Monitoring Manual

This document provides guidelines for monitoring the district trail bridge program in Nepal. It outlines 10 milestones to monitor, including critical milestones where inspectors can stop work and ordinary milestones where they can recommend changes. It describes monitoring from multiple perspectives: program, technical, and social. The frequency of inspections by the Trail Bridge Support Unit will gradually decrease as district capacities increase, with private sector monitors eventually taking over inspections. The goal is to strengthen district institutions over time while ensuring quality bridge construction and accountability to stakeholders.

Uploaded by

Bipin Gyawali
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
31 views

Monitoring Manual

This document provides guidelines for monitoring the district trail bridge program in Nepal. It outlines 10 milestones to monitor, including critical milestones where inspectors can stop work and ordinary milestones where they can recommend changes. It describes monitoring from multiple perspectives: program, technical, and social. The frequency of inspections by the Trail Bridge Support Unit will gradually decrease as district capacities increase, with private sector monitors eventually taking over inspections. The goal is to strengthen district institutions over time while ensuring quality bridge construction and accountability to stakeholders.

Uploaded by

Bipin Gyawali
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 36

MONITORING

MANUAL

Government of Nepal
Ministry of Local Development
Department of Local Infrastructure Development and Agricultural Roads
Trail Bridge Sub-Sector Program

July 2007
Trail Bridge Sub-Sector Program

ACRONYMS

BMC Bridge Maintenance Committee


CMS Critical Mile Stones
D Type Suspended Type
DDC District Development Committee
DG Distance Gained
DHQ Distance to District Headquarter
DoLIDAR/MoLD Department of Local Infrastructure Development and Agricultural
Roads of the Ministry of Local Development
DRH Distance to Road Head
DRILP Decentralized Rural Infrastructure and Livelihood Project 2006-2011
DTMP District Transport Master Plan
FY Fiscal Year
GoN Government of Nepal
LB Left Bank
LDO Local Development Officer
LSTB Long Span Trail Bridge (> 120 m)
MM Major Maintenance
MoM Minutes of Meeting
N Type Suspension Type
NC New Construction
NGO Non-governmental Organisation
OMS Ordinary Mile Stones
RAIDP Rural Access Improvement and Decentralization Project 2005-2010
RB Right Bank
RPC Regional Program Coordinator
SDC Swiss Agency for Development and Cooperation
SSTB Short Span Trail Bridge (≤ 120 m)
TBS/DoLIDAR Trail Bridge Section of the Department of Local Infrastructure
Development and Agricultural Roads
TBS/LIDP Trail Bridge Strategy which is auxiliary to Local Infrastructure
Development Policy
TBSU Trail Bridge Support Unit of Helvetas
TA Technical Assistance
TC Technical Coordinator
TIM Transport Infrastructure Map
TSDO Technical and Social Development Officer
UC Users' Committee

Monitoring Manual Page (i)


Trail Bridge Sub-Sector Program

Table of Contents

ACRONYMS..........................................................................................................I

1. FOREWORD ................................................................................................. 1

2. INTRODUCTION .......................................................................................... 1

3. MILESTONES ............................................................................................... 2

4. FREQUENCY OF INSPECTIONS .................................................................... 3

5. DATA COLLECTION AND DETAILED INSPECTIONS...................................... 4

6. REPORTING ................................................................................................. 5

7. MONITORING SCHEDULE ............................................................................ 6

Annexes:

Annex 1: Index of Forms, Agreements and Relevant Documents


Annex 2: DDC Reporting Format (Ref. 1.4)
Annex 3: Fabricator information and lable for sample collection

Monitoring Manual Page (ii)


Trail Bridge Sub-Sector Program

1. FOREWORD
This Manual has been developed for application by the Trail Bridge Support Unit (TBSU)
to monitor the District Trail Bridge Program for which a sub-sector approach has been
adopted.

In the current phase of the Trail Bridge Sub-Sector Program (2007-2010), the role of the
Trail Bridge Support Unit (TBSU) has been changed from facilitation to monitoring. At the
same time, TBSU is providing Technical Assistance to the different donors notably the
World Bank and the Asian Development Bank1. This calls upon a set of tools facilitating
accountability to the different stakeholders and the community at large. Similarly, these
tools will also help the trail bridge sub-sector in creating a common understanding of the
sub-sector.

2. INTRODUCTION
This Manual is a tool for TBSU staff responsible for monitoring the performance of District
Development Committees (DDCs) with respect to trail bridge building and to rectify any
“wrongs” at an as early stage as possible.

The basic norm used to identify “rights” and “wrongs” has been the Trail Bridge
Strategy/Local Infrastructure Development Policy (TBS/LIDP).

This Manual should not create the illusion that TBSU is responsible for the Quality
Assurance of each individual bridge. On the contrary, DDCs themselves are responsible!

TBSU’s role is that of strengthening the DDC as an Institution, a coach to DDCs, an


inspector vis à vis any donor sponsoring the sub-sector with respect to the quality of
bridge construction as well as a provider of selected bridge parts. The intensity of TBSU’s
inspections will gradually reduce as the performance of DDCs as institutions progress and
TBS/DoLIDAR assisted by private sector inspectors gradually take over which is
elaborated on Section 4 below.

Even though TBSU’s role is to gradually reduce, care must be taken to continuously
observe the post-conflict situation and the inherent unstable situation in DDCs and to thus
not rush the process overtly.

The users of this Manual must be aware of its limitations. There is always a tendency to
make monitoring processes/tools perfect. However, it is seldom realized and the
practicality of the tools then becomes a mere academic exercise. This has also been felt
while developing this manual. At the same time gross violations to the TBS/LIDP were
observed at the time which even “the best” Manual could not have filtered out. It is
especially these gross violations that deserve our foremost attention and not the
microscopic “violations”.

Hence users must not blindly follow the Manual and must first of all apply a good dose of
rational judgement and professional intuition. In case of doubt, users are encouraged to
discuss observations with their superiors and / or peers.

1
TBSU is providing Technical Assistance for the trail bridge component of the RAIDP funded by
the World Bank and the DRILP funded by the Asian Development Bank.

Monitoring Manual Page (1)


Trail Bridge Sub-Sector Program

This Manual is as comprehensive as realistically possible. The list of forms, agreements,


and guidelines and other relevant documents that form an essential component of this
manual can be found in the annex 1.

Complementing this manual, a reporting format has also been developed and presented
in annex 2 which shall help the DDCs to gather field data and information. This
information can then be processed for establishing its accountability vis-à-vis donors and
the central agencies.

3. MILESTONES
Reference is made to the Monitoring Schedule Table on Page 6.

To monitor the district trail bridge program, two kinds of milestones are distinguished. On
the horizontal axis one finds:

1 Critical Milestones CMS


2 Ordinary Milestones OMS

Critical Milestones (CMS) are those Milestones where the Inspector can conceivably
interrupt the work and demand corrective actions before he/she will allow the work to
proceed.

