is not complicated. Umpteen number of retail shops in and around the unit
would be the prospective buyers of spices in bulk.
The total estimated cost of required Furniture & Fixtures including electrical fittings
would be Rs.- 10,000.00/-.
PREOPERATIVE EXPENSES
The total estimated cost of required Preoperative Expenses would be Rs.- 10,000/-.
PLANT, MACHINERY AND EQUIPMENTS
Plant, Machinery, Tools, Shed and other equipment’s required for the proposed unit
are available indigenously. The various items required for installation of
Rs. 4,30,000/- details as per quotation attached herewith.
QUALITY CONTROL
The concern proposed to set up above unit for which provision testing equipment
have been proposed in the project report.
TRANSPORTATION
The proposed location is connected by road and near to the city. Thus the unit is not
likely to face difficulty on account of transportation.
UTILITIES
a) Power:
The total connected load for the smooth operations of the unit has been
estimated and Electricity connection will be obtained as per required load
including lighting load if required.
b) Water:
The water will be available. Necessary provision for storage of water and water
supply has been made in the project cost.
MANPOWER
The unit would require total manpower of person of different category. The details of
salary/wages proposed to be paid together with annual Salary/wages bill is given in
separate annexure.
DEPRECIATION
The depreciation on fixed assets has been computed in annexure of this project
report in accordance with the admissibility of the same under the Income Tax Act,
1961.
TRAINING
Applicant has to complete two week EDP training specially designed for the purpose,
which will be organized by KVIC/KVIB/DIC or the institution organized by or under
the administration control of Minister of MSME or any other training ce nter of repute
before disbursement of loan by the bank. After the successfully completion of EDP
training arranged by the KVIC/KVIB/DIC, the beneficiary will deposit his own
contribution in the bank as per the guideline of scheme.
Unit is eligible to get capital subsidy under Prime Minister Employment Generation
Programme 35% of the total cost of the project (except cost of land). Total subsidy to
be received Rs. 2,27,500/-
TERM LOAN AND WORKING CAPITAL LOAN PMEGP SCHEME
The unit proposed to have Term loan UNDER PMEGP of Rs. 4,17,500/- & working
capital limit of Rs. 2,00,000/- Own contribution of unit will be Rs. 32,500/-, which is
five percent of total cost of project. The total project cost will be Rs.6,50,000/-.
INTEREST COMPUTATION
PROJECTED INCOME/PROFITABILITY
The projected Income & profitability statement has been shown in the attached profit
& loss account. Projected Balance sheet for the next five years is also enclosed as
here for the reference.
ECONOMIC VIABILITY
CONCLUSION
1 Electricity 5000
2 Phone bill 500
3 Packing material 3000
TOTAL 8500
IV) NET CUREENT ASSETS (II-III) 505 834 1191 1577 1991
B-DISPOSAL OF FUND
I) FIXED ASSETS PURCHASED
1. Furniture & Fixtures 10 - - - -
2. Plant & Machinery 430 - - - -
II) CURRENT ASSETS
3. Increase in Stock 147 7 7 7 7
4. Increase in Debtors 250 13 13 12 13
5. Increase in Preliminary Exp. 10
6. Increase in Loans & Advances 10 - - - -
III) OTHERS
7. Payment of Term Loan 83 83 84 84 84
8. Decrease in Creditors 0
TOTAL ( B ) 941 103 103 103 103
Annexture-5
PROJECTED FINANCIAL RATIOS
(Rs. In '000)
Operating Years
PARTICULARS
1st 2nd 3rd 4th 5th
CURRENT ASSETS 724 1069 1442 1842 2270
1. CURRENT
RATIO CURRENT
420 436 450 465 480
LIABILITIES
1.73 2.46 3.20 3.96 4.73
=
TIMES TIMES TIMES TIMES TIMES
PAT+DEP.+INTT.
430 460 482 505 527
ON TERM LOAN
4. DSCR
INTEREST+LOAN
128 118 108 99 46
INSTALMENT
3.36 3.89 4.45 5.12 11.56
=
TIMES TIMES TIMES TIMES TIMES
4th Year 99 15 84 84
5th Year 89 5 84 0
DISCLAIMER
This project report is only for the purpose of reference and will give an idea and
guidance to budding and existing entrepreneurs on how to prepare a project Report.
The readers will come to know about the key components of a project. Every
earnest-effort has been made in collecting the data and information available on the
subject from different offline and online sources. This report (including any
enclosures and attachments) has been prepared solely for the purpose for which it is
provided.
Department suggest entrepreneurs to survey the market properly to find the actual
cost of fixed assets and working capital. The actual cost of the project or industry will
vary according to different elements like location, local regulation, financial
requirements of industry, capacity, type of industry, cost of resources and other
direct and indirect costs related to the project.
Department hereby disclaims any and all liability to any party for any direct, indirect,
implied, punitive, special, incidental or other consequential damages arising directly
or indirectly from any use of the Project Report Content which is provided “as is” and
“as available” basis without any warranties of any kind.
In no event shall Department will be liable for any damages whatsoever resulting from
the use or inability to use the project report content.
Prepared by