0% found this document useful (0 votes)
350 views5 pages

SPM Question Bank

This document contains a question bank with questions related to software project management. It is divided into 5 units, with each unit containing questions on various topics related to software project management concepts and processes. Some of the key topics covered include the project life cycle, project planning, estimation techniques, risk management, project monitoring and control, quality management models, and team management. The question bank provides a comprehensive set of questions to test knowledge of fundamental as well as advanced concepts in software project management.

Uploaded by

Vg
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
350 views5 pages

SPM Question Bank

This document contains a question bank with questions related to software project management. It is divided into 5 units, with each unit containing questions on various topics related to software project management concepts and processes. Some of the key topics covered include the project life cycle, project planning, estimation techniques, risk management, project monitoring and control, quality management models, and team management. The question bank provides a comprehensive set of questions to test knowledge of fundamental as well as advanced concepts in software project management.

Uploaded by

Vg
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

SPM Question Bank

T.Y. Information Technology Semester-V

Unit 1
1. Briefly explain the different phases of project management life cycle. Or Explain the
stages involved in Project Management Life Cycle in detail.
2. What is project charter in software project management? What are the elements of project
charter?
3. What is project portfolio management? Explain the key aspects of project portfolio
Management. Or Write a note on Project portfolio management. Or Write a short note on
Portfolio Management.
4. Write a note on risk evaluation and management.
5. Define a term Project and give the importance of Software Project Management.
6. What is a project product? Explain Product Breakdown Structure with the help of
example.
7. What do you mean by scope and objective of a project? List the activities involved in
identifying project scope and objective. Or what the importance is of identified the scope
and objective of a project.
8. Define project. Discuss some characteristics of software project which make them more
difficult to manage compared to other projects.
9. Define Business Case. Specify the content of business case document.
10. Define Net Profit, Payback Period and Returns on Investment.
Calculate these values for the following cash flow forecast of a project.

Year Cash flow


0 - 1,00,000
1 20,000
2 30,000
3 20,000
4 30,000
5 60,000

11. Outline the general approach that might be taken for project planning in an organized step
by step manner.
12. Name different. Give very brief description of all the phases of Project Management life
cyc.le (2 to 3 lines) and explain W5HH principle.
13. How is resource allocation managed in an activity of program management?
14. Define the following terms:
i)Net profit ii)Return on Investment iii)Payback period iv)Net present value
v)Internal rate of return

Compiled By Seema Gargote Page 1


SPM Question Bank
T.Y. Information Technology Semester-V

Unit 2
1. What do you understand by the term ‘ceremonies’ in a scrum project? Explain the
different types of ceremonies that are observed in a Scrum project and their significance.
2. List the advantages and disadvantages of software prototyping
3. Explain the five major components of Albrecht Function Point Analysis.
4. What are effort multipliers in COCOMO II model? List the effort multipliers used at
early design
5. Explain eight core principles of Dynamic Systems Development Method.
6. State Capers Jones rules of thumb for software estimation. Or State and explain Capers
Jones estimating rules.or Discuss Capers Jones estimating rules of thumb.
7. Describe briefly five steps of project analysis.
8. Explain Scrum. What do you understand by the term ‘ceremonies’ in a Scrum project?
Explain different types of ceremonies observed in a Scrum Project.
9. Discuss eight core Atern principles.
10. What are the problems generally faced during effort estimation? or Discuss the common
problem faced during effort estimation.
11. Explain briefly Albrecht/IFPUG function points and solve the following :-
For an organization, the following table summarizes the weightings to
be used for computing function points measures of a software
development project. The organization has undertaken the development
of a software having the following characteristics:-
Number of user inputs - 10(simple)
Number of user outputs 7 (simple)
Number of user inquiries 3 (average)
Number of files 6 (average)
Number of external 1 (complex)
interfaces
Calculate unadjusted function point measure of the size of the software
system?
12. What are the advantages and disadvantages of Spiral model.
13. Explain different approaches used for fast delivery of a project.
14. Explain the top down approaches associated with parametric models.
15. Write a note on COCOMO II model.