Ordinary Milestones (OMS) are those Milestones where the Inspector may recommend
remedial actions but for which he/she will not stop the work if the actions are not
undertaken.

There is a total of 10 Milestones, of which 6 are Critical and 4 Ordinary.

All Milestones except CMS-1 deal with individual bridges. CMS-1 deals with the
Institutional Capacity and plans of the incumbent DDC as well as an individual bridge.

Further, on the vertical axis, one finds the following Inspection Perspectives:

1 Program Perspective
2 Technical Perspective
3 Social Perspective

The Monitoring Schedule depicts ten Milestones vs. three Inspection Perspectives. Each
intersection defines the Inspection intent in broad terms.

The Monitoring Schedule also reveals the Critical Issues as well as the location (e.g. Site
or Factory) at which the Inspection is to occur.

The detailed Inspections that are required can be found in a tab that corresponds to the
Milestone #. Within the numbered tab are three coloured sub-tabs denoting the
Program-, Technical- and Social Perspectives.

Monitoring Manual Page (2)


Trail Bridge Sub-Sector Program

4. FREQUENCY OF INSPECTIONS
The support TBSU renders to DDCs follows the following steps:

1 Capacity Building
2 Coaching
3 Intensive Monitoring
4 Intermediate Monitoring
5 Pvt. Sector Monitoring

It is important to note that the graduation from one step to the next will depend on the
DDC’s maturity as an institution to handle the trail bridge program as well as predefined
criterion. A step does not necessarily represent one year. The DDCs falling in one of the
above categories and their progression into subsequent steps will be reviewed at the
outset of each new FY.

In principle, TBSU will reduce the frequency of its random Inspections as shown below:

STEP TBSU's inspection frequency TBS/DoLIDAR


1 Cap. Bldg. 100%
2 Coaching 70%
3 Intensive Monitoring 40%
4 Intermediate Monitoring 20%
(10% by Pvt Sector)
5 Pvt. Sector Monitoring 5%

At step 5, inspection responsibilities will have been fully devolved to TBS/DoLIDAR.

TBSU will reduce most of its inspections markedly as time progresses. However,
inspections for each individual bridge at the following Critical Mile Stones shall be
continued for as long as TA will be rendered through TBSU:

MILE-STONE INSPECTION PERSPECTIVE CRITICAL ISSUES


CMS-1 Program Institutional Pre-requisites,
Equitable Distribution,
Commitment of Budget
CMS-2 Technical Sound Economic Design
Social Inclusiveness
CMS-9 Technical Quality Construction
Social Payment as per Plan
CMS-10 Social Public Audit, Payment to Workers

TBSU’s hereby fulfills its mandate as an inspector vis à vis any donor sponsoring the sub-
sector with respect to the quality of bridge construction.

Monitoring Manual Page (3)


Trail Bridge Sub-Sector Program

5. DATA COLLECTION AND DETAILED INSPECTIONS

The tabs provide the prescribed inspections in chronological order.

The manual is as generic as possible. Wherever distinction is required between NC and


MM or SSTB and LSTB, it has been clearly indicated. Rehabilitation is considered identical
to NC for the purpose of inspection.

Where information is required, the prescribed inspection is preceded by a table that


simply needs to be completed.

The person in charge indicated in the last column has the option to interrupt further
construction when a certain issue is “unacceptable” or “conditionally acceptable”. He/she
can tick “remedied” in the last column once he/she is satisfied that the cause for his/her
objection has been sufficiently addressed. The tick indicates that he/she has agreed for
the works to proceed.

Emphasize has been put in trying to detect conceivable “wrongs” as early as possible in
order to keep costs of further harms down. E.g. technical inspections are emphasized at
CMS-9 (app. in the middle of construction) where rectifications are still relatively easy and
not at CMS-10 when the bridge is finished and rectifications are difficult and costly. This
contradicts the popular view that inspections should be held at the end of construction.

Critical Milestones are “critical” from either a program or a social and/or a technical
perspective. CMS-1 and CMS- 10 are exceptions. CMS-1 is critical only from a program
perspective while CMS-10 is critical from social perspective only. CMS-10 also differs from
other milestones in a sense that it has to be conducted not exactly at the time of the
milestone but sometime (< 3 months) thereafter. The main reason is that the DDC must
be given sufficient time to have settled all payments and CMS-10 mainly cross checks that
all payments were completed as committed at the outset.

It is important that every issue be properly addressed. This forms the proven record of
TBSU’s inspections vis à vis the counterpart as well as any donor.

It has to be born in mind that monitoring the application of the TBS/LIDP is the sole
responsibility of TBS/DoLIDAR. As a maturing section within the department, it has to be
upgraded / expanded with the additional resources (both human and financial) so that it
can address the challenges of the Trail Bridge Sub-Sector. TBSU therefore, is very much
in favour of involving TBS/DoLIDAR in the monitoring processes so that TBS/DoLIDAR can
assume monitoring roles spelled out in TBS/LIDP in a gradual and systematic manner.

Monitoring Manual Page (4)


Trail Bridge Sub-Sector Program

6. REPORTING
Principally, two kinds of reports listed below can be generated. The list below is not an
exhaustive one. All reports distinguish between New Construction (NC) and Major
Maintenance (MM); SSTB and LSTB, as well as “Suspended (D)” and “Suspension (N)”
type. As mentioned in the section 5, rehabilitation is considered identical to NC for the
purpose of inspection reporting.

1. A summary per Region for the RPC and/or TC regarding the Inspection
component indicating
1.1 bridges that have passed the inspections as well as the final
inspection / approval date.
1.2 pending bridges, passed inspections, indicating last milestone /
approval date.
1.3 bridges that did not pass the inspection, the reason and the last
inspection date.
1.4 bridges where the constructions have been interrupted, the reason,
the required remedial action and the last inspection date.

