Optimization of Gas Lift Design Using Graphical and Softwar Methods For Entisar Field - Elbouzidi Et. Al
Optimization of Gas Lift Design Using Graphical and Softwar Methods For Entisar Field - Elbouzidi Et. Al
Faculty of Engineering
Petroleum Engineering Department
Project By:
Eisa E. Mohamed Hani E. AlBouzidi
Taha M. AlMasalati
Supervised by:
Eng. Tarek. N.A . Daw
Spring- 2010
Dedication
To our parents….
To our brothers and sisters….
To our friends…..
Acknowledgement
We are so grateful to our supervisor Eng. Tarek N.A. Daw for his support
and guidance; also we are very thankful to our families, and to our friends for
helping us along the way.
Gas lift method is some kind of artificial lifting mechanism to lift the
crude oil to the surface.
Real data was obtained from four wells in Entisar field of Zueitina Oil
Company. Calculations were performed to compare the current and
proposed designs.
The operational conditions of the four wells have been evaluated with
the objective of detecting field conditions and find suitable Gas lift
equipment.
Oil flow from the reservoir to the wellbore and then trough the tubing
string and flow line to the separator, must has a sufficient pressure to
overcome sum of pressure losses occurring along the way to the separator.
Sometimes the reservoir has sufficient energy to overcome these pressure
losses, but as the production continue the reservoir pressure starts to
decline if is not maintained by water injection or any other form of
enhancing recovery, also water cut increases gradually leading to increase
the friction losses and hence increase in the flowing bottom hole pressure.
The consequence of reduction in pressure drawdown (reservoir pressure –
flowing bottom hole pressure) a significant reduction in the production or
even losing the total production from the well. To overcome this problem
(reduction in pressure drawdown) there are two way one way is to maintain
the reservoir pressure and another way is to reduce the gravitational losses
in the tubing string by utilizing a form of artificial lift.
Gas lift is widely used and proven to be successful and has low
relatively operating cost, high flow rate, and capable of handling corrosive
gases such as H2S and CO2. To achieve low operating cost a maximum
production should be produced from the available gas. many software
packages are being used nowadays for gas lift design and gas lift
distribution such as (Wellflo) from Petroleum Experts.
The aim of this project is to design gas lift wells for Entisar oilfield for
four wells, in order to overcome production decline from the producing oil
wells due to reduction in pressure drawdown, also optimizing the gas lift
wells to achieve the maximum production from the available gas, study
difference between Graphical and software methods.
Chapter I
Overview Of
* When this criterion is not met, natural flow ends and the well dies.
The artificial lift is Any system that adds energy to the fluid column in a
wellbore with the objective of initiating and improving production from the
well that refers to the use of artificial means to increase the flow of liquids,
such as crude oil or water, from a production well. Generally this is achieved
by the use of a mechanical device inside the well.
direction. At the take off point the distribution header sends the flow to
each well through a directly connected pipeline. The main trunk line
system is more economical for large fields because it is less expensive
than a large number of individual pipelines.
2.6.3 Combination system.
In some cases one part of a field is developed with numerous new wells
and the best option is to have a main pipeline plus a manifold with wells
connected to it. Using a manifold can save enormous cost due to the
reduced amount of large pipeline required, also from the manifold
operations can be centralised such as measurement and control see Figure
(2.5).
2.10.2.2 Disadvantages:
1. The performance can easily affect the design gas conditions such as
changes in specific gravity, pressure or temperature.
2.11 Gas treating.
Natural gas produced from gas wells or associated gas may contain
impurities such as acid gases H2S, CO2, and other impurities. These two
gases in particular become very corrosive in the presence of water or
water moisture. These acid gases can cause a lot of corrosion problems in
producing wells, injection wells, and transporting and processing
facilities. Therefore it is vital to remove these two acid gases from gas
stream in order to eliminate corrosion problems and meet sales gas
specification standards.
2.11.1 Methods of removing H2S and CO2 from the gas stream:
They can be classified depending on their chemical reaction,
absorption, adsorption or permeation:
1. Chemical solvent process using Aqueous Alkanolamine such as DEA.
2. Physical solvent process such as Fluor solvent and selexol.
3. Adsorption using molecular sieve.
4. Physical separation cryogenic “low temperature” distillation.
5. Membrane separation process.
6. Biological processes (Shell Pacques Process).
The conditions which affect hydrate formation are gas or liquid must be
at or below its water dew point or saturation condition liquid water does
not have to be present for hydrate to form. Presence of impurities such as
H2S and CO2 in the gas composition and increase of pressure and
decrease in temperature could increase the occurrence of gas hydrate.
Also mixing, kinetics, salinity and agglomeration such as pipe elbow,
orifice, thermo well or line scale have an effect.
Where :
Pp = production pressure operating, psi.
Pc = injection pressure, psi .
Pd = pressure in dome, psi.
Pt = tubing pressure, psi.
Ap = area of port, sq".
Ab = area of bellows, sq".
2.13.1 Purpose
Usually the level of completion fluid is close to the surface when the
work over is finished and the well is initially completed with gas lift
equipment. To unload the completion fluid to inject the gas to the required
depth needs very high pressure to overcome the hydrostatic pressure
caused by the fluid. High injection pressure may not be available, in this
case a series of gas lift valves are installed in the well.
Those valves are designed to use the available gas injection pressure in
order to unload the fluid and enable injecting gas to the desired depth in
the well.
2.13.2 API recommended practice for gas lift installation.
Recommended practice to reduce the potential of damage to the
unloading gas lift valves and to improve the unloading process:
1. Use clean completion and work over fluids to avoid skin damage.
2. Wellbore should be cleaned of any drilling mud before installing the
gas lift valves.
