1217 TDW Ebook Web
1217 TDW Ebook Web
Brought to you by
This image shows the extent of flooding directly outside of Con Edison’s East River Plant during Hurricane Sandy.
The waters receded in four hours, leaving a swath of destruction.
Utility personnel at Con Edison’s East River sub- the four-year, $1B “Fortifying the Future” Storm
station in lower Manhattan remember vividly how Hardening Program. Involving 21 generating sta-
quickly water from Hurricane Sandy’s storm surge tions and substations, the company-wide initiative
rose, prompting a speedy retreat to the upper floors extends to electric, gas, and steam.
of the facility’s offices. The project is now nearing completion, with final
Four hours later the water had receded, leaving approvals for the last phase expected in June 2018.
behind a wide swath of destruction —a total of 1.1 In December 2016, T&D World reported on the
million customer outages; the loss of 4K MW of gen- details of the East 13th substation improvements,
eration, five transmission substations, and 60% of which included a new elevated control room, a
Con Edison’s 345 kV feeders. Steam and gas services new fiber optics backbone network, perimeter wall
were also impacted. and doors gates hardened for storms, new 345 KV
The devastation caused by Hurricane Sandy led to breakers and disconnect switches, and a new digital
the biggest single initiative in Con Edison’s history, control system.
2 | TD World | tdworld.com
Con Ed Post-Sandy Fortification Effort
tdworld.com | TD World | 3
ComEd Updates Substation Design
Alternative switchgear arrangements are compared in
medium-voltage substations to improve grid hardening.
By Peter Tyschenko, Vincent Westfallen and Laura Garcia Garcia, Commonwealth Edison Co.
Typical outdoor 34.5-kV substation equipment at ComEd includes a straight bus arrangement (shown behind the bus capacitor
banks on the left) and a 34.5-kV circuit breaker with bus disconnects (right).
4 | TD World | tdworld.com
ComEd Updates Substation Design
After decades of successful service, upgrades to In the early 2000s, ComEd began installing mod-
these substations as well as additions to the sub- ular sheltered-aisle 34.5-kV switchgear at new sub-
station fleet are now taking place to continue to stations. ComEd had been using similar gear on its
meet the reliability expectations of the 21st century. 12.5-kV system for more than a decade, and the ap-
Based on the magnitude of these capital investments plication of this equipment on the 34.5-kV system
and the number of customers who count on these brought not only the obvious reduction in medi-
assets for service, it is critical that design decisions um-voltage equipment exposure but also proven
are made wisely. 12.5-kV design benefits like fewer feeders per bus
ComEd is providing record reliability, enhanced section, buses configured in a ring to provide two-di-
customer care and innovative savings programs, rection sourcing for each bus section and the abil-
and seeing record customer satisfaction as a result. ity to continue parallel operation of transformers
Strategic partnerships with state and regional de- during equipment outages.
velopment stakeholders to expand Illinois’ diverse A fully developed 138/34.5-kV substation at
business base have been successful, and Illinois’ ComEd employs four transformers serving as
economic growth depends on the utility continuing many as 16 34.5-kV feeders. ComEd’s distribu-
to deliver safe and reliable power. ComEd’s service tion system is generally planned and forecast-
territory is now one of the most active markets for ed with the goal of serving all customer elec-
new data center development. The suburban Chi- tric load under system normal (N-0) and first
cago, Illinois, data center market is seeing an influx transformer contingency (N-1) conditions. In
of new providers, many of whom take service at 34.5 some cases, second transformer contingency
kV, thereby increasing the need for dependable (N-2) conditions also are considered.
138/34.5-kV substations built on a solid design. During this study, ComEd gave considerable
all three designs. A comparison of bus designs includes the legacy configurations — straight, ring
and double ring — as well as the additional configurations considered — breaker
and a half and double bus double breaker.
tdworld.com | TD World | 5
ComEd Updates Substation Design
attention to the 34.5-kV bus configuration at these rations. The transmission study from which these
substations, analyzing and comparing five potential indices were adapted — “SCECO-East Experience
bus designs: straight bus, ring bus, double ring bus, with Switchgear Arrangement of Transmission Sub-
breaker and a half, and double bus double breaker. stations” by Zafar Choudhry, 1995 — essentially
In comparing these different bus designs, the engi- assigned a relative value to a design based on the
neering team applied five guiding principles: number of its elements subject to outage for various
• Reliability for isolating faults while minimizing fault modes, accounting for all possible instances of
impacts to healthy equipment each mode. The analysis considered strictly feeder
• Operability for reconfiguring under contin- outages because they represent direct customer im-
gencies to match available transformer capac- pact. ComEd also considered physical metrics and
ity with connected load cost, calculated simply as a square foot and dollar
• Feasibility to be scalable as well as built in a multiple of the number of circuit breakers required
variety of physical locations on the system for each configuration.