2. A bi-annual nationwide summary for the Coordination Unit, for the purpose
of accountability vis à vis donors and by means of the Yearly Plan of
Operation/Annual Project Reporting, indicating:
2.1 Outcomes / Access:
2.1.1 Number of projected users (average per bridge, average per DDC,
country average) per day
2.1.2 Ditto, segregated by ethnicity and gender.
2.1.3 Prime Purpose of a Bridge demand (per DDC, Nationwide)
2.2 Outcomes / Delegating Capacity and Capacity Building:
2.2.1 Number of competent practitioners (per DDC versus the
progression steps) (engineers, Sub-Engineer)
2.2.2 Ditto, for NGOs (Ass. Sub-Engineer)
2.2.3 DDCs that Delegated work to NGOs (for SSTB), to the private
sector (for LSTB).
2.2.4 Mutation rates in DDCs
2.2.5 Mutation rates in NGOs
2.3 Inspections:
2.3.1 number of bridges that have passed the inspections
2.3.2 number of pending bridges
2.3.3 number of bridges that did not pass the inspection
2.3.4 number of bridges where the construction has been interrupted
2.4 Political:
2.4.1 Bridge Requests (Demands) per District
2.4.2 Distance Gained (average per DDC, average for the Nation)
2.4.3 Ditto for DRH & DHQ, comparison to 2.4.2
2.4.4 Patterns of UC-composition (districts and nationwide)
2.5 Financial:
2.5.1 average estimated bridge costs per linear meter per bridge type
(district and nationwide)
2.5.2 average bridge cost per user (district and nationwide)
2.5.3 average contribution per stakeholder segregated by donor (district
and nationwide)

Monitoring Manual Page (5)


7.

Location Critical Issue Social Technical Program

CMS
CMS

OMS
OMS

Critical
Critical

Ordinary
Ordinary

Milestone
Milestone
Milestone
Milestone
Bridge Start

Institutional, Planning,
Institutional, Community
Equitable distribution, Application,

Monitoring Manual
CMS 1 DDC Visit CMS 1
Commitment of Composition of
Budget Beneficiaries,
Prioritization
Sound Economic
Design, Contribution
Site Assessment/
Pattern,
Trail Bridge Sub-Sector Program

CMS 2 Site Visit Public Hearing Survey/ Design/Cost CMS 2


Establishment of UC
Estimate
and no Dispute over
land

Community
MONITORING SCHEDULE

OMS 3 Desk Study OMS 3


Agreement

Procurement (Evaluation
OMS 4 Desk Study** OMS 4
of bids)

Insurance
coverage, Timely
Bridge Layout and
OMS 5 Desk Study payments, OMS 5
Foundation Excavation
Updating of Project
Book

Factory Visit for


Quality of raw Procurement/
CMS 6 steel/visit to the CMS 6
materials Fabrication start
site for cement

Procurement (Inspection
CMS 7 Factory Visit Quality of steel part CMS 7
and Certification)

Desk Study CMS and Concreting OMS 8

S8
OM
Quality construction, Cable Sag setting
CMS 9 Site Visit Public Review CMS 9
Payment as per plan (during)

Final Assessment
Payment as per plan, Public Auditing (all

Page (6)
CMS 10* Site Visit (Certification based on CMS 10*
Formation of BMC bridges)
Bridge End

random samples)
Trail Bridge Sub-Sector Program

COMPREHENSIVE BRIDGE LIST Long List

From Community Application Form Preliminary

Prioritization weight
Technical
Name of the VDC Bridge Type Remoteness
Feasibility

Ilaka No.

Rank

Questionable

Not Feasible
Right Bank
Left Bank
S.N. Preliminary

Feasible
Bridge Name River Name

LSTB
SSTB

DHQ

DRH
MM
Cost Estimate

DG
NC
NRs.

Bridges to be completed in 2 Cycles:


1. Site Assessment, Survey, Design, Cost Estimate, Procurement of steel parts & cement (app. 50 % of estimated value).
2. Layout, Construction, Formation of BMC (app. 50 % of estimated value).

Monitoring Manual Page (7)


Trail Bridge Sub-Sector Program

PERIODIC BRIDGE PLAN (ref # 1.1.2)


of Prioritized Bridges (from UC Application form)
From: ................................. To: ......................

Preliminary
Contribution Pattern in NRs.

Estimate
Carried
Over1

NRs.
Cost
 if
S.N. Bridge Name RAIDP3/
DDC VDC UC TBSU2 Other
DRILP

Total Newly Prioritized

Grand Total N/A


1. In case bridges got carried over from before the Periodic Plan, supply "Unpaid Balance of Cost Estimate" instead of "Preliminary Cost Estimate".
2. TBSU’s Support ends on December 31st, 2010
3. RAIDP’s Support end on June 30th, 2010
4. DRILP Support ends on August 31st, 2011

Monitoring Manual Page (8)


Trail Bridge Sub-Sector Program

PROGRAM: Critical Milestone 1 - [Institutional Issues (District wise)] DDC Visit


S. Generic Institutional Comments by RPC/TC
Details
N. Issues (Compulsory to comment on condition/hints if not met)
Last date updated: _________________
1 TIM ....................................................................................................
DTMP reflects TIM: Y □ □ N TIMs compulsory; update ≤ 1 yr

2 Periodic Bridge Plan Available: 3 Yr: Y □ N □ or 5 Yr: Y □ N □ ....................................................................................................


For period: ________________ To be updated if remaining period ≤ 1 yrs

3 Annual Bridge Plan Date approved by the DC: ________________ ........................................................................................


ABP is prepared and submitted within Chaitra for next FY
Available: Y□ N□ ...................................................................................................
4 District Bridge Record Updated up to FY: ________________
...................................................................................................
Includes bridge conditions: Y □ N□ DBR compulsory; update ≤ 1 yr
Staffs Available (nos)
Engineer(s) [ ] ...................................................................................................
Sub-Engineer [ ] ...................................................................................................
Technical Personnel planning
Asst. Sub-Engineer [ ]
5 (Staff Available & Trained in ...................................................................................................
Staffs Trained in bridge building (nos)
Bridge Building ) ...................................................................................................
Engineer(s) [ ]
Sub-Engineer [ ] ...................................................................................................
Asst. Sub-Engineer [ ] Minimum capacitated: Engineer 1 Sub-Engineer 1

6
Mgmt. Staffs Capacitated in LDO: Y□ N□
.......................................................................................
Y□ N□
Procurement
Engineer: Both must be capacitated
Cable Pulling Machine: Y□ N□
.....................................................................................................
Abney Level: Y□ N□ .....................................................................................................
7 DDC's Equipment (functional)
Drawing Table: Y□ N□ .....................................................................................................
.....................................................................................................
Camera: Y□ N□ Any missing equipment must be procured

8 NGO/Pvt. Sector Hired/contracted by DDC: Y□ N□ ........................................................................................