3. Gas lift valves should not be installed in the gas lift mandrels during
completion or work over activities such as acidizing or fracturing.
4. Fluid should not be circulated from the casing to the tubing string on a
well equipped with gas lift valves.
5. Clean gas injection line from debris and dirt before hook up especially
on new lines.
6. Bleed a small amount of liquid through the casing valve if there is
pressure in the casing.
7. Check the production system and make sure everything is working
properly such as separator capacity, stock tank level, valves all are fully
open.
8. Check the safety relief valve on the gas gathering system.
This chapter includes the final results, which were concluded from
applying the steps in this chapter on the used data, The analysis of the
data was done by two methods, as shown:
The first Method was done by hand calculation and Graphic.
The second Method was done by a software program (Wellflo),and its
work
Where:
GLRT: Total gas liquid ratio.
GLRP: Produce gas liquid ratio.
3.5.1 Introduction
WellFlo systems analysis software is a powerful and simple to use
stand alone application to design, model, optimize and troubleshoot
individual oil and gas wells, whether naturally flowing or artificially
lifted, using WellFlo software results in more effective capital expenditure
by enhancing the design of wells and completions, reduces operating
expenditure by finding and curing production problems and enhances
revenues by improving well performance.
3.5.2 Applications
The WellFlo software package is a single well tool which uses nodal
analysis techniques to model reservoir inflow and well outflow
performance. WellFlo modeling can be applied to designing, optimizing
and troubleshooting individual wells. Specific applications for which the
software can be used include:
• Well configuration design for maximum performance over life of well.
• Completion design to maximize well performance over the life of well.
• Artificial lift design.
• Prediction of flowing temperatures and pressures in wells and flowlines
and at surface equipment for optimum design calculations.
The field have (37 wells) producing oil, (3 wells) producing by ESP, (34
wells) producing by Gas lift, the Source of gas injection from field 103 D,
(Agip gas), and no wells produce by natural flow.
Chapter V
1.6x 6860
100𝐹+ 70+
100
a. Chart Avg . T = = 139 F̊ .
2
{86+196}
b. Actual Avg . T = = 141 F
2
139+460
3. Gas.grd (cor.) = 30.5 x = 30.3 (Psi/1000 Ft)
141+460
30.3∗6860
4. Psoc = (1290+14.7) + = 1511 Psia
1000
= 218.3 M scf/day
1.6x 6860
100𝐹+ 70+
100
c. Chart Avg. T = = 139 F̊ .
2
{86+196}
d. Actual Avg. T = = 141 F
2
139+460 𝑃𝑠𝑖
3. Gas.grd (cor.) = 30.0 x = 29.9
141+460 1000 𝑓𝑡
29.9∗6860
4. Psoc = (1274) + = 1479 Psia
1000
= 1009.3 M scf/day
Pressure (psig)
Depth (ft)
1.6x 8335
100F+ 70+
100
a. Chart Avg . T = = 151 F̊ .
2
{82+216}
b. Actual Avg . T = = 149 F
2
151+460 Psi
3. Gas.grd (cor.) = 35.0 x =35.1
149+460 1000 ft
35.1∗8335
4. Psoc = (1484) + = 1776 Psia
1000
= 1474.4 M scf/day
Pressure (psig)
Depth (ft)
1.6x 8195
100F+ 70+
100
a. Chart Avg . T = = 150.5 F̊ .
2
{82+216}
b. Actual Avg . T = = 149 F
2
150.5+460 Psi
3. Gas.grd (cor.) = 17.0 x =17.0
149+460 1000 ft
17.0∗8195
4. Psoc = (714) + = 853 Psia
1000
= 107.1 M scf/day
Pressure (psig)
Depth (ft)
Graphical Mandrel
Casing pressure Temperature F
No# valve Depth
Psig
Valve (ft)
1 2325 1390 117
2 4260 1440 139
3 5700 1480 156
4 6750 1510 168
5 7500 1524 175
Orifice 7960 1808 191
Table (6.7) graphical valve depth for E-15-103.
Gas lift designed for four wells (E-10, E-12, E-15, and E-17) in (103)
Entisar field. The conclusions as the following:
1. In well (E-17), the graphical given less number of valves than software
, due to low cost for well completion, but by in wells (E10, E-12, E-15)
two methods have same valves .
2. Graphical method of (E-12, E-15, E-17), the operating valve was
higher depth from software method, but in well (E10), operating valve
depth by graphical method was higher depth from software method.
3. Most wells orifice valve is nearer from each depth by two methods.
4. Over that software has easy to use, faster result and more accuracy
from graphical method.
Chapter VII
Recommendation
5.1 Recommendation:
Using WellFlo software results in more effective capital expenditure by
enhancing the design of wells and completions reduces operating
expenditure by finding faster result, over that understanding Graphical
techniques.
References
Reference
1. Boyun .Gud, etc "petroleum production Engineering ", Elseervier
Science & Technology Book, 2007.
2. BROWN, K E, The Technology of Artificial Lift Methods, Volumes
1-4, Pen Well Books, 1980.
3. Gilbert, W.E "Flowing and Gas lift well performance ", American
Petroleum Institute, 1954.
4. Mian M. A., “Petroleum Engineering Handbook for the Practicing
Engineer”, Volume 2, PennWell Books, 1992.
5. Reda Abushnaq ,” Gas Lift Design and Optimization”, MSC, The
Robert Gordon University, Aberdeen,2009.
6. Roy Fleshman ,” Artificial Lift For High Volume Production “ ,
Bartlesville , Oklahoma , 1999.
7. Taerk. N. A.Daw, “Gas Lift Design “, Paper, Alfateh University,
2009.
8. Website Zueitina Company.