• Interchangeability to leverage existing mainte-
nance and operating methods and expertise Survive or Recover
• Cost for balancing sound economic responsi- If reliability were the only consideration, the
bility with the other four guiding principles. double bus double breaker would have been the
clear champion for initial impact to feeders under
Evaluation Indices every type of fault. However, a deeper review of what
One of the greatest challenges the team encoun- these fault situations would look like in real life led
tered was creating a quantifiable methodology for ComEd to further assess the impact to feeders to
comparing the different bus designs. Discussions make repairs to faulted equipment. Enlightening
sometimes became clouded by opinions about the conversations with switchgear vendors and ComEd’s
importance of cost versus reliability, for instance, or own substation maintenance experts revealed some
what exactly flexible operability looks like, or how important facts.
important it is to have a scalable design, or one that Because of the complexity of the designs and
can be built in stages and in many places on the sys- compact nature of the buildings, one significant
tem. Engineers are passionate people, and it usually drawback of the breaker and a half as well as the
takes sound logic to influence their thinking. double bus double breaker in a modular switchgear
ComEd developed a reliability index approach lineup is the amount of equipment that would have
to compare the five possible 34.5-kV bus configu- to be taken out of service to provide the necessary
The 34.5-kV bus, circuit breakers and other equipment is housed indoors in a climate-controlled building.
6 | TD World | tdworld.com
ComEd Updates Substation Design
stopping at the first contingency This table provides a summary of the survive and recover Indices for the different
recover indices. However, in the configurations. Lower values of these unit-less, relative indices are more favorable.
spirit of the second immutable law,
Murphy’s Law, distribution planning engineers can- Bus Out for Maintenance or Repair and Subsequent Second Bus Fault
not help but take a look under the hood of each of 0.45
Depth of
these configurations to get a feel for the depth of 0.40 resiliency
resiliency they present. Having a bus section out for 0.35
Survive
Recover
maintenance or repair, and then being forced into 0.30
a survive situation because of a second bus fault is 0.25
both the worst second contingency scenario and not 0.20
an unreasonable circumstance to expect at some 0.15
point during the life of a substation. 0.10
The graph illustrates the relative depth of resilien- 0.05
cy of the five configurations that were studied. The 0.00
first contingency survive and recover indices are Straight Ring bus Double Breaker Double bus
bus ring bus and a half double breaker
represented by the diamond markers. The box plots
show the range of survive indices for a bus fault with The relative depth of resiliency of the five configurations in
one bus initially out for maintenance. survive and recover indices.
The difference between the survive and recover repair activities. For some of these designs, the first
index values and the depth of resiliency data for each contingency maintenance outage in and of itself is
bus arrangement can be thought of as in indication an operating hardship; the impact of a second con-
of the risk that is present during bus maintenance or tingency while that work is underway is catastrophic.
tdworld.com | TD World | 7
ComEd Updates Substation Design
8 | TD World | tdworld.com
THE TOTAL
PACKAGE
AFL offers electric utilities a wide range of custom-designed solutions that will help increase efficiency of
networking operation centers, power-generating facilities and substations. With more than 80 years of
industry expertise, our substation solutions are developed for applications up to 765 kV and available for
Swage, bolted or welded connections in bronze or aluminum materials. At AFL, we aren’t just one piece of the
solution, we are the solution.
AFLglobal.com/substation
800-235-3423
Bart Kers and Wim Kerstens from Stedin’s asset management deparment review documents for the project that will replace
the 10-kV switchgear, including protection, monitoring and control, in the 50/10-kV Utrecht Leidseveer substation.
Stedin Netbeheer B.V. is a regional network Stedin’s high-voltage (HV) subtransmission net-
operator responsible for the transmission and dis- work operates at 50 kV and 25 kV, with medium-volt-
tribution of electricity in Randstad, a large urban age (MV) distribution network voltages of 23 kV (as
area in western Netherlands. More than 2 million of 1990), 13 kV and 10 kV. Apart from three 50-kV
customers are supplied by Stedin in this area, which overhead lines, the HV and MV connections consist
includes the cities of The Hague, Rotterdam and of underground cables.