Date : ________________ NGO mandatory as per TBS/LIDP and Agreements
Staffs Available (nos)
Engineer(s) [ ]
Sub-Engineer [ ] .....................................................................................................
Trained Personnel in NGO / Asst. Sub-Engineer [ ] .....................................................................................................
9
Pvt. Sector Staffs Trained in bridge building (nos) .....................................................................................................
Engineer(s) [ ] .....................................................................................................
Sub-Engineer [ ] .....................................................................................................
Asst. Sub-Engineer [ ] ....................................Minimum capacitated: Asst. Sub-Engineer 1
Monitoring Manual Page (9)
Trail Bridge Sub-Sector Program

PROGRAM: Critical Milestone 1 - [Bridge Planning (District wise)] DDC Visit


Conditional Acceptability
S.
Generic Institutional Issues Acceptable Not Acceptable Hints on possible Decision by RPC
N. Explain condition
rectification needed
Covers all Ilakas
with rivers in need Ilaka without ..................................
of bridges
□ requests □ Mobilize NGO through
..................................
..................................
staff function to collect
1.0
Bridge Demand (Refer Comprehensive
Sufficient bridges
Partially available.
□ Inadequately more requests for next □ tick if rectified
Bridge Requests List)
for prioritization
Inconsistent data
filled in □ year and /or rectify To make verification
randomly to conform the
□ incomplete requests submitted information. In
case of any irregularities
report to TBS/DoLIDAR to
freeze any NC

If formula not ..................................


2.0 Prioritization formula Follows formula □ Ignores formula □ consistently

Re-Prioritize ..................................
..................................
applied
□ tick if rectified

All prioritized ..................................


3.0 Location of Prioritized Bridges in TIM bridges are located □ Not located □ ..................................
in TIM □ tick to override

The ranking is Budget allocation


..................................
guided by the requiring
..................................
Prioritization Weight construction
..................................
Budget allocation for Trail Bridges (In
but also considers a longer than 2 yr. □ ..................................
4.0
the Periodic and Annual Plan)
well balanced □ More than 25% of
..................................
budget amongst district trail bridge
RM, MM, Rehab and budget allocation
□ □ tick to override
NC (SSTB, LSTB) to a single NC Make sure complimentary
(order of priority) bridge budget (e.g., from the
donors) is secured
PP is prepared and
submitted within Not prepared/not ..................................
5.0 Procurement Plan
March (Chaitra) for □ submitted □ □ tick to override
next FY RPC to follow-up

Report submitted ..................................


Not prepared/not
6.0 Annual and Trimester reports within one month □ submitted □ □ tick to override
of reporting period.
RPC to follow-up

Monitoring Manual Page (10)


Trail Bridge Sub-Sector Program

PROGRAM: Critical Milestone 1 - [Annual Bridge Planning (District wise)] DDC Visit

Annual Bridge Plan Fiscal Year :…………………


Contribution in NRs.

 if Carried
Preliminary

Over1
S. Cost
Bridge Name RAIDP/
N. Estimate FY Budget DDC VDC UC TBSU Other
NRs. DRILP

1. In case bridges got carried over from before the Periodic Plan, supply "Unpaid Balance of Cost Estimate" instead of "Preliminary Cost Estimate".

Applies to all Bridges Per Annum


Conditional Acceptability
S.
Generic Institutional Issues Acceptable Not Acceptable Decision by RPC
N. Hints on possible
Explain condition
rectification needed

10% or less of the more than 10% of ...................................


1.1 Community Contribution in SDC districts
total cost □ the total cost □ ...................................
tick to override □

Community Contribution in RAIDP/DRILP 2% or less of the more than 2% of ...................................


1.2
districts total cost □ the total cost □ ...................................
tick to override □

25% or more of the less than 25% of ...................................


2.1 GoN/DDC/VDC contribution in SDC districts
total cost □ the total cost □ ...................................
tick to override □
...................................
GoN/DDC/VDC contribution in RAIDP/DRILP 8% or more of the less than 8% of
2.2
districts total cost □ the total cost □ ...................................
tick to override □
Monitoring Manual Page (11)
Trail Bridge Sub-Sector Program

TECHNICAL: Critical Milestone 2 - [Site Assessment (Bridge wise)] Site Visit


Conditional Acceptability
S. No. Issues Acceptable Not Acceptable Hints on possible Decision by TC
Explain condition
rectification needed
River Bank Protection
Works (app. NRs.
Prone to bank
30,000 per m.)
erosion by river □ River Training Works
cutting
(appro. NRs. 50,000 per
m.) Avoid as far as possible
Surface drainage and
Prone to sheet water management with
erosion by surface □ bio-engineering
runoff (app.NRs. 175,000 per
bank)
Sound rock or soil Signs of erosion
1.0 Stability of the bank/slopes
and fully vegetated □ and/or slides □ Prone to slides due
Retaining walls with bio-
to loose soil □ engineering (app.NRs.
250,000) Dry Stone Masonry
Prone to slide due
to highly Breast wall/Revetment
weathered soft □ (app. NRs. 150,000)
rock Dry Stone Masonry
Highly fractured Breast wall/Revetment
hard rock □ (app. NRs. 105,000)
Dry Stone Masonry
Other □
Nearby rivulet with Nearby gully
Check dams (app. NRs.
2.0 Influencing rivulets No nearby rivulets □ aggressive gully □ without sign of □ 20,000 per m.
erosion gully erosion Gabion wall check dams
Inspect periodically.
River is not hitting Banks are soils, Protect Bank if bank
River hits bank is
the bank or the bank river is hitting the condition is deteriorated
3.0 Meandering / Curving River
is rock even if river □ banks and the □ soft rock. No □ (app. Up to NRs. Mainly toe protection is
erosion yet.
is hitting erosion has started 300,000 may require in needed in long term
future) (caving)
not as per the
4.0 Source of Stone As per specifications □ specification □ Find alternative source
not as per the
5.0 Source of Sand As per specifications □ specification □ Screen and wash
not as per the Broken stones
6.0 Source of Gravel As per specifications □ specification □ aggregate to be used

Monitoring Manual Page (12)


Trail Bridge Sub-Sector Program

TECHNICAL: Critical Milestone 2 - [Design (Bridge wise)] Desk Study


Conditional Acceptability
S. N. Issues Acceptable Not Acceptable Hints on possible Decision by TC
Explain condition
rectification needed
Selected bridge .............................................
Selected bridge type type is not .............................................
is correct[(LSTB or correct[(LSTB or Selected bridge Consider more optimal
1.0 Bridge type selection
SSTB) / (Suspension □ SSTB) / □ type not optimal. □ type of bridge
.............................................
.............................................
or Suspended]. (Suspension or
.............................................
Suspended].

Both criteria (Slope ..............................................


