RUA AL MADINAH Infrastructure Works-Advance Package Recovery Schedule Rev00
AICC: Construction Schedule
Activity ID Activity Name Duration Start Finish 2022 2023
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
RUA AL MADINAH Infrastructure Works-Advance Package Recovery Schedule Rev00 356.83 22-Jun-21 A 09-Apr-23 RUA AL MADINAH Infrastructure Works-Advance Pack
Milestones 321.83 26-Jun-21 A 09-Apr-23 Milestones
MS.01 Project NTP ( Notice to Proceed ) 0.00 26-Jun-21 A
MS.7 Performance Security 0.00 27-Jun-21 A
MS.17 Insurance and Copies of Policies 0.00 24-Jul-21 A
MS.03 Completion of Section-1 ( Excavation Tunnel-2) 0.00 04-Nov-21
Completion
A of Section-1 ( Excavation Tunnel-2)
MS.04 Completion of Section-2 ( Excavation Tunnel-3) 0.00 10-Jan-22 A Completion of Section-2 ( Excavation Tunnel-3)
MS.02 Mobilization Completion 0.00 01-Mar-22 Mobilization Completion
MS.05 Completion of Section-3 (Excavation Haram Tunnel) 0.00 13-Mar-22* Completion of Section-3 (Excavation Haram Tunnel)
MS.06 Completion of Section-4 (Operation Al Amida Road) 0.00 24-Nov-22* Completion of Section-4 (Operation Al Amida Road)
MS.07 Completion of Section-5 (Overall Project) 0.00 09-Apr-23* Completion of Section-5 (Overall Project)
Mobilization 35.00 26-Jun-21 A 01-Mar-22 Mobilization
General Services for the Employer’s, PMC’s and Engineer’s staff 356.83 26-Jun-21 A 09-Apr-23 General Services for the Employer’s, PMC’s and Eng
Project's key Plans 27.00 01-Jul-21 A 28-Feb-22 Project's key Plans
Engineering 219.30 27-Jun-21 A 23-Oct-22 Engineering
Procurement 356.83 22-Jun-21 A 09-Apr-23 Procurement
Construction Works 356.83 26-Jun-21 A 09-Apr-23 Construction Works
Permits & NOC's Demlolition , Amida road Tunnels Zone 223.45 27-Jun-21 A 24-Nov-22 Permits & NOC's Demlolition , Amida road Tunnels Zone
Detour & Utilities diversion 268.88 17-Aug-21 A 02-Apr-23 Detour & Utilities diversion
Demlolition Works 319.83 26-Jun-21 A 02-Apr-23 Demlolition Works
Tunnel Works 175.00 01-Jul-21 A 31-Aug-22 Tunnel Works
AL Amida Road 247.40 12-Aug-21 A 24-Nov-22 AL Amida Road
Al Amida Road (Left with Median) Section 01 and 02 146.80 14-Aug-21 A 30-Jul-22 Al Amida Road (Left with Median) Section 01 and 02
Road Works 146.80 14-Aug-21 A 30-Jul-22 Road Works
Construction of Utilities 112.90 01-Nov-21 A 15-Jun-22 Construction of Utilities
Al Amida Road (Right) Section 03 and 04 103.60 12-Aug-21 A 24-Nov-22 Al Amida Road (Right) Section 03 and 04
Detour & Safety Arrangments 30.00 12-Aug-21 A 30-Aug-22 Detour & Safety Arrangments
Road Works 100.60 30-Jul-22 24-Nov-22 Road Works
Relocation & Construction of Utilities 100.60 30-Jul-22 24-Nov-22 Relocation & Construction of Utilities
Airport Road Tie In 24.00 22-Oct-22 19-Nov-22 Airport Road Tie In
Ali Ibn e Abi Talib Tunnel 356.83 19-Oct-21 A 09-Apr-23 Ali Ibn e Abi Talib Tunnel
Permits & NOC's Ali Ibn e Abi Talib Zone 356.83 01-Nov-21 A 09-Apr-23 Permits & NOC's Ali Ibn e Abi Talib Zone
Detour 30.00 19-Oct-21 A 23-Feb-22 Detour
Al Bin Talib Tunnel- Main 349.36 14-Dec-21 A 26-Mar-23 Al Bin Tali b Tunnel- Main
Dry Utility Tunnel 275.83 23-Feb-22 31-Jan-23 Dry Utility Tunnel
Wet Utility Tunnel 276.81 12-Mar-22 19-Feb-23 Wet Utility Tunnel
Cross over Ali Bin Talib- Road & Utilities work above tunnel & Package 4 346.01 24-Jan-22 27-Mar-23 Cross over Ali Bin Talib- Road & Utilities work above tunnel
Stage-3 Intersection and Incidental works 35.03 15-Feb-23 02-Apr-23 Stage-3 Intersection and Incidental works
Miscellaneous works 281.67 27-Apr-22 09-Apr-23 Miscellaneous works
Provisional Sum 50.00 16-Jan-23 15-Mar-23 Provisional Sum
Testing & Commisioning 208.03 01-Aug-22 09-Apr-23 Testing & Commisioning
Handing Over & Demobilization 19.00 11-Mar-23 09-Apr-23 Handing Over & Demobilization
Date Revision Checked Approved
Remaining Level of Effort Actual Work
Al Ayuni Investment & Contracting Company (AICC) Page 1 of 1
Actual Level of Effort Remaining Work