Utrecht. Stedin was formed by a merger of former Aging switchgear in need of replacement pres-
municipal network operators that had different ents the utility with an opportunity to re-evaluate
design philosophies on network structures, voltage the design and configuration of its current HV and
levels and substation layouts. As a result, the layouts MV substations while simultaneously exploring
of Stedin substations commissioned between the possibilities for integrating distribution automa-
1960s and 1980s differ widely. tion into its MV network. Switchgear replacement
10 | TD World | tdworld.com
Future Substation Configurations
tdworld.com | TD World | 11
Future Substation Configurations
12 | TD World | tdworld.com
Future Substation Configurations
0.45
0.20
0.15
0.10
0.05
0.00
Agr1 Pub1 Pub3 Pub4 Pub5 Ind1 Ind2 Ind3 Ind4 Ind5 System
overall
Area
SAIDI predictions for the different automation concepts using modeling for the Gorinchem medium-voltage distribution network.
tdworld.com | TD World | 13
Future Substation Configurations
14 | TD World | tdworld.com
Future Substation Configurations
tdworld.com | TD World | 15
The Denny Substation Project, Seattle’s first new substation in 30 years, is needed to power the South Lake Union neighborhood.
Images provided courtesy of NBBJ. Renderings produced by MOTYW.
Many cities hide their urban electrical substations by. But those designs do not invite people to the
behind buildings that are works of art. However, site and offer them fun things to do. The Denny
few offer their communities the destination activ- Substation design does.
ities that will become a part of Seattle City Light’s
planned Denny Substation in Seattle, Washington, A Focal Point
U.S. Some artistically designed urban substations When the Denny Substation is energized in the
include the dynamically formed Buzzard Point spring of 2018, it is expected to become a focal
Substation proposed in Washington, D.C., the point for surrounding neighborhoods. Seattle ar-
Mondrian-inspired abstract City North Substation chitecture firm NBBJ designed the substation to
in Sydney, Australia, and the seamless black basalt include an off-leash dog park and a 0.25-mile (0.4-
substation in Innsbruck, Austria. These are pleasing, km) interpretative walking loop elevated by gentle
artsy boxes designed to hide the industrial guts of slopes that will provide unique views of Denny Way
the substation. They present pretty faces to passers- and the cityscape.
16 | TD World | tdworld.com
Seattle Unveils NexGen Substation
Powering Growth
Seattle City Light started on the
path to building a new substation
in 2012 to serve future growth in
the area north of downtown, from
Denny Triangle to South Lake
Union. At that point, the utility’s
planners thought they had plenty
of time to design and build a new
substation. However, six months
after the Seattle City Council gave
the utility the go-ahead for full de-
Instead of a 40-ft-high screen wall typical of some urban substations, the Denny sign, the economic development
Substation design is faceted and stepped for a lower profile, and much of the enclosure
is transparent, particularly at street level. The Brewster Apartments and the Mirabella
dam burst. Companies’ plans for
residential buildings can be seen behind the substation. new high-density residential and
commercial space started becom-
tdworld.com | TD World | 17
Preparing the Denny Substation site included digging 40 ft down from the street surface to remove soil contaminated by diesel fuel
from the old Greyhound Bus maintenance facility. Photo by Jay Keeling.
ing a reality at a pace that had not been expected. Technical and Design Puzzles
Some of the best-known names in business are Seattle City Light selected 1250 Denny Way,
building high-rise office towers in the neighbor- the site of a former Greyhound Bus mainte-
hood. Amazon, the world’s largest online retailer, nance facility, as the location for its new sub-
is building a new corporate headquarters that will station. The 120,000-sq ft (11,150-sq m) area
include three 38-story office towers, two mid-rise offered several advantages:
office buildings and a meeting center, all built on • It was close to electrical load centers.
three city blocks. Vulcan, the company started by • It had an underground high-pressure, flu-
Microsoft cofounders Paul Allen and Jody Allen, is id-filled (HPFF) 115-kV line running through
putting up the Block 45 Project, a 12-story building the site.
in South Lake Union. • It had enough area for a substation.
Other nearby construction includes the Pacific • It offered the ability to disperse feeder lines
Northwest’s largest hotel, a 45-story project in the in every direction.