Criteria not met,
angle and frontage) Rectify the concerned
2.0 Foundation location
in the standard are □ Neither criteria met □ but is/are □ criteria
..............................................
rectifiable ..............................................
met ..............................................
Does not meet the
Meets the norms
3.0 Cable geometry
and standards □ norms and □ ..............................................
.............................................
standards
Cuttings/fillings not ..............................................
balanced,
Cutting and filling is ..............................................
excessive cut Conditions not met Maintain cut slopes and
4.0 Environmental consideration balanced and cut □ slopes, cut slopes □ but rectifiable □ provide slope protection
..............................................
slopes maintained ..............................................
not maintained and
..............................................
not protected.
Norms and
Does not meet the standards not met. ..............................................
Meets the norms
5.0 Overall design
and standards □ norms and □ The design can be □ Rectify the design ..............................................
standards. rectified to make it ..............................................
safe. ..............................................
≤ 20% of the > 50% of the > 20% and ≤ 50%
6.0 Design optimization prevailing district □ prevailing district □ requires a design □ Review Design ..............................................
.............................................
linear cost linear cost review
An exception can
be made for 4 to 5 ..............................................
m but only if the ..............................................
7.0 Free board ≥5m □ <4m □ river is wise and □ ..............................................
no chance of ..............................................
debris flow with ..............................................
trees

Monitoring Manual Page (13)


Trail Bridge Sub-Sector Program

TECHNICAL: Critical Milestone 2 - [Cost Estimate (Bridge wise)] Desk Study


Conditional Acceptability
S. No. Issues Acceptable Not Acceptable Hints on possible Decision by TC
Explain condition
rectification needed
1.0 Implementation approach Followed □ Not followed □ ..............................................
Rates ..............................................
Published reference substantiated by
Check if the ..............................................
rates based on the Rates that are not the DDC based on
2.0 Unit rates of Steel Parts
norms established □ substantiated □ the norms □ substantiated rates are ..............................................
reasonable
by DoLIDAR/MoLD established by ..............................................
DoLIDAR/MoLD ..............................................
Approved district
Unit rates (Portering, Labor, Approved district
3.0
Cement etc.) rates followed □ rates are not □ ..............................................

followed ..............................................
DDC's norms but not ..............................................
inferior to : 1 1 Porterday < 12.8 ..............................................
4.0 Portering distance Porterday = 12.8 Km □ Km or 8 miles for □ ..............................................
or 8 miles for 40 kg 40 kg weight
weight ..............................................

Monitoring Manual Page (14)


Trail Bridge Sub-Sector Program

SOCIAL: Critical Milestone 2 - [Public Hearing (Bridge wise)] Site Visit

Immediate Beneficiaries' Composition table


No. of Households Beneficiary Population
Cast/Ethnicity
Poor Total Women Men Total
Dalit
Janajati
Minorities
Others
Total
%

UC composition table (Preliminary)


Total UC Composition (%)
Positions Dalit Janajati Minorities Others
Sum Female Male Female Male
Chairperson
(Dy)Chairperson
Secretary
Treasurer
UC Members
Total
%

Conditional Acceptability
S. No. Issues Acceptable Not Acceptable Hints on possible Decision by TSDO
Explain condition rectification
needed
2007: 25% or more □ 2007: less than 25% □
Women representation in UC
1
(Preliminary)
2008: 30% or more □ 2008: less than 30% □
2009/10: 33% or more □ 2009/10: less than 33% □
2007/08: Not less than 2007/08: less than
Proportionate representation individual % times 0.75 □ individual % times 0.75 □
2 of Dalit, Janajaties and 2009/10: No
2009/10:Proportionate
minorities in UC (Preliminary)
representation □ disproportionate □
representation

Continues ………

Monitoring Manual Page (15)


Trail Bridge Sub-Sector Program

Continued ……....

SOCIAL: Critical Milestone 2 - [Public Hearing (Bridge wise)] Site Visit

Conditional Acceptability
S. No. Issues Acceptable Not Acceptable Hints on possible Decision by TSDO
Explain condition rectification
needed
................................
At least one key
................................
position (Chairperson No key position
or Secretary or (Chairperson or Secretary ................................
3 Key Position in UC Treasurer or if or Treasurer or if ................................
(Preliminary) applicable their □ applicable their deputy's) □ ................................
deputy's) given to a given to a woman or
................................
woman or dalit or Dalit or Janajaties in UC
Janajaties in UC ................................
...............................
Written evidence of ................................
Land is donated under
donated or ................................
4 Land donation
compensated land □ social pressure by the □ ................................
Community (SSTB Only)
(SSTB Only)
................................
Information :
Disseminate on ................................
insurance coverage, ................................
conditions & ................................
5 Insurance procedures. UC to
................................
submit regular
workperson attendance ................................
record. tick if done □
Information : DB to be ................................
6 Displaced Boatperson incorporated in DMBT ................................
and/or local labor
tick if incorporated □
Information : ................................
7 Signboard (Hoardingboard) Compulsory to be in ................................
place before Layout.
tick if is in place □

Monitoring Manual Page (16)


Trail Bridge Sub-Sector Program

PROGRAM: Critical Milestone 3 - [Community Agreement (District wise)] Desk Study

Contribution Pattern (based on a firm Cost Estimate)

Support in Payment Schedule from DDC/VDC to UC(Amount in %)


Total
Source Cash (NRs.) kind/Labor Source
(NRs.) Target 30 % Target 30 % Target 30 % Target 10 %
NRs. % 1st (OMS 3) 2nd (OMS 8) 3rd (CMS 9) 4th (CMS 10)
VDC DDC
DDC VDC
Community Total
TBSU
RAIDP/DRILP
Others
Total

Conditional Acceptability
S. No. Generic Institutional Issues Acceptable Not Acceptable Decision by RPC
Hints on possible
Explain condition
rectification needed
Insurance in place
for: workpersons, .............................................
1.0 Insurance
NGO persons, □
Any omission □ .............................................
goods in transit. .............................................

Community Contribution in SDC 10% or less of the more than 10% of .............................................
2.1
districts (confirmation of contributions) total cost □ the total cost □ .............................................

Community Contribution in
2% or less of the more than 2% of .............................................
2.2 RAIDP/DRILP districts (confirmation of
total cost □ the total cost □ .............................................
contributions)
GoN/DDC/VDC contribution in SDC 25% or more of the less than 25% of .............................................
3.1
districts (confirmation of contributions) total cost □ the total cost □ .............................................

