RUA AL MADINAH Project Recovery Schedule

This construction schedule outlines the timeline and milestones for the RUA AL MADINAH Infrastructure Works-Advance Package project from June 2021 to April 2023. Key activities include mobilization from June 2021 to March 2022, engineering from June 2021 to October 2022, and construction works from June 2021 to April 2023. The schedule also details timelines for permits and NOCs, demolition works, tunnel works, Al Amida Road works in sections, and the Ali Ibn e Abi Talib Tunnel works.

Uploaded by

Aamir Awan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
2K views1 page

RUA AL MADINAH Project Recovery Schedule

This construction schedule outlines the timeline and milestones for the RUA AL MADINAH Infrastructure Works-Advance Package project from June 2021 to April 2023. Key activities include mobilization from June 2021 to March 2022, engineering from June 2021 to October 2022, and construction works from June 2021 to April 2023. The schedule also details timelines for permits and NOCs, demolition works, tunnel works, Al Amida Road works in sections, and the Ali Ibn e Abi Talib Tunnel works.

Uploaded by

Aamir Awan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
  • Construction Schedule Overview

RUA AL MADINAH Infrastructure Works-Advance Package Recovery Schedule Rev00

AICC: Construction Schedule


Activity ID Activity Name Duration Start Finish 2022 2023
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
RUA AL MADINAH Infrastructure Works-Advance Package Recovery Schedule Rev00 356.83 22-Jun-21 A 09-Apr-23 RUA AL MADINAH Infrastructure Works-Advance Pack

Milestones 321.83 26-Jun-21 A 09-Apr-23 Milestones

MS.01 Project NTP ( Notice to Proceed ) 0.00 26-Jun-21 A


MS.7 Performance Security 0.00 27-Jun-21 A
MS.17 Insurance and Copies of Policies 0.00 24-Jul-21 A
MS.03 Completion of Section-1 ( Excavation Tunnel-2) 0.00 04-Nov-21
Completion
A of Section-1 ( Excavation Tunnel-2)
MS.04 Completion of Section-2 ( Excavation Tunnel-3) 0.00 10-Jan-22 A Completion of Section-2 ( Excavation Tunnel-3)
MS.02 Mobilization Completion 0.00 01-Mar-22 Mobilization Completion
MS.05 Completion of Section-3 (Excavation Haram Tunnel) 0.00 13-Mar-22* Completion of Section-3 (Excavation Haram Tunnel)
MS.06 Completion of Section-4 (Operation Al Amida Road) 0.00 24-Nov-22* Completion of Section-4 (Operation Al Amida Road)
MS.07 Completion of Section-5 (Overall Project) 0.00 09-Apr-23* Completion of Section-5 (Overall Project)

Mobilization 35.00 26-Jun-21 A 01-Mar-22 Mobilization

General Services for the Employer’s, PMC’s and Engineer’s staff 356.83 26-Jun-21 A 09-Apr-23 General Services for the Employer’s, PMC’s and Eng

Project's key Plans 27.00 01-Jul-21 A 28-Feb-22 Project's key Plans

Engineering 219.30 27-Jun-21 A 23-Oct-22 Engineering

Procurement 356.83 22-Jun-21 A 09-Apr-23 Procurement

Construction Works 356.83 26-Jun-21 A 09-Apr-23 Construction Works

Permits & NOC's Demlolition , Amida road Tunnels Zone 223.45 27-Jun-21 A 24-Nov-22 Permits & NOC's Demlolition , Amida road Tunnels Zone

Detour & Utilities diversion 268.88 17-Aug-21 A 02-Apr-23 Detour & Utilities diversion

Demlolition Works 319.83 26-Jun-21 A 02-Apr-23 Demlolition Works

Tunnel Works 175.00 01-Jul-21 A 31-Aug-22 Tunnel Works

AL Amida Road 247.40 12-Aug-21 A 24-Nov-22 AL Amida Road

Al Amida Road (Left with Median) Section 01 and 02 146.80 14-Aug-21 A 30-Jul-22 Al Amida Road (Left with Median) Section 01 and 02

Road Works 146.80 14-Aug-21 A 30-Jul-22 Road Works


Construction of Utilities 112.90 01-Nov-21 A 15-Jun-22 Construction of Utilities

Al Amida Road (Right) Section 03 and 04 103.60 12-Aug-21 A 24-Nov-22 Al Amida Road (Right) Section 03 and 04

Detour & Safety Arrangments 30.00 12-Aug-21 A 30-Aug-22 Detour & Safety Arrangments
Road Works 100.60 30-Jul-22 24-Nov-22 Road Works
Relocation & Construction of Utilities 100.60 30-Jul-22 24-Nov-22 Relocation & Construction of Utilities

Airport Road Tie In 24.00 22-Oct-22 19-Nov-22 Airport Road Tie In

Ali Ibn e Abi Talib Tunnel 356.83 19-Oct-21 A 09-Apr-23 Ali Ibn e Abi Talib Tunnel

Permits & NOC's Ali Ibn e Abi Talib Zone 356.83 01-Nov-21 A 09-Apr-23 Permits & NOC's Ali Ibn e Abi Talib Zone

Detour 30.00 19-Oct-21 A 23-Feb-22 Detour

Al Bin Talib Tunnel- Main 349.36 14-Dec-21 A 26-Mar-23 Al Bin Tali b Tunnel- Main

Dry Utility Tunnel 275.83 23-Feb-22 31-Jan-23 Dry Utility Tunnel

Wet Utility Tunnel 276.81 12-Mar-22 19-Feb-23 Wet Utility Tunnel

Cross over Ali Bin Talib- Road & Utilities work above tunnel & Package 4 346.01 24-Jan-22 27-Mar-23 Cross over Ali Bin Talib- Road & Utilities work above tunnel

Stage-3 Intersection and Incidental works 35.03 15-Feb-23 02-Apr-23 Stage-3 Intersection and Incidental works

Miscellaneous works 281.67 27-Apr-22 09-Apr-23 Miscellaneous works

Provisional Sum 50.00 16-Jan-23 15-Mar-23 Provisional Sum

Testing & Commisioning 208.03 01-Aug-22 09-Apr-23 Testing & Commisioning

Handing Over & Demobilization 19.00 11-Mar-23 09-Apr-23 Handing Over & Demobilization

Date Revision Checked Approved


Remaining Level of Effort Actual Work
Al Ayuni Investment & Contracting Company (AICC) Page 1 of 1
Actual Level of Effort Remaining Work