Denny Triangle area. A new 36-story office and Still, the site presented some demanding tech-
apartment tower is planned for just three blocks nical and design puzzles. A lot of equipment and
from the new Amazon headquarters. In all, more functions would have to go into a relatively limited
than a dozen major projects have been announced space that did not allow for an open-air insulation
or are under way. The electrical load density for substation. The diverse project team tackling those
this area is about to increase dramatically as more issues included POWER Engineers, serving as the
people and businesses come into the area. project manager and overseeing electrical design,
Adding more urgency to City Light’s plans is the and KPFF Consulting Engineers, serving as the
fact that the nearby aged Broad Street Substation has structural and civil engineer.
nearly reached its load limits. Moreover, construc- The Denny Substation and its network distribu-
tion of the Alaskan Way Viaduct replacement tunnel tion system have to be highly reliable. They are crit-
requires part of the Broad Street Substation distri- ically important to economic growth in the South
bution feeder system to be de-energized for a time. Lake Union and Denny Triangle neighborhoods.
Achieving the needed reliability in the available
18 | TD World | tdworld.com
Seattle Unveils NexGen Substation
space posed numerous design difficulties. Address- Electric Power Products Inc. and ABB Group. ABB
ing these issues was often at odds with the public proposed using higher-impedance transformers
amenities portion of the design, as both processes and its Is-limiter, a fast-acting switching device, in
moved in parallel. the ring bus. This resulted in additional switchgear
In some 15-kV fault scenarios such as bus faults or cubicles but solved the high fault current issue.
breaker failure, there had to be a way to avoid loop Mitsubishi will provide the 115-kV gas-insulated
flow. All of the transformers’ secondary winding had switchgear while ABB will provide the transformers
to be connected in parallel, requiring all of the tap and 13.8-kV equipment.
changers to be in the same position. One problem An existing 115-kV HPFF line runs through the
with connecting the network distribution trans- Denny Substation site. This transmission line, which
formers’ secondary winding in parallel is it causes will be above-grade during most of construction, will
extremely high fault currents. These high fault cur- be bisected to provide separate lines from the Den-
rents can push the capability for breaker interrup- ny Substation to the East Pine Substation and Broad
tion and could exceed the capability of downstream Street Substation. The HPFF transmission line is
13.8-kV feeder equipment, rated at 25 kA. proposed to operate at 115 kV with the potential
The project team studied several potential solu- for the East Pine connection to operate at 230 kV
tions such as increasing transformer impedance, in the future. The change to 230 kV is necessary as
adding inductors and other solutions. Each possible the electrical demand increases and more areas of
fix either required equipment that would not fit in north of downtown Seattle are switched to a network
the substation’s compact space or would not meet distribution system.
performance demands. In the end, the project Around 2019, a new high-voltage transmission
team decided to write a performance specification line will connect Denny Substation to the existing
for all the substation high-voltage equipment and Massachusetts Substation in the south of downtown
allow some really talented people at the original neighborhood, or SoDo as the area just south of
equipment manufacturers (OEMs) to propose solu- Pioneer Square and the Chinatown-International
tions. This approach allowed the project to capture District is called. Denny Substation and the associat-
available technical solutions as well as competitive ed transmission circuits will also serve as backup in
pricing proposals. case of outages or loss of equipment at nearby sub-
Seattle City Light received four different propos- stations. Receiving the equipment outline drawings
als from OEMs that offered unique approaches to and finalizing the 13.8-kV bus design for the Denny
the performance requirements. The utility chose Substation allowed the final layout of the yard and
a solution that split the work between Mitsubishi detail design to move ahead.
Project Attention
Denny Substation Equipment
Nearby South Lake Union neighbors
Four bays of 115-kV gas-insulated switchgear
of the Denny Substation project include
Three 115/13.8-kV power transformers
115-kV line reactor with integrated GIS
an upscale retirement community and
13.8-kV switchgear building the Seattle Cancer Care Center. Along
13.8-kV capacitor banks with providing power for all the new con-
13.8-kV grounding banks struction underway, the substation also
One lot of 115-kV cross-linked polyethylene cable between equipment supplier equipment will support the University of Washing-
One lot of 15-kV ethylene propylene rubber cable between equipment supplier equipment ton School of Medicine’s biotechnology
tdworld.com | TD World | 19
Seattle Unveils NexGen Substation