GoN/DDC/VDC contribution in
8% or more of the less than 8% of .............................................
3.2 RAIDP/DRILP districts (confirmation of
total cost □ the total cost □ .............................................
contributions)

Monitoring Manual Page (17)


Trail Bridge Sub-Sector Program

SOCIAL: Ordinary Milestone 3 - [Community Agreement (confirmation) (Bridge wise)] Desk Study

UC composition table (Confirmation)


UC Composition
Total
Positions Dalit Janajati Minorities Others (%)
Sum Female Male Female Male

Chairperson
(Dy)Chairperson
Secretary
Treasurer
UC Members
Total
%

Participants during Public Hearing


Total
Positions Dalit Janajati Minorities Others
Sum Female Male HH
Members from the
community
Total
%

DMBT Participants
Total
Boat Person
Dalit Janajati Minorities Others
(if applicable) Sum Female Male

Continues ………
Monitoring Manual Page (18)
Trail Bridge Sub-Sector Program

Continued ………

SOCIAL: Ordinary Milestone 3 - [Community Agreement (confirmation) (Bridge wise)] Desk Study

Conditional Acceptability
S. No. Issues Acceptable Not Acceptable Hints on possible Decision by TSDO
Explain condition rectification
needed
................................
2007: 25% or more □ 2007: less than 25% □
...............................
Women representation in Ucs ...............................
1
(Preliminary)
2008: 30% or more □ 2008: less than 30% □
...............................
...............................
2009/10: 33% or more □ 2009/10: less than 33% □ ...............................
2007/08: Not less than 2007/08: less than
Proportionate representation individual % times 0.75 □ individual % times 0.75 □ ................................
of Dalit, Janajaties and ...............................
2 2009/10: No
minorities in UC (Preliminary) 2009/10:Proportionate ...............................
representation □ disproportionate □ ...............................
representation ................................
At least one key
position (Chairperson No key position ................................
or Secretary or (Chairperson or Secretary ...............................
Treasurer or if or Treasurer or if
3 Key Position in UC
applicable their □ applicable their deputy's) □ ...............................
...............................
deputy's) given to a given to a woman or
woman or Dalit or Dalit or Janajaties in UC ...............................
Janajaties in UC ...............................
Proportional representation Less than individual % ................................
Same as compared to
4 of dalit, janajaties and
the UC □ times 0.75 excluding the □ ...............................
minorities in DMBT displaced boatperson
...............................

Monitoring Manual Page (19)


Trail Bridge Sub-Sector Program

TECHNICAL : Ordinary Milestone 4 - [Procurement / Evaluation of BIDs (Bridge wise)] Desk Study

A copy from DDC's job order (first page only)

Conditional Acceptability
S. No. Issues Acceptable Not Acceptable Hints on possible Decision by TC
Explain condition
rectification needed
The fabricator is
If not from the Inspect the fabricators
1.0 Job Award from the long listed □ listed fabricators □ and if they qualify
fabricators

Monitoring Manual Page (20)


Trail Bridge Sub-Sector Program

TECHNICAL: Ordinary Milestone 5 - [Layout and Foundation Excavation (Bridge wise)] Desk Study
Conditional Acceptability
S. No. Issues Acceptable Not Acceptable Hints on possible Decision by TC
Explain condition
rectification needed

Span and elevations


Review the design and
have been verified Deviation from the ...............................................
1.0 Span and elevation
and found to be as □ design/drawing □ quantities to be ordered
...............................................
(by DDC/NGO)
per design
tick if rectified □
Foundation size and
Deviation from the ...............................................
2.0 Foundation excavation (RB) Bed slope as per □ design/drawing □ Rectify
...............................................
design
tick if rectified □
.
Foundation size and
Deviation from the ..............................................
3.0 Foundation excavation (LB) Bed slope as per □ design/drawing □ Rectify
...............................................
design
tick if rectified □

As per design and Deviation from the ...............................................


4.0 Cutting slope (RB)
drawing □ design/drawing □ Rectify
...............................................

tick if rectified □

As per design and Deviation from the ...............................................


5.0 Cutting slope (LB)
drawing □ design/drawing □ Rectify
...............................................

tick if rectified □

Monitoring Manual Page (21)


Trail Bridge Sub-Sector Program

SOCIAL: Ordinary Milestone 5 - [(Bridge wise)] Desk Study

Conditional Acceptability
S. No. Issues Acceptable Not Acceptable Hints on possible Decision by TSDO
Explain condition rectification
needed
Report: MoM of UC
meetings, labor ................................
Project Book, community
1.1
approach
attendance and Income □ Any omissions □ ................................
and Expenditure in the
Project Book ...............................
Proper records of the
Instructions of the ................................
Project Book, contracting
1.2
approach
employer's engineer, □ Any omissions □ ................................
Quality Assurance
documentations ...............................

DDC to remind UC ................................


Regular attendance
2.1 Work person Insurance
submitted to DDC □ Any omissions thereof Late submission □ and NGO for ................................
attendance
...............................
TBS/DoLIDAR follow- ................................
Timely settlement of up with DDC and
2.2 Insurance Claim
any Insurance claims □ Late settlement □ DDC follow-up with ................................
Insurance company ...............................

Fund disbursement from Dues older than 1 ................................


TBS/DoLIDAR to
3.0 DDC/VDC to UC(SSTB) or month have been □ Any delays □ follow up with DDC ................................
Contractor(LSTB) settled
...............................
Payments must be DDC to remind UC ................................
Timely payment from
within one week after and NGO
4.0 UC(SSTB) or Contractor
receiving fund □ Any delays □ (SSTB)/Contractor ................................
(LSTB) to the laborers
disbursement (LSTB) ...............................

≥ 30% Women of ................................


NGO to play
5.0 UC Meeting those present, □ <30% □ proactive role ................................
participate
...............................

Monitoring Manual Page (22)


Trail Bridge Sub-Sector Program

TECHNICAL: Critical Milestone 6 - [Procurement/Fabrication start (Bridge wise)] Factory Visit

Refer the label (from RAIDP/DRILP and TBSU Program Districts) Annex 3

Conditional Acceptability
S. No. Issues Acceptable Not Acceptable Hints on possible Decision by TC
Explain condition
rectification needed
Absence of
Quality certificate
Quality of raw materials for Steel certificate or ....................................
from the lab
1.0 parts based on random sample
conforming the □ materials do not □ ....................................
collected at the factory conform the
standard
standard ...................................
Absence of
Quality certificate
certificate or ....................................
from the lab
2.0 Quality of GI wire
conforming the □ materials do not □ ....................................
conform the
standard
standard ...................................
To procure pre- If cement is set.
Quality of cement prior to approved (by Procurement of ....................................
3.0
procurement from the supplier TBS/DoLIDAR) □ non pre-approved □
....................................
brands brands
....................................

Are exactly as per ....................................


4.0 Templates/Jigs
design and drawing □ Any deviations □ ....................................
tick if rectified □

Monitoring Manual Page (23)


Trail Bridge Sub-Sector Program

SOCIAL: Ordinary Milestone 6 - [(Bridge wise)] Desk Study

Conditional Acceptability
S. No. Issues Acceptable Not Acceptable Hints on possible Decision by TSDO
Explain condition rectification
needed
Report: MoM of UC ................................
meetings, labor
Project Book, community ...............................
1.1
approach
attendance and Income □ Any omissions □
and Expenditure in the ................................
Project Book
...............................
Proper records of the
Instructions of the ................................
Project Book, contracting
1.2
approach
employer's engineer, □ Any omissions □ ................................
Quality Assurance
documentations ...............................

DDC to remind UC ................................