Compiled By Seema Gargote Page 2


SPM Question Bank
T.Y. Information Technology Semester-V

Unit 3
1. With the help of example explain forward pass and backward pass to calculate activity
duration in network diagram.
2. Write short note on Project Evaluation and Review Technique.
3. Explain Boehm’s top ten software project risks and the different strategies for reducing it.
4. Explain the different categories of cost incurred in a software project.
5. What is resource smoothing? Explain two different ways of prioritizing activities for
resource allocation.
6. Define activity. Discuss three approaches to identify the activities.
7. Define Risk and discuss the ways of dealing with them.
8. Explain the process of scheduling resources.
9. What is the necessity of activity planning?
10. Explain network planning model and the concept of backward pass.
11.
12. Discuss the factors to be taken into account while allocating individuals to task.
13. Define the term risk and discuss the ways to deal with them.
14. Describe Monte Carlo simulation.
15. Explain the nature of resources and their scheduling
16. What are the factors considered while allocating task to the individual.
17. Suppose four risks namely R1, R2, R3 and R4 have been identified and assigned the
probabilities of occurrence of 0.1, 0.2, 0.3 and 0.4 respectively. The likely damages due to
the four risks are Rs. 50, 000; Rs. 1, 00,000; 70,000; 60,000 respectively. Calculate the
risk exposure of all the risks.
18. Define the following terms
i)Critical path ii)Float iii)Free float iv)Interfering float v)Hammock activity

Compiled By Seema Gargote Page 3


SPM Question Bank
T.Y. Information Technology Semester-V

Unit 4
1. Explain review process model with the help of diagram.
2. What is meant by software configuration management? Explain the two principal
activities of configuration management.
3. Explain the main sections in a requirement document for contract placement.
4. What is fixed price contract? List the advantages and disadvantages of fixed price
contract.
5. What are three important categories of stress management techniques?
6. Explain Vroom’s expectancy theory of motivation.
7. Explain the change control process.
8. Define the following:- i) Schedule Variance ii) Cost Variance iii) Earned
Value iv) Schedule performance index v) Cost performance index
9. Explain briefly all the stages in Contract Placement.
10. Define Contract. Classify contracts on the basis of payment to suppliers.
11. Explain general recruitment process.
12. Discuss the factors of job satisfaction given by Oldham-Hackman. Also state the methods
of improving motivation.
13. Explain the stages in contract placement.
14. Explain Taylor’s model of motivation.
15. Write a note on change control.
16. Give the benefits of review in the process of project monitoring and control.
17. Write a note on ethical and Professional concerns as a member of any organization.
18. Explain the advantages and disadvantages of fixed price contracts.

Compiled By Seema Gargote Page 4


SPM Question Bank
T.Y. Information Technology Semester-V

Unit 5
1. Explain the advantages of a functional organization over project organization.
2. List the obstacles to good group decision making. Also explain Delphi decision making
process.
3. Write short note on SEI capability maturity model.
4. What is reliability growth model? Explain any two reliability growth models.
5. What are the steps of conducting a post implementation project review?
6. Explain the different reason for which a project may need to be terminated
7. What do you mean by team structure? Explain different types of team structures.
8. Explain five basic stages of Team development. Also state the different types of people
needed to form a balanced team. Or Write a role of different types of people needed to
form a balanced team.
9. State and explain different levels of Capability Maturity Model(CMM).
10. Define the term quality. Explain McCall’s quality model.
11. What is the importance of Software Quality? Discuss six major external software quality
characteristics identified by ISO 9126.
12. State four popular process capability models and explain any one of them.
13. Give a brief explanation of the main activities involved in Software Testing
14. Discuss the main reasons for project closure.
15. Describe a virtual team and the advantages of forming a virtual team.
16. Explain the metric correlation with software reliability.

Compiled By Seema Gargote Page 5

You might also like