Regular attendance
2.1 Workperson Insurance
submitted to DDC □ Any omissions thereof Late submission □ and NGO for ...............................
attendance
...............................
TBS/DoLIDAR follow- ................................
Timely settlement of up with DDC and
2.2 Insurance Claim
any Insurance claims □ Late settlement □ DDC follow-up with ................................
Insurance company ...............................

Fund disbursement from Dues older than 1 ................................


TBS/DoLIDAR to
3.0 DDC/VDC to UC(SSTB) or month have been □ Any delays □ follow up with DDC ...............................
Contractor(LSTB) settled
...............................
Payments must be DDC to remind UC ................................
Timely payment from
within one week after and NGO
4.0 UC(SSTB) or Contractor
receiving fund □ Any delays □ (SSTB)/Contractor ................................
(LSTB) to the laborers
disbursement (LSTB) ...............................

≥ 30% Women of ................................


NGO to play
5.0 UC Meeting those present, □ <30% □ proactive role ................................
participate
...............................

Monitoring Manual Page (24)


Trail Bridge Sub-Sector Program

TECHNICAL: Critical Milestone 7 - [Procurement (Inspection and Certification) (Bridge wise)]


Factory Visit
Conditional Acceptability
S. No. Issues Acceptable Not Acceptable Hints on possible Remarks
Explain condition
rectification needed

Verify there is a
Quality Certificate of ....................................
raw materials (CMS □ ...................................
6) and
...................................

Manufacturer ....................................
maintains QA □ ...................................
documentation and
...................................

Welding appears ....................................


1.0 Quality of finished steel parts
professionally done □ Any Deviation □ ...................................
and
...................................

Zinc coating checked ....................................


positively and □ ...................................
...................................

Assembled fittings ....................................


have been checked □ ....................................
positively. For details refer to quality

control manual □

Monitoring Manual Page (25)


Trail Bridge Sub-Sector Program

SOCIAL: Ordinary Milestone 7 - [(Bridge wise)] Desk Study

Conditional Acceptability
S. No. Issues Acceptable Not Acceptable Hints on possible Decision by TSDO
Explain condition rectification
needed
Report: MoM of UC ................................
meetings, labor
Project Book, community ................................
1.1
approach
attendance and Income □ Any omissions □
and Expenditure in the ...............................
Project Book
...............................
Proper records of the ................................
Instructions of the
Project Book, contracting ................................
1.2
approach
employer's engineer, □ Any omissions □
Quality Assurance ...............................
documentations
...............................
DDC to remind UC ................................
Regular attendance
2.1 Workperson Insurance
submitted to DDC □ Any omissions thereof Late submission □ and NGO for
...............................
attendance
...............................
TBS/DoLIDAR follow-
................................
Timely settlement of up with DDC and
2.2 Insurance Claim
any Insurance claims □ Late settlement □ DDC follow-up with ...............................
Insurance company ...............................
Fund disbursement from Dues older than 1 ................................
TBS/DoLIDAR to
3.0 DDC/VDC to UC(SSTB) or month have been □ Any delays □ follow up with DDC ...............................
Contractor(LSTB) settled
...............................
Payments must be DDC to remind UC
Timely payment from ................................
within one week after and NGO
4.0 UC(SSTB) or Contractor
receiving fund □ Any delays □ (SSTB)/Contractor ...............................
(LSTB) to the laborers
disbursement (LSTB) ...............................

≥ 30% Women of ................................


NGO to play
5.0 UC Meeting those present, □ <30% □ proactive role ...............................
participate
...............................

Monitoring Manual Page (26)


Trail Bridge Sub-Sector Program

TECHNICAL: Ordinary Milestone 8 - [Cement Stone Masonry & Concreting (Bridge wise)] Desk Study
Conditional Acceptability
S. No. Issues Acceptable Not Acceptable Hints on possible Decision by TC
Explain condition
rectification needed
..............................................
Dimensions of anchorage and As per design and Deviation from
1.0
foundation blocks drawing □ design/drawing □ Rectify ..............................................

tick if rectified □
As per drawing
..............................................
(Chiseled dressed
stones, hammer ..............................................
Quality of stones/aggregate /
2.0
sand
dressed stones and □ Deviations thereof □ Rectify ..............................................
broken stones) and for
..............................................
aggregate and sand
refer to CMS 2 tick if rectified □
As per specifications: ..............................................
Concrete/Mortar mix,
Deviation from ..............................................
3.0 Workmanship (General) Bond/joints, Plumb □ specifications □ Rectify
..............................................
vertical/horizontal and
Curing tick if rectified □
Laying of broken ..............................................
stones with proper
Dry stone masonry for dead ..............................................
4.0
load
bonding along with the □ Dry stone filling-up □ Deviations thereof □ ..............................................
peripheral cement
stone masonry tick if rectified □
Laying of
reinforcement / ..............................................
Concreting of Deadman anchorage steel parts
5.1
Beam and pipes and □ Deviations thereof □ ..............................................

..............................................
concreting as per
drawing tick if rectified □
..............................................
Anchor length/laying of
..............................................
5.2 Concreting of Drum reinforcement as per Deviations thereof □ ..............................................
drawing
tick if rectified □
..............................................
Laying of
Concreting of Anchorage / reinforcement and ..............................................
5.3
Foundation Block anchorage steel parts
Deviations thereof □ ..............................................
as per drawing
tick if rectified □
Monitoring Manual Page (27)
Trail Bridge Sub-Sector Program

SOCIAL: Ordinary Milestone 8 - [(Bridge wise)] Desk Study

Conditional Acceptability
S. No. Issues Acceptable Not Acceptable Hints on possible Decision by TSDO
Explain condition rectification
needed
Report: MoM of UC .........................................
meetings, labor
Project Book, community
1.1
approach
attendance and Income □ Any omissions □ .........................................

and Expenditure in the .........................................


Project Book .........................................
Proper records of the
Instructions of the
Project Book, contracting .........................................
1.2
approach
employer's engineer, □ Any omissions □ .........................................
Quality Assurance
documentations .........................................

DDC to remind UC .........................................


Regular attendance
2.1 Work person Insurance
submitted to DDC □ Any omissions thereof Late submission □ and NGO for .........................................
attendance
.........................................
TBS/DoLIDAR follow- .........................................
Timely settlement of up with DDC and
2.2 Insurance Claim
any Insurance claims □ Late settlement □ DDC follow-up with .........................................

Insurance company .........................................

Fund disbursement from Dues older than 1 .........................................


TBS/DoLIDAR to
3.0 DDC/VDC to UC(SSTB) or month have been □ Any delays □ follow up with DDC .........................................
Contractor(LSTB) settled
.........................................
Payments must be DDC to remind UC
Timely payment from .........................................
within one week after and NGO
4.0 UC(SSTB) or Contractor
receiving fund □ Any delays □ (SSTB)/Contractor .........................................
(LSTB) to the laborers
disbursement (LSTB) .........................................

≥ 30% Women of .........................................


NGO to play
5.0 UC Meeting those present, □ <30% □ proactive role .........................................
participate
.........................................

Monitoring Manual Page (28)


Trail Bridge Sub-Sector Program

TECHNICAL: Critical Milestone 9 - [Cable Sag Setting (during and right before the Public Review) (Bridge wise)] Site Visit
Conditional Acceptability
S.
Issues Acceptable Not Acceptable Hints on possible Decision by TC
N. Explain condition
rectification needed
Verify Concreting (Ref. to
..............................................
1.0 OMS 8: Item 5.1 through
5.3) done as reported tick if verified □
Dimensions of anchorage and Deviation from ..............................................
2.0 As per design and drawing □ □ Rectify
foundation blocks design/drawing tick if rectified □
As per drawing Chiseled
dressed, hammer dressed ..............................................
Cross check the Quality of
3.0
stones/aggregate /sand
and broken stones) and for □ Deviations thereof □ Rectify
..............................................
aggregate and sand refer
to CMS 2 tick if rectified □
As per specifications:
Concrete/Mortar mix, ..............................................
Deviation from
4.0 Workmanship (General) Bond/joints, Plumb □ specifications □ Rectify
..............................................
vertical/horizontal and
Curing tick if rectified □
Laying of broken stones ..............................................
Dry stone masonry for dead with proper bonding along
5.0
load with the peripheral cement □ Dry stone filling-up □ Deviations thereof □ Rectify ..............................................

stone masonry tick if rectified □


Without kinks and/or With kinks and/or
6.0 Quality of cable
broken strands □ broken strands □ □ ..............................................

..............................................

Sag is more than ± ..............................................


7.0 Cable sag As per design □ □ If within tolerance □ Adjust sag as per design
1% tick if adjusted □
Sag difference is ..............................................
8.0 Relative sag Equal sag of all cables □ □ If within tolerance □ Adjust sag
10mm or more tick if adjusted □
Less than the
9.0 Bulldog Grips As per design □ design □ ..............................................

..............................................
Vertical, No missing nuts
10.0 Tower (N types only) and bolts, Temporary □ Any deviations □
struts are in place ..............................................
As per specifications: Proper ..............................................
Painting works of non-
cleaning, Application of Red
11.0 galvanized steel parts
Oxide Zinc Chromate primer □ Any deviations □ ..............................................
(MM only) and Enamel coating tick if adjusted □
Monitoring Manual Page (29)
Trail Bridge Sub-Sector Program

SOCIAL: Critical Milestone 9 - [(Bridge wise)]


Participants during the Public Review Site Visit

Total
Dalit Janajati Minorities Others
Sum Female Male HH

Total

Conditional Acceptability
S. No. Issues Acceptable Not Acceptable Hints on possible Decision by TSDO
Explain condition rectification
needed
Endorsement or
Review of Technical Issues Non-viable technical
1.0
during cable hoisting
amendments that are □ "solutions" □ .........................................
technically viable .........................................
Fund disbursement from Dues older than 1 Dues older than 2 Dues settled .........................................
DDCs to catch up
2.0 DDC/VDC to UC(SSTB) or month have been □ months have not been □ between 1st and □ with delays .........................................
Contractor(LSTB) settled settled 2nd month Refer to RPC
Payments must be Payments made later
Timely payment from .........................................
within one week after than one week after
3.0 UC(SSTB) or Contractor
receiving fund □ receiving fund □ □ .........................................
(LSTB) to the laborers
disbursement disbursement .........................................

Minutes of Meeting must be recorded: to reflect shortcomings and action required by UC, NGO, DDC, TBSU, Others.

S.No. Stakeholders Shortcomings Comments by RPC (Action required)

4 UC

5 NGO

6 DDC

7 TBSU

8 Others…………..

Monitoring Manual Page (30)


Trail Bridge Sub-Sector Program

TECHNICAL: Ordinary Milestone 10 - [Final Assessment (Bridge wise)] Desk Study

S.N. Issues Norms Tolerance Instruction / Certification by TC

Sag is within ± 1% of
1.0 Cable sag As per design □ □ ........................................................................
Designed sag
tick if certified □
□ □
.......................................................................
2.0 Relative sag Equal sag of all cables Sag difference is 10mm or less
tick if certified □
Number, size and spacing as

.......................................................................
3.0 Bulldog Grips
per design
tick if certified □
Dimensions as per drawing □
........................................................................
Proper cut slopes as per
drawing □ ........................................................................
4.0 Anchorage / Foundation Block
........................................................................
Stone masonry and concreting
as per drawing and □ ........................................................................
specifications tick if certified □
Bridge Erection (Optional: Can only be
5.0
conducted if a field visit is envisaged.)

Cross beams and decks are ........................................................................


5.1 Walkway well assembled without □ ........................................................................
missing any nuts and bolts
tick if certified □
.......................................................................
No missing suspenders/parts,
5.2 Suspenders
All suspenders are vertical. □ .......................................................................

tick if certified □
Vertical, No missing nuts and .......................................................................
Tower (To conform rectification
5.3
carried out after CMS 9)
bolts, Temporary struts are □ .......................................................................
removed
tick if certified □
Hot dipped galvanized □ .......................................................................
5.4 Fixtures
None missing □ .......................................................................

tick if certified □
Wires are heavy zinc coated □ .......................................................................
5.5 Wire Mesh .......................................................................
Uniform mesh weaving and
properly fixed as per design □ tick if certified □
Monitoring Manual Page (31)
Trail Bridge Sub-Sector Program

SOCIAL: Critical Milestone 10 - [Public Audit (Bridge wise)] Site Visit

Participants during Public Audit

Total
Dalit Janajati Minorities Others
Sum Female Male HH

Total

Contribution Pattern (based on a firm Cost Estimate)

Support in Total
Source Cash (NRs.)
kind/Labor (NRs.)

NRs. %
VDC
DDC
Community
TBSU
RAIDP/DRILP
Others*
Total

Conditional Acceptability
S. No. Issues Acceptable Not Acceptable Hints on possible Decision by TSDO
Explain condition rectification
needed
Dues have not been
Record details on
Fund disbursement from settled for UC and
whom has not been
1.0 DDC/VDC to UC(SSTB) or Dues have been settled □ payments outstanding □ paid. Report to If not acceptable
Contractor(LSTB) for materials and road
transportation
RAIDP/DRILP recommend to freeze
NC □
Timely payment from Record details on
All payments have Payments not
2.0 UC(SSTB) or Contractor
been made □ Delay in payments. □ settled □ whom has not been If not acceptable

(LSTB) to the laborers paid. Report to DDC


recommend to freeze
NC □

Monitoring Manual Page (32)